COMMUNICATE • MEASURE • CONTROL Advanced Metering Infrastructure (AMI) at work, a case study. Hannover, April 11 th 2014 Davide Tappeiner – CEO, Tekpea Inc.

Upload: donato-mangialardo

Post on 18-Dec-2014

77 views

Category:

Environment


1 download

DESCRIPTION

Here is a preview of Tekpea's CEO Davide Tappeiner talk at the Smart Grid Forum of Hannover Messe, the world’s leading trade fair for industrial technology.

TRANSCRIPT

Page 1: Advanced Metering Infrastructure at work, a case study (preview)

C O M M U N I C AT E •   M E A S U R E •   C O N T R O L

Advanced Metering Infrastructure (AMI) at work, a case study.

Hannover, April 11th 2014Davide Tappeiner – CEO, Tekpea Inc.

Page 2: Advanced Metering Infrastructure at work, a case study (preview)

CASE STUDY: IND IA

India population of 1.2B

World’s most populous country by 2025

Exploding urbanization is creating unsustainable energy demand today

Page 3: Advanced Metering Infrastructure at work, a case study (preview)

ELECT IC ITY

Limited infrastructures

Critical grid conditions

Shortages too often impose limits to business and everyday life

Page 4: Advanced Metering Infrastructure at work, a case study (preview)

WATER

Scarcity due to human factors

Long dry season

70% is wasted for lack of storage

Page 5: Advanced Metering Infrastructure at work, a case study (preview)

TOWNSHIP

City within a city

6,000 residents

Location: Pune, India (pop. 6,000,000)

Page 6: Advanced Metering Infrastructure at work, a case study (preview)

REQUIREMENTS

Township is responsible for electricity, water, and gas distribution

Buys in bulk from each different Utility

Premium service – must guarantee 24/7 provisioning

Must back up with generators and water storage

Page 7: Advanced Metering Infrastructure at work, a case study (preview)

CHALLENGES

Bill consumption for actual usage

Detect and avoid waste

Engages consumers in conservation by sharing real time usage data

Page 8: Advanced Metering Infrastructure at work, a case study (preview)

BEFORE

No means of measurement

Manual

Wrong bills

Disputes

.

AFTER

Real time measurement

Fully Automated

Bill actual consumption

Customers happy and engaged

.

Page 9: Advanced Metering Infrastructure at work, a case study (preview)

LEARN MORE

Details about the solution will be presented at the Smart Grids Forum

Friday 11th, 11:40 AM

Hall 13 (by C35)

Page 10: Advanced Metering Infrastructure at work, a case study (preview)

END TO END PL ATFORM

Modular

Adaptable

Affordable

Page 11: Advanced Metering Infrastructure at work, a case study (preview)

APPL ICAT ION SOLUT IONS

Advanced Metering

Demand Response

Automation & Telemetry

Smart Lighting