achievements - gob achieveme… · achievements ministry of transports and communications three...
TRANSCRIPT
2015
ACHIEVEMENTS
Ministry of Transports and Communications
Three Years and a Half of Government
(August 2011 – December 2014)
Lima, February 2015
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
1
Table of Contents
I. Results Report …................................................................................................................................... 3
II. Main road projects.................................................................................................................................. 6
2.1 Road rehabilitation and improvement................................................................................................................................... 6 ..
2.2 National Road Network Paving…………....................................................................................................... 9
2.3 Longitudinal Road of the Highlands............................................................................................................. 10
2.4 National Road Network Maintenance…….......................................................................................................14
2.5 Support to Regional and Local Government’s Management ….................................................................... 15
III. Rail Transport ………............................................................................................................................ 17
3.1 Lima Metro…................................................................................................................................................ 17
3.2 Huancayo – Huancavelica Railway….......................................................................................................... 20
IV. Water Transport…. ............................................................................................................................. . 20
4.1 Private Investment in Ports............................................................................................................... 21
V. Air Transport….. .................................................................................................................................. 23
5.1 Investment in airports…............................................................................................................................... 23
VI. Telecommunications................................................................................................................................................................................... 26
6.1 Signing of Concession Contract for National Optical Fiber Backbone Network …….................................. 26
6.2 Signing of Concession Contract for 1.7/2.1 GHz band to provide 4G-LTE service ...…..……….. .............. 27
6.3 Signing of Concession Contract for 900 MHz band.............................................................................28
6.4 700 MHz Band Tender …………................................................................................................................ 29
6.5 Virtual Mobile Operators …… ..................................................................................................................... 29
6.6 Concession Contract Renewal for Telefónica Moviles ……….................................................................... 30
6.7 Awarding of Amazon Region Integration Project …................................................................................... 30
6.8 Awarding of Regional Optical Fiber Backbone Network............................................................................. 30
VII. Concesions........................................................................................................................................ 32
VIII. Private initiatives …............................................................................................................................. 33
8.1 Peripheral Ring Road.................................................................................................................................. 34
8.2 Central Economic Corridor …….................................................................................................................. 34
8.3 Road Corridor PE-3N Junction (Dv. Las Vegas) – Tarma – La Merced – Raither Bridge – Villa Rica – Dv. Puerto Bermúdez – Von Humbolt / Raither Bridge – Pichanaqui – Dv. Satipo – Puerto Ocopa………….……….... 34
8.4 Mass public transport system in the city of Arequipa……………………...........................................................34
8.5 Intelligent Transport System (ITS)............................................................................................................................35
8.6 Modernization of Salaverry Port Terminal...................................................................................................... 35
8.7 Ica - Dv. Quilca Road Corridor…………………...................................................................................................35
8.8 Container Terminal of Chimbote……….…….......................................................................................................35 8.9 Multi-Purpose Ilo Port Terminal ……….……........................................................................................................36
IX. Investment-Related Public Budget Execution...……………....................................................................................... 36
X Outstanding Projects…............................................................................................................................ 36
10.1 Granting of Regional Optical Fiber Networks…………………………………………………………………… 36
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
2
10.2 Awarding of 700 MHz band to provide cutting-edge mobile Internet (4G – LTE technology).............................................................................................................................................................. 38
10.3 Awarding of Block C of 1.7/2.1 GHz band to provide cutting-edge mobile internet (4G – LTE technology)…........................................................................................................................................................... 38
10.4 Awarding of Third Airport Group …..…………............................................................................................ 38
10.5 Inclusion of Amazon Region by Air ............................................................................................................ 38
10.6 Expansion and Modernization of Jorge Chavez International Airport (AIJCH)........................................... 39
10.7 Improvement of Avenida Santa Rosa (including Bridge over Rimac River)……… .......................................... 39
10.8 Move forward with consolidation of Lima’s Metro Network......................................................................... 39
10.9 Support to road management by subnational governments……................................................................ 40
10.10 Other pending issues…...............................................................................................................................40
“Decade of the Disabled Persons in Peru”
“Year of Promotion of Production Diversification and Education Strengthening”
3
ACHIEVEMENTS
Three Years and a Half of Government
(July 2011 – December 2014)
I. Results Report
During these three years and a half of government, the Ministry of Transport and
Communications (MTC) has given priority to investments in infrastructure and services, with a
multi-modal approach, organizing its operations under the Transport Logistics Services
Development Plan, which was conceived as a planning tool to address the challenges in
developing transport logistics and the related industry, to thus contribute to boosting the
country’s production capacity and to increasing its competitiveness, specifically by reducing
the logistics costs.
“Decade of the Disabled Persons in Peru”
“Year of Promotion of Production Diversification and Education Strengthening”
4
Flagship Projects
The 3,497 km long Longitudinal Road of the Highlands, which connects Desaguadero on
the border with Bolivia with Vado Grande on the border with Ecuador, will be paved
throughout its entire length, thereby contributing to providing favorable conditions for
improving production competitiveness in the Andean region, ensuring the population’s
permanent access to basic services, and offering millions of Peruvians a better quality of
life.
The Optical Fiber Backbone Network, whose concession was awarded in December 2013,
is also a flagship project, which implies laying 13,500 km of fiber optical cable across the
country; it will provide all province capitals with access to broadband technology; another
one of the sector’s flagship projects is the second line of the Lima Metro, whose concession
was granted in March 2014, and which will directly benefit more than one million passengers
a day, offering users considerable benefits and contributing to solving Lima’s urban
transport problems.
Achievements The main achievements by the MTC during the last three years and a half of government (August 2011 – December 2014) are summarized below:
Transport
During this period, 5,054 km of roads changed their category from unpaved to paved.
With this, the country reached a total of 17,411 km of paved roads, which is equivalent
to 75.5% of the National Road Network available¹ as of July 2001 (23,072 km).
The achievement during this period, i.e., the paving of 5,054 km of roads, exceeds the
achievements during the five-year period from 2006 to 2011, during which only 3,721
km were paved. By July 2016, the amount of paved kilometers is expected to double the
amount achieved in the preceding five-year period.
With respect to the total number of procedures in the National Road Network
(improvements, rehabilitation and change of category), during the previous five-year
period 8,194 km were involved, while the current administration, during the last three
years and a half, has included a total of 7,460 km; it is expected that by the end of this
administration period a total of 9,500 km of national roads will have been included.
1 National Road Network available as of July 2011: 23,072 km
“Decade of the Disabled Persons in Peru”
“Year of Promotion of Production Diversification and Education Strengthening”
5
During the period from August 2011 to December 2014, 947 km of the Longitudinal
Road of the Highlands were paved, thus reaching a total of 2,946 km, equivalent to
84.1% of the longitudinal road’s total (3,503 km).
Another achievement was maintenance work done on a total of 23,687 km of roads
from the National Road Network, of which 13,911 km involved service-level
conservation for five-year periods (38 contracts and 1 agreement with the Regional
Government of Cusco), 4,931 km involved concession contracts for periods of over 25
years, and the remaining 4,845 km receive routine maintenance from Provías
Nacional’s Zone Units.
Communications
The Concession Contract of the Optical Fiber Backbone Network was signed and
currently 13,500 km of fiber optical cable is being laid, which will provide the
infrastructure required for broadband-based massive data transmission and internet
access in 92% of the country’s province capitals (180 of the country’s 195 province
capitals).
Moreover, the concession contract for the 1.7/2.1 GHz band for implementation of 4G-LTE technology has been signed, which makes high-speed mobile internet possible (up to 10 times faster than prior technologies implemented in the country).
Concession Contract was signed and the 900 MHz band was assigned to the 4th mobile
telephony operator, which improves the mobile service offer for users, who now have a
new alternative to choose from.
Properties for the period (January 2015 – July 2016)
As priorities for the government period (August 2014 – July 2016), the following goals set
for 2016 were ratified in the Sector:
Achieving the strategic objective of paving 85% of the national roads (note that as of
July 2011 only 53.6% were paved), which is why 2,824 km are expected to be paved.
Achieving the strategic objective of paving 100% of the Longitudinal Road of the
Highlands (3,503 km), for which 558 km are expected to be paved.
Moving forward with the consolidation of Lima’s Metro network, continuing construction
of Line 2 and granting the concession for construction of Line 3, which – according to
studies performed – concentrate most of the city’s demand for public transport.
Furthermore, baseline studies for Line 4 of Lima’s Metro will be prepared.
“Decade of the Disabled Persons in Peru”
“Year of Promotion of Production Diversification and Education Strengthening”
6
Consolidating the Optical Fiber Backbone Network, which will comprise installation of
13,500 km of fiber optical cable to connect Lima with 180 province capitals, at a
national level, and moving ahead with the implantation of the Fiber Optic Regional
Networks, which will provide 1,800 district capitals throughout the country with data
transport and access to telecommunications services.
The investments committed during this 5-year period reach APPROXIMATELY
US$22,000 million in the Transport and Communications sector, through public works
and private public associations.
Goals for 2015
The sector has itself the target of achieving the following goals in 2015:
Starting construction of the Chincha – Pisco highway (Second Stage) and Pisco – Ica (Third Stage) of the Road Network No. 6.
Starting construction of the Pisco Port Terminal (First Stage). Awarding the following transport concessions:
Stretches 4 and 5 of the Longitudinal Road of the Highlands, planned for the end of 2015
Monorail-Type Rapid Mass Transport System, Arequipa
Huancayo – Huancavelica railway
II. Main road projects
NATIONAL ROAD NETWORK
2.1 Road rehabilitation and improvement
During the administration period from august 2011 to December 2014, 5,646 km of national
roads were rehabilitated and improved, with an investment of PEN14.64 billion, including both
public and private investment (concessions).
“Decade of the Disabled Persons in Peru”
“Year of Promotion of Production Diversification and Education Strengthening”
7
ROAD REHABILITATION AND IMPROVEMENT FROM NATIONAL ROAD NETWORK
AUGUST 2011 – DECEMBER 2014
PROCEDURES PHYSICAL PROGRESS (km) FINANCIAL PROGRESS
Rehabilitation Category
Change
Rehabilitation and
Improvement
NON-PRIVATIZED NRN
359 1,159
1,517
9,237,135
233 364
597
PRIVATIZED NRN
290
290
5,403,216
TOTAL PAVED
592 1,812
2,404
14,640,350
NON-PRIVATIZED NRN**
3,241
3,241
TOTAL REHABILITATION AND IMPROVEMENT
592 5,054
5,646
(*) Projected
(**) The category change corresponds to improvement of roads by paving, at basic solution level, implemented with the Service-Level
Maintenance Contracts under responsibility of Provías Nacional – UGC and financed by the regular budget.
Note: The 597 km of non-privatized NRN (National Road Network) correspond to updates and reclassification of routes.
Roads implemented with public resources:
From August 2011 to December 2014, rehabilitation and improvement works for 35 roads from the National Road Network were finished. The following are the most important ones:
7 stretches of Ayacucho - Abancay Road (371 km, Ayachucho, Apurimac) 4 stretches of Chongoyape – Cajamarca Road (203 km, Cajamarca) Punta de Bombón – Fundición – Ilo Road (91.6 km, Arequipa, Moquegua) Otuzco – Callacuyan Road (70 km, La Libertad) Alfamayo – Chaullay – Quillabamba Road (54 km, Cusco) Quinua – San Francisco Road, stretch from km 26 to 78.5 (50.9 km, Ayacucho) Reither Bridge – Paucartambo Bridge – Villarica Road (39.4 km, Junin and Pasco) San Ignacio – Integración Bridge Road (37.7 km, San Martin) El Descanso - Langui Road (19.8 km)
During this government period, rehabilitation and improvement works were initiated and completed on 15 roads of the National Road Network, totaling 677 km, which are as follows:
3 stretches of Ayacucho - Abancay Road (180.4 km, Ayacucho, Apurimac) 2 stretches of Cajamarca – Celendin - Balzas Road (68.8 km, Cajamarca) San Ignacio – Integración Bridge Road (46.0 km, Cajamarca) PE-1N junction stretch (Rio Seco Roundabout) – El Ahorcado – Sta. Rosa – PE-18
junction (Dv. Sayan) (42.6 km, Lima) Pizana – Tocache Road (37.7 km, San Martin) Cochabamba – Chota Road (31.9 km, Cajamarca)
Mala Calango – La Capilla Road (25.5 km, Lima)
“Decade of the Disabled Persons in Peru”
“Year of Promotion of Production Diversification and Education Strengthening”
8
Appendix 1 presents a list of completed roads.
Furthermore, during the current administration, rehabilitation and improvement works on
21 roads have been initiated supported by direct public investment, of which the most
important ones are the following:
Lima – Canta Road (175.6 km)
Huaura - Sayán - El Tingo Bridge Road (99.3 km, Lima)
Quinua – San Francisco Road, km 78,500 – 172,420 (94.6 km, Ayacucho)
Dv. Quilca – Matarani Road (94.5 km, Arequipa)
Dv. Imata – Oscollo – Negromayo Road (67.7 km Arequipa, Cusco)
Satipo – Mazamari – Dv. Pangoa Road (65.8 km, Junín).
Chota - Bambamarca – Hualgayoc Road (58.9 km, Cajamarca)
Imperial Pampas Road (36.9 km, Lima)
Appendix 2 presents a list of roads under implementation.
Roads implemented with private investment – concessions:
With regard to road concessions, there are 16 contracts for 6,852 km and an investment
commitment of US$4,241 million as of December 2014. The main progress and
achievements are as follows:
In April 2013, the second lane of the ‘’Autopista del Sol’’ (Sun Highway) was opened at a 29-km stretch from Piura to Sullana; it was implemented with an investment of US$28 million and will benefit more than 1,676,315 locals.
Additional works were carried out at the Southern Interoceanic Highway (IIRSA Sur):
in Stretch 3, lighting for the Billinghurst Bridge and river defenses for the Mavila and Tahuamanu bridges; in Stretch 4, the 750-m-long Socostaca Tunnel and the 460-m-long El Carmen Tunnel; and in Stretch 5, the Bello Bridge and access roads and the rehabilitation of the critical sector of San Camilo, located in the section Matarani – Southern Pan-American Highway junction. Additionally, in Stretch 1 the Ucros beltway, and in Stretch 4 the 750-m-long Wayrasenca Tunnel are about to be completed.
In February 2013, the construction of Tarapoto’s beltway (13.7 km) was completed, including the bridge of the same name (95 m).
In November 2013, construction of the access road to the New Port of Yurimaguas
(10.0 km) was completed, with an investment of US$30 million, comprising also a modern 110-m-long Metal Arch Bridge without central support over the Paranapura river.
In May 2013, the highway on the 70.7 km stretch from Casma to Huarmey was
opened, with an investment of US$36.8 million. Additionally, in December 2014, Stretch IV of the Pativilca – Huarmey road of Road Network 4 was opened,
“Decade of the Disabled Persons in Peru”
“Year of Promotion of Production Diversification and Education Strengthening”
9
corresponding to the second lane. This work demanded an investment of PEN135 million. All of this adds up to 160 km of two-lane roads.
The construction of Piura’s beltway was completed with an investment of US$17.9
million.
In January 2013, the concession contract for the 430-km-long Dv. Quilca – Tacna – Chilean Border Road was signed, achieving an investment commitment worth US$160 million.
On May 28, 2014, the concession contract for Stretch 2 of the Longitudinal Road of
the Highlands (875 km) was signed, committing an investment of approximately US$ 552 million.
In October 2014, the 760-m-long Socostaca Tunnel and the 487-m-long El Carmen
Tunnel were opened in Stretch 4 of the Southern Interoceanic Highway, in the department of Puno, implemented with an investment of US$73 million.
In April 2014, construction of Stage Two of the Huacho – Pativilca Stretch started;
this stretch is part of Road Network No. 5. In July 2014, rehabilitation and improvement works for the Cochabamba – Cutervo –
Chipe Road started (90 km), with an investment of US$148 million, within the framework of the concession for Stretch 2 of the Longitudinal Road of the Highlands.
In December 2014, construction of the 3.9-km-long Urcos Beltway was completed,
with an investment of PEN26.7 million.
Appendix 3 shows the concessions of current roads.
2.2 National Road Network Paving Strategic objective: Paving 85% of the National Road Network Main project: Paving 100% of the Longitudinal Road of the Highlands
This administration’s goal is to pave 7,878 km of roads belonging to the National Road Network, which involves an estimated investment of US$11 billion, including both public and private investment. With this, 85% of the National Road Network² available is expected to be paved as of 2016.
In the period from August 2011 to December 2014, 5,054 km of national roads were paved (with a category change). Thus, currently there are 17,411 km of paved roads, which is equivalent to 75.5% of the National Road Network (RVN, by its Spanish initials) as of July 2011 (23,072 km). Of this total length, 1,812 km were implemented to improve (providing an asphalt layer) and 3,241 km were carried out to provide a basic solution (economical pavement).
__________________________________
2 National Road Network available as of July 2011 (23,072 km)
“Decade of the Disabled Persons in Peru”
“Year of Promotion of Production Diversification and Education Strengthening”
10
NATIONAL ROAD NETWORK (km)
NATIONAL ROAD NETWORK
ACHIEVED
AUGUST 2011 –
DECEMBER 2014
July 2011 July 2012 July 2013 Dec 2013 July 2014 Dec 2014
Paved
12,358 14,123 15,086 15,906 16,187 17,411
5,054
Asphalted
Basic solution
11,951 12,416 12,860 13,306 13,459 13,763
407 1,707 2,225 2,599 2,727 3,648
1,812
3,241
Non-paved
10,714 9,970 9,857 9,100 9,214 8,377
Available RVN
23,072 24,092 24,943 25,005 25,400 25,789
% paved RVN*
53.6 61.2 65.4 68.9 70.2 75.5
Source: GTT-MTC, PVN-OPEI
2.3 Longitudinal Road of the Highlands
The 3,503-km-long Longitudinal Road of the Highlands will connect Desaguadero, on the
border with Bolivia, with Vado Grande, on the border with Ecuador. Achieving the goal of
paving 100% of this road is important, because it will contribute to rendering the Andean
Region’s production more competitive, while substantially improving the quality of life of
millions of Peruvians.
Situation as of 2014
The Longitudinal Road of the Highlands has a total length of 3,503 km, of which 84.1% were
paved as of December 2014. With regard to July 2011, it has been possible to pave 947 km
of this road by applying two strategies: a final solution (asphalting) and a basic solution
(economical pavement).
Longitudinal Road of the Highlands (km)
PAVEMENT SURFACE
Situation as of
JULY 2011
Situation as of
DEC 2014
Paving,
August 2011
– December
2014
Paved 1,999 2,946 947
“Decade of the Disabled Persons in Peru”
“Year of Promotion of Production Diversification and Education Strengthening”
11
Asphalted 1,854 2,359 505
Economical Pavement
145
587
442
Non-paved
1,306
558
Longitudinal Road available
3,305
3,503
Paved
60.5%
84.1%
Note:
The available length of the Longitudinal Road of the Mountains has varied due to reclassification of routes and changes of stretches
(*) Projected
Source: PVN-OPEI (20140620). Basic Road Inventory 2010 DGCF-MTC
It should be pointed out that part of the Longitudinal Road of the Highlands, which was 60%
paved as of July 2011, is being rehabilitated, since it had been in poor condition, while the
remaining 40% will be paved with an asphalt layer or economical pavement.
km of roads completed during period:
- Ayacucho – Abancay Road (7 stretches): 361.0 km
- Hualgayoc – Yanacocha Road: 51.0 km
- Cochabamba – Chota 31.0 km
- Santiago de Chuco – Shorey Road 33.4 km
- Others 28.6 km
- Economical pavement 442.0 km
TOTAL 947.0 km
Projection as of July 2016
The current government’s goal is to manage to pave 100% of the Longitudinal Road of the
Highlands by 2016; in this sense, there are procedures to pave a total of 558 km of roads
during the remainder of this administration, either with asphalt or with economical pavement.
The procedures scheduled for the remainder of this administration for the Longitudinal Road
of the Highlands regarding paving with a hot asphalt layer and economical pavement are:
“Decade of the Disabled Persons in Peru”
“Year of Promotion of Production Diversification and Education Strengthening”
12
No. Longitudinal Road of the Highlands Stretches (km)¹ʹ
ASPHALTED 80
1 Chota - Bambamarca – Hualgayoc Stretch 51.7
2 Mayocc-Huanta Stretch 27.9
ECONOMICAL PAVEMENT 478
1 Chuquicara – Huallanca Stretch 65.6
2 Santiago de Chuco – Cachicadan – Mollepata Stretch 79.5
3 Tauca - Pallasca Stretch (km 145+000 - 201+200) 40.6
4 Pallasca – Mollepata 18.1
5 PE 04-B Junction (Hualapampa) - Sondor 71.5
7 Huancabamba – PE-3N Junction (Socchobamba) 186.4
8 Huancabamba – Sondor – Tabaconas – San Jose del Alto 16.4
TOTAL LONGITUDINAL ROAD PAVED 558
1) The category of these stretches will change from Non-Paved to Paved; it depends on traffic whether paving is with an asphalt layer
or with economical pavement.
Committed Investment (2011-2016)
The investment committed for the Longitudinal Road of the Highlands for the period from
2011 to 2016 amounts to US$3.596 billion, which includes procedures involving an asphalt
layer (improvement when there is a category change and rehabilitation when the purpose
is to replace the asphalt because it is in poor condition) and economical pavement.
LONGITUDINAL ROAD OF THE HIGHLANDS STRETCHES
INVESTMENT IN MILLIONS OF DOLLARS
Pavement Surface
Stretch 1 Stretch 2 Stretch 3 Stretch 4 Stretch 5 Total
Paved
Asphalted
Improvement
92 174 1,256 261 1,783
“Decade of the Disabled Persons in Peru”
“Year of Promotion of Production Diversification and Education Strengthening”
13
Rehabilitation 466 521 388 1,375
Economical
Pavement
236 202 438
Total (million US$) 328 640 1,458 782 388 3,596
Source: PVN - OGPP- MTC
It should be noted that stretches 1 and 3 will be implemented as public works (tender within
the framework of the Contracting Law) adding up to US$1,786 million, and that the stretches
2,4 and 5 will be carried out through Public-Private Partnerships (APP) adding up to
US$1,810 million.
Additionally to the investment indicated in the previous chart, the amount committed to
(routine and periodic) maintenance and conservation activities along the Longitudinal Road
of the Highlands is US$510 million, which will guarantee trafficability and sustainability, as
well as a top-level customer service.
Procedures on Longitudinal Road of the Highlands
“Decade of the Disabled Persons in Peru”
“Year of Promotion of Production Diversification and Education Strengthening”
14
2.4 National Road Network Maintenance
During the administration period ranging from August 2011 to December 2014, 24,187 km
of national roads were maintained, with a total cost of PEN5.516 billion, both with public
resources and private investment in the privatized network.
These procedures include routine and periodic maintenance, as well as a Service-Level
Conservation Contract mode.
“Decade of the Disabled Persons in Peru”
“Year of Promotion of Production Diversification and Education Strengthening”
15
ROAD MAINTENANCE ON NATIONAL ROAD NETWORK
AUGUST 2011 – DECEMBER 2014
Includes self-sustaining privatized RVN (*) Projected
Note: Road maintenance corresponds to all privatized RVN
It is important to highlight that the Service-Level Maintenance Road Contracts include
commissioning, periodic maintenance, routine maintenance and emergency assistance by
the maintainer-contractor, thus assuring trafficability throughout the Corridor.
In 2014, 38 contracts and 1 agreement were entered into under 5-year Service-Level Road
Maintenance schemes, aiming to operate on 13,911 km of roads, committing a total
investment of PEN5.495 billion.
Among corridors that are being operated on, the following stand out: Huancayo - Imperial -
Izcuchaca - Ayacucho / Imperial - Pampas – Mayoc (430 km); Cajamarca – Celendín - Balsas
– Chachapoyas and Dv. Chachapoyas – Pedro Ruiz (367 km); PE 3S Junction (Abra Tocto)
– Querobamba – Puquio (372 km); Puquio - Cora Cora - PE-1S Junction (Chala) and
Coracora – Yauca – PE 1S Junction an PE32 Junction – Pausa (526 km); Rosario – Sivia –
Canayre and San Francisco – Santa Rosa – San Miguel – Tambo (324 km).
Appendix 4 shows a list of Service-Level Maintenance Contracts under implementation.
2.5 Support to Regional and Local Government’s Management
Provías Descentralizado aims at promoting, supporting and guiding the budget increase and
trafficability improvement of the departmental and rural transport infrastructure, as well as
institutional development in a decentralized, well-planned, articulated, and regulated manner
in order to contribute to the country’s development and to overcoming poverty.
Procedures Physical Progress
km
Financial Progress
Thousands PEN
NON-PRIVATIZED RVN
18,755 4,558,780
PRIVATIZED 4,931 957,609
TOTAL 24,187 5,516,388
“Decade of the Disabled Persons in Peru”
“Year of Promotion of Production Diversification and Education Strengthening”
16
During the period from July 2011 to December 2014, the main achievements include the
execution of rehabilitation and improvement works involving 1,307 km of departmental roads
and 1,226 km of rural roads, as well as the execution of construction works for 7 permanent
bridges throughout the country.
Furthermore, it should be mentioned that within the framework of the Sector’s strategy
regarding bridges, 245 modular steel bridges were purchased during 2014 to replace bridges
along departmental and rural roads throughout the country; these structures are expected to
be installed in the period 2015-2016.
Moreover, it is important to highlight projects that have a social component, which include
mainly projects to improve 825 km of bridle paths located in rural areas with high poverty
rates.
Overview of Road Infrastructure Projects
July 2011 – December 2014
Measure-
ment Unit
Physical Implementation
(July -December)
Physical Implementation
2012
Physical Implementation
2013
Physical Implementation
2014
Total Physical Implementation
Departmental Road Projects
Rehabilitation works km 185 329 662 131 1,307
Departmental Road Program – (PCD, by its Spanish initials)
km 183 318 609 129 1,239
Regular Resources km 2 11 53 2 68
Periodic Maintenance km 28 145 750 535 1,458
Departmental Road Program - PCD km 28 145 750 510 1,433
Regular Resources km - - - 24 24
Routine Maintenance (Manual) km 11 130 109 - 250
Departmental Road Program - PCD km 11 74 109 - 194
Regular Resources km - 56 - - 56
Routine Maintenance (Profiling) km 471 1,117 608 - 2,196
Departmental Road Program – PCD km 471 1,117 608 - 2,196
Rural Road Projects
Rehabilitation works km 230 626 216 154 1,226
Decentralized Rural Transportation Program (PTRD, by its Spanish initials)
km 2 79 95 2 178
Regular Resources km 228 547 122 147 1,044
Fund for Economic Inclusion in rural areas (FONIE, by its Spanish initials)
km - - - 4 4
Periodic Maintenance km 770 1,893 1,449 33 4,145
Decentralized Rural Transportation Program - PTRD
km 770 1,893 1,440 4,072
Regular Resources km - - 40 33 73
Bridle Path Projects
Improvement works km 72 365 310 78 825
Decentralized Rural Transportation Program (PTRD)
km 72 236 310 78 695
Regular Resources km - 129 - - 129
Bridge Projects
Construction works km 2 1 3 7
Built permanent bridges Bridge 1 2 1 3 7
On the other side, it must be highlighted that Provías Descentralizado has been performing
activities for developing and strengthening the capacities of subnational governments for an
appropriate decentralized road management; it should be pointed out that this has intensified
“Decade of the Disabled Persons in Peru”
“Year of Promotion of Production Diversification and Education Strengthening”
17
during 2013, through implementation of Budget Program 061 (Reduction of Costs, Times
and Road Risks in the Land Transport System).
These strengthening measures have promoted the preparation and updating of 24
Participatory Departmental Road Plans (PVDP, by its Spanish initials) and 193 Participatory
Province Road Plans (PVPP, by its Spanish initials), which are used as the main tool to
plan, prioritize, and program road infrastructure within the respective areas of competence.
It should be noted that the Decentralized Rural Transportation Program (PTRD, by its
Spanish initials) was successfully finished in 2013; it was implemented to support local
governments in the rehabilitation and maintenance of rural road infrastructure. Moreover,
the Departmental Road Program was finished in 2014; this program was carried out to
support regional governments in the rehabilitation and maintenance of rural road
infrastructure. Regarding the programs’ funding, both received technical support and were
co-financed by the Inter-American Development Bank and the World Bank.
III. Rail Transport
3.1 Lima Metro
Strategic objective: Consolidation of Lima’s Metro Network Main project: Line 2, Ate – Callao – Jorge Chavez Airport
Line 1: Villa El Salvador – Av. Grau – San Juan de Lurigancho (20.8 km)³
- LINE 1 of Lima’s Metro runs across nine districts, including 26 stations. The districts
are: Villa el Salvador, Villa María, San Juan de Miraflores, Santiago de Surco, San
Borja, La Victoria, El Cercado de Lima, El Agustino, and San Juan de Lurigancho.
Since its start of operation in December 2014, a total of 139,268,386 passengers
have been transported.
a) Operation of Line 1, Stretch I:
- Business operation started on January 9, 2012, with commercial operation of 5
trains with 6 cars each, which offered the public free rides until April 5, 2012; as of
this date the rides have to be paid, after 3 months of free test rides. 3 Business kilometers
“Decade of the Disabled Persons in Peru”
“Year of Promotion of Production Diversification and Education Strengthening”
18
- In 2012, a total of 32,786,832 passengers were transported, which is equivalent to
a monthly average of 2,732,236 passengers, while in 2013 a total of 36,148,315
passengers were transported, equivalent to a monthly average of 5,744,596
passengers. During the fiscal year 2014, 57,408,053 passengers were transported
on Stretch I, a monthly average of 4,784,004 passengers.
- Including all financing sources, the cumulative investment in the period from August
2011 to December amounted to PEN19,344,138 2014.
b) Works on Line 1, Stretch 2: Av. Grau – San Juan de Lurigancho
- Line 1, Stretch 2 has a total length of 12.24 km and runs across the following
districts: Cercado de Lima, El Agustino, and San Juan de Lurigancho. It has 10
stations and the estimated journey time is 20 minutes.
- Public business operation of the second stretch of Line 1 started on July 25.
Currently, 24 trains are in operation to cover all of the Line 1 service.
- A total of 12,295,186 passengers, equivalent to a monthly average of 2,519,683
were transported in 2014.
- Including all financing sources, the cumulative investment in 2014 amounted to
PEN212,555,812.
Line 2: Ate – Callao and Av. Faucett – Gambetta Branch
Line 2 (Ate – Callao) of Lima’s Metro was granted in concession, committing an
investment of US$5,658 million. Line 2 has an extension of 35 km and will run across 13
districts of Lima and Callao in 45 minutes. It includes the Avenida Faucett – Avenida
Gambeta Branch, which will provide access to Jorge Chávez International Airport. It will
transport more than half a million passengers a day, across 25 stations. Stage 1A
(Stretch 5) should be operational in mid-2016.
Line 2 of Lima’s Metro will be part of Lima and Callao’s Integrated Public Transport
System. Therefore, it will be connected to Line 1 of the Metro and to the Metropolitano
buses.
The construction works on Line 2 of Lima’s Metro started on December 29, 2014.
“Decade of the Disabled Persons in Peru”
“Year of Promotion of Production Diversification and Education Strengthening”
19
Line 2: Ate Callao
It will connect 13 districts and include 27 stations. Furthermore, its route will be connected to the Metropolitano at Estación Central, to Line 1 of the Metro at 28 de Julio Station, and to the future lines 3 and 4 of Lima and Callao’s Metro.
Avenida Faucett – Avenida Gambetta Branch
It will include 8 stations along its route, along the axis of Avenida Faucett from Avenida Oscar R. Benavides to Avenida
Gambetta. It will be connected to Line 2 at Carmen de la Legua Station and with the airport. This branch is a stretch of
the future Line 4 of Lima and Callao’s Metro.
Project objective
To provide a high-quality, modern4 and reliable public transport service. Thus, the aim is
to enable the population to move around in a safe, quick5 and comfortable way.
Commissioning
Stage 1A (Stretch 5) should be operational by mid- 2016 and the other stretches by 2019. Rolling stock worth PEN551,165,259.04 was acquired (drawdown included). Procedures to gain access to areas affected by right of way were performed:
4 The 35 stations of Line 2 will be fitted with the highest technological standards.
5 It will reduce the 2-hour-plus journey between Ate and Callao to 45 minutes, thus increasing people’s productivity; passengers will
spend less money on private transport (taxi) for visiting places close to the train route.
“Decade of the Disabled Persons in Peru”
“Year of Promotion of Production Diversification and Education Strengthening”
20
43 properties were identified as affected areas, of which 28 properties were public,
4 were private public, and 11 were private.
Inter-institutional agreements were signed with regard to the relocation of sanitary
sewer lines, water lines, power lines and telecommunication lines at areas where
stations and wells will be built. These agreements involved Telefónica, Claro and
Optical Net Works regarding telecommunications networks (Stage 1A) and Luz del
Sur regarding power networks; additionally, they involved the power company
Edelnor for Stage 2 of Line 2, as well as for the Avenida Faucett – Avenida Gambetta
Branch of Line 4.
Luz del Sur has been working since June, expecting to deliver the released area
on February 28, 2015.
It was managed to obtain approval for the proposed relocation of SEDAPAL lines,
which will be dealt with by the concessionary company Metro De Lima Línea 2, based
on the addendum signed on December 28, 2014.
Including all financing sources, there was a cumulative investment of PEN1,047,
488, 441 during 2014 (see details of activities, Appendix 5).
3.2 Huancayo – Huancavelica Railway
PROINVERSION is in charge of granting in concession. As of today, the hired consultant is
preparing the studies within the framework of the original scheme considered in Article 4 of
Emergency Decree No. 012-2005, under a “rehabilitation” alternative for infrastructure,
superstructure and rolling stock. The concession is expected to be granted in the last two-
month period of 2015.
At present, the Huancayo – Huancavelica Railway line is being operated with a mixed
passenger and cargo train, which provides its services every other day: It travels one day
from Huancayo and returns the following day from Huancavelica. The only day it does not
operate is on Sundays, which is when the equipment is maintained.
IV. Water Transport
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
4.1 Private Investment in Ports
South Container Terminal of Callao Port
This is a self-sustaining 30-year concession with a committed investment of US$704.8 million. The First Stage activities regarding the South Container Terminal of the Callao Port have been finished and the start of the Second Stage is being prepared, for which an addendum is being negotiated. Investment during this administration period amounts to US$4,448.7 million.
Multipurpose North Dock of Callao Port
This is a self-sustaining 20-year concession with a committed investment of US$883.5 million (17.5% of this had been executed as of December 2014).
In November 2012, construction works aimed at modernizing and expanding the
Multipurpose North Dock of the Callao Port started, with a total investment of US$307
million for carrying out the first and second stages, and with an investment of US$883.5
million for the entire project. The initial investments include dredging the areas adjacent
to the dock, as well as purchasing 4 gantry cranes for handling super-post-Panamax-
type ships, and 12 electric yard cranes. The investment executed as of May 2014
amounts to US$70 million.
Budget execution at the end of 2014 amounted to US$154,2 million.
Paita Port Terminal
This is a self-sustaining 30-year concession with a committed investment of US$267 million (63% executed as of December 2014). Construction works of the 1st stage of the Paita Port Terminal started in June 2012 and lasted 24 months. The important part of the first stage consisted of dredging the seabed up to 13 meters
deep at the berth and access channel area, as well as of a fill reclaimed from the sea
for construction of a 12-hectare container yard with a marginal 300-m dock, built with a
reinforced concrete cover and piles used to initially support a STS post-Panamax gantry
crane assisted by two RTG yard cranes; at present, works have already been
completed.
The investment executed as of December 2014 amounts to US$167 million.
21
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
Mineral Terminal of Callao Port
This is a self-sustaining 20-year concession with a committed investment of US$120.3 million (and 85.7% execution as of December 2014). Construction of the terminal started in August 2012 and it was opened in May 2014. This dock is located in the area adjacent to the north breakwater and has a length of approximately 200 meters and a draft of 13.1 meters, with a capacity to handle ships with a reference size of 226 meters. The implementation of this infrastructure will require an investment of US$160 million and will make more than 130 thousand ore concentrate truck trips redundant, reducing pollution levels and relieving other ports. The new 3-km infrastructure will allow transportation of up to 2,300 tons of copper, zinc and other minerals per hour, as compared to the current 600 tons.
Matarani Port Terminal
This is a self-sustaining concession with a committed investment of US$35.8 million (executed during previous administrations). So far, an addendum has been signed with the concessionaire of the Matarani Port Terminal, which will allow construction of a new mineral dock (expansion of Bahía Islay) with an investment of approximately US$260 million. Construction works are being executed and will last for about 24 months and will be initiated after the final studies are finished and approved.
New Yurimaguas Port Terminal – New Reform
This is a co-financed 30-year concession with a committed investment of US$43.7 million. The Technical Dossier of the New Yurimaguas Port – New Reform prepared by the concessionaire company was approved, including an investment amounting to US$36.1 million (1st stage). Construction works started in April 2014 and will be concluded in 24 months. At the end of 2014, progress was estimated at about 13.4%.
22
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
General San Martin Port Terminal (Pisco)
The General San Martin Port Terminal (Pisco) was granted in concession on April 30, 2014, for a period of 30 years. It has a committed investment of US$120.8 million, to which a complementary investment of US$80 million offered by the concessionaire must be added, totaling an investment of US$200.8 million. Since the project is a Comprehensive Public-Private Partnership (APP, in Spanish), it will include the following specialized services (which will be under the responsibility of the concessionaire): designing, financing, construction, operation and maintenance of the port terminal. The initial compulsory construction works, which are to be carried out within three years,
comprise the modernization of the multipurpose berth (Berth 3 and Berth 4) and storage
yard, construction of outer harbor, as well as dredging the access channel, maneuvering
area and berths to minus 12 (twelve) meters of depth. Additionally, they include the
implementation of ancillary facilities and power and water supply lines, as well as the port
equipment required for port terminal operation, such as a port tractor, hoists, mobile
cranes, and mobile equipment to absorb grains, chassis, etc.
With this Project, the General San Martin Port Terminal of Pisco will be modernized to
handle local and international freight, receive deep-draft ships, and support the steady
growth of the demand for port services within its area of influence.
V. Air Transport
5.1 Investment in airports
Jorge Chávez International Airport (AIJCH)
This is a self-sustaining 30-year concession with a committed investment of US$1,062 million (30% executed as of December 2014). The present administration managed to sign the addendum which allows partial delivery
of lands for the airport expansion (new passenger terminal and second runway); 3.85
million m2 of land have already been delivered, which is equivalent to 56.32% of the total
area intended for the expansion. The remaining land will be granted to the
concessionaire LAP upon finishing construction of the Nestor Gambetta Avenue stretch
that crosses the airport.
During this administration, it was managed to gain control over 100% of the land owned
by various landowners (agricultural and industrial land, and shantytowns).
23
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
Moreover, the second stage, which comprises Jorge Chavez’s expansion and
modernization (second runway for landing and take-off, new passenger terminal, and
new control tower), will require an investment of approximately US$850 million.
During the second quarter of 2014, the concessionaire LAP started preparing the
engineering design for expansion and modernization of AIJCH, whose cost amounts to
US$17.8 million and which is estimated to be completed in the second quarter of 2016.
The conceptual design of this project will be completed in the second quarter of 2015.
Chinchero International Airport (Cusco)
Chinchero International Airport (Cusco) was awarded in concession on April 30, 2014.
This is a co-financed 40-year concession that requires an investment of US$635 million
for starting operations – this amount could go up to US$776 million with future expansions
and rehabilitation during the operation stage.
The airport will offer passengers a high-quality service in a 40,000-m2 terminal with an
initial capacity to serve 4.5 million of passengers a year, expandable (depending on
demand) to up to 6 million passengers a year. Furthermore, it will offer direct international
connection to America’s main cities.
This airport infrastructure will help support the growth in the number of local and
international tourists to the Imperial City (Cusco), boosting the development of both the
department of Cusco and Peru.
First Group of Regional Airports (12 airports)
This is a co-financed 25-year concession with a committed investment of US$108.2 million, which will be spent on quick-impact projects, security and basic works of the remaining period (75.4% of execution as of December 2014). To date, updated master development plans (PMD, by its Spanish initials) for these projects have been concluded, which comprise development of the Northern Hub (Chiclayo). The goals for 2014 include achieving the approval of modernization studies for the airports of Iquitos, Cajamarca, Piura and Trujillo, as well as the improvement of runway systems and civil infrastructure for the airports of Piura and Chiclayo, which will require an additional investment of PEN320 million.
Second Group of Regional Airports (6 airports) 24
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
This is a co-financed 25-year concession with a committed investment of US$ 70.3 million (70.5% executed as of December 2014).
The initial contract period covers the expansion, adjustment and remodeling of terminals,
which are now underway.
Through the New Work Mechanism, a comprehensive rehabilitation of Juliaca Airport’s
runway is projected to be carried out, with an additional investment of PEN130 million
and a 24-month execution plan (from 2015 to 2016).
Arequipa Airport Modernization
In September 2013, the improved and expanded Alfredo Rodríguez Ballón Airport in
Arequipa was opened. Improvement and expansion works included new departure
lounges with a total of 250 seats, 9 new counters, and 120 additional cars to transport
baggage, as well as 2 boarding bridges. These works were implemented on an area of
2,200 m², with an investment of PEN64 million.
Pisco Airport
In September 2013, the remodeling works for the new Pisco Airport (Ica) started, with an
investment of PEN153 million.
The project aims to provide the International Airport of Pisco with the necessary
infrastructure for providing appropriate and sufficient commercial airport services (freight
and passengers). It comprises the construction of a new and modern terminal that meets
international requirements and service standards. Furthermore, this airport should be an
alternative to Jorge Chavez International Airport. The airport will start operations in 2015
and it is estimated to receive 400 thousand passengers a year starting 2017.
AS of December 2014, work progress was estimated at 83.4%, with completion expected
for May 2015.
Rehabilitation and Improvement of Jauja Airport
On May 26, 2014, through Report No. 693-2014-MTC/09.02, the profile-level pre-
investment study for the “Rehabilitation and Improvement of the Jauja Airport Passenger
Building and Pavements” project was approved.
During the second quarter of 2014, the project was exempted from conducting a pre-
investment feasibility study, while it was declared to be feasible based on its profile-level
pre-investment study, with an amount of US$85.4 million.
25
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
Execution and approval of the project’s final study is expected to occur in the first
semester of 2015, with subsequent start of construction works in the second quarter of
2015.
General Parking Platform for general aviation at Cusco Airport
Due to increased number of operations registered by Cusco’s Velasco Astete
International Airport (AIVA, by its Spanish initials), in 2013 the Directorate-General for
Civil Aviation (DGAC, by its Spanish initials) drafted a profile-level pre-investment study
and a final engineering study for expanding the airport’s parking capacity, which was
approved on December 13, 2013.
At the end of 2014, a budget of 5,419,809.96 (including VAT) was decided, intended
for starting procedures for the public tender process for execution and supervision
of works during the second quarter of 2015.
VI. Telecommunications
Strategic Objective: broadband in 180 province capitals
Main project: Optical Fiber Backbone Network
6.1 Signing of Concession Contract for National Optical Fiber Backbone Network
On June 17, 2014 the Concession Contract for the National Optical Fiber Backbone Network
was signed with Azteca Comunicaciones Perú S.A.C., with the objective of putting them in
charge of designing, laying and operating a 13,500-km optical fiber network that will
provide a mass data transfer infrastructure for achieving broadband internet access in 92%
of the country’s province capitals (180 of 196 province capitals6). The financing of the
backbone network is for a period of 20 years and amounts to US$333 million.
6 This will connect Lima with 180 province capitals, 22 of which are also regional capitals.
26
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
The abovementioned concession contract considers a gradual term of up to 24 months for
laying the fiber optic network (using existing high and medium voltage power networks),
which will be carried out in six quarterly stages. Therefore, the laying of the fiber optic network
is expected to be concluded in the first quarter of 2016. It should be noted that the laying of
the Backbone Network started in the district of Huaytara, in the region of Huancavelica, on
December 18, 2014; the first network stage is expected to be ready for commissioning in the
region’s seven province capitals by March 2015; after a final trial period, and it will start
operation in April 2015.
Currently, only one third of the province capitals have access to broadband internet.
However, thanks to this project, there will be an additional operator that will offer the service
at a much lower cost, and the other province capitals will finally have access to this
technology.
The country’s Backbone Network will allow larger network and service coverage, leading to
increased competition because it enables more operators to access the country’s various
regions and reduces the data transfer costs, enabling better access to telecommunications
services due to increased offer by new telecommunications operators in each region. The
broadband will also allow implementing other applications, such as online education, tele-
medicine, and e-government, among others, which will increase the country’s
competitiveness.
Additionally, regional broadband projects to extend optical fiber to districts and locations in
the interior of the country will be developed from this basis.
6.2 Signing of Concession Contract for 1.7/2.1 GHz band to provide 4G-LTE service
The 4G-LTE technology is a tool that dramatically boosts the increase in broadband internet
coverage to make the country more competitive. It significantly meets the population’s
needs and improves their quality of life, because it enables broadband use on mobile
terminals (smartphones, tablets, and USB modems, among others), providing fast and
efficient data connection at affordable prices due to the important economies of scale this
technology currently generates at a regional level.
Hence, in July 2013, the 1.7/2.1 GHz band (AWS band) was awarded for more than US$255
million, including both blocks (each block has 20+20 MHz); the concession contracts were
signed with Telefónica Móviles S.A. on October 10, 2013 (Block A), and with Americatel
Perú S.A on September 13, 2013 (Block B). It is estimated that the companies will have a
total investment greater than US$1.1 billion. Among other benefits, these concessions
substantially increase mobile internet speed, establishing a minimum speed, while
improving information provided to users since it is stipulated that the minimum guaranteed
speed be reported in a clearly visible way during the sales stage. Moreover, high internet
speed also boosts new industries related to applications, contents and interactive services. 27
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
It is worth stating that the AWS band concessionaries shall, gradually and within a 5-year
period, deploy the 4G- LTE Service in 234 cities and tourist sites throughout the country.
Thus, approximately two thirds of the country’s population (more than 18 million people) will
benefit from 4G coverage. To this date, Telefónica del Perú S.A.A. (formerly Telefónica
Móviles S.A.C.) started operations in the districts of Cercado de Lima, La Molina, Miraflores,
San Borja, San Isidro, San Miguel and Surco, in the province of Lima, on January 2, 2014;
in the case of Entel Perú S.A., it started operations in the district of San Borja, on September
24, 2014. In this sense, it is expected that cities such as Iquitos, Lima, Arequipa and Trujillo
will have full 4G internet coverage by the second quarter of 2016. The same is expected for
the country’s remaining towns and villages within the next 5 years.
Finally, the entry of new operators increase competition, by defining obligations that enable
access of Virtual Mobile Operators (OMV, by its Spanish initials) to the services of the
already established mobile operators, thus widening the range of 4G-LTE services offered,
favoring a cost reduction that will benefit users.
6.3 Signing of Concession Contract for 900 MHz band
On November 29, 2012, the concession contract for provision of 900 MHz band mobile
services was signed with the company Viettel Perú S.A.C., which enabled the consolidation
of this company as the country’s fourth mobile operator, thus contributing to diversifying the
offer of telecommunications services in the country.
It is worth pointing out that the Peruvian Government, in line with its inclusive policies,
established obligations in the granted concession that prescribe that the concessionaire has
to provide telecommunications services in the country’s geographically most remote areas.
It seems pertinent to highlight the following obligations imposed on VIETTEL as
concessionaire of the 900 MHz band mobile service:
Providing free internet and broadband to 718 public entities (438 schools, 112
hospitals and 168 municipalities) in the country’s 168 poorest districts. So far, the
service has been installed in 144 educational institutions, 59 district and province
municipalities, and 34 health centers.
Providing mobile service in forty eight (48) districts outside the province of Lima and
the constitutional province of Callao. The districts will be selected from a list of 294
districts where the MIDIS has been implementing and/or will implement social
programs, and must lack mobile coverage or have just a single mobile service
operator.
28
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
Having at least 15,000 operational mobile lines throughout the country within the
first year of operations, and achieving 357,000 operational lines in the fifth year.
6.4 700 MHz band tender
The 700 MHz band is one of the bands used throughout the world for deployment of 4G-
LTE technology because it enables providing high speed mobile internet to the masses.
For this reason, ProInversión has been entrusted with running this process, which is
expected to be concluded this year.
With the awarding of the 700 MHz band, the results obtained last year with the 1.7/2.1 GHz
band tender are expected to be exceeded. Therefore, the requirements to be proposed
include: establishing minimum speeds, aggressive coverage plans allowing rapid
nationwide deployment (more towns and villages than with 1.7/2.1 GHz band), and providing
better information to users, among others.
It is important to point that this band allows more efficient use of the operator companies’
networks, since their coverage has a larger geographic range (better propagation) and
greater penetration within buildings, which translates into better signal reception, service
quality and coverage in remote locations.
6.5 Virtual Mobile Operators
Within the regulatory scope, Law No. 30083 should be highlighted: It establishes measures
to strengthen competition in the mobile public service market and was published in 2013; it
also introduced the idea of Virtual Mobile Operators (OMV) to Peru, as an important element
to promote the entry of new operators into the country.
Virtual Mobile Operators are characterized by the provision of mobile services without
requiring an own network or radio spectrum, on the basis of agreements with the established
mobile operators, which do have networks and an assigned radio spectrum.
This Law allows rendering competition more dynamic, facilitating rapid market positioning to
Virtual Mobile Operators, thus generating the conditions for providing services to market
segments unattended by established operators; this promotes price reduction and a greater
mobile service offer, while encouraging among users the decision to migrate to the operator
providing the most convenient service.
29
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
The Law Regulation Project has been published for comments, which are being analyzed,
while coordinating with the competent entities in order to obtain a final version by the end of
March of this year.
6.6 Concession Contract Renewal for Telefónica Moviles
The concession contracts for Telefónica del Perú were renewed in January 2013 for a period
of 18 years and 10 months, committing an investment of PEN3.020 billion. These investment
commitments are related to provision of mobile telephony services at social fees, free internet
for the State (schools, health centers, police stations, etc.), and broadband internet
transmission to Iquitos through microwaves, and mobile telephony coverage in all district
capitals and villages or towns with more than 400 inhabitants.
So far, the mobile telephone service has been installed in 317 district capitals and in 1,113
other villages or towns. Moreover, a High-Capacity Transport Network has been installed,
which integrates the Amazon region in the section Iquitos – Yurimaguas – Tarapoto –
Moyobamba – Rioja; other telecommunications operators will also be able to use this
transmission network, which makes competition feasible, thus benefiting the Amazon
population. On the other hand, there are 361,967 Social Fee beneficiaries; and access to
Social Internet has been installed in 591 educational institutions, 1,482 health centers and
329 police facilities. Furthermore, access to Satellite Social Internet has been installed in
the 162 poorest districts and in 35 districts of border provinces, with which the coverage of
services has been extended across the country.
6.7 Awarding of Amazon Region Integration Project
This concession, which was granted in 2013, will connect Loreto and San Martin with the
land telecommunications network. With an investment of US$29.9 million, it will provide 70
villages and towns of the provinces of Maynas and Mariscal Ramón Castilla (Loreto) with
connectivity, in the section comprised between Iquitos and Santa Rosa (border between
Peru and Colombia).
6.8 Awarding of Regional Optical Fiber Backbone Network
30
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
These concessions are aimed at achieving comprehensive connection of a region with all its
towns and villages, thereby promoting local, regional and national integration, as well as
contributing to development.
It consists of a portfolio of regional projects of regional broadband connectivity for the country’s
21 regions. The scope of these projects will allow connecting more than 1,500 district capitals
through fiber optic cable. Hence, approximately 6,979 public educational institutions, 3,471
health centers, and 566 police stations will have at least one internet connection. These 21
regional projects represent a deployment of more than 30,352 km of fiber optic cable,
providing each of the 21 regions with high-speed, high-capacity networks. It is projected that
the estimated investment for the Transmission Network and Access Network will demand
financing worth about US$560,172,860 and US$586,347,472 million, respectively, with a
total investment estimated at US$1,146,520,332.
As of today, out of the 21 regional projects four (4) regional telecommunications projects are
in a promotion process in PROINVERSION, four (4) regional telecommunications projects
have been declared feasible by the National System of Public Investment (SNIP, by its
Spanish initials) and placed under the responsibility of PROINVERSION, two (2) projects
have been forwarded to the OPI to determine their feasibility, and eleven (11) projects are
being formulated. These projects consider a high-capacity transfer network (optical fiber)
that will extend the Optical Fiber Backbone Network (RDNFO, by its Spanish initials)
awarded in December 2013 to the intended district capitals. Moreover, each regional project
has an access network that will transfer broadband services to rural communities; in
particular, these projects will benefit public entities located in these areas (mainly schools,
health centers, and police stations).
List of regional projects with concluded pre-investment study:
- In process at PROINVERSION: Lambayeque, Huancavelica, Apurimac, Ayacucho, Tumbes,
Cajamarca, Piura, and Cusco.
- Under assessment at the OPI: Ica and Lima
31
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
32
VII. Concessions
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
33
On December 31, 2014, the Sector had a total of 31 concessions, corresponding to the
different means of transport:
16 road concessions (including Section 2 of the Longitudinal Road of the Highlands)
4 railway concession (including Line 2)
4 airport concessions (including Chinchero airport)
7 port concessions (including General San Martin Port Terminal)
These transport concessions represent a committed investment of US$13.772 billion, of
which US$4.865 billion have been implemented (as of December 2014).
It is worth noting that from August 2011 to December 2014, concessions with a committed
investment of US$6.351 billion (46.1% of the total) have been awarded.
VIII. Private initiatives7
Private initiatives are a Private Public Association-type investment project modality.
According to their classification, they can be either co-financed or self-sustaining. In the first
case, projects require public resources; in the second case, the projects do not require public
financing or they require minimum guarantees.
As of December 2014, the Sector had given a favorable opinion in relation to the relevance
and priority of eight co-financed private initiatives of national scope. Furthermore, it also
gave a favorable opinion related to the relevance and consistency of four self-sustaining
private initiatives, three of national scope and one of regional competence.
Only five of the eight co-financed private initiatives have gotten the budgetary capacity by
The Ministry of Economy and Finance. The following provides a brief description for the latter,
and of those self-sustainable projects of national scope.
Out of the eight co-financed private initiatives, only five initiatives received budgetary capacity
from the Ministry of Economy and Finances. Following is a brief description of the latter, as
well as of the self-sustaining projects with national scope.
Co-financed private initiatives
The co-financed private initiatives under assessment include:
8.1 Peripheral Ring Road
The general purpose of this private initiative is to consolidate part of the Multimodal Axis
reaching from the Amazon Region to the Central Region, along the stretch comprised by the
surroundings of the metropolitan area of Lima, and therefore to form one of the three bi-
national Peru-Brazil integration axes, because there is a direct connection between the
Northern and Southern Pan-American Highway and the Central Highway, which presents
the Ramiro Priale Highway as variant in the surroundings of the metropolitan area.
7 Confidential information in accordance to Legislative Decree No. 1012.
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
34
In addition, the project creates a new itinerary, which completes the road infrastructure of
Lima’s metropolitan area; it creates a new alternative to Lima’s beltway (Via de Evitamiento),
which presents high levels of traffic congestion.
At present, the project is in the concurrent assessment stage of the pre-investment study (it
is being simultaneously assessed by PROINVERSION, the MEF and the MTC), in order to
obtain its feasibility approval and proceed with the corresponding declaration of interest.
8.2 Central Economic Corridor
Its main objective is to connect the main highland cities with the coast with approximately
580 km of road infrastructure. This projects comprises different types of procedures,
including construction in the Ambo – Oyon stretch; conservation, maintenance and
exploitation of the stretches Pumahuasi Bridge – Cerro de Pasco, Oyon – Churin, a nd
Oyon – Rio Seco; and construction of toll booths. These construction works will have an
investment of over US$450 million.
8.3 Road Corridor PE-3N Junction (Dv. Las Vegas) – Tarma – La Merced – Raither
Bridge – Villa Rica – Dv. Puerto Bermúdez – Von Humbolt / Raither Bridge –
Pichanaqui – Dv. Satipo – Puerto Ocopa
Project involving design, construction, operation and maintenance of the road that joins the
cities of Tarma, La Merced, Villa Rica, Puerto Bermúdez, Von Humboldt, Satipo and Puerto
Ocopa, in the central region of the country, with an investment of US$300 million.
The proposal under assessment includes the following procedures: commissioning,
construction of bridges and tunnels, new roadways, drainage systems, various civil
engineering works, and signposting.
Within their scope, the construction works comprise approximately 600 km of roads and
include stretches to be carried out, in a complementary manner, as public works.
8.4 Mass public transport system in the city of Arequipa The goal is to provide an alternative to the city of Arequipa for an appropriate and
convenient solution to deal with the current traffic volume, offering an efficient, fast, safe,
comfortable, environmentally-friendly and sufficiently flexible public transport system in
order to cope with any potential demand variations.
The proposal consists of the design, construction, electromechanical equipment, systems,
rolling stock, financing, operation, and maintenance of a 19-km monorail-type high-speed
mass public transport system in the city’s metropolitan area. These works will have an
investment of over US$960 million.
8.5 Intelligent Transport System (ITS)
It comprises the design, financing, construction, provision, operation, and maintenance of a
digital transfer and logistics infrastructure, including a control and operation center,
specialized observation equipment, installation of speed control systems and dynamic
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
35
weighing devices; technological modernization; as well as operation and maintenance of toll
units which are currently managed by the Ministry.
Self-sustaining private initiatives
The self-sustaining private initiatives under assessment include the following: 8.6 Modernization of Salaverry Port Terminal
This project is currently being studied by the proposer, who is assessing the increase of the
initiative’s scope, as it is now not only a project for construction, installation, operation, and
exploitation of a mineral dock and conveyor belt, but a comprehensive, multi-purpose project
(different type of cargo). Hence, the private initiative estimates an investment of over US$100
million.
8.7 Ica - Dv. Quilca Road Corridor
Road infrastructure concession project (approximately 518 km) specifically in the section of
the Southern Pan-American Highway from Ica to Dv. Quilca, with the exception of the stretch
Nazca - Dv. San Juan de Marcona, which belongs to the Southern Inter-Oceanic Highway
and which is under concession.
The project will allow consolidating the Southern Pan-American Highway as a road offering
top-level service for transport along Peru’s southern coast, thus optimizing transport flows
and reducing logistics costs, increasing both the national and regional competitiveness.
The private initiative proposes the construction of beltways, second lanes and third, fast
lanes along various stretches. These works will have an investment of over US$ 90 million.
8.8 Container Terminal of Chimbote
Its purpose is to meet the demand for specialized port services in the country’s northern
central region, through the development of a new port infrastructure specialized in
container traffic, hence contributing to a reduction of sea freight costs for exporters and
importers.
The private initiative proposes the provision of stevedoring services for containerized vessel
cargo, as well as transferring handling, and stacking national and international containers in
yards. With these objectives, there is a proposal to build a dock and to habilitate a stockyard,
in addition to expanding the port based on demand. The proposal will have an investment
of over US$70 million in its first stage.
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
36
8.9 Multi-Purpose Ilo Port Terminal
At present, this project has been accepted for the procedure stage (PROINVERSION) and
is being assessed by the MTC regarding its relevance and priority.
IX. Investment-Related Public Budget Execution
The investment amounts from the MTC’s public investment and its execution percentage at
the end of each financial year during the period of 2001-2014 are shown in the graph below.
It can be seen that in 2014 the MTC’s investments amounted to PEN6.703 billion, of which
98.0% were implemented.
MTC Investment Budget 2001 - 2014 (expressed in millions of Peruvian Nuevos Soles)
6,086
5,438
6,703
98.0%
3,435
5,241
96.1%
97.0%
5,105
97.9%
98.7%
1,048
1,800
1,311
1,017 1,036 1,231
1,331 1,344
95.3%
79.1% 74.2% 92.3% 82.9% 75.2% 75.3% 73.3%
2,001 2,002 2,003 2,004 2,005 2,006 2,007 2,008 2,009 2,010 2,011 2,012 2,013 2,014
Source: MTC - OGPP – Budget Office; MEF - Friendly Consultation.
Prepared by MTC - OGPP
X. Outstanding Projects
10.1 Granting of Regional Optical Fiber Networks
The purpose of regional projects is to achieve comprehensive connection of a
region with all its towns and villages, thus promoting local, regional and national
integration, which favors and facilitates social inclusion, economic
development, competitiveness, national security, and organizational
transformation towards an information and knowledge society.
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
37
The Technical Secretariat of the Telecommunications Investment Fund (FITEL, by its
Spanish initials) has been appointed by the Vice-Ministry of Communications for preparing
the pre-investment studies for the regional networks projects, which will expand the points
of presence of the Optical Fiber Backbone Network (RDNFO).
To this end, FITEL is in charge of formulating twenty-one (21) regional projects, of which ten
(10) have a completed pre-investment study, while the formulation of the remaining (11)
regional projects will entirely take place in 2015.
List of regional projects that will complete their pre-investment studies in 2015.
No.
Region
SNIP Code
Current Status
1
Lambayeque
226458
In process at PROINVERSION
2
Huancavelica
258101
In process at PROINVERSION
3
Apurímac
258219
In process at PROINVERSION
4
Ayacucho
263291
In process at PROINVERSION
5
Tumbes
263348
Entrusted to PROINVERSION
6
Cajamarca
263246
Entrusted to PROINVERSION
7
Piura
264822
Entrusted to PROINVERSION
8
Cusco
267611
Entrusted to PROINVERSIÓN
9
Ica
311058
Under assessment at the OPI
10
Lima
311125
Under assessment at the OPI
11
Huánuco
266628
In Formulation
12
Tacna
NA In Formulation
13
Ancash
NA In Formulation
14
Pasco
NA In Formulation
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
38
15
Arequipa
NA In Formulation
16
La Libertad
NA In Formulation
17
Junín
NA In Formulation
18
Puno
NA In Formulation
19
Amazonas
NA In Formulation
20
San Martín
NA In Formulation
10.2 Awarding of 700 MHz band to provide cutting-edge mobile Internet (4G – LTE
technology)
The awarding of the three 700 MHz band blocks for nationwide provision of cutting-edge
mobile internet (4G – LTE technology) is expected to take place in 2015.
10.3 Awarding of Block C of 1.7/2.1 GHz band to provide cutting-edge mobile internet
(4G – LTE technology)
Based on a proposal by the “Permanent Multisectoral Committee in charge of issuing
technical reports and recommendations for planning and managing the radio spectrum,” the
Directorate-General for Regulation and International Affairs in Communications has
proposed to carry out a public tender for Block C of the 1.7/2.1 GHz band for providing
cutting-edge mobile internet (4G – LTE technology), which will generate more competition
in the mobile public service market.
10.4 Awarding of Third Airport Group
This includes granting the concession for the third group of airports, which includes the
following national airports: Jauja, Huánuco, and Jaén. Previously, the Jauja Airport will be
part of a program to improve its infrastructure, as public work, as part of the execution of its
master plan.
10.5 Inclusion of Amazon Region by Air
The objective of this program is to improve access and inclusion for people living in towns
and villages of the Peruvian Amazon Region through a subsidized flight scheme, providing
adequate operational conditions and facilities for provision of passenger air transport
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
39
services from the region’s major cities, giving priority to isolated villages and towns located
in border areas and to those with economic and/or tourism potential.
As part of the program, 20 aerodromes have been selected to form a network, articulated to
4 regional hubs (Iquitos, Pucallpa, Tarapoto, and Puerto Maldonado) considering social,
economic and geographic criteria.
At the end of 2014, fieldwork had been carried out in 10 of the 20 aerodromes, in order to
determine the airport infrastructure’s current condition and to establish a set of improvements
to be implemented through Public Investment Projects (PIP), which must be prepared in
2015.
The audited involved are El Estrecho, Caballococha, Gueppi, Colonia Angamos, and San
Lorenzo (Loreto); Breu, Sepahua, Puerto Esperanza and Atalaya (Ucayali), and Galilea
(Amazon Region).
10.6 Expansion and Modernization of Jorge Chavez International Airport (AIJCH)
The objective is to initiate the implementation of the second stage, which comprises the
expansion and modernization of Jorge Chavez International Airport (second runway, new
passenger terminal, and new control tower), which will require an investment of
approximately US$850 million.
During the second quarter of 2014, the concessionaire LAP preparing the Engineering
Design for Expansion and Modernization of AIJCH, which will cost US$17.8 million and is
estimated to be finished by the second half of 2016. The Conceptual Design of this project
will be finished in the second quarter of 2015.
10.7 Improvement of Avenida Santa Rosa (including Bridge over Rimac River)
As part of the implementation of the second stage comprising the expansion and
modernization of Jorge Chavez International Airport, the MTC has been developing the
project for an access road to the new passenger terminal along Avenida Santa Rosa. To
this effect, procedures to reclassify the road as “national road” are underway, which will
allow PROVIAS NACIONAL to formulate both the pre-investment (Profile and Feasibility in
one) and final studies.
10.8 Move forward with consolidation of Lima’s Metro Network
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
40
The purpose is to move forward with the consolidation of Lima’s Metro Network, continuing
the execution and follow-up for granting the concession for Line 3 of Lima’s Metro, which
concentrates most of the city’s demand for public transport. Furthermore, the baseline
studies for Line 4 of Lima’s Metro will be prepared.
10.9 Support to road management by subnational governments
In order to continue supporting the rehabilitation and conservation of the rural road
infrastructure, as well as to strengthen road management skills capabilities by promoting the
articulation of sectoral policies in sub-national governments, Provias Descentralizado has
been preparing the Subnational Transport Support Project (PATS, by its Spanish initials),
which will be executed during the 2016-2020 period, with an estimated investment of US$600
million.
10.10 Other pending issues
Other pending issues for the current administration include implementing the project
corresponding to the Intelligent Transport System (ITS), the Truck Center project (support
service for shipping agents), the relocation of Arequipa’s Rodriguez Ballon Airport to the Air
Force Base of La Joya, as well as assessing the relocation of the Chachapoyas Airport.
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
41
ANNEXES
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
42
ANNEX 1: ROADS COMPLETED BETWEEN AUGUST 2011 AND DECEMBER 2014
Nº
PROJECTS
LOCATION
LENGTH
Km.
Start Date
End Date
1 Casma-Yautan-Huaraz Road, Pariacoto – Yupash Stretch Ancash 39.33 May 02, 2009 October 08, 2011
2 Ayacucho Abancay Road, Km. 98 000 - 154 000 Apurimac, Ayacucho 55.20 July 13,2012 August 06, 2014
3 Ayacucho – Abancay Road, Km. 154 000 - Km. 210 000 Apurimac 41.97 May 21, 2010 October 04, 2012
4 Ayacucho – Abancay Road, Km. 210 000 - Km. 256 000 Apurimac 45.40 April 07, 2010 November 17, 11
5 Ayacucho – Abancay Road, Andahuaylas - Dv. Kishuara Stretch Apurimac 53.30 September 15, 2009 October 15, 2012
6 Ayacucho – Abancay Road, Dv. Kishuara - Sahuinto Bridge Stretch Apurimac 76.45 January 09, 2013 December 22, 2014
7 Punta de Bombon - Fundicion - Ciudad Jardin - Ilo Road Arequipa, Moquegua 91.60 March 31, 2010 February 29, 2012
8 Ayacucho – Abancay Road, Km. 00 000 - Km. 50 000 Ayacucho 50.00 April 01, 2010 October 31, 2011
9 Ayacucho – Abancay Road, Km. 50 000 - Km. 98 800 Stretch Ayacucho 48.80 April 01, 2012 September 20, 2013
10 Quinua - San Francisco Road, Km 26 -78 +500 Stretch Ayacucho 50.91 April 01, 2011 August 19, 2013
11 Chongoyape – Llama Road Cajamarca, Lambayeque 59.34 October 19, 2010 September 26, 2012
12 Llama – Cochabamba Road Cajamarca 60.46 December 01, 2010 December 02, 2013
13 Cochabamba – Chota Road Cajamarca 31.86 December 20, 2011 December 31, 2014
14 Hualgayoc – Yanacocha Road Cajamarca 51.00 May 23, 2009 February 17, 2012
15 Cajamarca - Celendin – Balzas Road, Km 52 – Celendin Stretch Cajamarca 42.78 December 06, 2011 November 10, 2013
16 Cajamarca - Celendin – Balzas Road, Km. 26+000 - 52+000 (balance) Stretch
Cajamarca 26.00 January 12, 2013 June 11, 2014
17 San Ignacio - Integración Bridge Road Cajamarca 45.99 March 16, 2012 December 21, 2013
18 El Descanso – Langui Road Cusco 19.82 October 29, 2010 March 27, 2012
19 Alfamayo - Chaullay – Quillabamba Road Cusco 54.09 April 09, 2010 August 27, 2013
20 Sambarai - Dv. Puente Echarati Road Cusco 21.34 September 30, 2010 December 30, 2013
21 Dv. Las Vegas – Tarma Road Junin 32.62 September 29, 2012 July 02, 2014
22 Lunahuana - Dv Yauyos - Chupaca Road, Ronchas – Chupaca Stretch Junin 16.30 June 30, 2010 September 23, 2011
23 Reither Bridge - Paucartambo Bridge – Villarica Road Junin, Pasco 39.40 April 01, 2011 August 12, 2013
24 Santiago De Chuco – Shorey Road La Libertad 37.33 February 12, 2011 June 13, 2012
25 Dv. Otuzco - Dv. Callacuyan Road La Libertad 70.90 November 04, 2010 March 28, 2014
26 Ramiro Priale - Las Torres Highway - Central Highway Lima 9.11 March 16, 2010 October 11, 2011
27 Churin – Oyon Road, Churin Stretch 1 - Km. 131 Lima 24.19 June 02, 2010 December 18, 2011
28 Churin – Oyon Road, Stretch. 2: Km 131 - Oyon - Km 135+050 Lima 4.89 November 17, 2009 January 18, 2012
29 Mala - Calango - La Capilla Road Lima 25.48 August 12, 2012 December 03, 2013
30 PE-1N junction Rio Seco – El Ahorcado Road– PE-18 (Sayan) junction
Lima 42.60 March 08, 2013 August 08, 2014
31 North Pan-American Highway, Stretch III Km 886+600 - 1033+100* Piura 146.50 September 17, 2013 July 31, 2014
32 Construction of Piura’s beltway (Via de Evitamiento) Piura 11.54 March 02, 2014 July 30, 2014
33 Ilave-Mazocruz Road, Ilave – Checca Stretch Puno 10.03 August 18, 2012 August 05, 2013
34 Pizana Bridge – Tocache Road San Martin 37.70 June 06, 2012 December 07. 2013
35 Juanjui – Campanilla Road San Martin 43.28 April 05, 2013 December 08, 2014
TOTAL 1,517.50
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
43
ANNEX 2: ROADS UNDER EXECUTION
Nº
PROJECTS
LOCATION
LENGTH
Km.
Start Date
End Date
1 El Arenal - Punta de Bombon Road Arequipa 45.21 January 10, 2015 December, 2016
2 Dv. Quilca – Matarani Road Arequipa 94.46 May 04, 2013 November, 2015
3 Dv. Imata - Oscollo – Negromayo Road Arequipa, Cusco 67.73 April 30, 2013 March, 2016
4 Quinua - San Francisco Road, Stretch 2: km 78+500 - km 172+420 (San
Francisco) Ayacucho 94.59 April 10, 2012 October, 2016
5 Chota - Bambamarca – Hualgayoc Road Cajamarca 58.86 May 13, 2012 December, 2015
6 Pericos - San Ignacio Road (Via Evitamiento) Cajamarca 54.58 January 15, 2013 March, 2015
7 San Marcos – Cajabamba Road Cajamarca 58.80 September 03, 2013 January, 2016
8 Huacavelica-Lircay Road, Stretch: km 1+550 (Av. Los Chancas) - Lircay Huancavelica 71.95 March 02, 2015 February, 2017
9 Dv Imperial – Pampas Road Huancavelica 36.85 November 07, 2014 May, 2016
10 Mayocc – Huanta Road Huancavelica, Ayacucho 27.54 September 03, 2013 June, 2015
11 Satipo - Mazamari - Dv. Pangoa – Ocopa Port Road Junin 65.82 May 07, 2013 November, 2015
12 Yanango Tunnel and accesses Junin 1.75 January 13, 2015 July, 2016
13 Huamachuco – Sacsacocha - Pallar Bridge R o a d (*) La Libertad 28.32 April 01, 2013 January 13, 2015
14 North Pan-American Highway, Stretch 0-I y II: km 557+000 t o km 886+600 La Libertad, Lambayeque 329.60 May 16, 2014 May, 2015
15 Construction Completion of Pimentel-Chiclayo Path Lambayeque 2.97 February 01, 2014 March, 2015
16 Cañete – Lunahuana Road Lima 37.84 January 11, 2014 August, 2015
17 Lima – Canta Road Lima 79.47 May 26, 2012 July, 2015
18 Lima-Canta-Huayllay-Dv. Cochamarca Road Corridor- PE 3N junction, Canta -
Huayllay Stretch Lima, Pasco 96.11 September 30, 2014 September, 2016
19 Huaura - Sayan Road - Tingo Bridge Lima 99.28 April 24, 2013 December, 2015
20 Stretch III - B of the Improvement Program for Aven id a Nestor Gambetta – Callao
Lima 2.10 May 07, 2014 November 28, 2014
21 Dv. La Tina - La Tina Surpampa - Chirinos – Cachaquito Road Piura 14.33 October 11, 2014 April, 2015
22 Selva Alegre Road - PE-5N junction Road (La Calzada) San Martin, Amazonas 27.39 March 02, 2015 February, 2016
23 Expansion of the Second Roadway, Stretch: Dv. Pucallpa Airport – Close to Jardin del Buen Recuerdo Cemetery.
Ucayali 10.03 May 01, 2014 September, 2015
24 Chino B r i dg e – Aguaytia Road, Damaged Sectors Ucayali 7.94 August 01, 2015 November, 2015
TOTAL 1,413.51
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
44
ANNEX 3: ROADS CONCESSIONS
Nº
CONCESSION
TERM
(YEAR
S)
LENGTH
(km.)
ENGAGED
INVESTMENT
(US$ Mill.)
ACCRUED
INVESTMENT
(Dec-14)
(US$ Mill.)
CONTRACT
DATE
MODE
1
Multimodal Axis of the North Amazon Region
25
955.07
510.26
453.09
17/06/05
Co-financed
South IIRSA Inter-Ocean South Corridor
2
Stretch 1: San Juan de Marcona - Urcos
25
757.64
145.42
139.52
23/10/07
Co-financed
3
Stretch 2: Urcos - Inambari
25
300.00
653.66
650.16
04/08/05
Co-financed
4
Stretch 3: Inambari - Iñapari
25
403.20
616.15
601.93
04/08/05
Co-financed
5
Stretch 4: Inambari - Azangaro
25
305.90
686.17
661.05
04/08/05
Co-financed
6
Stretch 5: Matarani - Azangaro, Ilo - Juliaca
25
854.68
199.27
186.89
24/10/07
Co-financed
7
Road Network No. 5: Ancon - Huacho - Pativilca
25
182.66
75.05
59.22
15/01/03
Self-sustainable
8
Road Network No. 6: Pucusana - Ica
30
380.09
231.86
92.34
20/09/05
Self-sustainable
9
Road Network No. 4:Pativilca-Casma-Trujillo – Salaverry Port
25
356.21
286.17
115.48
18/02/09
Self-sustainable
10
Chancay Roundabout / Dv. Variant Pasamayo-Huaral-Acos
Costa-Sierra Road Program
15
76.50
41.57
37.07
20/02/09
Co-financed
11
Mocupe-Cayalti-Oyotun New
Costa-Sierra Road Program
15
46.80
24.85
24.83
26/01/09
Co-financed
12
Autopista del Sol, Trujillo - Sullana
25
475.00
299.96
56.40
25/08/09
Self-sustainable
13
Axis of the Central Amazon of IIRSA, Stretch II: Ricardo Palma Bridge – La Oroya - Huancayo / La Oroya - Dv. Cerro de Pasco
25
377.00
100.00
0.00
27/09/10
Self-sustainable
14
1B junction - Buenos Aires - Canchaque
15
78.13
36.75
36.75
09/02/07
Co-financed
15
Vial Dv. Quilca - Dv. Arequipa - Dv. Matarani - Dv.
Moquegua - Dv. Ilo - Tacna - La Concordia
25
428.61
160.00
0.00
30/01/12
Self-sustainable
16
Longitudinal Road of the Highlands, Stretch: Ciudad de Dios -
Cajamarca - Chiple, Cajamarca - Trujillo y Dv. Chilete - Empalme PE-3N
25
874.11
173.87
14.30
28/05/14
Co-financed
TOTAL 6,851.60 4,241.00 3,129.03
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
45
ANNEX 4: SERVICE-LEVEL MAINTENANCE CONTRACTS
Nº
Corridor
Department Contract
Length km
Initially Contracted
S /.
Subscription Date
End Date
1
Juliaca - Huancane- Moho-Tilali- Bolivia Border-and dv. Huancane-Putina-Sandia- San Ignacio
Puno
438.80
188,656,802 October, 2009
November, 2014
2
Regional limitation: Dv. Bayovar a nd Via Evitamiento Chiclayo - Lambayeque - Mocce - Dv Olmos
Lambayeque
261.66
63,184,567
October, 2009
September, 2014
3
3S junction - La Quinua -San Francisco - Union Mantaro (Pto Ene) - Punta de Carretera
Ayacucho
306.00
125,721,100
December, 2009
December, 2014
4
Ricardo Palma Bridge-La Oroya- Huancayo-and Jauja- Tarma
Lima, Junin
349.39
149,465,843
December, 2009
November, 2014
5 3S Comas junction. Satipo-Mazamari- Ocopa Port-Atalaya and Mazamari-San Martin de
Pangoa- Punta de Carretera
Junin
472.80
235,991,800
January, 2010
February, 2015
6 Pe 1N junction - Dv. Otuzco -dv. Cayacuyan- Huamachuco -Cajabamba - San
Marcos - Cajamarca
La Libertad- Cajamarca
334.00
104,197,512 January, 2010
February, 2015
7
1N Conococha junction- Huaraz-Caraz-Molinopampa- and 3N junction - Chiquian- Aquia- 3N junction
Ancash
332.00
175,638,809 January, 2010
March, 2015
8 Pimentel Road - PE 1N junction/ Chiclayo-Chongoyape- Cumbil Bridge - PE 3N
junction (cochabamba)-Chota- Hualgayoc- and 3N junction- Santa Cruz-Cumbil
Bridge
Lambayeque -
Cajamarca
394.00
132,727,173
February, 2010
March, 2015
9
Dv. Bayovar - Bappo - Sechura - Piura - Dv. Bayovar
Piura
253.00
64,918,500 February, 2010
January, 2015
10 PE-22B junction (Raither Bridge)- Paucartambo Bridge-Villa Rica- Bermudez Bridge- Von Humbolt and Paucartambo Bridge- Oxapampa
Junin- Pasco
365.00
204,295,529 February, 2010
March, 2015
11
Dv. Las Vegas – Tarma – La Merced - Satipo
Junin
230.40
71,875,238 February, 2010 January,
2015
12 Dv. Paita-Sullana-Dv. Talara-Mancora-Aguas Verdes, Sullana-Macara and International Border of Peru side, Axis Road No. 01
Tumbes, Piura
437.60
141,409,094 February, 2010 January,
2015
13 3S junction (Izuchaca)-Huancavelica-Plazapata-Castrovirreyna-Ticrapo-Pampano-Santa
Ines- Pilpichaca y Rumichaca
Huancavelica
290.00
133,896,680
March, 2010 March, 2015
14
Chachapoyas- Molinopampa-Rodriguez de Mendoza- Punta Carretera
Ancash
135.00
77,232,106
April, 2010
July,1205
15
PE 18 A junction (Dv. Tingo Maria) Aucayacu-Nuevo Progreso Tocache- Juanui Picota- Tarapoto
San Martin Ucayali
458.00
181,376,627 April, 2010
April, 2015
16
Dv. Abancay- Chuquibambilla-Chalhuahuacho- Santo Tomas -Yauri
Apurimac- Cusco
436.00
176,737,225 April, 2010
May, 2015
17
Guadalupe- Ica- Palpa- atico
Ica, Arequipa
379.78
113,725,146 April, 2010
March, 2015
18
Dv. Cochabamba-Cutervo - North IIRSA junction- Chamaya-Jaen- San Ignacio-Puente la Balsa
Cajamarca - Amazonas
267.00
106,709,571
May, 2010 June, 2015
19 Cusco Pisac-Urcos- La Raya- Urubamba Chincheros y Yauri- San Genaro- Sicuani y
Huarcapay- Huambutio- Pisac- Alfamayo-Quillabamba
Cusco
515.88
165,511,462
June, 2010
May, 2015
20
Puno - Desaguadero, Calapuja - La Raya e Ilave - Mazocruz
Puno
367.50
127,755,067
September, 2010
August, 2015
21
Atico – Dv.Quilca -La Reparticion, Dv.Matarani-Pte.Montalvo a n d Dv.Ilo-Pte.Camiara Arequipa - Moquegua -
Tacna
457.82
170,988,279
October, 2010
September, 2015
22
Ciudad de Dios – Cajamarca, Chilete – Contumaza and Chicama - Cascas
Cajamarca - La Libertad
285.90
90,580,460
February, 2011 January, 2016
23
Punta Pejerrey San Clemente Ayacucho
Lima - Ayacucho
365.56
128,608,590
July, 2011 June, 2016
24
Cajamarca - Celendin - Balsas - Chachapoyas and Dv. Chachapoyas - Pedro Ruiz
Cajamarca - Amazonas
367.00
156,245,079
May, 2012
May, 2017
25 Santa - Yuracmarca - Sihuas - Huacrachuco - San Pedro De Chonta - Uchiza - Pe-5n junction
and Huarochiri Bridge- Huallanca - Molinopampa
Ancash- Huanuco
536.00
172,127,298 May, 2012 May, 2017
26
Huancayo - Imperial - Izcuchaca - Ayacucho E Imperial- Pampas- Mayocc
Junin- Huancavelica
430.00
177,593,943 May, 2012 May, 2017
27
PE 04-B junction (Hualapampa) - Sondor - Huancabamba - Pacaipampa - Socchabamba -
Puesta Vado Grande/Sondor - Tabaconas - PE 5N junction (Ambato) / Huancabamba -
Canchaque y Socchabamba - Ayabaca.
Piura Cajamarca
610.00
241,744,268
August, 2012
August, 2017
28
PE 3S junction (Abra Toccto) - Querobamba - Puquio
Ayacucho
372.00
176,226,889 August, 2012 August, 2017
29 Puquio - Cora Cora - 1S junction (Chala)/Cora Cora - Yauca - PE 1S junction/ PE junction
(Ullaccasa) - Pausa
Ayacucho - Arequipa
526.00
237,437,331 August, 2012 August, 2017
30
Rosario – Sivia – Canayre and San Francisco – Santa Rosa – San Miguel - Tambo
Ayacucho
324.00
149,776,440
December, 2012
December, 2017
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
46
“Decade of Persons with Disabilities in Peru”
“Year of the promotion of productive diversification and strengthening of education”
47
ANNEX 4: SERVICE-LEVEL MAINTENANCE CONTRACTS
Nº
Corridor
Department Contract
Length km
Initially Contracted
S /.
Subscription Date
End Date
31 Ayacucho – Tambillo – Ocros - Pe-32 A junction (Chalco) and Pampa Cangallo – Carapo -
Huancasancos-Llauta-Palpa
Ayacucho - Ica
341.00
164,342,506
January, 2013
December, 2017
32 Chuquicara Bridge - Cabana - Pallasca - Santiago de Chuco - Shorey y Tauca - Bambas - Dv.
Sihuas
Ancash - La Libertad
408.00
129,101,477
April, 2013 March 2018
33 Huancavelica - Lircay - PE-3S junction (Huallapampa) a nd PE 3S junction (La Mejorada) -
Acobamba - PE 3S junction (Alcomachay Bridge)
Huancavelica
Ayacucho
343.00
171,761,703
July, 2013 June, 2018
34
PE-5N junction (El Reposo) - Duran-Puente Wawico - Nieva-Saramiriza Bridge / Wawico
Bridge - Urakusa - Santa Maria de Nieva - Saramiriza and Juan Velasco Alvarado - Achoaga –
PE junction
5NC (Nuevo Seasmi)
Amazonas
378.00
194,713,291
July, 2013
June, 2018
35
Pumahuasi Bridge- Chino Bridge Aguaytia San Alejandro Neshuya Pucallpa
Ucayali
234.49
141,938,642
January, 2014
January, 2019
36
Huanuco- La Union- Huallanca- Dv. Antamina
Huanuco- Ancash
172.00
20,190,546
February, 2014 April, 2015
37 Dv Cerro de Pasco - Tingo Maria and 5N junction (Pumahuasi Bridge) Pasco 249.00 136,795,444 March, 2014 February, 2017
38
Lima-Canta-Huayllay-Dv. Cochamarca- PE 3N junction
Lima, Pasco
207.00
94,050,000
June, 2014 April, 2022
TOTAL CONTRACTED
13,631
5,495,248,037
AGREEMENT
39
PE-28B junction (San Francisco Bridge) - Kimbiri - Chahuares (Dv. Quellouni) - Dv. Echarati
Cusco
280
December, 2012
a/ Agreement 003-2013-MTC/20, Contract No 190-2012-GR CUSCO/GGR
TOTAL CONTRACTED AND UNDER AGREEMENTS
13,911
5,495,248,037