abstract this report summarizes the results of the startup ... · 3.3 thermal power measurement 12...
TRANSCRIPT
INDIAN POINT UNIT NO. 2
STARTUP PHYSICS TESTrREP9RT
CYCLE, 5
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. DOCKET NO. 50-247
AUGUST 1981
~. -~-x
810908007o7 810824 ( 7" PD ADc 05000247 P_____ PDR - ~--.~--'--~----7-
(' 'c (-,p
ABSTRACT
This report summarizes the results of the Startup Physics Tests
for Cycle 5 of the Indian Point Unit No. 2 reactor performed at
Hot Zero Power condition, and during reactor power level escala
tion. Results of these tests demonstrate adequate conservatism
of the Cycle 5 design for safe operation in accordance with the
Indian Point Unit No. 2 Technical Specifications.
Ai)
r,: ~
TABLE OF CONTENTS
PAGE8 NO.
ABSTRACT i TABLE OF CONTENTS ii LIST OF TABLES iii LIST OF FIGURES iv
1. INTRODUCTION
2. REACTOR CORE DESCRIPTION
2.1 REACTOR CORE CONTROL 4 2.2 REACTOR CORE INSTRUMENTATION 6 2.3 FUEL 6 2.4 CORE LOADING VERIFICATION 9
3. MEASUREMENT METHODS
3.1 REACTIVITY MEASUREMENT 10 3.2 CORE POWER DISTRIBUTION MEASUREMENT 12 3.3 THERMAL POWER MEASUREMENT 12
4. HOT ZERO POWER (HZP) TESTS
4.1 INITIAL CRITICALITY 13 4.2 END POINT BORON CONCENTRATIONS 16 4.3 RCC BANK DIFFERENTIAL AND INTEGRAL WORTHS 19 4.4 ISOTHERMAL TEMPERATURE COEFFICIENT 23 4.5 DIFFERENTIAL BORON WORTH 25
5 5. POWER TESTS
5.1- CORE POWER DISTRIBUTIONS 26 5.2 REACTOR COOLANT SYSTEM FLOW DETERMINATION 35
6. REACTOR INSTRUMENTATION CALIBRATION
38 6.1 EXCORE DETECTOR CALIBRATION 43 6.2 INCORE T/C AND WIDE RANGE RTD CALIBRATION 6.3 OVERPOWER AND OVERTEMPERATURE DELTA-T SETPOINTS 45
7. APPENDICES
A. CHRONOLOGICAL EVENTS 48 B. ACCEPTANCE CRITERIA 49
8. REFERENCES 50
(ii4
LIST OF TABLES
TABLE TITLE PAGE NO.
1.1 IP-2 Cycle 5 Startup Physics Test Program 2
3.1 Reactor Period and Reactivity Results 11
3.2 Delayed Neutron Data BOL Cycle 5 11
4.1 End Point Boron Concentrations 18
4.2 Control Rod Bank Integral Worth Summary 20
4.3 Isothermal Temperature Coefficients 24
5.1 Summary of Results of Incore Analysis, IP-2 Cycle 5 Startup Maps 27
5.2 Results of Reactor Coolant System Flow Determination at various Power Levels 37
6.1 Primary Loop Narr Range RTD Correction Factors as a Function of Tempe ture (OF) 44
6.2 Overpower And Overtemperature Delta-T 46 Setpoints
(iii)
LIST OF FIGURES
FIGURE
2.1
2.2
2.3
4.1
4.2
4.3
4.4
4.5
5.1
5.2
5.3
5.4
6.1
6.2
6.3
6.4
TITLE
Contol Rod Locations
In-Core Instrumentation, Thermocouples and Moveable Detectors
IP-2 Cycle 5 Core Loading Arrangement
Inverse Count Rate Ratio vs. Dilution Water
Inverse Count Rate Ratio vs. RCC Bank Position
Differential Rod Worth vs. Neutron Flux
Differential and Integral Bank D Worth
Differential and -Integral Bank C Worth
IP-2 Cycle 5 BOL and HZP Condition Power Map
IP-2 Cycle 5, 50% Power Map
IP-2 Cycle 5, 90% Power Map
IP-2 Cycle 5, 100% Power Map.
Excore Detector Current vs. Axial Offset Channel N-41.
Excore Detector Current vs. Axial Offset Channel N-42.
Excore Detector Current vs. Axial Offset Channel N-43.
Excore Detector Current vs. Axial Offset Channel N-44.
PAGE NO.
5
7
8
14
15
17
21
22
28
30
32
34
39
40
41
42
(iv)
- .- . . Ii
I
Indian Point Unit No. 2 attained initial criticality
for Cycle 5 operation on May al, 1981. The startup
physics test Program described in Table 1.1 was con
* ducted. The objectives of this program were:
(a) To demonstrate that the core parameters dur
ing reactor operation 'would be within the
assumption of the accident analyses in FSAR
(Reference 1) and within Technical Specifi
cation (Reference 2) limits.
(b) To verify the nuclear design calculations.
(c) To provide the bases for the calibration of
reactor instrumentation.
Section 2 of this report gives a brief description of
the reactor core and Cycle 5 core loading. Section 3
deals with measurement methods used in startup tests.
In Section 4, results from Hot Zero Power (HZP) phy
sics tests are presented and in Section 5, physics
tests at different power levels up to 100% power are
described. Reactor instrumentation (excore detectors,
incore thermocouples (T/C) and resistance temperature de
tectors (RTDs)) calibration is treated in Section 6.
The test results reported here are compared against
Westinghouse nuclear design results (Reference 3).
-1-M
7.41 M
Table 1.1
Indian Point Unit No. 2 Cycle 5 StartupPhysics Test Program Outline
1. Pre-criticality Measurements
Incore Thermocouple and RTD calibrations.
2. Hot Zero Power (HZP), Xenon'Free Condition Tests
2.1 Initial Criticality
2.2 Isothermal Temperature Coefficient at control rod configurations given below.
(i) All Rods Out (ii) Control Bank D In
2.3 End Point Boron Concentrations for control rod configurations given below.
(i) All Rods Out (ii) Control Bank D In
2.4 Control Rod Worth (Integral and Differential) Measurements
(i) Control Bank D (ii) Control Bank C with Control Bank D In
3. Power Ascension Tests
3.1 Excore Detectors Calibration at 90% of reactor power.
3.2 Movable Incore Detector Flux Maps at power levels .<l%,-50%,--90% and- 100% of reactor power.
3.3 Reactor Coolant Flow Measurement.
3.4 Overpower and Over Temperature AT Setpoints.
2
-2-
The acceptance criteria for the Cycle 5 startup tests
are given in Appendix B. These criteria are used as
guidelines for interpreting startup test measurements.
- 3 -
2. REACTOR CORE DESCRIPTION
The Indian Point Unit 2 core consists of 193 fuel assem
blies of slightly enriched uranium dioxide. Each fuel
assembly contains 204 fuel rods with zirconium alloy
cladding, 20 rod'.cluster control (RCC) guide tubes for
inserting control rods, and a central instrument thimble.
Cycle 5 contains 24 fuel assemblies containing 12 burnable
poision (BP) rods each for a total of 288 fresh burnable
poison rods. Burnable poison rods are composed of a
borosilicate Pyrex glass. Burnable poison rods are in
serted in assemblies to provide a negative moderator
temperature coefficient during reactor operations, to
control excess reactivity in the beginning of life, and
to improve the power distribution. Installation of two
primary neutron sources was required due to a projected
long outage during Cycle 4/5 refueling. Two primary
neutron sources at locations G-2 and J-14 and two 'sec
ondary neutron sources at positions H-3 and H-13 are
added to the loading to maintain.a minimum count rate
during core loading.
2.1 Reactor Core Control
In addition to the chemical shim control by boric
acid, dissolved in the coolant water, control and
shutdown of the reactor is accomplished by 53
full-length Rod Cluster Control Assemblies (RCCA's).
The -latter consist:of four control and four shut
down banks. Figure 2.1 is an X-Y cross section of
the reactor core describing-RCC bank positions. -4-
2115 14 13 12 11 10 9 8 7
1800
2700
SYMBOL
0 0 0
,V 0 C)
NUMBER OF ROD CLUSTERS
9
• 6
8
Figure 2.1 Control Rod Locations
-5-
p
BANK SA • SB
sci SD $C A
D
6 5,
2. REACTOR CORE DESCRIPTION (Cont'd)
2.2 Reactor Core Instrumentatilon
The reactor core instrumentation consists of
excore neutron detectors, six movable incore
detectors (M/D) capable of scanning up to 50
fuel assemblies through4 the central instru
ments thimble and 65 incore thermocouples
(T/C) to monitor exit coolant temperatures.
Figure 2.2 shows the incore instrumentation.
2.3 Fuel
Cycle 1 through Cycle 4 were operated with a
high-parasitic (HIPAR) fueled core. Beginning
with Cycle 5, the first transitional cycle, the
core was refueled with a low-parasitic (LOPAR)
fuel region. The Cycle 5 core contains 125
HIPAR fuel assemblies and 68 LOPAR fuel assem
blies;, (See Figure 2.3). The active core height
of the HIPAR assemblies is approximately 142
inches while that of LOPAR assemblies is ap
proximately 144 inches. The RCC guide thimbles
and instrumentation thimbles in HIPAR fuel are
of type 304 stainless steel welded to the In
conel-718 spring clip grids (9 per assembly)
and to the top and bottom assembly nozzles.
In the LOPAR fuel, the RCC guide thimbles
and instrumentation thimbles are Zircaloy-4,
* -6-
L
j
J
r
D
C
THERMOCOUPLE
E~1
MOVABLE DETECTOR
-FLOW-mIXING DEVICE
FIXED DETECTOR,
Figure 2-2 In-Core .Instrumentation and Movable Detectors
ThermOcouPles
-- 7"
I.
Figure. 2.3
A 8 C D E
I607 G37 da3 4 32g
SI !.337 334 iZP114 I 655 DO? FI6 D64 .343 R0687 R51
.. 04 F25 F-38 FI1 I 304 118 RZ8 42
GI 6-5 034 F44 E49 64( E31 F07 652 662 E38 F29 P0 46 4 9 ( 0 3 312 16epl3 R37 68, / |2PIO. !06 13 RIT I2Ptio 210 108 R43 1,Pt 303
r-ir E32 F20 E23 651 119 F37 E40 F47 0/3 640 E37 F&3 E25 416 306 R50 76 41 MPl3 R03 29 R30 15 FA948itzpp.Z 86 70 R'3 316 613 672 E44 F02 E02 F04 E04 FIO E47 F13 E28 F43 E50 C,54 619 313 f6oO R09 120 R29 88 74 127 207 3( 112 17 R20 4Poi 31
421 E55 F09 1961 F30 E18 F48 P71 F49 03 F33 V&5 F15 E05 631 321 R16 107 R19 12. R40 99 R26 208 PR24 // R7I 85 R33 331 60 764 E29 F6 2 E1 F64 E58 F57 E45 F?8 E43 F41 E 22G57633 3?0 imtnO R15 89 01 08 I2, 105 67 100 R12 79 1R07 !Ltop 333 (Z11 E57 F24 E17 1656 D43 F17 E20 F681050 GI1 E35 F31 E27 60Z 311 R04 104 82 ,ploq F?48 51 R53/6 RV Ri!p 07 3 R44 302
632 66I 21 P1 0 ,9 E59jFG67E 46 663 E.?G F5210671 467~ 64 332 1pio2 R.2 48 125 12i~yo RIO 166 9712P107 94 .27 R52 j:11 oa 1Ai.
I 17 FOS F ,6 {349 65 R45 (7,| 05 D01 F6C
305. 1?08 28 I 9 622
G09 16 1.3091,P
G H 'J K L M " N P R z' ' 0 ' ' '0V
25 344 336131013301 I I
R4 ilPI5 R3 4 0 7 E:9 ~ 3GE'G18 4124 R4 7 1 IP1151 R 14 'PR 394plo43 B
F42 1I_5
IF34VE10F39 j03 F54 E39 F53 1F51 -03 184 /2 175 IR40I205 1209196 IR341 36
750 60116 15
,5I7 317
640 340 335
I I I
.3281 291C38 32913291338
I I I
I I
izPl/e 3Ol11315 . 614 I I
1 iI
1800
P54 P.41
E40
129Fob
LEGEND
G66 = Assembly Number
16PI0I w Insert M
S/S= Secondary Source
P L P/ : Primary Source
D - REGION 4
E - REGION 5 F-- REGION 6 G - REGION 7
Insert Number With Letter P" in it,is a Burnable .-Poison Assembly.
-8-
(HIPAR) (HIPAR) (HIPAR) (LOPAR )
FIGURE N
270.0- -
FZ7EI iFI2rE42 FOL fP45F'4(P26 C08
I1! 36 . [R 13 ZO6 R46 40 1R49 308(726 32(.
G27 327
02 6 E3 4 ,#35 24 F55. 063 F14 ID52 1623 4 I L I5 13 Z
I
_p 02 .1669 E53 j 711 1_ _ k-pto5IR02(; [_ v,-F1o31F321
13
-12
- II
-10
-9!
-8 -6I
-5
-3 9 7
-2
-I
900
I
2. REACTOR CORE DESCRIPTION (Cont'd)
with type 304 stainless steel sleeves posi
tioned at each axial location of an Inconel
718 spring clip grid. The sleeves are welded
to the nine grids, spaced approximately equi
distant along the length of the fuel assembly.
The Zircaloy-4 thimbles are fastened to the
top and bottom nozzles.
2.4/ Core Loading Verification
Cycle 5 core loading verification was carried
out by monitoring the movement of each assembly
during actual core loading. The location of
each assembly as it was loaded into the core
was verified using a detailed procedure pre
pared from the Cycle 5 loading pattern., The
final core loading verification was carried
out upon the completion of core loading, by
viewing the television screen. The iden
tification numbers of 193 fuel assemblies
and BP insert numbers of assemblies bearing
BP rods and neutron source assemblies were
verified against the Cycle 5 design loading
pattern.
-9- .--
.'r - -. .... . .- .
3. MEASUREMENT METHODS
The reactor was maintained at the just critical state
during the physics measurements and the reactor power
was held constant via control rod/boron exchanges and/
or control rod/coolant temperature .exchanges. Small
changes in core reactivity during the test were moni
tored by a reactivity computer. The axial power dis
tributions in the instrumented assemblies were obtained
using the movable incore detectors.
3.1 Reactivity Measurement
The absolute measurement of small changes in
reactivity was provided by the on-line solu
tion of the point-reactor kinetics equations
using an analog reactivity computer. The com
puter was checked out by comparing the reacti
vity obtained from the reactor period with that
given directly by the reactivity computer. This
comparison is shown in Table 3.1. A good agree
ment between reactivities obtained from two
sources demonstrated the reliability of delayed
neutron data, given in Table 3.2, which were used
as an input to the neutron kinetics equations
of the reactivity computer.
-10-
Table 3. 1
REACTOR PERIOD AND REACTIVITY RESULTS
Doubling Time Reactor Period (sec) (sec)
164.2 64.0
237.0 92.0
Reactivity Predicted
(pcm)
26.2 57.6
Reactivity Measured
(pcm)
26.0 57.5
Difference (M-P) %)
P
-0.76 -0.17
M = Measured Value
P = Predicted Value
Table 3.2
DELAYED NEUTRON DATA BOL CYCLE 5
0.00177
0.001263
0.001137
0.002336
0.000807
0.000276
A1i (sec - )
0.0126
0.0308
0.1174
0.3148
"1.2503
3.3329
L*= 15.09/Asec (Prompt Neutron Life Time)
= 0.970 (Delayed Neutron Importance Factor)
peff = 0.005816.
- i -
Group
1
2
3
4:
5
6
• } .7
3. MEASUREMENT METHODS (Cont'd)
3.2 Core Power Distribution Measurement
The Movable Detector (M/D) Flux Mapping System
was used to collect power distribution data dur
ing start up tests at various power levels. Data
from the M/D system provided input to the INCORE 2
code (Reference 4) to generate three dimensional
core power profiles. The INCORE 2 code combines
measured flux distributions with calculated de
sign flux distribution to yield measured hot
channel factors and F,, quadrant tilt, core
average axial offset and relative assembly
power distributions.
3.3 Thermal Power Measurement
Core thermal power was determined by performing
a heat balance across each of the steam genera
tors. This measurement required the determina
tion of steam generator pressure, feedwater
inlet temperature, feedwater and steam generator
blowdown flow and other parameters.
- 12 -
4. HOT ZERO POWER (HZP) TESTS
4.1 Initial Criticality
The Indian Point Unit No. 2 Cycle 5 attained ini
tial criticality on May 21,, 1981. The criticality,
at beginning of life (BOL), and HZP condition, was
obtained by the sequential withdrawal of RCC shut
down and control banks and by subsequently diluting
the borated reactor coolant. During the approach to
criticality, ICRR (Inverse Count Rate Ratio) plots
versus dilution water and RCC bank position (Figures
4.1, 4.2), were maintained. Measured critical boron
concentration, xenon free BOL, HZP and ARO (All Rods
Out) core condition, was equal to 1367 ppm compared
to the design prediction of 1360 ppm (Reference 3).
The difference of 7 ppm between measured and design
boron concentrations was well within the acceptance
limit (+50ppm of design) for this measurement.
Neutron flux range for HZP test was determined by
the following method. The upper flux limit was de
termined by observing the effect of nuclear heating
which-decreased reactivity and increased reactor
coolant temperature. The upper flux limit for test
ing was set below the'flux value at which nuclear
heating was observed..' The flux level for nuclear
heating was determined to be above l. 5x10- Amps,
as shown in Figure 4.3. The lower limit was governed
-13 .
It I' j.
~I'
f~) ~ t
litl
~tt Ih
lit
t ..
v-un. p. *v
,1
II I I! I * I.
'~1 1~I
*1' .1 jt I~
i
46 6010
FLUX LEVEL(FWhPS)
C
-J Ij
MIA
W.E 5' -- *AI 70CILE DlVImONs
- I H 0't
~.J.
L~J
.4.1 it .J
A~~
4. HOT ZERO POWER (HZP) TEST (Cont'd)
by the background noise level. In the presence
of background noise the reactvity computer
* underestimates changesiin core reactivity.
The lower limit was determined by measuring
the differential worth of control bank "D"
at various neutron flux levels. As shown in
Figure 4.3, above the lower limit of zero power
physics range (10- Amp) differential rod worth
is essentially independent of flux level. HZP
Physics tests were carried out at a neutron
flux level between 10-' and 10- Amps. on the
Keithley picoammeter,.over this-flux range the
effects of nuclear heating and background noise
are absent.
4.2 End-Point Boron Concentrations
In Table 4.1, measured end-point boron concen
trations, for different control rod configur
ations are presented. The corresponding
design values, from Reference 3, are also
listed. The maximum-deviation, as shown in
Table 4.1, is 8 ppm. This satisfied the accep
tance criteria of + 50 ppm.
4.3 RCC Bank Differential and Integral Worths
-Measurements of the differential and'integral
worth of individual RCC control banks (C and D)
0 . -17
wir7
Table 4.1
End-Point Boron Concentrations
Configuration
All Rods Out
D In
(1) Measured
(Ppnf)
1367
.1278
(2) Design (ppm)
(i) - (2) Deviation (ppm)
1360
1270
77777
4. HOT ZERO POWER (HZP) TESTS (Cont'd)
were carried out via boron/RCC exchange, while
the reactor was in the critical state. The re
* activitycomputer trace provided the change in
reactivity during insertion/withdrawal of an
RCC bank. The differential worth of bank is .4
defined as the amount of change in reactivity
per unit step of bank position around an average
bank position. The integral control bank worth
was obtained by summing the differential worths
for the bank positions during the insertion
or withdrawal of the RCC bank. In Table 4.2,
the integral worths of individual control banks
"C" and "D" are presented along with the design
values. In Figures 4.4 and 4.5 differential
and integral worths of control banks "C" and
"D" are shown.
Measured integral worths in all cases are
within + 10% of design value, (Reference 3),
the acceptance criterion for the RCC banks.
4.4. Isothermal Temperature Coefficient
Isothermal temperature coefficient measurements
were carried out for two control rod configura
tions (All Rods Out, and control bank-D In). Mea
surements involved heatup and cooldown of the
19-
TABLE 4.2
CONTROL ROD BANK INTEGRAL WORTH SUMMARY
CONFIGURATION
ARO
D IN
(1) (2)
MEASURED DESIGN
Worth (pcm) Worth (pcm)
840 819
896 909
(1) - (2) (1)
DIFFERENCE
+2.50
-1 .45
BANK
D
C
I t'j 0
44i
20 X f0 TO TE~E ICH MP 7 ', loit WEKEUFFE TO ESSER IC- wc It; l
'HI~- J-~ ,I
I, -17
.1 *1
I
-.1
46 124.0
4
[7] VTi7 j77V171.7f7]I
I I
I I Ii I
ii
:1 :
... ,,
*1 ''I
~I I I*1 IL;
& (~ (j
- I.
~ ~ ~n
I ~ -~- K Lf~ -0
(f\ *1
It
I-c ~
- julri
In,
%A
jjI i!
j;!I
.. ..-- -- . I----I.I I. I 4
F71;
A~CAJ 7/h' Li
71 Tfl
I i
II
I I-
I-
I''~!* g F,, i
i t '
F!: .
(s?) 46 12410
I.;1A
-4
i -.
4
Ti
I
* I
i.-.II~ K1
KIN
I-'
I I
6, I
I Z:
* 20 X 2.0 TO THE INCii - ?XV WE I<UUFFLI & ESSE.R CUO m- IN -
I
4. HOT ZERO POWER (HZP) TEST (Cont'd)
reactor coolant. In Table 4.3, measured as well
as design values of isothermal temperature coef
ficients for All Rods Out (ARO) and Bank D In
cases are presented. Measured values are obtained
from the reactivity versus temperature curves
provided by an X-Y plot recorder. The design
values shown in Table 4.3 are from Reference 3.
Measured isothermal temperature coefficients
were all negative and within the acceptance
criterion of + 3 pcm of design values.
Using the design value of Doppler coefficient at
HZP condition equal to -2.48pcm/°F, moderator
temperature coefficients calculated from measured
isothermal temperature coefficients are equal to
+0.lpcm/°F, and -0.12 pcm/°F at the rod configu
rations of ARO and Control Bank D In, respectively.
The Indian Point Unit 2 Technical Specification
(Ref. 2) requires operation of the reactor at a
negative moderator temperature coefficient, in
the operating power range. Therefore, the allowed
boron concentration limit below which reactor
operation is permitted, is established using the
negative moderator temperature coefficient limit.
The maximum allowed boron concentration of 1350 ppm
required partial insertion of control bank D for
plant startup operation.
-23-
Table 4.3
ISOTHERMAL TEMPERATURE COEFFICIENTS
Configuration
ARO
D In, C Out
(1) Measured (IPCM/0 F)
-2.38
-2.6
(2) Design
(PCM/OF)
-2.4
-3.4
(1) - (2) Difference (PCM/°F)
+0.02
+0.80
S.- - ~1~"
- 24 -
4.5, Differential Boron Worth
Based upon measured end-point boron concentra
tions and control rod worth data given in Tables
4.1 and 4.2, the measured differential boron
worth was calculated t o be equal to 8.78pcm/ppm
at 1322 ppm boron concentration compared to the
design value of 9.15 pcm/ppm (Ref. 3).
-25-
5. POWER TESTS
The power measurement tests consisted of: (a) relative
assembly power distributions at HZP <1%,-50%,90%,-l00%
of full power; .and (b) reactor coolant flow determination.
5.1 Core--Power Distributions
The purpose of the low 'power flux map testing was:
1) to verify that the Cycle 5 core loading
pattern was correct.
2) to verify that quadrant power tilts, hot
channel factors, and relative assembly
powers met the acceptance criteria.
3) to verify the design calcuations
Table 5.1 is a summary of the calculated INCORE parameters
for the four maps.
5.1.1" Hot Zero Power Map
The low level power flux map (HZP map)
was taken at a core power below 1%. The
HZP map was taken at a power level at
the onset of nuclear heating with D-bank
at 198 steps withdrawn.
Figure 5.1 gives;the measured versus de
sign assembly power distribution for the
HZP map. The measured hot channel peak
ing factors met the IP2 Technical Speci
fication limit.
-26 -" "-: "-
Table 5.1
SUMMARY OF RESULTS OF INCORE ANALYSIS, IP2 CYCLE 5 STARTUP MAPS
APPROXIMATE Power (%)
Axial Offset (%)
Quadrant Tilt (%)
Measured Peak FW*
Peak Fq**
HZP
22.510 9.050
3.73
1.562
2.473
1.80
1.479
1.964
90 100
3.258
1.27
1.440
1.846
1.220
0.88
1.451
1.852
*Includes measurement uncertainty factor of 1.04 **Includes measurement and engineering uncertainty factor
of 1.0815
4..697. .952. 1.104.
S16,2 -123- --' 12 ; 3.
.. ,
ii
U'
''Hn"
.607.
N . 12.5.
M ~ ,. I.0 1.007*
M . 11.0
.7. 1,035,
L * 17.0. 9.6
. .965. .999 'K . . 8. 8.5
1.106. 1.261 -J. • 11.9. 11.4
1.144. 1.173
H 12.4. 11.9
1.095. 1.260 6 • 11.4.. 11.1
. . . , .
.888, .934
'F - 4.8. 4.6
• .651. 1.005
E • 8.5. 8.6
D. 11.9
.608 'C 13.9
31. 9
B'
A
.598. 1,002. 12.1. 12.0.
. .. • •.
.737, 1.236. * 11.9. 7.7.
1. 4 9• " "*7
1.256. 1,285. 8.7, 4.9.
.857o 1.196. .5. .3.
* . . •, . .
* 1.177. .961.
# 2.2. .1. . , .c o • . ,
.966. 1.101. 2.4. -4.0.
. . •. . .,
1.105. .867.
. -6. . - 6.
.969. 1.084. -. 8. -6.6.
, , .• , •.,
. 1.150. .904. 0 -. 5. -6*7. . . . •, . •.
* .895. 1.187. . 5.6. -. 5.
* • o. . , . ,
1.213. 1.218. * 5,7. -.6.
#.720, 1.243. .1 9.2. 7.5.
.627 1.045. 16.1* 15.2.
1.075. 16,2.
985. 16.2.
1.153. --3.4,
.920. -2.5.
1 . 057. -5.2*
.970. -6.4.
I • 166. --E .0.
"977, -6.t6.
1.052. -6.7.
.914, -3. 2?
1 4 1.1534. -3.*2.
826.
1 00 1 12, 1[
1 *2,52. 8.2.
.936.
-3,4, -. 4.
1.090" -3.4,
.861. -7.2.
1 • 138. -8 , 9.
I . 077. -10.2.
1.134. - :1. (.) 0.
.816. -12 ,0.
1 ,024. -8 2.
. . 1.# 005
* , , . . +
1 .269. 11•9.
. ,
1 057, El 3.
I. 0, 1 1 •.095.• -5.6.
.987. -5.7.
1,154. -8 4
.963. -11 .2.
1.059. -12.0.
- .9#
1.108. -11,4.
. 0,
*.945. -8.8.
1 •052. -8.*2.
.911. -3,4.
1.221, 7.8.
• . 4
* , 1.147. 12.7.
. .$
1,177. 12,3.
o 116o 1.116. .7,
o 860. -7,3,
1,174. -7*4,
1 * 068, -11.0.
1.053# -12.6.
•793. -13.1.
1.050. --12.8.
1,054. --12.1.
1,129. -10*9.
. , ,61
B861o -7,.2.
1.082, -2.4.
1.092. 4.2.
1.130. 14.3.
1,231. 8.7.
.901* -4.5.
1 082. -5*6.
.951. -8.3.
1.114. -10. .
.962. -11,3. .o .•
1*065. -11.5.
.960. -1 1 *
1.102, -12.6.
.930. -1i.I.
1 .098. --5,4,
.965. -1.2.
1.146.
1.1 S..,
.700. .974. 1,069. 1.097. 1,013. .866. .614.
• 13.9. 12.8. 8.2. 7.8. 3.1. 2.2. 2#3.
MEASURED' AND PERCENT. DIFF. OF FIHN If:'2 CY R 1 1
.969, 12,3..-
.964. 4.7,
. , ,
1.102. -4.4. S. , .
.918. -4 .4.
1.020. --8,5.
.818.
1,121. .-11,*1,
1 •068•
-10o9.
1 . 108 --11I.3.
.812. -12.5. . . •
.962. -14.8.
•945. -2.4.
1.147. -• 8•
.884. -1.0.
.687. 11.9.
1.000#
.885. 3.7,
1.194.'
.2.
.847. -10.2.
1. 013. -10,2.
.955. -8.7.
1.157. -8,7.
.945. -8 * 8•
1,002o
-10,1.
.924. -2.1*
1.168 -2•.1
.849. •.
.927.
* 2,
.972. 7.1.
1.231. 6,5.
1 , , 1,.253. 1
2.3. 0 " . 4 1.221'.
2.3.
.991. 2,4.
1,083o -6.7.
, , ,
852.
-8. 3.
1 • 044. -7.2.
.8139. -7.3.
1 . 167. -2. 1
1.215. -. 8.
1.181. 2.9.
.934. 4.4.
.590. 9,2.
.719. 9.1.
.241. 8.1.
•867'. 2".3.
I *•: 18:L•
2..2.
,973. -. 4.
4 , .
1 0090. -1.6.
.91 8. -2.7.
1 .096. -4#8.
.835. -2.1.
1.162. '.•
#695. 5.6.
.590. 10.6.
.608. 13.9.
1*020. 14.0.
945.
,949.
6,2.
1 * 198
5.7.
7.1.
1 .166. 2.9.
,943.
2.5.
.962. 1.9.
.91 1
,570. 5.6.
gj*
. r S
• I11FF
re 5.1 RI ,5-21"-61 HZFEDIN=I198 STEPS
4 #
.612. 2.0.
.905. 6.8.
1•042. 6.0.
1 .093. 7,5.
1.056,.
6.9.
1.1.
.676. 10,2.
-3.2. -5.8. , . 4. 1.076. 1.038.
14,0. 12.7..
• • . . • . • • # l • • , @ • • @+
5. POWER TEST (Cont'd)
The quadrant power'tilt met the ac
c6ptance criterion :of 4% for HZP
flux map (see Appendix B).
The Cycle 5 HZP map demonstrated an
in-out power tilt, which was also
present in the HZP maps of earlier
cycles. The acceptance criteria for
the measured assembly power distri
bution were +15% for relative assembly
power (Pi) < 0.9 and +10% for (Pi) > 0.9.
Due to the presence of in-out tilt some
periphery and interior assemblies ex
ceeded the acceptance criteria for the
measured assembly power distribution.
See Figure 5.1.
5.1.2 50% Power Incore Flux Map
A full core map was taken at 50% power
on June 2, 1981 with control D-bank at
210 steps withdrawn. Figure 5.2 gives
measured versus calculated assembly power
distributions for the 50% power map.
Measured hot channel factors and quadrant'
power tilt were within Technical Specifi
cation limits and were, therefore acceptable.
-29-
y SURED AND PERCENT. DIFF. OF VR R * . . . 9 •
R .-...... .. 8...
P • 9.5.
S.0 .732# N . 9.9. 9.3.
.990. 1.235# m 7.5. 6,5.
.695. 1.011. .857. ....-L . 9.6. 5.1. -.5.
# .929. .979. 1.153. K * 4,7. 3.2. -.5.
1.041. * ........ J." 3.8.
-: . • 1.070.
H 4.2.
"-,. . 1.054. -.I 0.* 5.8.
• I • .901. F. 3,5.
* .659.
1.180. .-937. 3#4-. -. 9.
1.093. 1.076, 3,8. -2.7,
+9--.. ., . .
1.207. .970. 5,7. -.8.
•-... •.-. .. . .
.951. 1.154. 3.3. -.6.
1.003 .sR.1'- E . 6.4. 6.4.
II * .991, SlD l 9,1.
..... -* . .. ..... • •607 1. ...... .C . .... . 11.0.
3.8. ",.. + ..
1.196.
.716. 70.
" .. .625, * 13,1.
+
A
8.2,
1.210. 5.1.
1.•252.
2.8.
1. 177, -.6.
.948. -. 7,
1.107. -2.4,
.882, -4. 1
1.099, -4.2.
o913, -5.2.
1 *168.
-1o4, I -!o I 1.2.01. -1#4#
1.9225. 5.6,
1.032. 12.0.
FDHN IP2 CYCLE
re 5.2
2 57 OE STARTUP MAF,DIN=210 STEPS 6C
.689. .931. 1.049. 1.084. 1.077, .946. .600. 11.3. 6.9, 5.3. 5.6. 7.5. 6,7. 7.3.
11.3. 6.6, 5.0. 5.3. 4,1. 1.8. 3.3. 4.7. 7.3.
.952. 11.3,
1.163. -1.9.
.916, -1.8.
1*060, -3.2.
.90. -3.7.
,1 . .
-4.7,
.985, -4. 1.
1.051. -5.2.
.912* -2,4,
1. 156. -2.4.
.840. -2.4.
1065. 10.8.
. . •
1.189. 1.001. 1.099, .915. 1,121, .877. 1.208, .718. .618. 2.3. 2.3. -#7. -3.2, -3,2. 1.9, 4.2. 7.3. 13.0.
•944. 1.109, .881,. 1,092. .924, 1.174, 1,231. 1.233, 1.027. -1.8, --3,3. -4.2, -3.7. -3.2. -.8 1.1. 7.1, 13.1. " + : ' .. .. ....... .. .. " 8 , : : . . . . 1.07, .993. 1.186. .971. 1.046, 8B4. 1.198 .863. .949. .623. -1.9, -3*3. -4.2. -4.6.l -4*6. . -5.4,. ....1.1,... .9. .7. .6.
.874. 1.173i 1.105. 1.152, .857. 1.048, .973. 1.171. .946. .898 -4.1. -4.6, -5.5. -5.5, -5.9# -5.4, 1.1, .B. 2.8. 3.2.
1.160, 1.001. 1.112. 1.007, 1,166. .. 993. 1.133. .980, 1.169. 1.022, -4,8, -5.8. -5.9. -5.3. --5.1. -3,4. -1.2. .1. 2.4. 2. 6.
1,109. 1.112, 862, 1.122, 1,115. 1•202. 896, 1,103. 1.065.. 1.061. -5.2, -5.9. -6.1, -5.1, -4*6. -2.9. -2.5, -. 2. 3,1. 3.3.
1.171. 1,002. 1.104. 1.002. 1.154. .987. 1.100. -. 933. 1.152. 1.036. -4.7. -5.7, --6.6. -5,8. --5.4, -3,0. -3.0. -1.4. 1.0. 3+4.
.853. 1.147. 1.093. 1.143. .852. i.050. .917. 1.115. 958. .939. -6,3, -5.9. -6.5, -7.0. ..-6,5# -4.2, -3o9, -3*7. 1.0. 5.8.
1.042, .967, 1.162. .964. 1,012. .920,. 1165. B7 69+0 ,6.+ .8 7 .970,.•671. -4.9. -5,0. -6,2. -6,2, -8.7. -16,. -1.7. .- 1.6. .9. 5.9.
.909. 1.079. .877, 1.104. .941. 1.166. 1.211. 1.165, .925. -+4,8, -4,8, -4.6. -3,8. --2.2. -1.6. -. 6. .4. .4.
1.118, .925. "1,083, .960: 1.140. .844* 1*145* -*672. .555. --3.5. -2.2, -2.0, -1.8. -18 . -1.3, ..-. 6. #4. 4.
1.026. 1.181. 1.067, 1.132. .903, .931. .894. .549. 8.1, 3., 1*4. -.9, -1.9. -1,3, -1, ..
.702, .959. 1,040, 1.063. .998, •861. -613. -~ -..---...-- ~ ... .-. MEAS. 10,7. 8.2. 3.8, 3.6. .2. -. 0. -1.0,
DIFF4 * ~. 99 -*' . ~9 *~ - .-. 9-r- 9--------------------
, . .
5. POWER TEST (Cont'd)
In-out power tilt fbr the 50% map was
reduced compared to HZP map; however,
a few :assemblies exceeded the measured
power distribution acceptance criteria.
5.1.3 90% Power Incore Flux Map
A 90% power map was taken on June 6, 1981
at approximately 150 MWD/MTU with bank-D
at 210 steps withdrawn. This map was a
base case map for the BOL Cycle 5 Incore/
Excore calibration. The measured hot chan
nel factors and quadrant power tilt were
within the Technical Specification limits.
The In-out power tilt was still present
in the 90% map. Figure 5.31 gives meas
ured versus design assembly power distr
butions for the 90% map.
5.1.4 100% Power Incore Flux Map
A 100% power map was taken on July 2, 1981
with control bank-D at 211 steps withdrawn
and burnup of 899.7 MWD/MTU. Measured hot
channel peaking factors and quadrant power
tilt were within the Technical Specifica
tion-limits. In-out power tilt present in
the 90% power map persisted in the.,100% power
31.-
O. i . . . . . . . .
MEASURED AND PERCENT DIFF. OF FDHN IP2 CYC! R 1,1
.... .................... 5 ' 9"9
: -- -4 4 599*
... ... ......... . ... 6 .7.
*.607. .730. N * 7.2. 6.5.
. .969. 1.203. - M 5.4. 3.8.
* .691-, .900 .849. L • 9.4. 3.8* -2.3.
.. . 919. .969. 1.144. K • 5,8. 3.2. -. 9.
. 1.022. 1.167. .945. J . 5.7. 5.4. -.4.
* 1.048. 1.088. 1.087,
r H 6.0. 5.7s -1.4. ._-4... 4 -..-. 4,..-..... 4
. 1.009* 1,160. * 955.
G * 4,8. 4.6. -2.5.
- . .856, .913. 1.131. F * ,0. -. 1. -2.4.
-- -- 4 .- 4.- .... ... 4. 4 4+ '''' ' I
. .647, .976. .885. E , 4.3. 4.3. 2.4.
" . .. * . .984. 1.191. -D , 8.3. 3.5.
61A. 725, C * 9.4. 5..9
- o -. 4 4
. .626. B .. .. 10.5.
A
..681..'915. _9_..8. 6.9.
.963. 1.028. .976. 6.0. 9.8. 6.7.
1.176. .949, 1.204, 2.2. 9.8. 3,9
4 . .l . , 4 •
1.217. 1,169. .958. o2. -1.6. -1.6.
1.158. .925. 1.093. -2.4. -2,3. -1.6.
.942. 1.059. .891. -2.4. -3.7. --4.0.
1.108. .989, 1.171. -3,0. -4.2. -4#9.
. . 4 , . • • , •
.897. -4,0.
14107. -4.1.
.924. -5.0
.•j .0
1.171. -1.4.
1.198. -- 1.4.
1.209. 4.4.
1.014. 10.4.
1,188. -4.7.
.999. -4.0,
19055.
1,114, -.5.7,
1.173. -544.
* . , 4
.856. -7.7.
,• . .--.• ,. o
.923. 1.061. -2.5. -3.5. ' ' , ' 9 24 1.157. .932. -2.5. -3.5.
". o o • . •
.848. 1.114. -2,4. -3.5.
1,049. 1.028. 10.2. 9.4.
rure 5.3
I5FC3 ,6-06-81,150 MWD B.U.,DBANK 210 STEPS
* * -. - .1 • 9 # f
1.031. 1,061* 1.056. -7.1o, 7.4, 9.2.
1.185. 1.102 ...1.165,6.8#. 7.1. .- 5.2.
Power
.939. ,680. 8.0* 7.7.
,. -, -4 4: ,. - . 4 - . .>..- ... .. .
,962. .984, .956. .601. 2.4. ...3.3. 4.1, 6.1.
1,018, 1.097, .912, 1,111. .802. 1,200l .727. .620. 3.9. -.5# -3.9. -3#8, 1,5, 3.6. 6*1. + 10,5.
1.122. .893. 1,097. .929. 1.174. 1.223. 1.216. 1.005. -2.8. -4.5, -4.0. -3,+8. -1.1. .6. 5.6. 10.6.
1,011, 1,192. .902. 1.042* .893, 1.195. .058 . 929. .615. -2,8, -4,4. -4.9. -5.3. -5.7. .6. -. 8, -. 8. -. 8.
1.185. 1.113. 1.160. .067. 1.047. ,966. 1.150. .945. .088.
-4.5, -5.8 -5,8, -6,5. -5.7. -. 7, -.8. 3*4. 3.8.
1.017. 1.122, 1.021. 1.1'71. .996. 1.112. .973. 1.147. .998.
-6.1. -6,7. -5.0. -5.6. -4.3, -3.7. --.7. 3.3. 3.7,
1.122. .879. 1.134. + 1.119. 1,195. .894. 1.096. 1.002. 1.042.
-6.7. -7.1. -5.7. -5.3. -4.1. -4.3. - -. 6. 5.1. 5.4. 4.-. .. .. , ,4.4 . .. . 4. 9. ... ..- .. . . 4... . . . .
1.017, 1.122, 1.024, 1,161. .988, 1.097i .935. 1.131. 1.014.
-6.1. -6.7. -5.4, -5.7, -4.2. -4.b. -1. 4. 2.2. 4.8.
.159. 1.104. 1.161. ,864, 1.043. .927.,1.120. .957. -".930.-
-5,9. -6.6o -6.4. -6,9. -5.2. -4.1. -3.0. 1.9. 7.0.
.991, 1,178. .982. 1.016. 934. 1.172. .858. .966, .677.
-3.9. -5.5. -5,6, -8.5, -1,4. -1.3. -1.3. 1.5. •7.1.
1,098. .904. 1i17..956, 1,172. 1.210, 1.164. .923.
-3.9. -3.3. -32., -1,8. -1.4. -. 4. .,. ..
.932, 1.089, ,970. 1.159. .872. 1,103. .719. .595,
-1.7, -1.3. -. 2.: -.0. .9. 2,8, 5.0. 5,0.
1.171, 1,060. 1.123. .913. .946. .946. .614. 5.7.- , 3.0, 1,2. •-.2. - 1.0. 4.2, 9.4.
9 4 9 ,
.696. .951. 1,025# 1,044. .992, -.882. .641. .. .. ... . ...... .. MEAS
10.2. 9.4. 6,0. 5.7. 3.0. -3.1. 3,3,.. . DIFF .-
.8. . 4 .
5. POWER TEST (Cont'd)
map and a few assemblies exceeded the meas
ured power-distribution acceptance criteria.
However, it did not violate the Technical
Specification limit for FO and thus does
not have an impact on the safe operation
of the plant. Figure 5.4 gives measured
assembly power distributions versus de
sign values.
5.1.5 Summary of Incore Flux Maps
Table 5.1 gives a summary of four Incore
flux maps(HZP,-50 90% and"-lO0% power)
results. Measured hot channel factors
F~H and Fa for all four maps were within
IP2 Technical Specification limits.
Quadrant power tilt for the HZP map was
3.73% which was within the acceptance
limit of 4% quadrant tilt for the HZP
condition, and for the three'other maps
(-50%,-90% and100%) quadrant tilt was
lower than 2%. In-out power tilt was
predominant at HZP, and in general was
smaller at higher power. The relative
assembly power distributions of a few
assemblies at the periphery of the core
exceeded the acceptance criterion, given
- 33 -
.;j
J :
L •
K
-o - J
H.
CA G •
uj.
I. E.
.598. 5.5.
.606. .730. . 5.9. 5.3.
.971. 1.198. 5.6. 3.1.
.o .701. 1.000. .846. 12.3. 5.5. -2.9.
.o S919. .952. 1.139. 8.2. 4.9. -. 9.
1.025. 1.183. .947. 7.7. 7.3. -.4.
1.056. 1.105. 1.094. 8.1. 7.7. -1.3.
., 1.023. 1. 189. .968.
7.8. 7.6. -i.4.
S870. .919. 1.141. 3.8. 3.8. -1.1.
.649. .988. .890. 5.8. 5 .8. 2.6.
.980. 1.178. 7.7. 2.0.
.615. .724. 8.4. 4.4.
.625 [ % i:.9.1.
.970. 1.050. 6.5. 12.4.
1.163. .975. .6. 12.4.
1.215. 1.162. -. 4. -2.9.
1.158. .925. -3.1. -3.8.
.945. 1.064. -3.2. -5.3.
1.095. .979. -5.0. -6.1.
.89 .1171. -5.7. -6.5.
1.096. .990. -5.8. -5.7.
.921. 1.062. -6.3. -6.3.
1.152. .923. -3.7. -4.1.
1.174. 1.146. -3.7. -4.1
1.191. .836. 2.5. -4.1.
1.021. 1.071. 11.0. 13.0.
.967. 9.3.
1.228. 6.4.
.955. -2.9.
1.101. -2.9.
.889. -5.5.
1.150.
-6.8.
i .092 -7.4.
1 .155. -7.1.
.860. -8.6.
1•051. -6.4.
916. -6.2.
1.098. -4.5.
1.015. 11.8.
1.206. 9.1.
1.045. 6.4.
1.111.
-4.5.
1 .003. -4.5.
1. 170. -5.9.
.999. -7.3.
S0;3 -7.8.
996. -7.5.
1. 139. -7.7.
•979. -6..0.
1 .083. -5. 9.
934. -1.8.
1. 184. 7.4.
5.4 IC4,100% POWER., 07-02-81,D-BANK=211, BU=899.
1.072. 1.065. 9.7.-- 11. 9-.
1.122. 9.4.
1.110. .2.
887. -6.0.
1. 176. -6.1 .
1.096. -7.0.
1.098. -7.4.
834. -7. 9.
1.089. -8.2.
1.083. -8.1.
1.162. -7.2.
.896. -5.0.
1.098. ". 9.
1.070. 4.3.
1.183.
7.3.
.913. -3.9.
1.097. -4.8.
.97 6 -6.4.,
1.147. -7.1.
1.002. -7.0.
1.105. -6.8.
1 .000. -7.1.
1.144 -8.0.
.977. -7.0.
1.124. -3.4.
986. .4.
1.131. 2.4.
• .690. .917. 1.038. --o--- 12 .4_ 9--5. ---9-.4.
.946. ...1 .'4.
.951. 4 .7.
.1. 106. -3.7.
•938. -3.9.
i.050. -6.5.
.868. -7.8.
1.155. -7.1.
1.096. -7.0.
1.141. -7.5.
860. -8.6.
1.022. -9.9.
970. -1.4.
1.161. .7.
893. .9.
•681. .9 2.
.985. 4.0.
.883. 1.3.
1.179. -1.3.
•894. -7.1.
1.054. -7.1.
.990. -5.8.
1 .179. -5. 9.
980. -6.0.
1 .041. -7.3.
953. -1.0.
1. 185. -1 .0.
.882. 1.6.
• 952.
1 9.
.950. 3.3.
1.194. 2.8.
1.210.
-. 8.
1.187. -. 8.
1.029. 4.7.
1.108. -4.8.
.888. -5. 9.
1.096. -4.8.
930. -4. 7.
1.175. -1.7.
1.207. -1.1.
1.182. 2.3.
949. 4.3.
. 705. .950. 1.025. 1.049. .991. .878. .643.
13.0. 11.8. 7.7.. 7.4. 4.5. 4. 8. 4.8.
Fig IMEASURED AND PERCENT. DIFF. OF FDHN IP2 C
R 1 1
(D
Ln
D
B
B
.60 4. 5.5.
.731. 5.4.
1.210. 4.7.
.908. 4.7.
1.207. 4.7.
992.
1.099. -. 7.
939 . -1.3.
1.123. -2.3.
.857. -1.7.
1. 148. -1.2.
.722. 4.0.
.620. 9.3.
.625. 10.2.
1.003. 10.2.
.978. 4.7.
947. 7.0.
i.170. 5.9.
1.090. 6.3.
1.146. 4.0.
.947. 4.3.
972. 2.5.
.909. -1.2.
.596. 4.0.-
4.
•EAS
•DLIFF.;
PER MTU -
.642. 4.7.
.899. 7.3.
1.007. 6.2.
1.041. 6.6.
1 .020. 7.2.
942. 10.9.
.692. 10. 9.
.. ,
5.0 POWER TEST (Cont'd)
in Appendix B, but the hot channel factor,
was below the Technical Specification
limit. All safety related core parameters
associated with power distribution such as
hot channel factors, Fh and Fj, and quad
rant tilt met the acceptance criteria for
the measured values and are, therefore,
acceptable. In-out power tilt present in
the flux maps discussed above will have
no safety impact on the Cycle 5 operation
as long as safety related core parameters
are within Technical Specification limits.
5.2 Reactor Coolant System Flow Determination
The Technical Specification (Ref.2) requires that
the total RCS flow exceeds 340,800 gpm prior to 98%
of licensed power. Prior-to achieving 98% of power,
a number of calorimetric data sets, Delta-T readings[
and elbow tap differential pressure readings were
taken and the corresponding RCS flow rate determined!
to ensure that the total RCS flow exceeds the re
quired flow rate of 340,800 gpm.
Since the elbow tap transducer measurements of the
reactor coolant flow rate, are-sometimes inconsis
tent an independent method using the reactor thermal.
power-program, plus the RTD data for coolant leg
4 -35-
5.0 POWER TEST (Cont'd)
Delta-T was used. Usingthe known reactor thermal
power (Q), enthalpies h(T.) and h(T ) at hot and
cold leg.temperatures, flow rate (W) is given by
W= Q h (T ) - h(T')
The volumetric flow rate, then, is the mass flow rate
multiplied by the specific volume, at cold leg tem
perature.
On June 6, 1981, with the reactor power at 90% of
nominal, the calculated flow rate using this method
was 379,250 gpm.
This exceeds the acceptance flow rate (340,800 gpm)
by a margin greater than the analyzed measurement
uncertainty of 4.2%, thus Technical Specification
requirements are met. Measurements made at other
power levels, using the calorimeter as well as elbow
tap methods are given in Table 5.2. The results con
sistently show the RCS flow rate to be greater than
what is required.
- 36 -
Table 5.2
RESULTS OF REACTOR COOLANT SYSTEM FLOW DETERMINATION AT VARIOUS POWER LEVELS
Reactor Power (%)
50.6
70.0
90.0
Measured .Flow(%) of Design Calorimetric Elbow Tap
Method Method
106.2
107.7
105.7
104.5
104.3
104.4
Note: Measured flow exceeded 100% of design flow even after taking into/account measurement uncertainty of 4.2%
- 37 -
~0~* -- - -~----.: ~ '..,-'----,.-"--
,,- -- - I
6. REACTOR INSTRUMENTATION CALIBRATION
The calibrations of excore power range detectors, re
actor coolant loop resistance temperature detectors
(RTD's) and incore thermocouples are presented:in this
section.
6.1 Excore Detector Calibration
An excore detector calibration using movable
incore detectors was performed at90% of full
power. A range of axial offsets were obtained
by inducing an axial xenon oscillation by rod
insertion and subsequent withdrawal, following
xenon buildup in the upper portion of the core.
A full core map was taken at equilibrium con
ditions prior to the onset of the xenon oscil
lation. Quarter core (partial) maps were also
.,taken at various axial offsets. The full power
total excore detector output currents were ex
trapolated from the currents-obtained at reduced
power levels. For each map, top and bottom de
tector currents for each detector were normalized
to the extrapolated full power current. Plots of
detector current versus the. axial offset calcu
lated by the INCORE 2 code are given in Figures
6.1 through 6.4. A linear least square fit using
the axial offset and excore detector current data
was performed. The results of least square fit
* -38.-
T. li II I
'ii a F ~ftEt~ft
VlT 71fl F 1TTIT
I
.5..,
., . ni*,IflJ'I, U dvd *gd tif
(A(
geOrOlsO 66VV4 uo -OOU OD ,oof xI XoI in, "nlgj I Dy,.ilgl :4-"i st f) Ki9f I ~ )3 "BNOIGIAII O OZ AS OUI 'SAVM JLONS H)Nt U.3d .9NOISI, I . OZ OW, (.N
.in!
Ii
F
I-..
I1
03
p.'
u rot
ti
0
NO. a10 So DIVISIONS PER INCH MUI WAYS. ibu UY 2011 DIVISIONS.
L,iTa ~/7tI~VHLj
I = IiT ~T TflTTTI~4.IiTi I
114 1 I
I' 2 ~
.::t .' j
!:
.
" " F:TfHI
'Iii'.li! FII I l
xC Jo ,IN STOCK DIlECT ROM CI;X 1o UK CU.. NORWOUD. MAbIA. 02062 So c IPRININU.S.A. GRAPH PAPER® A _____
I -T1 t17 Its
'Il.
-. :L " 1'! , c ' ' V7 '
J1 a
lal
111,113 [
*----
T .FT
', 1 I.F ' I I _. i it
M- --1 ,I I I
-i -T
.... : .141.
H~L I
iii FTf1l7II rt
liii Ii
L4
* *- U
ooz asvw1 aoomuom "o-, mobi ?.m, v:lb ll I Ijf ~~* n~~E*I1 fl'' kri fl'i -SVM 111011q liZIVJ ZVlf 1 S40Ibb1tr0' flI n
' ItT 41
STHi
mi!"!
,1
~LL 'wijji
-4 *1
V.
I ~
II
IA I ,
ORAPH PAPER a 0
t"~ie a
PUIN-C IN U.S.A.
I F 1.
V I H
F
-1-U'tt
lit, . " ! "4
-. .::
~ iT ' ".
"Ut. F
4H11
'liT
6. REACTOR INSTRUMENTATION CALIBRATION (Cont'd)
for top and bottom detector current vs-axial
offset were used to calibrate the-Delta Flux
(AI) Meters and Overpower Delta-T and Over
temperature Delta-T setpoints.
6.2 Incore T/C and Wide Ran@e RTD Calibration
During the Reactor Coolant System heatup elec
trical resistance of RTDs (including spares),
along with their lead wire resistance, core
exit thermocouple outputs and wide range RTD
amplifier outputs were monitored at approximately
50 0 F intervals from 320OF to 5250F. RTD resist
ances were converted into temperature using
factory-supplied calibration tables and were
plotted against time. The RTDs with minimum
correction factors were selected for use in
the protection and process circuits, and four
additional RTDs were selected for the saturation
meter. Table 6.1 shows the correction factors.
of each RTD from the average temperature for
data taken over 320OF to 525OF temperature
range. Incore thermocouples provide a continuous
on-line monitoring of assembly exit temperatures
of 65 assemblies which are about evenly.distri
buted throughout the core. Thermocouple and
wide range RTD correction .factors were obtained
by comparing their temperature readings with the
- 43 .
TABLE 6.1
PRIMARY LOOP NARROW RANGE RTD CORRECTION AS A FUNCTION OF TEMPERATURE (OF)
FACTORS
Temperatures
RTD
410A 411A** 412A* 410B 411B*
412B 420A*** 421A* 422A** 420B
421B 422B* 430A 431A* 432A**
430B 431B 432B* 44 0A** 441A*
442A 440B* 441B 442B
32,0 OF
-0.8 1.2 0.7 0.7
-0.4
-0.4
0.4 -0.5 -0.1
5.7 0.0 1.7
-0.1 -0. 1
-0.1 0.3 0.1
-0 0.4
0.1 0.2
-0.1, 0.1
4200 F
19.9 1.8 0.5 0.5
-0.3
-0.4
0.2 -0.8 -0.6
5.2 -0.5 4.2 0.2
-0.1
-0.1 0.3
0.2 -0.1 0.1
0.1 -0.2 -0.2 -0.2
470°F
-20.8 1.7 0.5 0.7 0.
-0.1
-0.3
-0.6 -0.2
5.5 -0.2 4.3 0.2 0.2
-0.4 0.1
-0.1 0.2 0.1
0.2 0.2 0.1
-0.1
Note:. *RTD **RTD ***RTD
initially used for protection'system used for RCS Saturation meter capped Correction factor = Best estimate temperature - measured temperature-
- 44 -
525°F
-0.9 1.0 0.6 0.6
-0.1
-0.5
-0.'5
-0.6 -0.3
5.6 -0.1 4.3
-0.1 -0.3
0.3
0.4 0.2 0.3
-0.
0.3 -0 -0.1 -0.4
777'
6. REACTOR INSTRUMENTATION CALIBRATION (Cont'd)
narrow range RTD readings taken during the
heatup of the primary coolant system.
6.3 Overpower and Overtemperature Delta - T Setpoints.
Reactor coolant Delta-T measurements, which are
used to determine the overpower and overtem
perature Delta - T setpoints were performed dur
ing power escalation. Thot and Tcold were measured
in volts and then converted into degrees Farenheit.
Delta-T, which is (Thot - Tcold), was plotted
against the power level-, up to 90% power for each
loop. The Prodac-250 computer Delta-T readouts for
each loop were also plotted on the same graph to give
additional data points.
The full power Delta-Ts used for the setpoints were
obtained from best estimated values extrapolated
from 90% power. Table 6.2 shows the Delta-T
setpoints for each loop.
-45-
TABLE 6.2
OVERPOWER AND OVERTEMPERATURE DELTA-T SETPOINTS
LOOP
21 22 23 24
AT (-F)
51.0 51.0 50.0 50.5
- 46 -
'S ~S
APPENDICES
- 47 -
d ; I -
APPENDIX A CHRONOLOGICAL EVENTS
DATE
10/17/80 12/30/80 2/21/81 5/14/81 5/14/81 5/18/81 5/19/81 5/19/81 5/21/81
5/21/81 5/21/81 5/21/81 5/21/81 5/21/81 5/21/81 5/21/81 5/21/81
5/21/81 5/22/81 5/22/81 5/22/81
5/22/81 6/02/81 6/06/81 6/07/81 7/02/81
TIME
8:26 9:30 8:30
11:00 5:45 7:40
7:45-11:02 11:02
13:07-14:35 14:35-15:10
19:30 20:00 22:30
23:50 1:45 3:45 4:30
5: 22-7: 20 10:22
14:32 6:20
14:57
TEST DESCRIPTION
Reactor Shutdown (End of Cycle 4)o Fuel Shuffle started Fuel Shuffle completed RC4 Flow Elbow tap data taken RTD and Thermocouple data @ 5250 F RTD and Thermocouple data @ 320°F RTD and Thermocouple data @ 420OF RTD and Thermocouple data @ 470OF Start RCC withdrawal to ARO condition Start to dilute boron to criticality Monitoring approach to criticality Reactor Critical Zero Power Testing Flux Range Reactivity Computer Check HZP Flux map completed ARO boron endpoint Isothermal temperature coefficient (ARO) Start control bank D measurement End control bank D in Boron endpoint bank D in Isothermal Temperature Coefficient, bank D in Control bank C worth measurements.1 50% Power Flux Map completed 90% Power Flux Map completed Incore-Excore data collection completed 100% power flux map completed
- 48 -
U-.
L ~|
Appendix B Acceptance Criteria
Parameter Acceptance Criteria
1. Boron Endpoint (a) ARO (b) Control Bank D In.
2. Integral Rodworth (a) Control Bank D (b) Control Bank C
3. Isothermal Temperature Coefficient
4. HZP (a) (b) (c)
Incore-Flux Map
Fq Quadrant tilt*
5. At Power Incore Flux Maps (a) FO (b) Fq (c) Quadrant tilt
Within +50 ppm of design value
Within +10% of design value
Within + 3 pcm/°F of design value
Within Tech. Spec. Within Tech. Spec. Less than 4%
Within Tech. Spec. Within Tech. Spec. Less than 2%.
* At HZP, higher quadrant tilt is anticipated.
criteria is based upon analysis.
limits limits
limits limits
Acceptance
Note: Acceptance criteria are guidelines which are used to
assist in evaluation of startup physics tests results.
- 49 -
8. REFERENCES
1. Docket No. 50-247 Final Facility Description and
Safety Analysis Report, Consolidated Edison Com
pany, of New York, Inc., Indian Point Nuclear Generating Unit No. 2
2. Docket No. 50-247 Technical Specifications as amended through Amendment No. 70 to Facility Operating License No. DPR-26 (Appendix A), Consolidated Company of New York, Inc., Indian Point Nuclear Generating Unit No. 2.
3. "Indian Point Cycle 5 Nuclear Design Report" by M, A. Kotun, L. L. Phelps, M. F. Muenks - WCAP-9881 May 1981.
4. The INCORE code by W. D. Legget, etal WCAP-7149 Rev., ..February 1972.
- 50-