acid bricks lining_bid
TRANSCRIPT
-
8/4/2019 Acid Bricks Lining_BID
1/2
Part III Priced Bid
D:\Backup D\dk\PAP\price bid pap art.doc
SCHEDULE OF RATES PERCETAGE RATE TEDER
ame of Work :-Acid Proof Lining work at PAP inside RCF
Trombay Factory.
Sr.No. DESCRIPTION QUANTITY UNIT
RATE
(Rs./Unit) AMOUNT (Rs.)
1
Removing existing Acid resistant brick /Tiles from the position including beddingmortar & underneath layers to exposethe surface area as directed transportingthe bricks / tile to RCF store or other sitecarting away the unserviceable materialas directed.
100.00 m2
89.19 8919.02
2Providing & applying Bitumen Masticuniformly formulating the consistentcomposition as specified, 12 mm thick.
600.00 m3
312.17 187299.32
Providing and laying acid resistant tilesof size 230 x 114 x 38 mm thick with
potassium silicate bedding and bondingmortar about 6 mm thick to the unitsurface keeping the joint width 3 to 4mm within the adjacent bricks & properlyset removing the mortar from the joint tofull size and to a depth of 20 mm and
jointing with following particular type ofchemical resistant mortar as permanufacturer's Specification and asdirected.
3
Furan Resin Mortar 350.00 m3
1204.07 421423.47
5
Providing & Jointing the spoilt, damagedjoint of the existing acid resistant bricks /tiles after removing the mortar from the
joints to full side cleaning the sameincluding preparation of surface withparticular type of chemical resistantmortar as mentioned below :Furan / Phenolic resin mortar
300.00 m2
312.17 93649.66
6
Laying acid / alkali resistant bricks / tilessupplied by RCF after cleaning oldstains of mortar, pointing, beddingmortar as per procedure mentioned inthe item no. 3
7 Furan Resin Mortar 50.00 m2
713.52 35676.06
Supplying of manpower with tools andtackles for attending misc. jobs for 8hours per day
a Semi Skilled 10.00 Nos 217.62 2176.20
b Unskilled 10.00 Nos. 210.77 2107.70
TOTAL (```.) Excluding Tax 751251.43
(B.K. Joshi)
CE (C)
-
8/4/2019 Acid Bricks Lining_BID
2/2
Part III Priced Bid
D:\Backup D\dk\PAP\price bid pap art.doc
ote :
1) For all above items specifications BMC FMRS 2009 shall be considered.2) Contractor shall bring material by making proper entry at RCF gate No:2 through
CISF.
PART : B
The following taxes shall be payable extra:
VAT under Composition @ 8.00 % On All above Items
Service Tax under Composition @ 4.12 % On All above Items
(B.K. Joshi)CE (Civil)
PART : C
Our Quoted Rates are . % above / below the rates specifiedin PART A
Contractors Signature with Seal & Date