BY M A R I A RA M O S , P E , L E E D A P , C X A
ACHIEVING ASHRAE 90 PLUS 30
![Page 2: Achieving ASHRAE 90 plus 30](https://reader035.vdocument.in/reader035/viewer/2022062412/5885f7011a28ab864f8b6dc7/html5/thumbnails/2.jpg)
ABOUT ME
• Employed at Fosdick and Hilmer in Cincinnati• First LEED project in 2007• Performed energy modeling on about 10 LEED
projects• Have achieved platinum, gold and silver status• Use primarily Trace 700 for energy modeling. I
have also used Equest.
![Page 3: Achieving ASHRAE 90 plus 30](https://reader035.vdocument.in/reader035/viewer/2022062412/5885f7011a28ab864f8b6dc7/html5/thumbnails/3.jpg)
AUDIENCE
• What is your experience with LEED?
![Page 4: Achieving ASHRAE 90 plus 30](https://reader035.vdocument.in/reader035/viewer/2022062412/5885f7011a28ab864f8b6dc7/html5/thumbnails/4.jpg)
RESOURCES AVAILABLE FOR GUIDANCE
• ASHRAE Advanced Energy Guidelines• http://aedg.ashrae.org/• Has guides for a variety of buildings, achieving
plus 30 and plus 50% savings
![Page 5: Achieving ASHRAE 90 plus 30](https://reader035.vdocument.in/reader035/viewer/2022062412/5885f7011a28ab864f8b6dc7/html5/thumbnails/5.jpg)
SAMPLE MODEL ASSUMPTIONS
• Midrise Medical Office building, 5 floors, 150,000 SF• Space types: enclosed office, open plan office,
corridor, conference area, exam rooms, operating rooms• Started out with baseline and proposed both
100% ASHRAE compliant (so nothing in the proposed did not meet ASHRAE 90)• 32% glass• System 7s with 95% filtration, ducted return• Hot water boiler, screw chillers
![Page 6: Achieving ASHRAE 90 plus 30](https://reader035.vdocument.in/reader035/viewer/2022062412/5885f7011a28ab864f8b6dc7/html5/thumbnails/6.jpg)
ECM #1
• Increase roof insulation to R-30 and wall insulation to R-15.6 ci• Cumulative savings: 0.2%
![Page 7: Achieving ASHRAE 90 plus 30](https://reader035.vdocument.in/reader035/viewer/2022062412/5885f7011a28ab864f8b6dc7/html5/thumbnails/7.jpg)
![Page 8: Achieving ASHRAE 90 plus 30](https://reader035.vdocument.in/reader035/viewer/2022062412/5885f7011a28ab864f8b6dc7/html5/thumbnails/8.jpg)
ECM #2
• Fenestration improvements, U value of 0.29, SHGC=0.34• Resulted in cumulative savings of 0.61%• Added in sunshades for south facades, but took
them back out because they caused a slight increase in energy usage• Glass ECMs may have a bigger impact on a
different building• What happens when there is an unexpected
result?
![Page 9: Achieving ASHRAE 90 plus 30](https://reader035.vdocument.in/reader035/viewer/2022062412/5885f7011a28ab864f8b6dc7/html5/thumbnails/9.jpg)
![Page 10: Achieving ASHRAE 90 plus 30](https://reader035.vdocument.in/reader035/viewer/2022062412/5885f7011a28ab864f8b6dc7/html5/thumbnails/10.jpg)
![Page 11: Achieving ASHRAE 90 plus 30](https://reader035.vdocument.in/reader035/viewer/2022062412/5885f7011a28ab864f8b6dc7/html5/thumbnails/11.jpg)
![Page 12: Achieving ASHRAE 90 plus 30](https://reader035.vdocument.in/reader035/viewer/2022062412/5885f7011a28ab864f8b6dc7/html5/thumbnails/12.jpg)
ECM #3
• Improve lighting W/SF• Exam rooms, 1.2 (1.66 allowed)• Laboratory, 1.2 (1.8 allowed)• Office, 0.9 (1.1 allowed)• Did not change patient rooms (0.62 allowed), operating
rooms (1.89 allowed), or corridor (0.89 allowed)• Did not include any savings for occ sensors in non-
required areas
• Cumulative savings 1.35%
![Page 13: Achieving ASHRAE 90 plus 30](https://reader035.vdocument.in/reader035/viewer/2022062412/5885f7011a28ab864f8b6dc7/html5/thumbnails/13.jpg)
![Page 14: Achieving ASHRAE 90 plus 30](https://reader035.vdocument.in/reader035/viewer/2022062412/5885f7011a28ab864f8b6dc7/html5/thumbnails/14.jpg)
ECM #4
• Improve HVAC plants• VFD on tower fans• Reduce cooling, heating pumping energy (22 W/GPM
allowed, 19 W/GPM allowed)• HW boiler 90% efficient
Cumulative savings: 3.2%
![Page 15: Achieving ASHRAE 90 plus 30](https://reader035.vdocument.in/reader035/viewer/2022062412/5885f7011a28ab864f8b6dc7/html5/thumbnails/15.jpg)
ECM #5
• Improve chiller efficiency to 0.57 kw/T (need a VFD chiller to accomplish this)• Cumulative savings: 5.4%• A lot more can be done here if your building has
centrifugal chillers
![Page 16: Achieving ASHRAE 90 plus 30](https://reader035.vdocument.in/reader035/viewer/2022062412/5885f7011a28ab864f8b6dc7/html5/thumbnails/16.jpg)
ECM #6
• HVAC—Increase motor efficiency on fans (to 95%)• Calculate kw-cfm/in-wg for each fan• Cumulative savings: 12.5%
![Page 17: Achieving ASHRAE 90 plus 30](https://reader035.vdocument.in/reader035/viewer/2022062412/5885f7011a28ab864f8b6dc7/html5/thumbnails/17.jpg)
ECM #7
• Bring miscellaneous equipment down to around 25% of baseline (by energy usage, not cost at this stage)• Not strictly an ECM, but helps other ECMs have
more impact• Will impact the baseline• Cumulative savings: 14.5%
![Page 18: Achieving ASHRAE 90 plus 30](https://reader035.vdocument.in/reader035/viewer/2022062412/5885f7011a28ab864f8b6dc7/html5/thumbnails/18.jpg)
![Page 19: Achieving ASHRAE 90 plus 30](https://reader035.vdocument.in/reader035/viewer/2022062412/5885f7011a28ab864f8b6dc7/html5/thumbnails/19.jpg)
ECM #8
• Add daylighting with continuous dimming, all exterior rooms in proposed• Cumulative savings: 17%
![Page 20: Achieving ASHRAE 90 plus 30](https://reader035.vdocument.in/reader035/viewer/2022062412/5885f7011a28ab864f8b6dc7/html5/thumbnails/20.jpg)
WHAT TO DO NEXT?
• We’ve exhausted our list from the plus 30 guide• Go to the plus 50 Hospital. Also browse the other
guides• Some other resources:• http://www.i2sl.org/resources/toolkit.html• http://energy.gov/eere/efficiency/buildings
• I’m going to add a few ECMs I’ve used previously
![Page 21: Achieving ASHRAE 90 plus 30](https://reader035.vdocument.in/reader035/viewer/2022062412/5885f7011a28ab864f8b6dc7/html5/thumbnails/21.jpg)
ECM #9
• Reduce airflow in O.R.s at night• Reduce from 20 ACH daytime to 50% at night• Will require tracking boxes on supply, return for
pressurization control• Can be used in labs or other spaces where a high
airchange rate is required by ASHRAE 170• Cumulative savings: 22.8%
![Page 22: Achieving ASHRAE 90 plus 30](https://reader035.vdocument.in/reader035/viewer/2022062412/5885f7011a28ab864f8b6dc7/html5/thumbnails/22.jpg)
ECM#10
• Add heat recovery chiller to proposed• 250 T heat recovery chiller, rejects heat to the heating
plant• Cost
Cumulative savings: 26.0%
![Page 23: Achieving ASHRAE 90 plus 30](https://reader035.vdocument.in/reader035/viewer/2022062412/5885f7011a28ab864f8b6dc7/html5/thumbnails/23.jpg)
OTHER POTENTIAL ECMS
• Separate OA treatment• Energy recovery• Use energy star rated computers, etc and take
credit for it in the W/SF receptacle density• More efficient elevators (trackless), take credit for
it in the miscellaneous loads
![Page 24: Achieving ASHRAE 90 plus 30](https://reader035.vdocument.in/reader035/viewer/2022062412/5885f7011a28ab864f8b6dc7/html5/thumbnails/24.jpg)
MINOR REFINEMENTS
• Custom unloading curves• Raise chilled water temps if you can (and use
improved chiller kw/T)• Calculate out actual u value of window assy• Consider exterior lighting savings• Increase supply air reset by 1 degree
![Page 25: Achieving ASHRAE 90 plus 30](https://reader035.vdocument.in/reader035/viewer/2022062412/5885f7011a28ab864f8b6dc7/html5/thumbnails/25.jpg)
LEED/HIGH ENERGY SAVINGS PROCESS
Development of
Schematic Energy Model
•Identify and evaluate major cost impact items, i.e. Daylighting sensors, LED lights, Heat recovery chiller, improved glass or insulation. Contractor input very helpful for pricing.
DD/CD
•May have to create an energy model before rooms are known. This model will be “throw away”
Major cost impact items
Construction•Energy model assumptions are documented in submittals
• Refine equipment selections, make sure any model assumptions are reflected in bid docs
![Page 26: Achieving ASHRAE 90 plus 30](https://reader035.vdocument.in/reader035/viewer/2022062412/5885f7011a28ab864f8b6dc7/html5/thumbnails/26.jpg)
QUESTIONS?