Abington Senior High School Construction Update Abington Senior High School Back-to-School September 19, 2019

Upload: others

Post on 18-Aug-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Abington Senior High School Construction Update€¦ · 9/19/2019  · Abington Senior High School •Interdisciplinary Wing and Library •The contractors completed their work on

Abington Senior High SchoolConstruction Update

Abington Senior High School

Back-to-School

September 19, 2019

Page 2: Abington Senior High School Construction Update€¦ · 9/19/2019  · Abington Senior High School •Interdisciplinary Wing and Library •The contractors completed their work on

Additions and Renovations to Abington Senior High School

• Interdisciplinary Wing and Library• The contractors completed their work on Wednesday, August 28, 2019

• The moving company, contracted by the District, moved furniture back into the classrooms on Thursday, August 29, 2019

• The Library shelves, furniture and books were in place by Saturday, August 31, 2019

• District staff arranged and cleaned furniture on Saturday, August 31, 2019

• Classes resumed on schedule Tuesday, September 3, 2019

• Lockers arrived and were put in place Tuesday evening, with installation completed Wednesday evening, September 4, 2019

Page 3: Abington Senior High School Construction Update€¦ · 9/19/2019  · Abington Senior High School •Interdisciplinary Wing and Library •The contractors completed their work on

Library Interior

Page 4: Abington Senior High School Construction Update€¦ · 9/19/2019  · Abington Senior High School •Interdisciplinary Wing and Library •The contractors completed their work on

Library Interior

Page 5: Abington Senior High School Construction Update€¦ · 9/19/2019  · Abington Senior High School •Interdisciplinary Wing and Library •The contractors completed their work on

Temporary Nurse’s Suite Room 162

Page 6: Abington Senior High School Construction Update€¦ · 9/19/2019  · Abington Senior High School •Interdisciplinary Wing and Library •The contractors completed their work on

Classroom Interior

Page 7: Abington Senior High School Construction Update€¦ · 9/19/2019  · Abington Senior High School •Interdisciplinary Wing and Library •The contractors completed their work on

Corridor

Page 8: Abington Senior High School Construction Update€¦ · 9/19/2019  · Abington Senior High School •Interdisciplinary Wing and Library •The contractors completed their work on

Corridors With No Floor Finish

• Removed Flooring

Page 9: Abington Senior High School Construction Update€¦ · 9/19/2019  · Abington Senior High School •Interdisciplinary Wing and Library •The contractors completed their work on

Corridors With No Ceilings

• Removed Ceilings

Page 10: Abington Senior High School Construction Update€¦ · 9/19/2019  · Abington Senior High School •Interdisciplinary Wing and Library •The contractors completed their work on

Main Corridor – September 5, 2019

Page 11: Abington Senior High School Construction Update€¦ · 9/19/2019  · Abington Senior High School •Interdisciplinary Wing and Library •The contractors completed their work on

Areas Being Renovated

• Administration

• January 2020

• Auditorium Lobby

• January 2020

• Audion and Nurse Suite

• January 2020

Page 12: Abington Senior High School Construction Update€¦ · 9/19/2019  · Abington Senior High School •Interdisciplinary Wing and Library •The contractors completed their work on

Additions and Renovations to Abington Senior High School

• Classroom Addition• The next section of structural steel started to be erected on Tuesday,

September 3, 2019

• Interior block walls are continuing

• Administration and Career Center Wing• Footings and foundations are continuing

• Underground sanitary and storm water piping is being installed

Page 13: Abington Senior High School Construction Update€¦ · 9/19/2019  · Abington Senior High School •Interdisciplinary Wing and Library •The contractors completed their work on

Structural Steel

Page 14: Abington Senior High School Construction Update€¦ · 9/19/2019  · Abington Senior High School •Interdisciplinary Wing and Library •The contractors completed their work on

Interior Block Installation

Page 15: Abington Senior High School Construction Update€¦ · 9/19/2019  · Abington Senior High School •Interdisciplinary Wing and Library •The contractors completed their work on

Administration and Guidance

Page 16: Abington Senior High School Construction Update€¦ · 9/19/2019  · Abington Senior High School •Interdisciplinary Wing and Library •The contractors completed their work on

Inspections

• Prior to the start of the school year following inspections were performed:

• Township Code Inspector for above ceiling inspections

• Township Fire Marshal for above ceiling inspections

• Township Code Inspector and Fire Marshal for occupancy inspections

• Montgomery County Health Department safety inspection

• During construction, occupied space indoor air quality testing is being performed

• Results can be found on the Facilities section of the Abington School District’s website

Page 17: Abington Senior High School Construction Update€¦ · 9/19/2019  · Abington Senior High School •Interdisciplinary Wing and Library •The contractors completed their work on

Facilities Notifications on ASD Website

• Resources related to annual notifications and results of water and air quality testing across District facilities can be found on the Facilities page of the ASD website

• AHERA (Asbestos Hazard Emergency Response Act) Notification

• Pesticide Notification

• Drinking Water Tests

• Construction Updates• Additions and Renovations to Abington Senior High School

• Occupied Space Indoor Air Quality Testing

• https://www.abington.k12.pa.us/administration/facilities/

Page 18: Abington Senior High School Construction Update€¦ · 9/19/2019  · Abington Senior High School •Interdisciplinary Wing and Library •The contractors completed their work on
Page 19: Abington Senior High School Construction Update€¦ · 9/19/2019  · Abington Senior High School •Interdisciplinary Wing and Library •The contractors completed their work on

Estimated Completion Dates

Classroom Addition

Fall 2020

Administration &

Guidance Addition

Winter 2020

Auxiliary Gym

Addition

Summer 2020

Cafeteria & Gym

Entrance Addition

Spring 2021Hig

hla

nd A

venue

Page 20: Abington Senior High School Construction Update€¦ · 9/19/2019  · Abington Senior High School •Interdisciplinary Wing and Library •The contractors completed their work on

Auxiliary Gymnasium Construction

New Traffic Patterns Starting

Early November 2019

Weekdays 6:30 AM – 2:30 PM:

The hill between the Gym and Stadium

will be closed to all traffic.

All other times:

The hill will be one-way only, with traffic flowing

toward Susquehanna Avenue. Construction

scaffolding will be erected on the roadway.

Construction Area:

The construction area will be enclosed

with fencing.