advanced open pit planning and design 2014(for nicico)finaldraft

Upload: juanito

Post on 05-Oct-2015

95 views

Category:

Documents


5 download

DESCRIPTION

mining

TRANSCRIPT

  • 5/11/2014

    1

    ADVANCED OPEN PIT MINE

    PLANNING AND DESIGN

    Presenter

    Prof Emmanuel Chanda

    The University of Adelaide, Australia

    ADVANCED OPEN PIT MINE

    PLANNING AND DESIGN

    M1-Strategic mine planning M2-Open pit optimisation M3-Mine Production scheduling M4-Optimum Cut-off Grades M5-Mine Planning Software M6-Mine-to-Mill Optimisation M7-Equipment Selection M8-Financial Technical Modelling M9-Dewatering and Pumping

    Open Pit Mine Planning and Design 2

  • 5/11/2014

    2

    Objectives

    Fundamentals of open pit mine design and current developments in planning and design methodology,

    Current industry practices to maximise economic return.

    Open pit mine planning and design process in theory and practice,

    Unit Operations Drill-Blast-Load-Haul Apply this knowledge to plan/evaluate new

    open pit projects and/or existing mines.

    Open Pit Mine Planning and Design 3

    What do you expect to learn from this

    Course?

    Open Pit Mine Planning and Design 4

  • 5/11/2014

    3

    Module 1

    Strategic Mine Planning

    Open Pit Mine Planning and Design 5

    1. What is strategic planning?

    2. Mine planning process

    3. Mining strategy

    4. Feasibility Studies

    5. Exercises

    Big picture mine planning and design process

    Big picture decision-making process

    Applies to Greenfields as well operating mines

    SP takes place at all levels of the company Corporate level: vision, mission, feasibility, etc Business unit level: expansion of production Mine level: medium/long term production strategy

    Analogy: military strategy

    Overview/scope

    Open Pit Mine Planning and Design 6

  • 5/11/2014

    4

    What is Strategic Mine

    Planning?

    Strategic mine planning is concerned with those

    decisions that largely determine the value of the

    mining business whereas tactical mine planning

    deals with the tasks required to actually achieve

    that value.

    Both types of planning are necessary; they can be

    looked at separately, even discussed separately,

    but they cannot be separated in practice!

    Open Pit Mine Planning and Design 7

    Prospecting Exploration Closure

    Life cycle of an orebody

    Min

    e P

    lan

    nin

    g

    Strategic Mine

    Planning

    Development Production

    Types of planning and mine life cycle

    Tactical Mine

    Planning

    Open Pit Mine Planning and Design 8

  • 5/11/2014

    5

    Strategic mine planning focuses on those technical variables that affect the life of a mine and the value of the underneath mineral resource

    It starts with the discovery of the mineral resource and finishes when it is exhausted or abandoned.

    Go! List variables (factors) considered in SMP

    Open Pit Mine Planning and Design 9

    Business Strategy

    Strategic

    Planning

    Economic

    Evaluation

    Decision-

    Making

    Behaviour

    Mine Planning

    Open Pit Mine Planning and Design 10

  • 5/11/2014

    6

    Decision-Making Behaviour:

    Risk Averse seeks other business goals

    Risk Neutral seeks maximise NPV

    Open Pit Mine Planning and Design 11

    12

    Mine Planning Process Flowchart

    Open Pit Mine Planning and Design

  • 5/11/2014

    7

    Mine Planning Process

    Four main stages of mine planning process:

    Geology of resource

    Value of resource

    Long-Term planning (Strategic) feasibility

    studies

    Medium-term/Short-term planning - production

    Mine Planning Process*:

    Geology + Data Analysis Resource Model

    Optimisation

    Mining Method Selection

    Mine Design Financial Technical Model Optimal Schedulling

    * A dynamic and iterative process * Open Pit Mine Planning and Design 13

    Activity 1: Work in Groups of 2-4

    To plan a new open pit mine in Kerman Province. List all the

    data required to perform a feasibility study and where these data would come from.

    Open Pit Mine Planning and Design 14

  • 5/11/2014

    8

    Technical Aspects:

    Once the geological features are understood and the physical characteristics of the ore body are determined, the main technical decisions that follow are:

    Mining method selection

    Processing route

    Scale of operation (size)

    Mining sequence

    Selective cut-offs (e.g. cut-off grade at the mine)

    Open Pit Mine Planning and Design 15

    All these variables are inextricably interrelated in the sense that they cannot be determined in isolation from each other

    Moreover, they cannot be determined without taking into account the market variables and related data from the geologic, metallurgical, geotechnical, and environmental models.

    .as shown on next slide

    Open Pit Mine Planning and Design 16

  • 5/11/2014

    9

    MARKET

    Metallurgical

    Model

    Geotechnical

    Model Environmental

    Model

    Geological

    Model

    Mining

    Method

    Scale of

    Operation Mining

    Sequence

    Selective

    Cut-offs

    Processing

    Route

    MINE PLAN

    Open Pit Mine Planning and Design 17

    Mining Method Selection

    The choice of the mining method depends on the

    shape, emplacement and properties of the

    orebody and host rock; again, beyond technical

    considerations, this is an economic decision

    In general, there are two main mining methods:

    Surface mining (open pit, quarries)

    Underground mining (block caving, cut & fill)

    Open Pit Mine Planning and Design 18

  • 5/11/2014

    10

    However, depending on the emplacement of the orebody and its grade distribution, there are cases where both methods are feasible e.g. open-pit followed by underground mining or the other way around

    This is the classic case of sub-vertical deposits such as kimberlitic pipes containing diamonds and some porphyry copper deposits

    Open Pit Mine Planning and Design 19

    Many decisions concerning the choice of the mining method are related to the "opportunity cost concept

    For example:

    In massive, disseminated deposits that are close to surface, open pit mining is more productive than an underground

    Underground mining usually requires more development and preparation works

    Economic considerations

    Open Pit Mine Planning and Design 20

  • 5/11/2014

    11

    Considerations in Mining Method Selection Finances:

    Finance influences method selection: Length of pre-production development and phases

    Thoroughness of the ore body delineation program

    Scale of operations bulk mining methods, eg., block

    caving

    Technology applications - automation

    Open Pit Mine Planning and Design 21

    Markets

    The mining method should be flexible enough to respond to market changes. When and how to high grade during peak commodity prices Changes to mine development schedule Focus on production of by-products (eg. cobalt in copper ore) Mining companies are price takers. What can be done about this?

    Open Pit Mine Planning and Design 22

  • 5/11/2014

    12

    Technology and Human Resources

    Choice of particular mining method commits operation to certain type of technology, equipment, human resources and processes. Later change in method will be at a cost Must allow for possibility of introducing new technology Necessary skills must be available to operate selected mining system Lack of expertise may eliminate a particular mining method, though technically suitable. Consider specific training and supervision

    Open Pit Mine Planning and Design 23

    Processing route

    The selection of the processing route depends

    essentially on the characteristics of the ore; however,

    beyond technical considerations, this is a business

    decision

    Essentially, there are basically two main routes:

    Physical methods (concentration)

    Chemical methods (hydrometallurgy)

    Open Pit Mine Planning and Design 24

  • 5/11/2014

    13

    Acceptable

    Mineral

    Comminution Liberation

    Unacceptable

    Classification

    Separation Concentration

    Physical Chemical

    Open Pit Mine Planning and Design 25

    Factors to consider

    Products recovered

    Recoveries and achievable grades

    Environmental aspects

    Market considerations

    Capital and operating costs

    Cycle times

    Mine plan

    Cash flow and profitability

    In short, technical and financial considerations

    Open Pit Mine Planning and Design 26

  • 5/11/2014

    14

    Lab testing for initial investigation

    Core samples and samples from outcrops

    (chip samples) Pilot tests to confirm lab tests and design

    Core samples and some bulk samples from

    underground workings Industrial tests to feasibility

    Bulk samples from underground workings

    and additional core samples

    Metallurgical tests

    Open Pit Mine Planning and Design 27

    Scale of the operation

    The scale of the operation refers to production capacity, which in turn is related to the physical size of the installations at the mine and plants

    This is directly related to the capital investment required to produce the final output deemed to put in the market

    The larger the scale, the higher the investment and production

    Open Pit Mine Planning and Design 28

    Case Study: Olympic Dam Expansion Project

    in South Australia

  • 5/11/2014

    15

    From the point of view of a mining project, the scale of the operation is the dominant factor for establishing the mine life and business value

    There is a compromise between the NPV of a project and its size the optimum size exits, because a very large operation may shorten the mine life too much, making the marginal investment unworthy

    Open Pit Mine Planning and Design 29

    Scenario 500 kt/d

    Scenario 150 kt/d

    Scenario 72 kt/d

    Scenario 300 kt/d NPV

    (MUS$)

    Scale of operation

    1000

    2000

    2700

    3000

    Size-profitability-risk relationship

    Risk

    Open Pit Mine Planning and Design 30

  • 5/11/2014

    16

    Mining Sequence and Final Limits

    It refers to the path or trajectory employed to exploit a mine from an initial situation until reaching the final limits or exhausting the ore reserves

    Usually, these two variables are treated separately but because of their co-dependency they should be handled together

    Open Pit Mine Planning and Design 31

    The mining sequence is usually defined in terms of sequential cuts or "sectors in which a final mining envelope is split to guide the mining extraction

    These sectors can be phases, cut-backs or push-backs as they are usually called in open-pit mining; or blocks, panels, rooms or stopes as these are commonly referred to in underground mining

    Open Pit Mine Planning and Design 32

  • 5/11/2014

    17

    It is worth noting that the partition of a final

    mining envelope into cuts or sectors is done

    because the time value of money

    In effect, the purpose is to postpone

    expenditures and bring forward revenue as

    much as possible from production sales

    Open Pit Mine Planning and Design 33

    To illustrate how the time value of money

    affects the economics of mining it is useful to

    introduce the saw graph tool

    It assumes that mining activities always

    require some preparation works

    (development) prior to ore extraction:

    Stripping in open pit mining (t, m3)

    Developments in underground (m3,

    m2, m, t)

    The scheduling saw graph

    Open Pit Mine Planning and Design 34

  • 5/11/2014

    18

    The scheduling Saw Graph

    Time yr-1 yr-2 yr-3 yr-4 yr-5 yr-6

    Minimum Ore Exposure

    Open Pit Mine Planning and Design 35

    Integral optimisation of the final pit

    1

    2

    3

    4

    5

    6

    100 t (waste)

    500 t (ore)

    Revenue 2.2 $/t

    Cost -1.0 $/t

    Exploitation phases

    Open Pit Mine Planning and Design 36

  • 5/11/2014

    19

    Partial and cumulative tonnage

    Ore Waste O/W Ratio Ore Waste O/W Ratio

    1 500 100 0.2 500 100 0.2

    2 500 300 0.6 1,000 400 0.4

    3 500 500 1.0 1,500 900 0.6

    4 500 700 1.4 2,000 1,600 0.8

    5 500 900 1.8 2,500 2,500 1.0

    6 500 1,100 2.2 3,000 3,600 1.2

    7 500 1,300 2.6 3,500 4,900 1.4

    Partial tonnage Cumulative tonnagePhase

    Breakeven point Phase 6

    Open Pit Mine Planning and Design 37

    When neither the time value of money nor other

    operational factors such as mine and plant

    capacities are taken into account, the optimal final

    limit is reached at Phase 6

    The implicit assumption is that ore is exposed

    simultaneously with waste and that ore revenue

    occurs at the same time as waste cost

    Open Pit Mine Planning and Design 38

  • 5/11/2014

    20

    When accepting that ore and waste extraction have to consider certain physical restrictions in their programming (phase size and available equipment), then the time value of money becomes a relevant issue

    The programming can be done using the saw graph early described

    Open Pit Mine Planning and Design 39

    Case 1: Open pit plan with 6 phases

    yr-1 yr-2 yr-3 yr-4 yr-5 yr-6

    Plant 500 t/y

    Mine 1,300 t/y

    500

    500

    1,000

    1 2

    3

    4 5

    5

    4

    2

    1

    3 6

    6

    Time

    Waste removal

    Open Pit Mine Planning and Design 40

  • 5/11/2014

    21

    Economic evaluation: Phase 6

    Time yr-1 yr-2 yr-3 yr-4 yr-5 yr-6

    1,000

    - 1,000

    +1,250

    0

    - 800

    - 300

    -225 -546 +706

    Present value(t=0, r=10%) = - 65

    Open Pit Mine Planning and Design 41

    Economic evaluation: Phase 5

    Time yr-1 yr-2 yr-3 yr-4 yr-5 yr-6

    1,000

    - 1,000

    +1,250

    0

    - 500 - 400

    -331 -376 +776

    Present value(t=0, r=10%) = + 70

    Open Pit Mine Planning and Design 42

  • 5/11/2014

    22

    Case 2: Open pit plan with 5 Phases

    yr-1 yr-2 yr-3 yr-4 yr-5

    Plant 500 t/y

    Mine 1,300 t/y

    500

    500

    1,000

    1 2

    3

    4 5

    5

    4

    2

    1

    3

    Time

    Open Pit Mine Planning and Design 43

    Economic evaluation: Phase 5

    Time yr-1 yr-2 yr-3 yr-4 yr-5 yr-6

    1,000

    - 1,000

    +1,250

    0

    - 800

    - 100

    -83 -601 +776

    Present value (t=0, r=10%) = + 92

    Open Pit Mine Planning and Design 44

  • 5/11/2014

    23

    Economic evaluation

    Partial Cum Partial Cum

    1 1,036 1,036 1,036 1,036

    2 733 1,769 733 1,769

    3 485 2,254 485 2,254

    4 250 2,504 275 2,529

    5 70 2,574 92 2,621

    6 -65 2,509 - -

    Phase

    Net Present Value @ r = 10 % ($)

    Case 1 (6 Phases) Case 2 (5 Phases)

    Open Pit Mine Planning and Design 45

    Summary of results

    1

    2

    3

    4

    5

    6

    Breakeven final

    limit (Phase 6)

    Discounted final

    limit (Phase 5)

    Open Pit Mine Planning and Design 46

  • 5/11/2014

    24

    Considering an underground

    alternative

    1

    2

    3

    4

    5

    6

    Open Pit Mine Planning and Design 47

    2 open pit phases, 4 underground lifts

    3

    4

    5

    6

    NPV(1)

    $ 800

    (1) Net present value at the beginning of year 1

    1

    2

    Open Pit Mine Planning and Design 48

  • 5/11/2014

    25

    3 open pit phases, 3 underground lifts.

    3

    4

    5

    6

    NPV(1)

    $ 450

    $ 200

    $ 50

    (1) Net present value at the beginning of year 1

    1

    2

    Open Pit Mine Planning and Design 49

    NPV of underground lifts

    Lifts

    500

    +800

    0

    +450

    NPV Lift 3 (t=0, r=10%) = + 350

    +200

    +50

    3 6 4 6 5 6 6

    NPV Lift 4 (t=0, r=10%) = + 250

    NPV Lift 5 (t=0, r=10%) = + 150

    NPV Lift 6 (t=0, r=10%) = + 50

    Open Pit Mine Planning and Design 50

  • 5/11/2014

    26

    Economic evaluation

    (Open Pit vs Underground)

    Partial Cum Partial Cum

    1 1,036 1,036 1,036 1,036

    2 733 1,769 733 1,769

    3 485 2,254 485 2,254

    4 275 2,529 275 2,529

    5 92 2,621 150 2,679

    6 50 2,671 50 2,729

    Phase

    Net Presente Value @ r = 10 % ($)

    Case 3 (OP/UG) Case 4 (Optimum)

    Open Pit Mine Planning and Design 51

    Optimum configuration

    3

    4

    5

    6

    1

    2

    Open Pit Mine Planning and Design 52

  • 5/11/2014

    27

    Summary of evaluations

    1 1,036 1,036 1,036 1,036

    2 1,769 1,769 1,769 1,769

    3 2,254 2,254 2,254 2,254

    4 2,504 2,529 2,529 2,529

    5 2,574 2,621 2,621 2,679

    6 2,509 - 2,671 2,729

    Net Present Value @ r = 10 % ($)Phase

    Case 1 Case 2 Case 3 Case 4

    Open Pit Mine Planning and Design 53

    NPV and Shareholder Value

    Net present value ($) 2,509 2,621 2,671 2,729

    Firm's net debt ($) 1,000 1,000 1,000 1,000

    Firm's market value ($) 1,509 1,621 1,671 1,729

    N Shares 1,500 1,500 1,500 1,500

    Share value ($/Sh) 1.01 1.08 1.11 1.15

    Case 1 Case 2 Case 3 Case 4Firm's Information

    Open Pit Mine Planning and Design 54

  • 5/11/2014

    28

    Role Of Feasibility Studies

    Why Feasibility Study

    Scoping Study

    Preliminary Study

    Bankable Feasibility Study

    Risks

    Open Pit Mine Planning and Design 55

    Origin of the FS The Feasibility Study is a development of mine

    valuation reports. These had remained almost invariable from 1900 to 1960s.

    More complex and larger mining operations in 1960s and 1970s required sophisticated studies and reporting. The FS was developed which:

    Brings together all aspects of an operation into one study

    Looks at the inter-relationships and tries to solve any problems

    Aims to determine technical and economic viability of a project

    Open Pit Mine Planning and Design 56

  • 5/11/2014

    29

    Feasibility Studies

    Demonstrate that the project is economically

    viable to the satisfaction of the Board, the

    shareholders and all other stakeholders.

    The FS enable the financing of:

    Preliminary earthworks

    Engineering construction

    Infrastructure

    Open Pit Mine Planning and Design 57

    Provide a detailed analysis of all the

    factors affecting a projects viability.

    Enable determination of a go or no go decision

    Have become an aid in obtaining

    financial backing

    Feasibility Studies

    Open Pit Mine Planning and Design 58

  • 5/11/2014

    30

    Phases

    Scoping Study

    Pre-Feasibility Study

    Final Feasibility Study

    Open Pit Mine Planning and Design 59

    Scoping Study The Scoping Study is a preliminary investigation into a

    project between a back of envelope and a pre-feasibility study, or an assessment of necessary size, grade of a target to explore.

    It may also be called a Concept(ual) Study.

    The study is normally undertaken with limited technical and other data being available.

    There is high reliance on experience and knowledge of similar projects and it normally involves a basic level of literature search.

    Open Pit Mine Planning and Design 60

  • 5/11/2014

    31

    Aim of A Scoping Study

    Provide a document for decision-making.

    Identify key factors that will influence the

    overall outcome of the project.

    Identify and briefly assess possible options,

    identify risks

    Give an indication of the potential financial

    worth of the project

    MCA Project Management in Mine Planning and Design

    Open Pit Mine Planning and Design 61

    Outcomes of Scoping Study The outcomes will depend on the situation of the

    particular project and reasons for the study. The

    outcomes of a scoping study mayl include:

    Information for decisions regarding the future of

    the project.

    Identification of key factors and probably risk

    areas, requiring further early investigation.

    Highlighting project activities or aspects which

    have the greatest influence (sensitivity) on the

    project value or return.

    Highlighting project parameters that require

    more accurate measurement or definition.

    A proposed plan to advance, or close, the project

    with schedules and estimated costs. Open Pit Mine Planning and Design 63

  • 5/11/2014

    32

    Open Pit Mine Planning and

    Design

    A scoping study for the Flying Fox T1 deposit as a stand-alone underground mine with offsite ore treatment was prepared by mining consultants Golder Associates Pty Ltd.

    Main outcomes of the T1 scoping study were as follows: Mineable Resources at 196,000t @ 5.4% Ni*

    Contained nickel in concentrate 10,587 Ni tonnes

    Gross Revenue (after royalties) A$101 million

    Operating costs (mining, site, transport, treatment) A$201/tonne ore (A$1.70/lb Ni produced)

    Capital costs - Establishment A$6.0 million

    - Mine development A$12.8 million

    Undiscounted Net cash flow (before tax and D&A) A$37.2 million

    * Note : Mineable Resources do not constitute a JORC compliant

    resource or reserve category.

    Scoping Study- Case Study

    64

    Preliminary Feasibility Study

    Decisions: Abandon project, change or continue?

    Planning: Focus continued investigations on project-critical areas.

    Justify detailed site investigation and resource definition.

    Determine the optimum project scope.

    Identify risks opportunities and potential show stoppers/fatal flaws.

    Economic justification: Justify a full feasibility study.

    Help sell the project.

    Obtain private finance.

    Development: Support permitting and stakeholder liaison

    MCA Project Management in Mine Planning and Design

    Open Pit Mine Planning and Design 65

  • 5/11/2014

    33

    Open Pit Mine Planning and

    Design

    Pre Feasibility looking at

    alternate scenarios Andean Golds Cerro Negro project in Argentina

    Open pit optimization for the Vein Zone was completed using Whittle 4x software and recovered gold block grades. A US$800/oz gold price was used as the base case and the remaining inputs are as shown below:

    Pit Optimization Parameters

    Bench Angle 85o

    Berm Width 9 metres every 20 metres

    Pit Slope 52o overall slope with ramps

    Mining Cost $1.50 per tonne mined

    Processing Cost $14.00 per tonne ore

    General & Administrative Cost $3.00

    per tonne ore

    Pit

    Revenue

    Factor

    Waste

    Tonnes

    ('000)

    Ore

    Tonnes

    ('000)

    Recovered

    Au (g/t)

    Recovered

    Ounces

    ('000)

    Strip Ratio

    (W:O)

    1 0.30 9,763.1 2,083.3 5.30 355.0 4.69

    5 0.38 11,922.4 2,580.3 4.84 401.3 4.62

    10 0.48 14,631.9 3,111.4 4.43 443.6 4.70

    15 0.58 15,704.0 3,580.2 4.06 467.2 4.39

    20 0.68 16,357.2 3,941.0 3.81 482.6 4.15

    25 0.78 16,697.4 4,143.1 3.68 489.8 4.03

    28 0.84 16,765.5 4,247.6 3.61 493.0 3.95

    29 0.86 25,403.2 4,547.3 3.56 520.4 5.59

    30 0.88 25,370.3 4,581.3 3.54 521.2 5.54

    36 1.00 25,725.8 4,750.5 3.45 526.2 5.42

    40 1.14 26,977.6 5,016.1 3.31 534.3 5.38

    45 1.28 27,120.3 5,110.1 3.26 536.3 5.31

    50 1.42 27,163.4 5,199.4 3.22 537.9 5.22

    55 1.60 29,865.5 5,363.9 3.15 543.6 5.57

    60 1.72 29,983.6 5,422.6 3.12 544.6 5.53

    67 2.00 30,555.8 5,536.6 3.07 546.5 5.52

    66

    Open Pit Mine Planning and

    Design

    Pre Feasibility scheduling

    production

    Period

    Oxide

    "Ore"

    (000's

    Tonnes)

    Oxide "Ore"

    (g/t Au)

    Mix "Ore"

    (000's

    Tonnes)

    Mix "Ore"

    (g/t Au)

    Totals

    (000's

    Tonnes)

    Totals

    (g/t Au)

    Waste

    (000's

    Tonnes)

    Strip

    Ratio

    Pre-production 2.4 2.58 2,290.7

    Year 1 644.1 3.05 28.2 4.00 672.3 3.09 3,615.3 5.38

    Year 2 670.6 3.71 4.7 2.18 675.3 3.7 5,063.0 7.50

    Year 3 643.1 4.62 31.7 3.65 674.9 4.58 2,022.2 3.00

    Year 4 758.0 4.39 89.3 3.45 847.3 4.29 7,476.7 8.82

    Year 5 1,186.7 2.55 163.3 2.76 1,350.0 2.58 7,619.7 5.64

    Year 6 279.6 4.39 130.4 2.52 410.0 3.8 2,287.7 5.58

    Totals 4182.1 3.59 447.7 2.96 4,629.8 3.53 30,375.3 6.56

    Portable Ore Portable Ore Portable Ore

    000's Tonnes 000's Tonnes 000's Tonnes

    Year 1 672.3 3.09 677.7 11.54 242.81 1,350.0 7.33 121.89

    Year 2 675.3 3.70 674.7 14.07 258.86 1,350.0 8.88 129.37

    Year 3 674.9 4.58 675.1 12.97 203.05 1,350.0 8.77 101.55

    Year 4 847.3 4.29 502.7 6.69 120.41 1,350.0 5.18 44.84

    Year 5 1,350.0 2.58 1,350.0 2.58 0.00

    Year 6 410.0 3.80 410.0 3.80 0.00

    Totals 4,629.8 3.53 2,530.2 11.63 212.16 7,160.0 6.39 74.97

    Cerro Negro Total

    g/t Au g/t Ag g/t Au g/t Agg/t Au

    Period

    Vein Zone Eureka

    Open pit schedule

    Open pit and underground schedule

    67

  • 5/11/2014

    34

    Open Pit Mine Planning and

    Design

    Pre Feasibility things will change

    over time Brisas Gold Mine Venezuela

    Key Economic Parameters and Results 2008 2006

    Mill Through-Put Range (tonnes per day) 75,000 - 68,000 70,000

    Metallugy Recovery

    Plant Recovery - Gold 83% 83%

    Plant Recovery - Copper 87% 87%

    Net Payable Metal - Gold 82% 81%

    Net Payable Metal - Copper 83% 83%

    Life of Mine Production (payable metals)

    Gold (million ounces) 8.35 8.41

    Copper (million ounces) 1,156 1,113

    Average Annual Production

    Gold (ounces) 457,000 456,000

    Copper (ounces) 63 60

    Mine Life (years) 18.25 18.5

    Initial Capital Cost ($million) 2008 2006

    $ $

    Mine 59.0 76.6

    Mill 314.7 241.5

    Infrastructure 67.8 65.8

    Tailings management facility 38.3 23.8

    Owner's Costs 63.4 55.6

    Pre-Stripping 16.7 18.3

    Indirect Costs (includes EPCM and Camp) 127.6 97.0

    Contingency 43.8 59.4

    Total Initial Capital $731.3 $638.0

    69

    Open Pit Mine Planning and

    Design

    Pre Feasibility things

    will change over time Base Case Economics 2008 2006

    $ $

    Metal Prices

    Gold per ounce $600 $470

    Copper per pound $2.25 $1.80

    Cash Operating Cost Per Ore Tonne

    Mining and Dewatering $2.68 $2.08

    Processing 3.00 2.59

    General and Administrative 0.43 0.42

    Transport and Freight 0.43 0.34

    Smelting and Refining 1.08 1.02

    Total cash operating cost per tonne $7.62 $6.45

    Cash per Ounce of Gold

    Cash Operating Costs $120 $126

    Exploitation Tax 22 16

    Capital Cost (initial, sustaining and sunk) 135 111

    Total Costs (including sunk costs) $277 $253

    Total Cost (excluding sunk costs) $268 $245

    Pre-Tax

    Internal Rate of Return 20.5% 15.4%

    Net Present Value (NPV)

    @ 0% discount (billions) $2.77 $1.91

    @ 5% discount (billions) $1.29 $0.7870

  • 5/11/2014

    35

    (Final) Feasibility Study (FFS)

    The Feasibility Study Report is a decision-making

    document based on verified facts and minimum

    assumptions (criteria). The report may be used for

    several purposes:

    Assemble a comprehensive framework of facts.

    Present a detailed project description.

    Forecast profitability.

    Facilitate partners and/or sources of finance.

    Basis for detailed engineering.

    MCA Project Management in Mine Planning and Design

    Open Pit Mine Planning and Design 71

    Requirements of a FS to be

    bankable

    A FS must be;

    Credible

    Definitive

    Relevant

    Independent

    Open Pit Mine Planning and Design 72

  • 5/11/2014

    36

    Open Pit Mine Planning and

    Design

    Final Feasibility high level issues Geology and ore reserves - size, shape and depth of the ore, the grade of the

    ore and distribution, how homogeneous, any major faults or intrusions and hydrological reports.

    Mining method and schedule surface, open cut, underground, annual production rate vs life of mine, phasing of development, envisaged ROM grade, capital equipment and manning levels required. (High production rate, high capital expenditure, shorter mine life what is the optimum?)

    Infrastructure requirements - including ancillary buildings, roads, drainage,

    tailings disposal, general arrangement drawings of infrastructure layout.

    Metallurgy/concentrator/washery design recovery factor, concentrate grade, product quality.

    Recommendations for the process plant including:

    Flow diagram

    Material and water balances

    Equipment list (major items) together with budget quotations

    General arrangement plan and elections of process plant to scale

    1:100

    Electrical system (line diagram)

    73

    Open Pit Mine Planning and

    Design

    - high level issues continued Infrastructure, water, power, accommodation and environmental issues

    source, capital and operating cost, disposal of tailings.

    Permits right to mine and discharge waste and make good.

    Construction schedule timing, how long to first production the quicker the better.

    Logistics - of supply materials, equipment and manpower to site including an investigation of transport modes.

    Identification of strategic decisions required - early ordering of long delivery items, early starts to opening of negotiations for right-of-way dispensation etc.

    Preliminary programme -for carrying-out the Project.

    Construction cost minimum expenditure to get the project operating, which varies depending on type and size of mine. All costs to include transport and commissioning costs, fees and all management costs except for Client's own costs.

    Markets and marketing transport to market (FOB or CIF), price for product quality sold, secondary processing costs, adequate demand for product.

    Financial analysis put all of the above together to determine if the project is financially viable.

    74

  • 5/11/2014

    37

    Combination of many errors in forecasting can be fatal for any project.

    Project owner is Pegasus Gold Inc and wrote off US$353.5 million in November 1997 after closing down the project.

    This write down of shareholders funds was of balance sheet items amounting to US$122.6 million of acquisition costs, US$49.4 million of deferred preproduction and development expenses and US$181.3 million for property and equipment.

    75

    Rudenno, 2008

    Things can go wrong

    Mt Todd gold mine

    Open Pit Mine Planning and Design

    Case Study Mt Told Gold

    Project

    Commodity price overoptimism resulted in a

    forecast gold price of US$385 per ounce,

    including a hedging premium above

    expected spot prices.

    Spot prices while the project was operating

    were about US$315 per ounce and the

    hedging premium was small.

    76

    MCA - Risk Assessment in Mine Planning and Design

    Open Pit Mine Planning and Design

  • 5/11/2014

    38

    77

    Forecast Actual Change

    Reserves grade 1.07g/tAu 0.96g/tAu -10%

    Metallurgical recovery of gold 84% 74% -12%

    Throughput per year 8 Mt 6.7 Mt - 16%

    Crushing costs $1.36/t $2.49/t +83%

    Contract mining $1.00/t $1.15/t +15%

    Power costs $0.058/kwh $0.075/kwh +29%

    Cyanide usage 0.68kg/t 0.86kg/t +26%

    Total cash costs $11.86/t $13.58/t +15%

    Cash costs per ounce gold

    produced

    US$287/oz US$415/oz +45%

    Gold price US$385 US$315 -18%

    Exchange rate, A$1.00=US$ 0.7 0.74 +6%

    Case Study Mt Told Gold

    Project

    MCA - Risk Assessment in Mine Planning and Design Open Pit Mine Planning and Design

    Open Pit Mine Planning and Design 78 of 10

    NATURE & PURPOSE OF

    FEASIBILITY STUDIES IN MINING

    Type Scoping Preliminary Feasibility

    Audience Internal Technical Mixed Professional External

    Exploration Business

    Development

    Executive

    Executives

    Joint venture

    Extracts to stake

    holders

    Boards

    Financiers

    Investors

    Consultants

    Their Interests Critical factors

    Potential

    Optimum project scope

    Profitability

    Cost of next stage

    Profitability

    Costs

    Schedule

    Risks, etc

    Your Audience

  • 5/11/2014

    39

    Open Pit Mine Planning and Design 79 of 10

    Scoping

    Study

    Preliminary

    Feasibility

    Feasibility

    Study

    Project Control

    Estimate

    Class 1

    (+/- 30% - 50%)

    Class 2

    (+/- 25%)

    Class 3

    (+/- 10% - 15%)

    Class IV

    (+/- 5% - 10%)

    Order of

    magnitude

    Capacity factor

    estimate

    Equipment factor

    estimate Forced detail estimate

    Definitive;

    Fall out detail estimate

    Cost Accuracy

    Mining is a Business, but risky

    Open Pit Mine Planning and Design 80

  • 5/11/2014

    40

    MINING PROJECT RISKS

    TECHNICAL RISKS OH&S RISKS

    POLITICAL

    RISKS

    ECONOMIC / FINANCIAL

    RISKS

    81

    Participants discuss these elements of

    Risk in Mining Projects.

    Open Pit Mine Planning and Design

    Conclusion

    Strategic planning (SP) involves developing a range

    of options, carrying out some form of evaluation,

    assessing criteria and decision-making.

    Open Pit Mine Planning and Design 82

    http://images.google.com/imgres?imgurl=http://www.uniforum.org/publications/ufm/sept96/mining.gif&imgrefurl=http://www.uniforum.org/publications/ufm/sept96/mining.html&h=367&w=341&sz=90&hl=en&start=7&tbnid=G39bOsT-YZHkKM:&tbnh=122&tbnw=113&prev=/images?q=mining&gbv=2&ndsp=18&hl=en&sa=N

  • 5/11/2014

    41

    Activity 2: Individual learning

    Refer to worksheet 1

    Development of a mining strategy: open pit and/or

    underground?

    Complete the task and discuss the calculations with the person(s) sitting next to you!

    Open Pit Mine Planning and Design 83

    Module 2

    OPEN PIT OPTIMIZATION

    Open Pit Mine Planning and Design 84

    What you will learn:

    Block Values and Cost calculation

    Pit Optimisation techniques

    Pit Optimisation Software

  • 5/11/2014

    42

    Block Grade to Block Value

    Some factors to consider:

    Location of the block relative to the surface effect on

    cost

    Processing costs my depend on rock type

    0.3%Cu -$1.13/t

    Dollar Value = Revenue - Costs

    86

    Dollar Value = Revenues - Costs

    Revenues can be calculated from:

    Ore tonnages

    Grades

    Recoveries

    Product price

    Costs can be calculated from:

    Mining cost

    Milling cost

    Overheads

    Open Pit Mine Planning and Design

  • 5/11/2014

    43

    VALUE

    = (METAL*RECOVERY*PRICE - ORE*COSTP) - ROCK*COSTM

    A Formula for a Block Value used in Whittle

    Calculate the value of ore block X:

    200 grams of metal

    100 tonnes of rock/ore

    Metallurgical recovery = 97%

    Selling price of metal $10.00 per gram

    Cost of processing $12.00

    Cost of mining $5.00

    BV = [200x0.97x10 100x12 100x5] = $240

    X

    88

    Calculating Costs

    Must calculate values for:

    Mining Cost per Tonne Mined

    Processing Cost per Tonne Processed

    Rehabilitation Cost per Tonne of Waste

    Selling Cost per Unit of Product

    Some Time Costs must be included

    Open Pit Mine Planning and Design

  • 5/11/2014

    44

    89

    Include

    Any cost which is directly proportional to the tonnes

    or units of product:

    Fuel oil

    Wages

    Spare parts

    Explosives

    etc

    Include with the appropriate activity

    Open Pit Mine Planning and Design

    90

    Include

    Time costs which would stop if mining

    stopped:

    Site administration

    Site infrastructure maintenance

    Interest on working capital loan

    Fall in resale value of equipment

    Capital replacement

    Truck purchase (long project)

    Open Pit Mine Planning and Design

  • 5/11/2014

    45

    91

    What to do with Time Costs

    When mill limited

    Divide annual time cost by annual mill throughput and add the result to the processing cost

    When mining limited

    Divide annual time cost by annual mining capacity and add the result to the mining cost N.B. Even add the mill time costs!

    When selling limited ...

    Open Pit Mine Planning and Design

    92

    Dont Include

    Time costs which continue whether

    you continue mining or not

    Up-front/sunk costs

    Open Pit Mine Planning and Design

  • 5/11/2014

    46

    Activity 3: Individual learning

    Refer to worksheet 2

    Block Values and Cost Calculation

    Complete the task and discuss the calculations with the person(s) sitting next to you!

    Open Pit Mine Planning and Design 93

    Open Pit Mine Planning and Design 94

    Resource Model

    Mine survey

    Diluted Resource

    Ore Reserve estimate

    Proved and Probable

    Resource estimate

    Measured

    Indicated

    Inferred

    Dilution &

    ore losses

    Beneficiation

    factors

    Operating

    Costs

    Economic

    Parameters

    Resource

    Classification

    Ore Reserve Model

    Mining production

    schedule

    Beneficiation

    product

    Potential Ore

    Reserve

    Overburden

    & sub-grade

    Process

    Parameters

    Open pit optimisation

    and design

    Reserve

    Classification

    Revenue, cost and

    slope parameters

    position in mine

    planning flow

    sheet

    Open Pit Optimisation

  • 5/11/2014

    47

    Activity 4 : Individual learning

    Refer to worksheet 3

    Pit Optimisation Task 1

    Complete the task and discuss the calculations with the person(s) sitting next to you!

    Open Pit Mine Planning and Design 95

    96

    Any feasible outline has a Dollar Value. In this context

    feasible means that it obeys safe slope requirements

    The optimal outline is defined as the one with the highest

    dollar value (Profit = Revenue Costs)

    Nothing can be added to an optimal outline which will

    increase the value without breaking the slope constraints.

    Nothing can be removed from an optimal outline which

    will increase the value without breaking the slope

    constraints.

    Definition of the Optimal Outline

    Open Pit Mine Planning and Design

  • 5/11/2014

    48

    97

    Pit Optimisation Techniques

    Moving/Floating/Dynamic Cone Algorithm

    Lerchs-Grossmann 2-D Dynamic Programming

    Algorithm

    LG 3-D Graph Theory Algorithm.

    Network Analysis Algorithm

    Linear Programming (integer programming)

    etc

    Open Pit Mine Planning and Design

    98

    Floating Cone Method

    Position an inverted cone, with the required slopes,

    on each block with a positive value

    If the total value of all blocks in the cone is positive,

    mine those blocks

    Repeat these steps until no cone has a positive

    value

    There are two problems

    Open Pit Mine Planning and Design

  • 5/11/2014

    49

    99

    Floating Cone Method

    Open Pit Mine Planning and Design

    Courtesy: Kores Corpration

    100

    Floating Cone- Mining too little

    -30

    -80 -80

    +100 +100

    Open Pit Mine Planning and Design

  • 5/11/2014

    50

    101

    Floating Cone- Mining too much

    Open Pit Mine Planning and Design

    102

    Lerchs-Grossman Algorithm

    Works with block values

    Works with block mining precedence

    Guarantees to find the three-dimensional

    outline with the highest possible value

    Open Pit Mine Planning and Design

  • 5/11/2014

    51

    103

    Lerchs-Grossman Algorithm

    Works with block values

    Works with block mining precedence

    Guarantees to find the three-dimensional

    outline with the highest possible value

    Open Pit Mine Planning and Design

    104

    Lerchs-Grossman Algorithm

    Open Pit Mine Planning and Design

  • 5/11/2014

    52

    LG 3d block and graph representation

    Orthogonal set of blocks 2 basic geometries to represent open pit

    Arrows point to the blocks that first need to be removed to access the underlying block (at the base)

    Open Pit Mine Planning and Design 105

    106

    Final Pit Design composite plan

    Open Pit Mine Planning and Design

  • 5/11/2014

    53

    Activity 5 : Individual learning

    Refer to worksheet 3

    Pit Optimisation Task 2

    Follow the example calculation of the LG pit optimisation algorithm

    Open Pit Mine Planning and Design 107

    The algorithms to determine the final pit

    limit assume that an economic value can be

    assigned to each block

    However, many of the costs are time costs;

    it means that assigning them to blocks

    requires an assumption about what is the

    unitary operation that restricts production

    (to express these costs in terms of that

    activity)

    Precautions with the OP algorithms

    1) Ascribing costs to blocks

    Open Pit Mine Planning and Design 108

  • 5/11/2014

    54

    To calculate the net value of a block one has

    to assume a breakeven cut-off grade

    A common assumption is to classify as ore

    those blocks with a positive value and waste

    those blocks with a negative value. If the

    mine is the limiting operation, this misses the

    opportunity to create value.

    2) Assumption of a breakeven grade

    Open Pit Mine Planning and Design 109

    There are costs that can not be estimated

    without a mining plan. This is the case of waste

    material, which has to be placed in a dump and

    the cost will depend on the time that this

    happens because of the haul distance

    This can be solved by iterations!

    3) Time value of money

    Open Pit Mine Planning and Design 110

  • 5/11/2014

    55

    There are cases where blocks should be

    blended with others to be classified as

    ore. But that again requires a mining plan in

    advance.

    This can also be solved by iterations!

    4) Blending requirements

    Open Pit Mine Planning and Design 111

    Major General Mine Design Systems

    Fully functional packages (with build-in CAD systems):

    VULCAN

    DATAMINE/CAE

    SURPAC/GEMCOM

    MineSight

    Minex/Gemcom - WHITTLE

    Micromine

    CAD overlaying packages:

    AutoCAD

    SurvCADD/Carlson

    LKAB System

    Open Pit Mine Planning and Design 112

  • 5/11/2014

    56

    Data Import

    Import

    +

    3D Borehole

    Processing

    Open Pit Mine Planning and Design 113

    Geological Interpretation

    Open Pit Mine Planning and Design 114

  • 5/11/2014

    57

    Block Model + Grade Assessment

    Block Model with Grade

    Open Pit Mine Planning and Design 115

    Economical Model - Grade

    >>> $Value

    >>> Au [g/t]

    Value

    $$$

    Open Pit Mine Planning and Design 116

  • 5/11/2014

    58

    Optimisation/Design

    Major optimisation programs based on Lerchs-

    Grossman algorithm:

    Whittle FX Optimiser (stand alone)

    MineMax Planner (stand alone)

    Pit Optimizer (Vulcan 3D)

    NPV Scheduler (Datamine)

    Pit Optimiser (Surpac)

    Open Pit Mine Planning and Design 117

    Whittle FX

    Strategic Mine Planning Software

    Import Block Model Pit by Pit Graph

    Constrains:

    Economical

    Geometrical

    Operational No access constrains

    No haul road/ramp Open Pit Mine Planning and Design 118

  • 5/11/2014

    59

    Optimal Pit

    Open Pit Mine Planning and Design 119

    Mine Design

    Open Pit Mine Planning and Design 120

  • 5/11/2014

    60

    Mine Design

    Geomechanics/Geotechnical

    Access constraints

    Equipment selection

    Ventilation network (underground)

    Rehabilitation

    Environmental constraints

    Open Pit Mine Planning and Design 121

    Final Optimal Pit

    Open Pit Mine Planning and Design 122

  • 5/11/2014

    61

    Final Optimal Pit & Pushbacks

    Open Pit Mine Planning and Design 123

    Reporting & Evaluation

    Open Pit Mine Planning and Design 124

  • 5/11/2014

    62

    Scheduling

    Open Pit Mine Planning and Design 125

    The Pushbacks Generation

    Open Pit Mine Planning and Design 126

  • 5/11/2014

    63

    Optimizing Production

    Schedules

    Open Pit Mine Planning and Design 127 of 26

    Optimizing Production Schedules

    + =

    Open Pit Mine Planning and Design 128

  • 5/11/2014

    64

    Activity 6 : Individual learning

    Review the following technical paper:

    Chanda, E.K., Spencer, E. (1999). Maximising Resource Utilisation in Open Pit Design, in Proc. 28th International Symposium on Computer Applications in the Minerals

    Industry, 20-22 October, Colorado School of Mines, pp359-366, (SME-AIME, Littleton).

    1) What is unique about the the approach used by the

    authors? Open Pit Mine Planning and Design 129

    waste dump planning

    Open Pit Mine Planning and Design 130

    What you will learn:

    Principles of dump design and

    Dump optimisation

  • 5/11/2014

    65

    Why waste dump planning?

    Open Pit Mine Planning and Design 131

    A strip ratio of 10:1, say, implies that for every unit of

    ore mined, 10 times of waste rock is mined.

    The waste rock ends up being stored in a waste

    dump

    Traditionally little attention has been paid to dump

    design and planning, the focus being on planning of

    ore extraction

    It has been recognised that dump design and

    planning is an integral part of pit design.

    Rock flow in an open pit mine

    Open Pit Mine Planning and Design 132

    Yu (2014)

  • 5/11/2014

    66

    133 of 10

    Waste Dump Design

    Two main approaches:

    1) Top-down dumps waste rock is dumped

    over an advancing face (angle of repose)

    approx 38o from horizontal. After

    dumping is complete . The dump is

    reshaped to its intended configuration,

    usually using bulldozers.

    Open Pit Mine Planning and Design

    134 of 10

    Waste Dump Design

    2) Bottom-up storage waste rock

    is dumped in series of piles ,

    and then spread to form a

    relatively thin layer. Also known as paddock dumping.

    Open Pit Mine Planning and Design

  • 5/11/2014

    67

    135 of 10

    Waste Dump Design

    Hybrid dumping whereby top

    down used is used to produce

    relatively thick layers (10 or 15 m,

    say), which are then overlain by

    subsequent equally thick layers.

    This approach is safer and

    requires leas reshaping.

    Open Pit Mine Planning and Design

    136 of 10

    Waste Dump Design

    Dump progression with shortest haul first strategy

    Open Pit Mine Planning and Design

  • 5/11/2014

    68

    137 of 10

    Waste Dump Design

    Dump design considering NAF PAF material (Yu 2013)

    Open Pit Mine Planning and Design

    138 of 10

    Waste Dump

    Optimisation- how?

    MINEMAX Software

    Simultaneous pit and waste dump design

    Dump modelled as blocks

    WHITTLE Software

    Dump optimisation as mirror image of open pit

    optimisation

    XPAC Advanced Destination Scheduler) Software

    Module schedules rock placement

    Open Pit Mine Planning and Design

  • 5/11/2014

    69

    139 of 10

    Waste Dump Optimisation-

    Recent Developments

    Integrated modelling of dumping system (Yu 2013)

    Open Pit Mine Planning and Design

    Module 3

    PRODUCTION SCHEDULING

    Open Pit Mine Planning and Design 140

    What you will learn:

    Principles of production scheduling

    Scheduling Software

  • 5/11/2014

    70

    Mine Scheduling (definition)

    A mining schedule, which tell us when things occur, can be constructed by applying

    production constraints to the mining

    sequence

    Basis for preparing and controlling the

    mines development and production

    A schedule determines the cash flow ($$$)

    associated with mining.

    Open Pit Mine Planning and Design 141

    Typical Timeline

    Year

    -2 -1 +1 +2

    Pre-production

    (Development

    Construction)

    Production

    Open Pit Mine Planning and Design 142

  • 5/11/2014

    71

    Inputs

    The scope of the work to be done from Mining

    Layout Designs

    Rates at which this work is normally prepared,

    from Key Performance Indicators (KPI)

    Labour working hours and rosters from

    Strategic Planning module

    Plant capacities, from the Strategic Planning

    modules

    Production schedules, Ore reserves, tonnes and

    grades, recoveries and dilutions

    Open Pit Mine Planning and Design 143

    Types of Mining Schedule

    Production schedules

    Long Term or Life of Mine (10+ years)

    Medium Term (5 years approx.)

    Short Term (3 months 2 years)

    Extremely Short Term (down to a shift, or for specific jobs)

    Exploration drilling schedules

    Development schedules

    Production drilling schedules

    Equipment schedules

    Labour schedules

    Filling schedules

    Consumable schedules

    Special project schedules Open Pit Mine Planning and Design 144

  • 5/11/2014

    72

    Scheduling Packages

    XPAC

    iGannt

    MS Project

    MS Excel

    Whittle 4D

    In-house

    Open Pit Mine Planning and Design 145

    XPAC

    Developed by Runge Software

    Business focussed mine scheduling application

    Specifically developed for forecasting, reserve

    database and mine scheduling management of all

    types of mineral deposits and mining methods

    Easy-to-use tools for the adaptation, analysis and

    scheduling of mineral resources

    Designed for surface/underground coal mining

    Has limitations in underground mining or in pits with

    complex geometries

    Open Pit Mine Planning and Design 146

  • 5/11/2014

    73

    iGantt

    Developed by MineMax

    Tool for open-pit and underground production

    scheduling

    Integrates Gantt chart, 3D visualization and

    spreadsheet views of a production schedule

    Used for scheduling a single operation or multiple

    operations across an enterprise

    Open Pit Mine Planning and Design 147

    Open Pit Mine Planning and Design 148

  • 5/11/2014

    74

    Open Pit Mine Planning and Design 149

    Open Pit Mine Planning and Design 150

  • 5/11/2014

    75

    Financial Technical Model

    Plant design

    Infrastructure (road, power, water, village, etc.)

    Equipment selection

    Capitals

    Operating costs

    Royalty

    Tax

    Revenue

    NCF NPV, IRR, PB, etc.

    Open Pit Mine Planning and Design 151

    Activity 8 : Individual learning

    Refer to worksheet 4

    Production Scheduling

    Calculate the monthly production figures for a small gold mine

    Open Pit Mine Planning and Design 152

  • 5/11/2014

    76

    Module 4

    Cut-off grade optimization

    Open Pit Mine Planning and Design 153

    1. Background

    2. The model

    3. Example 1: an hypothetical case

    4. Example 2: a copper open pit mine

    & mill

    5. Conclusions

    6. References

    1. Background

    This model was developed in the early

    1960s by Ken Lane, a mathematician who

    made his professional career in the Rio

    Tinto Group

    At the time, the model was used in various

    mines of Rio Tinto including Palabora

    mine in South Africa, and Bougainville

    mine in PNG. Open Pit Mine Planning and Design 154

  • 5/11/2014

    77

    2. The model

    Qm

    Qc

    Waste

    M

    Cut-off gx

    Concentrates

    Tailings

    Ore

    C

    Qr

    R

    Slag

    Final product

    Open Pit Mine Planning and Design 155

    M = Mine capacity per period (t of material)

    C = Plant capacity per period (t of ore)

    R = Refinery capacity per period (t of product)

    Qm = Quantity of run-of-mine material (t of material)

    Qc = Quantity of ore (t of ore)

    Qr = Quantity of final product (t of product) = Qcgy

    T = Time to mine, process or refine Qm

    P = Profit

    Variables used in Lanes Model

    Open Pit Mine Planning and Design 156

  • 5/11/2014

    78

    d = annual discount rate

    m = mining costs ($/t of material)

    c = concentrating costs ($/t of ore)

    r = refining and marketing costs ($/t of product)

    f = fixed costs, per period ($/period)

    s = selling price ($/t of final product)

    y = overall metallurgical recovery

    Models variables (cont)

    Open Pit Mine Planning and Design 157

    The profit equation for Qm

    TfQmQcQ r- sP mcr

    (1a) TfQmQcyg r- sP mc

    (1)

    As c r

    y g Q Q

    Open Pit Mine Planning and Design 158

  • 5/11/2014

    79

    Profit from Qm

    and Present Value

    Qm

    Grade

    f

    gx

    Qc

    W

    V

    V = Present value at the beginning of period T

    W = Remaining present value after mining Qm

    Open Pit Mine Planning and Design 159

    Time

    P P2 P3 P4 Pn

    W

    V

    T

    0

    T

    d)(1

    WPV

    (2)

    Open Pit Mine Planning and Design 160

  • 5/11/2014

    80

    If time T is small:

    (1 + d)T 1 + dT (3)

    Replacing in (2):

    (4)

    Re-arranging:

    V(1 + dT) = P + W (5)

    T)d(1

    WPV

    Open Pit Mine Planning and Design 161

    Re-arranging:

    v = V - W = P - dVT (6)

    Where v is the contribution that the

    fraction Qm of the ore deposit makes to

    the present value of the business

    As such, v is the variable to maximise

    when choosing the optimum cut-off

    grade

    Open Pit Mine Planning and Design 162

  • 5/11/2014

    81

    Replacing (1) in (6):

    (7)

    TVdfQmQcQrsv mcr

    But the optimum present value V on the

    right side of equation (7) is unknown

    until the cut-off grade policy is optimised

    This chicken and egg problem is solved

    by iterations, using an arbitrary value of

    V in the first iteration and stoping when V

    converges Open Pit Mine Planning and Design 163

    Economic cut-off grades

    (7)

    In equation (7), time T depends on the

    stage that limits the pace at which ore is

    mined

    That is, the quantities Qm, Qc or Qr and

    their respective capacities M, C, or R

    This leads to three economic cut-off

    grades:

    TVdfQmQcQrsv mcr

    Open Pit Mine Planning and Design 164

  • 5/11/2014

    82

    a) When the mine imposes a limit (M)

    In this case, M

    QT m

    Replacing this in expression (7):

    mcrm QM

    VdfmQcQrsv

    Max vm 0

    g

    vm

    Open Pit Mine Planning and Design 165

    As Qm is given, g only affects Qc and Qr

    Then g must be chosen to make (s-r)Qr - cQc

    as large as possible

    yrsc

    gm

    cc QcygQr-s

    Therefore:

    Open Pit Mine Planning and Design 166

  • 5/11/2014

    83

    b) When the plant imposes a limit (M)

    In this case, C

    QT c

    Replacing this in expression (7):

    mcrc QmQC

    VdfcQrsv

    Max vc 0

    g

    vc

    Open Pit Mine Planning and Design 167

    In the same way, as Qm is given, g must be

    chosen to maximise:

    yrsC

    Vdfc

    gc

    cc QC

    VdfcygQr-s

    Therefore:

    Open Pit Mine Planning and Design 168

  • 5/11/2014

    84

    c) When the refinery imposes a limit (R)

    In this case, R

    QT r

    Replacing this in expression (7):

    mcrr QmQcQ

    R

    Vdfrsv

    Max vr 0

    g

    vr

    Open Pit Mine Planning and Design 169

    In the same way, as Qm

    is given, g

    must be chosen to maximise:

    y

    R

    Vdfrs

    cgr

    cc QcygQ

    R

    Vdfrs

    Therefore:

    Open Pit Mine Planning and Design 170

  • 5/11/2014

    85

    The operation is sometimes limited by two or

    eventually three stages simultaneously

    Then, three balancing cut-off grades can be

    introduced into the analysis

    gmc: Mine-Plant

    gmr: Mine-Refinery grc : Refinery-Plant

    Balancing cut-off grades

    Open Pit Mine Planning and Design 171

    gmc fully utilises mine and mill capacities;

    that is, maximum stripping ratio at the mine

    and throughput at the mill

    Mine-mill example

    Grade

    f

    gmc

    Qm

    gm gc

    Open Pit Mine Planning and Design 172

  • 5/11/2014

    86

    Mine capacity: 650,000 t/d

    Mill capacity: 150,000 t/d

    gm: 0.25 %Cu

    gc: 0.65 %Cu

    Possible throughputs:

    Cut-off % Cu

    Mine t/d

    Mill t/d

    Grade % Cu

    0.25 450,000 150,000 0.9

    0.50 650,000 150,000 1.2

    0.65 650,000 120,000 1.3

    0.5 %Cu is a balancing cut-off

    Open Pit Mine Planning and Design 173

    In summary, Lanes model considers six

    cut-off grades:

    three economic cut-off grades, and

    three balancing cut-off grades

    The former depend on economic factors

    and capacities whereas the latter are

    determined by the grade distribution that

    can vary widely throughout irregular ore

    bodies

    None of these considers mining costs!

    Open Pit Mine Planning and Design 174

  • 5/11/2014

    87

    The overall optimum is one of the six cut-

    off grades already defined:

    1) gm

    2) gc

    3) gr

    4) gmc

    5) gmr

    6) grc

    To assess which one is the optimum it is

    best to consider each pair of stages in

    turn

    Optimum cut-off grades

    Open Pit Mine Planning and Design 175

    To see which one is the optimum it is best

    to plot the value functions considering

    each pair of stages in turn

    Mine-Concentrator

    mcrm QM

    VdfmQcQrsv

    mcrc QmQC

    VdfcQrsv

    Open Pit Mine Planning and Design 176

  • 5/11/2014

    88

    g

    v

    gmc gc gm

    Gmc = gm vc vm

    g

    v

    gmc gc gm

    Gmc = gmc vc vm

    Open Pit Mine Planning and Design 177

    g

    v

    gmc gc gm

    Gmc = gc

    vc vm

    In a similar way, by considering the other

    pair of stages, it is possible to obtain Gmr

    and Grc

    Open Pit Mine Planning and Design 178

  • 5/11/2014

    89

    g

    v

    gmc gc gm

    vc vm

    vr

    gr gmr grc

    The overall optimum cut-off grade is:

    G = Middle value (Gmc,Gmr,Grc)

    Open Pit Mine Planning and Design 179

    Mine capacity (M) = 100

    Plant capacity (C) = 50

    Refinery capacity (R) = 40

    Mining costs (m) = 1

    Concentrating costs (c)= 2

    Refining costs (r) = 5

    Fixed costs (f) = 300

    Selling price (s) = 25

    Overall recovery (y) = 100 %

    Annual discount rate (d)= 15 %

    3. Example 1: an hypothetical case

    Open Pit Mine Planning and Design 180

  • 5/11/2014

    90

    Grade-tonne relationship

    Grade interval

    Quantity

    0.0 0.1 100

    0.1 0.2 100

    0.2 0.3 100

    . .

    .

    0.9 1.0 100

    1000

    g

    f(t)

    100

    0 0.5 1.0

    Open Pit Mine Planning and Design 181

    Balancing cut-off grades

    Cut-off Tonnage Ratios

    Mine Mill Grade Ref. M/C M/R C/R

    0.0 1000 1000 0.50 500 1.00 2.00 2.00

    0.1 1000 900 0.55 495 1.11 2.02 1.82

    0.2 1000 800 0.60 480 1.25 2.08 1.66

    0.3 1000 700 0.65 455 1.43 2.20 1.54

    0.4 1000 600 0.70 420 1.67 2.38 1.43

    0.5 1000 500 0.75 375 2.00 2.67 1.33

    0.6 1000 400 0.80 320 2.50 3.13 1.25

    0.7 1000 300 0.85 255 3.33 3.92 1.18

    0.8 1000 200 0.90 180 5.00 5.56 1.11

    0.9 1000 100 0.95 95 10.00 10.53 1.05

    M/C = 100/50 = 2.00 gmc = 0.50

    M/R = 100/40 = 2.50 gmr = 0.45

    C/R = 50/40 = 1.25 grc = 0.60

    Balancing cut-off grades

    Open Pit Mine Planning and Design 182

  • 5/11/2014

    91

    Economic cut-off grades

    0.10

    yrs

    cgm

    0.40

    yrsC

    Vdfc

    gc

    0.16

    yR

    Vdfrs

    cgr

    For V = 0

    Open Pit Mine Planning and Design 183

    Optimum cut-off grades

    Gmc = Mid (0.10, 0.40, 0.50) = 0.40

    Gmr = Mid (0.10, 0.16, 0.45) = 0.16

    Grc = Mid (0.16, 0.40, 0.60) = 0.40

    G = Mid (0.16, 0.40, 0.40) = 0.40

    Open Pit Mine Planning and Design 184

  • 5/11/2014

    92

    Intermediate mine plan

    Year Cut-off Mine Mill Ref. Profit

    1 0.4 83.3 50 35 216.7

    2 0.4 83.3 50 35 216.7

    . . . . . .

    . . . . . .

    . . . . . .

    12 0.4 83.3 50 35 216.7

    P = (25 - 5)35 250 183.3 3001

    P = 216.7

    PV@12y and 15% = 1174

    Open Pit Mine Planning and Design 185

    Second iteration

    0.10

    yrs

    cgm

    0.58

    yrsC

    Vdfc

    gc

    0.25

    yR

    Vdfrs

    cgr

    For V = 1174

    Open Pit Mine Planning and Design 186

  • 5/11/2014

    93

    Optimum cut-off grades

    Gmc = Mid (0.10, 0.50, 0.58) = 0.50

    Gmr = Mid (0.10, 0.25, 0.45) = 0.25

    Grc = Mid (0.25, 0.58, 0.60) = 0.58

    G = Mid (0.25, 0.50, 0.58) = 0.50

    Open Pit Mine Planning and Design 187

    A new mine plan...

    With the new cut-off grade of 0.5, a new

    mine plan can be developed but this time

    changing the present value from year to year

    If annual profits are discounted to time 0 and

    added up, it gives another estimate of V

    If the difference of the initial and final value

    of V exceeds a defined tolerance threshold,

    the whole process is repeated

    Open Pit Mine Planning and Design 188

  • 5/11/2014

    94

    Annual profit for the first year...

    P = (25 - 5)37.5 250 1100 3001

    P = 250

    PV@ 10y and 15% = 1255

    For a 0.5 cut-off grade, the annual profit and

    present value is as follow:

    Open Pit Mine Planning and Design 189

    Optimum mine plan and cut-off grades policy

    Year Cut-off Mine Mill Ref. Profit PV

    1 0.50 100 50 37.5 250 1255

    2 0.50 100 50 37.5 250 1194*

    3 0.50 100 50 37.5 250 1123

    4 0.50 100 50 37.5 250 1041

    5 0.50 100 50 37.5 250 947

    6 0.50 100 50 37.5 250 840

    7 0.50 100 50 37.5 250 716

    8 0.49 97 50 37.1 245 573

    9 0.46 93 50 36.5 238 414

    10 0.41 89 50 35.9 229 238

    11 0.41 21 13 8.8 55 45

    * W = V(1+d) - P

    W = 1255 1.15 250 = 1194

    1000 513 380.8 2517

    PV @ 11y and 15%= 1256

    Open Pit Mine Planning and Design 190

  • 5/11/2014

    95

    Relevant data: Mine capacity (M) = 18.9 Mt/a

    Plant capacity (C) = 7.2 Mt/a

    Mining costs (m) = 0.85 $/t material

    Milling costs (c) = 3.7 $/t ore

    Fixed costs (f) = 3.5 M$/a

    Copper price (s) = 2205 $/t Cu ($1.0 /lb)

    TC/RC & selling cost (r) = 705 $/t Cu ($0.32 /lb)

    Overall recovery (y) = 85 %

    Annual discount rate (d) = 10 %

    4. Example 2: a copper open pit mine & mill

    Open Pit Mine Planning and Design 191

    A set of four pushbacks

    B

    D

    C

    A

    Open Pit Mine Planning and Design 192

  • 5/11/2014

    96

    Input to the model: four scheduled, nested pits

    (periods) from a preliminary mine plan

    1

    1

    1

    3

    2

    2

    3

    4

    4

    3

    PP

    Open Pit Mine Planning and Design 193

    Grade-tonnage relationship for the four pits

    Cut-off Period 1 Period 2 Period 3 Period 4

    % Cu Mt % Cu Mt % Cu Mt % Cu Mt % Cu

    0.0 20.3 1.05 36.5 0.79 56.3 0.57 80.1 0.59

    0.2 18.7 1.13 30.1 0.92 40.8 0.76 60.4 0.77

    0.4 15.3 1.32 24.4 1.08 28.5 0.97 50.2 0.87

    0.6 12.9 1.47 19.7 1.22 21.7 1.11 38.3 0.98

    0.8 11.0 1.61 13.7 1.45 15.1 1.30 22.7 1.18

    1.0 8.6 1.80 10.2 1.64 10.0 1.49 14.6 1.35

    1.2 7.1 1.95 7.6 1.83 6.9 1.67 9.0 1.49

    1.4 5.9 2.08 5.6 2.02 4.4 1.88 5.0 1.65

    1.6 4.4 2.27 4.0 2.24 2.7 2.11 2.9 1.75

    Open Pit Mine Planning and Design 194

  • 5/11/2014

    97

    Output for a Base case

    Year Period 1 Cut-off (% Cu)

    Mine (Mt)

    Mill Ratio (W/O)

    Profit (M$)

    PV (M$) (Mt) (% Cu)

    1 1 0.85 14.2 7.2 1.67 0.97 110.3 475.5

    2 1 0.78 6.1 3.4 1.59 0.82 49.6 412.8

    2 2 0.78 9.8 3.8 1.43 1.56 44.8 412.8

    3 2 0.72 16.8 7.2 1.37 1.34 81.3 359.6

    4 2 0.67 9.9 4.7 1.31 1.13 50.4 314.2

    4 3 0.61 6.7 2.5 1.12 1.62 19.4 314.2

    5 3 0.61 18.9 7.2 1.12 1.62 56.3 275.8

    6 3 0.60 18.6 7.2 1.11 1.58 55.8 247.0

    7 3 0.56 12.1 4.9 1.08 1.45 36.5 215.9

    7 4 0.56 4.5 2.3 0.96 0.98 14.9 215.9

    8 4 0.53 13.6 7.2 0.94 0.89 44.5 186.1

    9 4 0.50 13.1 7.2 0.92 0.82 43.3 160.3

    10 4 0.47 12.6 7.2 0.91 0.75 42.4 132.9

    11 4 0.44 12.1 7.2 0.89 0.68 41.4 103.9

    12 4 0.41 11.6 7.2 0.87 0.61 40.2 72.9

    13 4 0.37 11.2 7.2 0.86 0.55 38.9 39.9

    14 4 0.33 1.5 1.0 0.84 0.50 5.1 5.0

    193.2 94.6 1.11 1.04 PV = 475.5

    Open Pit Mine Planning and Design 195

    Output for an expanded case (Mill from 7.2 to 9.0 Mt/a)

    Year Period 1 Cut-off (% Cu)

    Mine (Mt)

    Mill Ratio (W/O)

    Profit (M$)

    PV (M$) (Mt) (% Cu)

    1 1 0.78 16.3 9.0 1.59 0.81 131.8 521.2

    2 1 0.71 4.0 2.3 1.53 0.71 33.1 441.6

    2 2 0.67 14.0 6.7 1.30 1.10 71.3 441.6

    3 2 0.65 18.5 9.0 1.29 1.05 95.4 381.3

    4 2 0.60 4.1 2.2 1.22 0.86 22.1 324.0

    4 3 0.45 14.2 6.8 1.00 1.10 46.6 324.0

    5 3 0.45 18.9 9.0 1.00 1.10 62.0 287.7

    6 3 0.45 18.9 9.0 1.00 1.10 62.0 254.4

    7 3 0.45 4.2 2.0 1.00 1.10 13.7 217.9

    7 4 0.51 12.9 7.0 0.93 0.84 43.2 217.9

    8 4 0.48 15.9 9.0 0.91 0.76 54.1 182.8

    9 4 0.45 15.2 9.0 0.89 0.69 52.9 146.9

    10 4 0.42 14.6 9.0 0.88 0.62 51.5 108.8

    11 4 0.38 14.1 9.0 0.86 0.56 50.0 68.1

    12 4 0.34 7.4 4.9 0.84 0.51 26.4 25.0

    193.2 103.9 1.06 0.86 PV = 521.2

    Open Pit Mine Planning and Design 196

  • 5/11/2014

    98

    Conclusion for this case

    The Base Case produces a declining cut-off

    grade policy starting at 0.85 %Cu and yielding

    a PV of $ 475.5 million

    The Expanded Case lowers the initial cut-off

    from 0.85 to 0.78 %Cu and increases the PV

    by $46 million from $475.5 to $521.2 million

    If the expansion capital investment is less than

    $46 million, then it is worth going ahead

    Open Pit Mine Planning and Design 197

    5. Concluding remarks

    Lanes cut-off grade model is a first attempt to

    define economically what material is ore in a

    life-of-mine (LOM) plan

    It requires a holistic view of mining in that the

    optimisation needs a preliminary LOM plan.

    That is, a final pit limit, pushbacks design and

    scheduling based on a breakeven cut-off - the

    mine or plant cut-off grade, for instance

    Open Pit Mine Planning and Design 198

  • 5/11/2014

    99

    Activity 8 : Individual learning

    Refer to worksheet 5

    Cutoff Grade Optimisation

    Follow the calculations to the problems

    Open Pit Mine Planning and Design 199

    Lanes model considers various variables as

    fixed input capacities, and downstream cut-

    offs such as metallurgical recovery at the mill

    Most recent developments have expanded the

    model to include some of these variables and

    handle them simultaneously

    When the problem becomes too complex, it is

    solved using other mathematical tools, integer

    linear programming being one of them

    Open Pit Mine Planning and Design 200

  • 5/11/2014

    100

    6. References

    Kenneth F. Lane - The economic definition of ore, Mining

    Journal Books, London 1988

    Kenneth F. Lane - Choosing the optimum cut-off grade,

    Colorado School of Mines Quarterly. Vol. 59-4, 1964, pp. 811-

    829

    Blackwell, M. Some aspects of the evaluation and planning of

    the Bougainville copper project, Decision-Making in the

    Mineral Industry, CIM Special Vol 12, 1971 pp. 261-269

    Open Pit Mine Planning and Design 201

    Module 5

    Mine Planning Software

    Open Pit Mine Planning and Design

    202

    Software Packages

    Categories

    Capabilities

    Providers

  • 5/11/2014

    101

    Common Software Packages

    Open Pit Mine Planning and Design

    203

    Categories of Mining Software

    Open Pit Mine Planning and Design

    204

  • 5/11/2014

    102

    Mapping Software

    Open Pit Mine Planning and Design

    205

    Geological & Data managent

    Open Pit Mine Planning and Design

    206

    Source: (Sable, 2013)

  • 5/11/2014

    103

    Geological Modelling/

    Resource Estimation

    Open Pit Mine Planning and Design

    207

    Drill hole display (Source: Geovia, SUPARC)

    Geological Modelling/

    Resource Estimation

    Open Pit Mine Planning and Design

    208

    Ore body model(Source: CAE, STUDIO 3)

  • 5/11/2014

    104

    Mine Design

    Open Pit Mine Planning and Design

    209

    Pit Design (Source: Maptek, VULCAN)

    Planning and Scheduling

    Open Pit Mine Planning and Design

    210

    Pit Design (Source: Geovia, MineSched)

  • 5/11/2014

    105

    Financial Evaluation

    Open Pit Mine Planning and Design

    211

    Financial Analysis Software (RungePincockMinarco)

    Optimisation/Risk Analysis

    Open Pit Mine Planning and Design

    212

    Pit Optimisation (Geovia, WHITTLE)

  • 5/11/2014

    106

    Monitoring & Control

    Open Pit Mine Planning and Design

    213

    Truck Dispatching (Modular Mining System; (DISPATCH)

    Simulators

    Open Pit Mine Planning and Design

    214

    Coal Mining Simulator (Immersive Technologies)

  • 5/11/2014

    107

    Virtual Reality

    Open Pit Mine Planning and Design

    215

    ViMine VR Software 3D Ore body model

    Summary

    Open Pit Mine Planning and Design

    216

    Advances in Computer technology has

    made it possible to model complex mining

    environments

    Most widely software is for Mine Design &

    Planning

    Further developments in simulation and

    risk modelling

    Mining software harmonisation by

    suppliers

  • 5/11/2014

    108

    Module 6

    mine to mill optimisation

    Open Pit Mine Planning and Design

    217

    Concept embraced and practiced by mining

    companies

    The philosophy is base on:

    Characterise

    Track

    Measure

    Model

    Potential to save mining companies thousands of

    Dollars

    Open Pit Mine Planning and Design 218

    Drilling

    Blasting

    Loading

    Hauling

    Milling (Crushing, grinding)

    Examine total system with regard to cost,

    productivity, product quality, optimisation...

    Mine production system processes

  • 5/11/2014

    109

    Open Pit Mine Planning and Design 219

    Loading: increased fragmentation => higher rate of shovel productivity, hence lower costs per BCM.

    Hauling: Truck production per hour will increase with

    greater fragmentation due to faster shovel loading rates.

    Reduced cycle time.

    Crushing: Lower crushing costs result from increased

    fragmentation as more material pass through as under

    size.

    Drilling and blasting costs are harder to relate to

    fragmentation).

    Open Pit Mine Planning and Design 220

    Unit costs as a function of the degree of

    fragmentation

    Systems optimisation:

    Optimum Fragmentation Curves

    Degree of fragmentation

    Overall Cost Curve

  • 5/11/2014

    110

    Blasthole Drilling

    Bore diameter

    Hole deviation monitor

    Geophysical data

    Real time drilling data

    Exploration Drilling

    Intact rock data

    Mineralogy data

    Fracture frequency data

    Ore body modeling and pit design

    Blast Modelling Displacement model Fly rock Heave mechanics

    Blast Design

    Pattern layout

    VOID

    Powder factor

    Explosive

    Muckpile properties

    Size distribution* Voids ratio* LCM Visualization Density

    S01U264007

    0

    20

    40

    60

    80

    100

    120

    1 10 100 1000

    Size (mm)

    Pe

    rce

    nta

    ge

    Pa

    ssin

    g (

    %)

    S01U264007

    35.2Mtpa ROM Target

    Excavation/Loading

    Digability* Dig rate* Dipper design Power consumption Swing analysis Autonomy

    Hauling

    Payload data Voids ratio* LCM TKPM rating Autonomy Routing data

    Crushing/grinding

    Energy data Bond's Work Index Settings

    Process

    Optimization

    Blast design,

    Load-Haul

    Open Pit Mine Planning and Design 222

    Examine individual components and the whole system

    Goal: achieving a prescribed level of fragmentation at

    minimum cost

    In-situ ore with particle size considered to be very large

    and reducing to size in the order microns (eg -80 mesh).

    Measuring Fragmentation, how?

    Diggability (BCM/HR)

    Size distribution of muckpile (WIPFrag Software), Split-Desktop software

    Photographs are taken from muck pile, digging

    face, moving truck, etc.

    Optimum Fragmentation

  • 5/11/2014

    111

    Open Pit Mine Planning and Design 223

    Fragmentation evaluation

    Measurement of parameters- correlate with

    fragmentation

    Photographs are taken from muck pile, digging face,

    moving truck, etc.

    Crusher monitoring - energy, feed, product size,

    throuputghput

    Shovel monitoring- load, wait, down time, swing, power

    Drilling and Blasting SubSystem

    Open Pit Mine Planning and Design 224

    Case Study

  • 5/11/2014

    112

    Open Pit Mine Planning and Design 225

    Case Study

    Modeling Muck Pile Fragment Size to Optimize

    Excavator Productivity in Open Pit Mining

    Prominent Hill Copper Mine, South Australia

    Open Pit Mine Planning and Design 226

    Prominent Hill

  • 5/11/2014

    113

    Open Pit Mine Planning and Design 227

    Prominent Hill

    Muckpile Image Analysis using SPLIT DESKTOP:

    The split desktop system uses digital image

    analysis technology to convert an image

    captured from a digital camera to a distribution

    of defined areas within the photograph.

    The software was developed from a system of

    manual image analysis where a photographic

    image was manually delineated and the diameter

    of each particle measured

    Open Pit Mine Planning and Design 228

    Prominent Hill

    Camera

    Photo of muckpile

    Photo collection and scale placement on flitch face.

  • 5/11/2014

    114

    Open Pit Mine Planning and Design 229

    Prominent Hill

    Blast master 10040RL

    Open Pit Mine Planning and Design 230

    Prominent Hill

  • 5/11/2014

    115

    Open Pit Mine Planning and Design 231

    Prominent Hill

    Open Pit Mine Planning and Design 232

    Prominent Hill

    Our modelling of the excavator production rates

    has suggested that P80 of 800 mm would be the

    optimal size to maximise excavator productivity

    at 6300 t/hr.

    However due to mine machinery and crusher

    constraints we believe a revised figure of 600

    mm would be more appropriate

  • 5/11/2014

    116

    Module 7

    Equipment Selection

    Open Pit Mine Planning and Design

    233

    Simulation modelling using GPSS/H Case Study

    Cost Estimation (Capital & Operating)

    Study Background

    Methodology

    Results

    Discussion

    Conclusion

    Recommendations

    Simulation and Animation of an

    Australian Surface Mine

    Open Pit Mine Planning and Design 234

  • 5/11/2014

    117

    Wilcherry Hill Iron Ore Mine

    The Wilcherry Hill project is

    located 30 km north of the

    township of Kimba in South

    Australia.

    The Wilcherry Hill project

    comprises of four tenements

    and covers an area of 976

    square kilometres.

    The tenements are EL4162-

    Wilcherry Hill, EL4286-Valley

    Dam, EL4421- Peterlumbo,

    EL3981-Eurilla Dam.

    Open Pit Mine Planning and Design 235

    Development at Wilcherry Hill is proposed in three phases; stage 1, 2 and 3.

    Stage 1 will be the focus of this project

    Comprises mining, crushing and export of Direct Shipping Ore (DSO)

    Ore sourced from the upper parts of the mining pits.

    Project Development

    Open Pit Mine Planning and Design 236

  • 5/11/2014

    118

    Methodology

    Aim

    Simulation and animation model using the Stage

    1 layout of the mine

    Determine the optimum number of shovels and

    trucks required for this mining scenario

    Provide the company with a model they can use

    for many what if? scenarios.

    Open Pit Mine Planning and Design 237

    Programming in GPSS/H

    Approximately 1,200 lines of computer code were

    used to model this mining scenario

    Over 60,000 command lines were used to generate

    this animation

    Open Pit Mine Planning and Design 238

  • 5/11/2014

    119

    Methodology

    GPSS/H Simulation Main Commands

    Open Pit Mine Planning and Design 239

    Methodology Variables, User Information and Generate

    Variables:

    REAL &X,&Y,&Z,&A,&B,&C,&D,&E,&F,&G,&H,&I

    User Information:

    PUTSTRING (' ')

    PUTSTRING ('HOW MANY TRUCKS?')

    PUTSTRING (' ')

    INTEGER &TRUCKS

    GETLIST &TRUCKS

    Generate:

    GENERATE 3,,0,&TRUCKS,,12PH,12PL

    Open Pit Mine Planning and Design 240

  • 5/11/2014

    120

    Methodology

    Animation

    Open Pit Mine Planning and Design 241

    Methodology

    Mine Layout (Draw, Class and Paths)

    Open Pit Mine Planning and Design 242

  • 5/11/2014

    121

    Methodology

    Run

    Open Pit Mine Planning and Design 243

    Methodology

    Animation

    Open Pit Mine Planning and Design 244

  • 5/11/2014

    122

    Methodology Animation

    Open Pit Mine Planning and Design 245

    Results

    HD 785

    EMPTY: 72 t

    LOADED: 164 t

    LOADED SF: 147.6 t

    ORE WEIGHT: 75.6 t

    STRUCK BODY CAPACITY: 40 m3

    ORE SPECIFIC GRAVITY: 4

    FULL STRUCK LOAD ORE WEIGHT: 160 t

    HOURS PER SHIFT: 8

    Assumptions

    Open Pit Mine Planning and Design 246

  • 5/11/2014

    123

    Results

    Ore Results

    TRUCKS: 3 4 5 6 7

    ORE DUMPS PER SHIFT: 9 13 17 20 23 DUMPS

    STOCKPILE DEPOSITION PER SHIFT: 1440 2080 2720 3200 3680 T

    STOCKPILE WITHDRAWAL RATE: 180 260 340 400 460 T/HR

    COMPARISON (IRONCLAD): 291 T/HR

    Open Pit Mine Planning and Design 247

    Results

    Ore Results

    Open Pit Mine Planning and Design 248

  • 5/11/2014

    124

    Results

    Waste Results

    TRUCKS: 3 4 5 6 7

    WASTE DUMPS PER SHIFT: 68 87 104 123 142 DUMPS

    DUMP DEPOSITION PER SHIFT: 5140.8 6577.2 7862.4 9298.8 10735.2 T

    DUMP RATE: 642.6 822.15 982.8 1162.35 1341.9 T/HR

    COMPARISON (IRONCLAD): 885 T/HR

    Open Pit Mine Planning and Design 249

    Results

    Waste Results

    Open Pit Mine Planning and Design 250

  • 5/11/2014

    125

    Conclusion

    GPSS/H Simulation and Animation

    Number of shovels: one shovel

    Number of trucks: five trucks and possibly an extra standby truck

    TALPAC simulations

    Number of shovels: one shovel

    Number of trucks: six trucks

    Open Pit Mine Planning and Design 251

    Acknowledgements

    Postgraduate Students:

    Sophie Mellor

    Jian Liu

    Open Pit Mine Planning and Design 252

  • 5/11/2014

    126

    Cost Estimation

    Capital Costs

    Operating Costs

    Open Pit Mine Planning and Design

    254 of 10

    Capital cost estimation: general

    considerations

    Indicative capital cost estimates

    Based on empirical data from other

    projects

    Estimates are within +/- 30% accuracy

    Suitable for scoping or pre-feasibility

    studies

    Often use rules-of-thumb to estimate

    costs

  • 5/11/2014

    127

    Capital cost estimation: general considerations:

    Indicative capital cost estimates (cont.)

    The sixth-tenths rule (Mular, 1978):

    Cost 1 / Cost 2 = (Capacity 1 / Capacity 2)0.6

    Capacity 2 and Cost 2 relate to a known similar operation in a similar environment

    Capacity 1 relates to the operation being studied

    Cost 1 is then estimated

    Annualised cost per tonne rule:

    Annualised cost per tonne of a known operation

    = {Total capital cost} {tonnes per year}

    Use this factor directly to estimate capex for another, similar operation.

    Open Pit Mine Planning and Design 255

    Capital cost estimation: general

    considerations

    Cost indices

    Most cost estimations are based on historical

    data available to the estimator.

    These data date and cost indices can be used to

    update them:

    Cost now = {cost then}{cost index now/cost index

    then}

    Indices available from Cost Guides

    Open Pit Mine Planning and Design 256

  • 5/11/2014

    128

    Open Pit Mine Planning and Design

    257 of 10

    Capital cost estimation: general

    considerations

    Working capital

    This is the capital component of operating

    costs needed to support the operation

    prior to substantial revenue inflows.

    Often underestimated and can result in

    project failure.

    Sometimes a factor (such as 10% of fixed

    capital cost) is applied. However a more

    detailed analysis is usually good practice.

    258 of 10

    Capital cost estimation: general

    considerations Options for capital equipment

    Contract mining

    capital not available;

    short duration;

    specialist skills required; and/or

    specialist equipment required.

    Hired equipment

    machine only and hirer responsible for fuel, oil, servicing and operation (dry hire); or

    full hire (all inclusive), usually hourly rate with standby rate.

    Open Pit Mine Planning and Design

  • 5/11/2014

    129

    Capital cost estimation: general

    considerations Ownership cost

    Fixed cost per hour irrespective of whether

    the machine is working or not

    It is a function of:

    purchase price

    cost of any extras

    freight charges

    tyre costs

    resale value

    depreciation period

    Open Pit Mine Planning and Design 259

    Capital cost estimation: general

    considerations Ownership cost (cont.)

    Straight-line depreciation formula:

    D = (P - R) / (N.H) where D is depreciation per

    hour, P is purchase price, R is residual value, N is

    usefu