Department of Social Welfare and DevelopmentM.H. Del Pilar St., Molo, Iloilo City
KC-NCDDPACCOMPLISHMENT REPORT
For the Period from September 22, to September 30, 2014
Area Municipality : NabasSRPMT Province : Aklan
Date Planned/Target Activities
StatusRemarks/Reasons PINCOS
Status
Accomplished Not Accomplished
Not Resolved (Why)
Resolved (How)
Sept. 22
Roll-out and pre-deployment
training for Area Coordinating team
/
Training is intended to pre-deployment for Area coordinating teamDay 0 – Expectation, Rules during the Training including House Rules, Discuss the Objective. Perform Activities to know more the participants in Cluster 4.
Sept. 23
Roll-out and pre-deployment
training for Area Coordinating team
/
Day 1: host team group 1, recapitulation of yesterday activities.Resource person, Mrs. Joy Velasco, discuss the Self-awareness, our role in life to know, to love, to serve; God, our self and the people around us. Performed and discuss Team building.
Sept. 24
Roll-out and pre-deployment
training for Area Coordinating team
/
Day 2: Host team group 2 Recapitulation of yesterday activities Resource person Mr. Nante M. Lasay discuss the poverty situation in the Philippines and the National Strategy to solve this problem. Roles of ACT members and Discuss the NCDDP program and CEAC.
Sept. 25 Roll-out and pre-deployment
training for Area
/ Day 3: Host team group 3 Recapitulation of yesterday activities. CEAC Demonstration Activity followed by discussion of;
![Page 2: Accomplishment Report Sept.22-30 2014](https://reader036.vdocument.in/reader036/viewer/2022081816/55cf9402550346f57b9f12b1/html5/thumbnails/2.jpg)
Coordinating team
Stage 1, Social Preparation stage1.1 Municipal orientation1.2 Consultation Meeting on disaster impact &
Barangay ranking allocation1.3 Community consultation (1st Barangay (BA)) Stage 2. Community planning & project proposal development2.1 Municipal forum2.2 Project Proposal Development (PDW)2.3 Community Consultation (2nd BA)2.4 Subproject Final Technical Review & Approval for Fund Release
Sept. 26
Roll-out and pre-deployment
training for Area Coordinating team
/
Day 4: Recapitulation of yesterday activities. CEAC demonstration followed by discussion of;Stage 3 Community–managed implementation and Organization formation and Development3.1 Barangay Assembly & Action Planning3.2 Community-managed Implementation of Projects3.3 Formation of Community Organization for Operation and MaintenanceStage 4 Community Monitoring4.1 Accountability Reporting
Sept. 27
Roll-out and pre-deployment
training for Area Coordinating team
/
Day 5: Recapitulation of yesterday activities. Project Proposal Development the process of determining and designing of the most appropriate & responsive solution to the community.Community Managed and Implementation of Sub-projects.
Sept. 28 Roll-out and pre-deployment
training for Area Coordinating team
/ Day 6: Recapitulation of yesterday activities.Community-managed implementation andorganization format and development CBO, CBFM, O&M, M&E
![Page 3: Accomplishment Report Sept.22-30 2014](https://reader036.vdocument.in/reader036/viewer/2022081816/55cf9402550346f57b9f12b1/html5/thumbnails/3.jpg)
Sept. 29
Roll-out and pre-deployment
training for Area Coordinating team
/
Day 7; GEO Tagging, GRS components, administrative matters, Accounting budget cash and forms
Sept. 30
Roll-out and pre-deployment
training for Area Coordinating team
/
Planning ,Re-entry planning objective done
Submitted by : Checked and Noted by : Approved by :
FREDD SHERWIN N. PANIM MARILEE TROMBINI SHARON T. TUSALEMCommunity Empowerment Facilitator Area Coordinator Regional Project Coordinator