FACTORY ACCEPTANCE TEST

(HT SWITCHGEAR) AMARA HOTEL UPGRADING Project

Date: 28 Mar 2012 Rev.:0

1 of 19

FACTORY ACCEPTANCE TEST

TESTING PROCEDURE

FOR

22 KV HT

SWITCHGEAR

Page 2: ABB HT FAT Proceedure

FACTORY ACCEPTANCE TEST

(HT SWITCHGEAR) AMARA HOTEL UPGRADING Project

Date: 28 Mar 2012 Rev.:0

2 of 19

AGENDA

Project Name : Amara Hotel Upgrading Project Project No. : SG-46011513 Customer : Kurihara Kogyo Co. Ltd FAT Date : 28 Mar 2012 (14:00 hrs) Location of FAT : ABB Pte Ltd No.2 Ayer Rajah Crescent Singapore 139935 Tentative Testing Schedule 14:00AM – 16:00PM : Testing of IC, and Bus Section Feeders 16:00PM – 16:30PM : Testing on Transformer Feeder 16:30PM _ 17:00PM : Summary of tests carried out and signing off of all test reports

Page 3: ABB HT FAT Proceedure

FACTORY ACCEPTANCE TEST

(HT SWITCHGEAR) AMARA HOTEL UPGRADING Project

Date: 28 Mar 2012 Rev.:0

3 of 19

FAT Procedure - Table of Contents

Visual Inspection…………………………………………………………………………...4

Function Test ………………………………………………………………………….…...4

Primary Injection Test on CT’s Ratio & Polarity .................................................................5

Secondary Injection Test.......................................................................................................8

Secondary Injection for Pilot Wire Relay Operation Check.................................................9

Figures

Figure 1: Circuit Diagram for CT Ratio & Polarity Check ..................................................6

Figure 2: Circuit Diagram for CT Ratio & Polarity Check ................................................. 6

Figure 3: Circuit Diagram for CT Ratio & Polarity Check ..................................................7

Figure 4: Circuit Diagram for CT Ratio & Polarity Check ..................................................7

Figure 5: Circuit Diagram for Relay Test ............................................................................8

Figure 6: Circuit Diagram for Solkor Relay Test ……........................................................9

Test Form & customer signed-off Form

Form1: Visual Inspection Test …………………………………………………………...10

Form 2: Electrical / Mechanical Function Test …………………………………………..11

Form 3: Primary Injection Test on CT (PI) / Voltmeter Ratio Test ………………………13

Form 4: Overcurrent & Earth Fault Relay Operation Test (SI)…………………………..15

Form 5: Pilot Wire Protection Operation Test …………………………………………...16

Form 6: Attendance List………………... ……………………………………………….17

Form 7: Customer comment & signed off ……………………………………………….18

Page 4: ABB HT FAT Proceedure

FACTORY ACCEPTANCE TEST

(HT SWITCHGEAR) AMARA HOTEL UPGRADING Project

Date: 28 Mar 2012 Rev.:0

4 of 19

Visual inspection

Panel Arrangement

Built In Equipment

Check Finishing Paint Work

Rating and Equipment Identification Labels

Check Mimic Diagram

Function Test

OC/EF & Pilot Wire Protection Trip

T/F Alarm/trip

Electrical/Mechanical Interlock

CB on/off

Disconnector/Earthing switch on/off operation

Page 5: ABB HT FAT Proceedure

FACTORY ACCEPTANCE TEST

(HT SWITCHGEAR) AMARA HOTEL UPGRADING Project

Date: 28 Mar 2012 Rev.:0

5 of 19

Primary Injection Test on CT’s Ratio & Polarity

1. Ensure that the switchgear has been de-energized.

2. Note down the particulars of the switchgear and CT’s.

3. Do not remove any wires, use the provided test plugs if applicable or use

clamp meters.

4. Measure the CT’s secondary phases and spill current using a clamp meter.

5. Select all meters to ampere range.

6. Inject a current of 10 to 20A onto the brown and black phases. Check the spill current,

it should be as low as milli-ampere. If the spill current is high, check for CT’s terminal

tightness or any mistake on the wiring.

7. Reduce to zero and off the supply, change the spill current meter (A4) to milliampere

range.

8. Inject a current of 50% and 100% of the CT primary current on brown (L1) and black

(L2) phases. Record the reading.

9. Reduce to zero and off the supply.

10. Repeat item 6 to 8 for black (L2) and grey (L3) phases.

11. Repeat item 6 to 8 for brown (L1) and grey (L3) phases.

12. Select all meters to ampere range.

13. Inject a current of 10 to 20A onto black phases (L2) to earth. Check the spill current

(A4). It should be the same current as the phase current (A2).

14. Inject a current of 50% and 100% of the CT primary current on black (L2) phase to

earth. Record the reading.

Page 6: ABB HT FAT Proceedure

FACTORY ACCEPTANCE TEST

(HT SWITCHGEAR) AMARA HOTEL UPGRADING Project

Date: 28 Mar 2012 Rev.:0

6 of 19

Page 7: ABB HT FAT Proceedure

FACTORY ACCEPTANCE TEST

(HT SWITCHGEAR) AMARA HOTEL UPGRADING Project

Date: 28 Mar 2012 Rev.:0

7 of 19

Page 8: ABB HT FAT Proceedure

FACTORY ACCEPTANCE TEST

(HT SWITCHGEAR) AMARA HOTEL UPGRADING Project

Date: 28 Mar 2012 Rev.:0

8 of 19

Secondary Injection Test 1. Ensure that the switchgear is de-energized.

2. Note down the relay particulars on test form.

3. Check or record the setting of the relay.

4. Increase the current gradually until the relay pick up. Record the reading.

5. Set a current of two times of the plug setting and off the injection set.

6. Press the start button of the injection set and record the tripping time as shown on the

test equipment.

7. Repeat item 5 to 6 for three and five times of the plug setting.

8. Repeat item 5 to 7 for black (L2) and grey (L3) element.

9. Repeat item 4 to 7 for earth element.

Page 9: ABB HT FAT Proceedure

FACTORY ACCEPTANCE TEST

(HT SWITCHGEAR) AMARA HOTEL UPGRADING Project

Date: 28 Mar 2012 Rev.:0

9 of 19

Secondary Injection for Pilot Wire Relay Operation Check

1. Ensure that the switchgear is de-energized and PTW is issued.

2. Remove the relay from the casing and check the relay connection. It is either

Solkor R or Solkor Rf mode. Typically it is used at Solkor R mode. Change the

connection accordingly to your application.

3. Connect the circuit on Brown (L1) and neutral phase as shown on the diagram.

4. Increase the current gradually until relay pick up. Record reading A1, A2, A3 and A4

on the test form

5. Increase the current furthermore until the dummy relay pick up.

6. Record reading A1 on the test form.

7. Repeat step 3 to 5 for Black-E, grey-E, Brown-Black, Black-Grey and Grey-brown.

Page 10: ABB HT FAT Proceedure

FACTORY ACCEPTANCE TEST

(HT SWITCHGEAR) AMARA HOTEL UPGRADING Project

Date: 28 Mar 2012 Rev.:0

10 of 19

FAT Test Form

1. VISUAL INSPECTION TickBox / Remark

Panel Arrangement

Built In Equipment

Check Finishing Paint Work

Rating and Equipment Identification Labels

Check Mimic Diagram (if any)

Tested By (Name & Signature) : __________________________________________ Witnessed By (Name & Signature) : __________________________________________ Date : : _________________________________________

Page 11: ABB HT FAT Proceedure

FACTORY ACCEPTANCE TEST

(HT SWITCHGEAR) AMARA HOTEL UPGRADING Project

Date: 28 Mar 2012 Rev.:0

11 of 19

2. ELECTRICAL / MECHANICAL FUNCTION TEST

TickBox / Remark

Local CB Close Operation

Local CB Open Operation

Remote CB Close Operation

Remote CB Open Operation

Local / Remote CB “OFF” Indication

Local / Remote CB “ON” Indication

Disconnector switch Close Operation (GIS)

Disconnector switch Open Operation (GIS)

Earthing switch Close Operation, if any

Earthing switch Open Operation, if any

Electrical Interlock Operation

Mechanical interlock

Earthing switch mechanism

Circuit Breaker mechanism

3-way switch mechanism (GIS)

Page 12: ABB HT FAT Proceedure

FACTORY ACCEPTANCE TEST

(HT SWITCHGEAR) AMARA HOTEL UPGRADING Project

Date: 28 Mar 2012 Rev.:0

12 of 19

OCEF Trip REF Trip, if any

PW Trip, if any

T/F Temperature Trip/Alarm, if any

T/F Pressure Trip/Alarm, if any

T/F Low Oil Trip/Alarm, if any

T/F Winding Temp Trip/Alarm, if any

T/F Door Open Trip/Alarm, if any

Intertrip receive, if any

Intertrip send, if any

Tested By (Name & Signature) : __________________________________________ Witnessed By (Name & Signature) : __________________________________________ Date : : _________________________________________

Page 13: ABB HT FAT Proceedure

FACTORY ACCEPTANCE TEST

(HT SWITCHGEAR) AMARA HOTEL UPGRADING Project

Date: 28 Mar 2012 Rev.:0

13 of 19

3. PRIMARY INJECTION TEST ON CT/VOLTMETER RATIO TEST

CT Data

CT Ratio:__________ CT Class: _____________ VA / Vkp:__________________

CT Serial No

L1: ___________________ L2: _______________ L3 : _______________

Panel No. ___________

Primary

Connectio

n

Primary

Injectio

n

Current

(A)

CT Ratio Spill

Current

(<50mA

)

Primary Primary

Injection

Current

(A)

CT Ratio Spill

Current

(<50mA) L1 L2 L3

Connectio

n L1 L2 L3

L1L2 2.5 2.5

L1L2 2.5 2.5

5.0 5.0 5.0 5.0

L2L3 2.5 2.5

L2L3 2.5 2.5

5.0 5.0 5.0 5.0

L3L1 2.5 2.5

L3L1 2.5 2.5

5.0 5.0 5.0 5.0

Tested By (Name & Signature) : __________________________________________ Witnessed By (Name & Signature) : __________________________________________

Date : : __________________________________________

Page 14: ABB HT FAT Proceedure

FACTORY ACCEPTANCE TEST

(HT SWITCHGEAR) AMARA HOTEL UPGRADING Project

Date: 28 Mar 2012 Rev.:0

14 of 19

AMMETER CALIBRATION CURRENT TRANSDUCER

I/P O/P

Primary Current (A) NA NA NA L1 NA A NA mA

Meter Reading (A) NA NA NA L2 NA A NA mA

PT S / NO. L1: NA L3 NA A NA mA

L2 : NA

L3 : NA CURRENT / VOLTAGE TRANSDUCER

I/P

O/P

P.T. VOLTMETER RATIO TEST

L1 NA

A / V

NA mA

Primary Voltage ( kV ) L2 NA A / V NA mA

Meter Reading ( kV ) L3 NA

A / V NA mA

Tested By (Name & Signature) : __________________________________________ Witnessed By (Name & Signature) : __________________________________________ Date : : _________________________________________

Page 15: ABB HT FAT Proceedure

FACTORY ACCEPTANCE TEST

(HT SWITCHGEAR) AMARA HOTEL UPGRADING Project

Date: 28 Mar 2012 Rev.:0

15 of 19

4. OVECURRENT AND EARTH FAULT RELAY OPERATION TEST (I/C)

Particular of Relays:

Make

Type Tripping

Characteristics

Rating

S/No

O/C Relay

E/F Relay

Test Results of HT Installation: Panel No / Circuit Name: /

O/C Relay

E/F Relay

Plug

Setting A

Sec

Cur, A

Operation Time, sec

Plug

SettingA

Sec

Cur, A

Opn

Time, sec

TM

Setting

Std

Time, sec

L1

L2

L3

2.5

5.0

5.0

25

10

10

1.0

2.0

1.0

10

4

2

1.0

1.0

0.1

Plug Setting, A

Starting Current, A

Plug

Setting A

Starting

Current, A

L1

L2

L

2.5 5.0

1.0

2.0

High Set, A

Operating Current, A

High Set, A

Operating Current, A

L1

L2

L3

30

15

Secondary Wiring Insulation Resistance: M

Tested By (Name & Signature) : __________________________________________ Witnessed By (Name & Signature) : __________________________________________ Date : : __________________________________________

Page 16: ABB HT FAT Proceedure

FACTORY ACCEPTANCE TEST

(HT SWITCHGEAR) AMARA HOTEL UPGRADING Project

Date: 28 Mar 2012 Rev.:0

16 of 19

4. OVECURRENT AND EARTH FAULT RELAY OPERATION TEST (T/F)

Particular of Relays:

Make

Type Tripping

Characteristics

Rating

S/No

O/C Relay

E/F Relay

Test Results of HT Installation: Panel No / Circuit Name: /

O/C Relay

E/F Relay

Plug

Setting A

Sec

Cur, A

Operation Time, sec

Plug

SettingA

Sec

Cur, A

Opn

Time, sec

TM

Setting

Std

Time, sec

L1

L2

L3

0.5

1.0

1.0

5

2

2

1.0

2.0

1.0

10

4

2

1.0

1.0

0.1

Plug Setting, A

Starting Current, A

Plug

Setting A

Starting

Current, A

L1

L2

L

0.5 1.0

1.0

2.0

High Set, A

Operating Current, A

High Set, A

Operating Current, A

L1

L2

L3

6

3

Secondary Wiring Insulation Resistance: M

Tested By (Name & Signature) : __________________________________________ Witnessed By (Name & Signature) : __________________________________________ Date : : __________________________________________

Page 17: ABB HT FAT Proceedure

FACTORY ACCEPTANCE TEST

(HT SWITCHGEAR) AMARA HOTEL UPGRADING Project

Date: 28 Mar 2012 Rev.:0

17 of 19

5. PILOT WIRE PROTECTION RELAY OPERATION TEST Particulars of Relays: Test Relay Make: Reyrolle Type: Rolkor R S/No.:___________

Dummy Relay Make: Reyrolle Type: Rolkor R S/No.:___________

Panel No. _________ Test Mode : ____________________________

Test Result

Relay Operating Coil Current Pilot Wire Secondary Operating

Current Amp D.C. mA Current

Test Relay Dummy Relay

Test Relay Dummy Relay AC mA

L1 - E

L2 - E

L3 - E

L1 - L2

L2 - L3

L3 - L1

Tested By (Name & Signature) : __________________________________________ Witnessed By (Name & Signature) : __________________________________________ Date : : __________________________________________

Page 18: ABB HT FAT Proceedure

FACTORY ACCEPTANCE TEST

(HT SWITCHGEAR) AMARA HOTEL UPGRADING Project

Date: 28 Mar 2012 Rev.:0

18 of 19

6. Attendance List

PROJECT: __________________________ FAT DATE:__________________________

NAME DESIGNATION COMPANY INITIAL

Page 19: ABB HT FAT Proceedure

FACTORY ACCEPTANCE TEST

(HT SWITCHGEAR) AMARA HOTEL UPGRADING Project

Date: 28 Mar 2012 Rev.:0

19 of 19

7. Customer comment & signed-off Form Remarks :

Tested By : 1. ________________________________________ (ABB Pte Ltd) Witnessed By : 1. ________________________________________

(Kurira Kogyo Co. Ltd) : 2. ________________________________________

: 3. ________________________________________