advanced open pit planning and design 2014(for nicico)finaldraft
DESCRIPTION
miningTRANSCRIPT
-
5/11/2014
1
ADVANCED OPEN PIT MINE
PLANNING AND DESIGN
Presenter
Prof Emmanuel Chanda
The University of Adelaide, Australia
ADVANCED OPEN PIT MINE
PLANNING AND DESIGN
M1-Strategic mine planning M2-Open pit optimisation M3-Mine Production scheduling M4-Optimum Cut-off Grades M5-Mine Planning Software M6-Mine-to-Mill Optimisation M7-Equipment Selection M8-Financial Technical Modelling M9-Dewatering and Pumping
Open Pit Mine Planning and Design 2
-
5/11/2014
2
Objectives
Fundamentals of open pit mine design and current developments in planning and design methodology,
Current industry practices to maximise economic return.
Open pit mine planning and design process in theory and practice,
Unit Operations Drill-Blast-Load-Haul Apply this knowledge to plan/evaluate new
open pit projects and/or existing mines.
Open Pit Mine Planning and Design 3
What do you expect to learn from this
Course?
Open Pit Mine Planning and Design 4
-
5/11/2014
3
Module 1
Strategic Mine Planning
Open Pit Mine Planning and Design 5
1. What is strategic planning?
2. Mine planning process
3. Mining strategy
4. Feasibility Studies
5. Exercises
Big picture mine planning and design process
Big picture decision-making process
Applies to Greenfields as well operating mines
SP takes place at all levels of the company Corporate level: vision, mission, feasibility, etc Business unit level: expansion of production Mine level: medium/long term production strategy
Analogy: military strategy
Overview/scope
Open Pit Mine Planning and Design 6
-
5/11/2014
4
What is Strategic Mine
Planning?
Strategic mine planning is concerned with those
decisions that largely determine the value of the
mining business whereas tactical mine planning
deals with the tasks required to actually achieve
that value.
Both types of planning are necessary; they can be
looked at separately, even discussed separately,
but they cannot be separated in practice!
Open Pit Mine Planning and Design 7
Prospecting Exploration Closure
Life cycle of an orebody
Min
e P
lan
nin
g
Strategic Mine
Planning
Development Production
Types of planning and mine life cycle
Tactical Mine
Planning
Open Pit Mine Planning and Design 8
-
5/11/2014
5
Strategic mine planning focuses on those technical variables that affect the life of a mine and the value of the underneath mineral resource
It starts with the discovery of the mineral resource and finishes when it is exhausted or abandoned.
Go! List variables (factors) considered in SMP
Open Pit Mine Planning and Design 9
Business Strategy
Strategic
Planning
Economic
Evaluation
Decision-
Making
Behaviour
Mine Planning
Open Pit Mine Planning and Design 10
-
5/11/2014
6
Decision-Making Behaviour:
Risk Averse seeks other business goals
Risk Neutral seeks maximise NPV
Open Pit Mine Planning and Design 11
12
Mine Planning Process Flowchart
Open Pit Mine Planning and Design
-
5/11/2014
7
Mine Planning Process
Four main stages of mine planning process:
Geology of resource
Value of resource
Long-Term planning (Strategic) feasibility
studies
Medium-term/Short-term planning - production
Mine Planning Process*:
Geology + Data Analysis Resource Model
Optimisation
Mining Method Selection
Mine Design Financial Technical Model Optimal Schedulling
* A dynamic and iterative process * Open Pit Mine Planning and Design 13
Activity 1: Work in Groups of 2-4
To plan a new open pit mine in Kerman Province. List all the
data required to perform a feasibility study and where these data would come from.
Open Pit Mine Planning and Design 14
-
5/11/2014
8
Technical Aspects:
Once the geological features are understood and the physical characteristics of the ore body are determined, the main technical decisions that follow are:
Mining method selection
Processing route
Scale of operation (size)
Mining sequence
Selective cut-offs (e.g. cut-off grade at the mine)
Open Pit Mine Planning and Design 15
All these variables are inextricably interrelated in the sense that they cannot be determined in isolation from each other
Moreover, they cannot be determined without taking into account the market variables and related data from the geologic, metallurgical, geotechnical, and environmental models.
.as shown on next slide
Open Pit Mine Planning and Design 16
-
5/11/2014
9
MARKET
Metallurgical
Model
Geotechnical
Model Environmental
Model
Geological
Model
Mining
Method
Scale of
Operation Mining
Sequence
Selective
Cut-offs
Processing
Route
MINE PLAN
Open Pit Mine Planning and Design 17
Mining Method Selection
The choice of the mining method depends on the
shape, emplacement and properties of the
orebody and host rock; again, beyond technical
considerations, this is an economic decision
In general, there are two main mining methods:
Surface mining (open pit, quarries)
Underground mining (block caving, cut & fill)
Open Pit Mine Planning and Design 18
-
5/11/2014
10
However, depending on the emplacement of the orebody and its grade distribution, there are cases where both methods are feasible e.g. open-pit followed by underground mining or the other way around
This is the classic case of sub-vertical deposits such as kimberlitic pipes containing diamonds and some porphyry copper deposits
Open Pit Mine Planning and Design 19
Many decisions concerning the choice of the mining method are related to the "opportunity cost concept
For example:
In massive, disseminated deposits that are close to surface, open pit mining is more productive than an underground
Underground mining usually requires more development and preparation works
Economic considerations
Open Pit Mine Planning and Design 20
-
5/11/2014
11
Considerations in Mining Method Selection Finances:
Finance influences method selection: Length of pre-production development and phases
Thoroughness of the ore body delineation program
Scale of operations bulk mining methods, eg., block
caving
Technology applications - automation
Open Pit Mine Planning and Design 21
Markets
The mining method should be flexible enough to respond to market changes. When and how to high grade during peak commodity prices Changes to mine development schedule Focus on production of by-products (eg. cobalt in copper ore) Mining companies are price takers. What can be done about this?
Open Pit Mine Planning and Design 22
-
5/11/2014
12
Technology and Human Resources
Choice of particular mining method commits operation to certain type of technology, equipment, human resources and processes. Later change in method will be at a cost Must allow for possibility of introducing new technology Necessary skills must be available to operate selected mining system Lack of expertise may eliminate a particular mining method, though technically suitable. Consider specific training and supervision
Open Pit Mine Planning and Design 23
Processing route
The selection of the processing route depends
essentially on the characteristics of the ore; however,
beyond technical considerations, this is a business
decision
Essentially, there are basically two main routes:
Physical methods (concentration)
Chemical methods (hydrometallurgy)
Open Pit Mine Planning and Design 24
-
5/11/2014
13
Acceptable
Mineral
Comminution Liberation
Unacceptable
Classification
Separation Concentration
Physical Chemical
Open Pit Mine Planning and Design 25
Factors to consider
Products recovered
Recoveries and achievable grades
Environmental aspects
Market considerations
Capital and operating costs
Cycle times
Mine plan
Cash flow and profitability
In short, technical and financial considerations
Open Pit Mine Planning and Design 26
-
5/11/2014
14
Lab testing for initial investigation
Core samples and samples from outcrops
(chip samples) Pilot tests to confirm lab tests and design
Core samples and some bulk samples from
underground workings Industrial tests to feasibility
Bulk samples from underground workings
and additional core samples
Metallurgical tests
Open Pit Mine Planning and Design 27
Scale of the operation
The scale of the operation refers to production capacity, which in turn is related to the physical size of the installations at the mine and plants
This is directly related to the capital investment required to produce the final output deemed to put in the market
The larger the scale, the higher the investment and production
Open Pit Mine Planning and Design 28
Case Study: Olympic Dam Expansion Project
in South Australia
-
5/11/2014
15
From the point of view of a mining project, the scale of the operation is the dominant factor for establishing the mine life and business value
There is a compromise between the NPV of a project and its size the optimum size exits, because a very large operation may shorten the mine life too much, making the marginal investment unworthy
Open Pit Mine Planning and Design 29
Scenario 500 kt/d
Scenario 150 kt/d
Scenario 72 kt/d
Scenario 300 kt/d NPV
(MUS$)
Scale of operation
1000
2000
2700
3000
Size-profitability-risk relationship
Risk
Open Pit Mine Planning and Design 30
-
5/11/2014
16
Mining Sequence and Final Limits
It refers to the path or trajectory employed to exploit a mine from an initial situation until reaching the final limits or exhausting the ore reserves
Usually, these two variables are treated separately but because of their co-dependency they should be handled together
Open Pit Mine Planning and Design 31
The mining sequence is usually defined in terms of sequential cuts or "sectors in which a final mining envelope is split to guide the mining extraction
These sectors can be phases, cut-backs or push-backs as they are usually called in open-pit mining; or blocks, panels, rooms or stopes as these are commonly referred to in underground mining
Open Pit Mine Planning and Design 32
-
5/11/2014
17
It is worth noting that the partition of a final
mining envelope into cuts or sectors is done
because the time value of money
In effect, the purpose is to postpone
expenditures and bring forward revenue as
much as possible from production sales
Open Pit Mine Planning and Design 33
To illustrate how the time value of money
affects the economics of mining it is useful to
introduce the saw graph tool
It assumes that mining activities always
require some preparation works
(development) prior to ore extraction:
Stripping in open pit mining (t, m3)
Developments in underground (m3,
m2, m, t)
The scheduling saw graph
Open Pit Mine Planning and Design 34
-
5/11/2014
18
The scheduling Saw Graph
Time yr-1 yr-2 yr-3 yr-4 yr-5 yr-6
Minimum Ore Exposure
Open Pit Mine Planning and Design 35
Integral optimisation of the final pit
1
2
3
4
5
6
100 t (waste)
500 t (ore)
Revenue 2.2 $/t
Cost -1.0 $/t
Exploitation phases
Open Pit Mine Planning and Design 36
-
5/11/2014
19
Partial and cumulative tonnage
Ore Waste O/W Ratio Ore Waste O/W Ratio
1 500 100 0.2 500 100 0.2
2 500 300 0.6 1,000 400 0.4
3 500 500 1.0 1,500 900 0.6
4 500 700 1.4 2,000 1,600 0.8
5 500 900 1.8 2,500 2,500 1.0
6 500 1,100 2.2 3,000 3,600 1.2
7 500 1,300 2.6 3,500 4,900 1.4
Partial tonnage Cumulative tonnagePhase
Breakeven point Phase 6
Open Pit Mine Planning and Design 37
When neither the time value of money nor other
operational factors such as mine and plant
capacities are taken into account, the optimal final
limit is reached at Phase 6
The implicit assumption is that ore is exposed
simultaneously with waste and that ore revenue
occurs at the same time as waste cost
Open Pit Mine Planning and Design 38
-
5/11/2014
20
When accepting that ore and waste extraction have to consider certain physical restrictions in their programming (phase size and available equipment), then the time value of money becomes a relevant issue
The programming can be done using the saw graph early described
Open Pit Mine Planning and Design 39
Case 1: Open pit plan with 6 phases
yr-1 yr-2 yr-3 yr-4 yr-5 yr-6
Plant 500 t/y
Mine 1,300 t/y
500
500
1,000
1 2
3
4 5
5
4
2
1
3 6
6
Time
Waste removal
Open Pit Mine Planning and Design 40
-
5/11/2014
21
Economic evaluation: Phase 6
Time yr-1 yr-2 yr-3 yr-4 yr-5 yr-6
1,000
- 1,000
+1,250
0
- 800
- 300
-225 -546 +706
Present value(t=0, r=10%) = - 65
Open Pit Mine Planning and Design 41
Economic evaluation: Phase 5
Time yr-1 yr-2 yr-3 yr-4 yr-5 yr-6
1,000
- 1,000
+1,250
0
- 500 - 400
-331 -376 +776
Present value(t=0, r=10%) = + 70
Open Pit Mine Planning and Design 42
-
5/11/2014
22
Case 2: Open pit plan with 5 Phases
yr-1 yr-2 yr-3 yr-4 yr-5
Plant 500 t/y
Mine 1,300 t/y
500
500
1,000
1 2
3
4 5
5
4
2
1
3
Time
Open Pit Mine Planning and Design 43
Economic evaluation: Phase 5
Time yr-1 yr-2 yr-3 yr-4 yr-5 yr-6
1,000
- 1,000
+1,250
0
- 800
- 100
-83 -601 +776
Present value (t=0, r=10%) = + 92
Open Pit Mine Planning and Design 44
-
5/11/2014
23
Economic evaluation
Partial Cum Partial Cum
1 1,036 1,036 1,036 1,036
2 733 1,769 733 1,769
3 485 2,254 485 2,254
4 250 2,504 275 2,529
5 70 2,574 92 2,621
6 -65 2,509 - -
Phase
Net Present Value @ r = 10 % ($)
Case 1 (6 Phases) Case 2 (5 Phases)
Open Pit Mine Planning and Design 45
Summary of results
1
2
3
4
5
6
Breakeven final
limit (Phase 6)
Discounted final
limit (Phase 5)
Open Pit Mine Planning and Design 46
-
5/11/2014
24
Considering an underground
alternative
1
2
3
4
5
6
Open Pit Mine Planning and Design 47
2 open pit phases, 4 underground lifts
3
4
5
6
NPV(1)
$ 800
(1) Net present value at the beginning of year 1
1
2
Open Pit Mine Planning and Design 48
-
5/11/2014
25
3 open pit phases, 3 underground lifts.
3
4
5
6
NPV(1)
$ 450
$ 200
$ 50
(1) Net present value at the beginning of year 1
1
2
Open Pit Mine Planning and Design 49
NPV of underground lifts
Lifts
500
+800
0
+450
NPV Lift 3 (t=0, r=10%) = + 350
+200
+50
3 6 4 6 5 6 6
NPV Lift 4 (t=0, r=10%) = + 250
NPV Lift 5 (t=0, r=10%) = + 150
NPV Lift 6 (t=0, r=10%) = + 50
Open Pit Mine Planning and Design 50
-
5/11/2014
26
Economic evaluation
(Open Pit vs Underground)
Partial Cum Partial Cum
1 1,036 1,036 1,036 1,036
2 733 1,769 733 1,769
3 485 2,254 485 2,254
4 275 2,529 275 2,529
5 92 2,621 150 2,679
6 50 2,671 50 2,729
Phase
Net Presente Value @ r = 10 % ($)
Case 3 (OP/UG) Case 4 (Optimum)
Open Pit Mine Planning and Design 51
Optimum configuration
3
4
5
6
1
2
Open Pit Mine Planning and Design 52
-
5/11/2014
27
Summary of evaluations
1 1,036 1,036 1,036 1,036
2 1,769 1,769 1,769 1,769
3 2,254 2,254 2,254 2,254
4 2,504 2,529 2,529 2,529
5 2,574 2,621 2,621 2,679
6 2,509 - 2,671 2,729
Net Present Value @ r = 10 % ($)Phase
Case 1 Case 2 Case 3 Case 4
Open Pit Mine Planning and Design 53
NPV and Shareholder Value
Net present value ($) 2,509 2,621 2,671 2,729
Firm's net debt ($) 1,000 1,000 1,000 1,000
Firm's market value ($) 1,509 1,621 1,671 1,729
N Shares 1,500 1,500 1,500 1,500
Share value ($/Sh) 1.01 1.08 1.11 1.15
Case 1 Case 2 Case 3 Case 4Firm's Information
Open Pit Mine Planning and Design 54
-
5/11/2014
28
Role Of Feasibility Studies
Why Feasibility Study
Scoping Study
Preliminary Study
Bankable Feasibility Study
Risks
Open Pit Mine Planning and Design 55
Origin of the FS The Feasibility Study is a development of mine
valuation reports. These had remained almost invariable from 1900 to 1960s.
More complex and larger mining operations in 1960s and 1970s required sophisticated studies and reporting. The FS was developed which:
Brings together all aspects of an operation into one study
Looks at the inter-relationships and tries to solve any problems
Aims to determine technical and economic viability of a project
Open Pit Mine Planning and Design 56
-
5/11/2014
29
Feasibility Studies
Demonstrate that the project is economically
viable to the satisfaction of the Board, the
shareholders and all other stakeholders.
The FS enable the financing of:
Preliminary earthworks
Engineering construction
Infrastructure
Open Pit Mine Planning and Design 57
Provide a detailed analysis of all the
factors affecting a projects viability.
Enable determination of a go or no go decision
Have become an aid in obtaining
financial backing
Feasibility Studies
Open Pit Mine Planning and Design 58
-
5/11/2014
30
Phases
Scoping Study
Pre-Feasibility Study
Final Feasibility Study
Open Pit Mine Planning and Design 59
Scoping Study The Scoping Study is a preliminary investigation into a
project between a back of envelope and a pre-feasibility study, or an assessment of necessary size, grade of a target to explore.
It may also be called a Concept(ual) Study.
The study is normally undertaken with limited technical and other data being available.
There is high reliance on experience and knowledge of similar projects and it normally involves a basic level of literature search.
Open Pit Mine Planning and Design 60
-
5/11/2014
31
Aim of A Scoping Study
Provide a document for decision-making.
Identify key factors that will influence the
overall outcome of the project.
Identify and briefly assess possible options,
identify risks
Give an indication of the potential financial
worth of the project
MCA Project Management in Mine Planning and Design
Open Pit Mine Planning and Design 61
Outcomes of Scoping Study The outcomes will depend on the situation of the
particular project and reasons for the study. The
outcomes of a scoping study mayl include:
Information for decisions regarding the future of
the project.
Identification of key factors and probably risk
areas, requiring further early investigation.
Highlighting project activities or aspects which
have the greatest influence (sensitivity) on the
project value or return.
Highlighting project parameters that require
more accurate measurement or definition.
A proposed plan to advance, or close, the project
with schedules and estimated costs. Open Pit Mine Planning and Design 63
-
5/11/2014
32
Open Pit Mine Planning and
Design
A scoping study for the Flying Fox T1 deposit as a stand-alone underground mine with offsite ore treatment was prepared by mining consultants Golder Associates Pty Ltd.
Main outcomes of the T1 scoping study were as follows: Mineable Resources at 196,000t @ 5.4% Ni*
Contained nickel in concentrate 10,587 Ni tonnes
Gross Revenue (after royalties) A$101 million
Operating costs (mining, site, transport, treatment) A$201/tonne ore (A$1.70/lb Ni produced)
Capital costs - Establishment A$6.0 million
- Mine development A$12.8 million
Undiscounted Net cash flow (before tax and D&A) A$37.2 million
* Note : Mineable Resources do not constitute a JORC compliant
resource or reserve category.
Scoping Study- Case Study
64
Preliminary Feasibility Study
Decisions: Abandon project, change or continue?
Planning: Focus continued investigations on project-critical areas.
Justify detailed site investigation and resource definition.
Determine the optimum project scope.
Identify risks opportunities and potential show stoppers/fatal flaws.
Economic justification: Justify a full feasibility study.
Help sell the project.
Obtain private finance.
Development: Support permitting and stakeholder liaison
MCA Project Management in Mine Planning and Design
Open Pit Mine Planning and Design 65
-
5/11/2014
33
Open Pit Mine Planning and
Design
Pre Feasibility looking at
alternate scenarios Andean Golds Cerro Negro project in Argentina
Open pit optimization for the Vein Zone was completed using Whittle 4x software and recovered gold block grades. A US$800/oz gold price was used as the base case and the remaining inputs are as shown below:
Pit Optimization Parameters
Bench Angle 85o
Berm Width 9 metres every 20 metres
Pit Slope 52o overall slope with ramps
Mining Cost $1.50 per tonne mined
Processing Cost $14.00 per tonne ore
General & Administrative Cost $3.00
per tonne ore
Pit
Revenue
Factor
Waste
Tonnes
('000)
Ore
Tonnes
('000)
Recovered
Au (g/t)
Recovered
Ounces
('000)
Strip Ratio
(W:O)
1 0.30 9,763.1 2,083.3 5.30 355.0 4.69
5 0.38 11,922.4 2,580.3 4.84 401.3 4.62
10 0.48 14,631.9 3,111.4 4.43 443.6 4.70
15 0.58 15,704.0 3,580.2 4.06 467.2 4.39
20 0.68 16,357.2 3,941.0 3.81 482.6 4.15
25 0.78 16,697.4 4,143.1 3.68 489.8 4.03
28 0.84 16,765.5 4,247.6 3.61 493.0 3.95
29 0.86 25,403.2 4,547.3 3.56 520.4 5.59
30 0.88 25,370.3 4,581.3 3.54 521.2 5.54
36 1.00 25,725.8 4,750.5 3.45 526.2 5.42
40 1.14 26,977.6 5,016.1 3.31 534.3 5.38
45 1.28 27,120.3 5,110.1 3.26 536.3 5.31
50 1.42 27,163.4 5,199.4 3.22 537.9 5.22
55 1.60 29,865.5 5,363.9 3.15 543.6 5.57
60 1.72 29,983.6 5,422.6 3.12 544.6 5.53
67 2.00 30,555.8 5,536.6 3.07 546.5 5.52
66
Open Pit Mine Planning and
Design
Pre Feasibility scheduling
production
Period
Oxide
"Ore"
(000's
Tonnes)
Oxide "Ore"
(g/t Au)
Mix "Ore"
(000's
Tonnes)
Mix "Ore"
(g/t Au)
Totals
(000's
Tonnes)
Totals
(g/t Au)
Waste
(000's
Tonnes)
Strip
Ratio
Pre-production 2.4 2.58 2,290.7
Year 1 644.1 3.05 28.2 4.00 672.3 3.09 3,615.3 5.38
Year 2 670.6 3.71 4.7 2.18 675.3 3.7 5,063.0 7.50
Year 3 643.1 4.62 31.7 3.65 674.9 4.58 2,022.2 3.00
Year 4 758.0 4.39 89.3 3.45 847.3 4.29 7,476.7 8.82
Year 5 1,186.7 2.55 163.3 2.76 1,350.0 2.58 7,619.7 5.64
Year 6 279.6 4.39 130.4 2.52 410.0 3.8 2,287.7 5.58
Totals 4182.1 3.59 447.7 2.96 4,629.8 3.53 30,375.3 6.56
Portable Ore Portable Ore Portable Ore
000's Tonnes 000's Tonnes 000's Tonnes
Year 1 672.3 3.09 677.7 11.54 242.81 1,350.0 7.33 121.89
Year 2 675.3 3.70 674.7 14.07 258.86 1,350.0 8.88 129.37
Year 3 674.9 4.58 675.1 12.97 203.05 1,350.0 8.77 101.55
Year 4 847.3 4.29 502.7 6.69 120.41 1,350.0 5.18 44.84
Year 5 1,350.0 2.58 1,350.0 2.58 0.00
Year 6 410.0 3.80 410.0 3.80 0.00
Totals 4,629.8 3.53 2,530.2 11.63 212.16 7,160.0 6.39 74.97
Cerro Negro Total
g/t Au g/t Ag g/t Au g/t Agg/t Au
Period
Vein Zone Eureka
Open pit schedule
Open pit and underground schedule
67
-
5/11/2014
34
Open Pit Mine Planning and
Design
Pre Feasibility things will change
over time Brisas Gold Mine Venezuela
Key Economic Parameters and Results 2008 2006
Mill Through-Put Range (tonnes per day) 75,000 - 68,000 70,000
Metallugy Recovery
Plant Recovery - Gold 83% 83%
Plant Recovery - Copper 87% 87%
Net Payable Metal - Gold 82% 81%
Net Payable Metal - Copper 83% 83%
Life of Mine Production (payable metals)
Gold (million ounces) 8.35 8.41
Copper (million ounces) 1,156 1,113
Average Annual Production
Gold (ounces) 457,000 456,000
Copper (ounces) 63 60
Mine Life (years) 18.25 18.5
Initial Capital Cost ($million) 2008 2006
$ $
Mine 59.0 76.6
Mill 314.7 241.5
Infrastructure 67.8 65.8
Tailings management facility 38.3 23.8
Owner's Costs 63.4 55.6
Pre-Stripping 16.7 18.3
Indirect Costs (includes EPCM and Camp) 127.6 97.0
Contingency 43.8 59.4
Total Initial Capital $731.3 $638.0
69
Open Pit Mine Planning and
Design
Pre Feasibility things
will change over time Base Case Economics 2008 2006
$ $
Metal Prices
Gold per ounce $600 $470
Copper per pound $2.25 $1.80
Cash Operating Cost Per Ore Tonne
Mining and Dewatering $2.68 $2.08
Processing 3.00 2.59
General and Administrative 0.43 0.42
Transport and Freight 0.43 0.34
Smelting and Refining 1.08 1.02
Total cash operating cost per tonne $7.62 $6.45
Cash per Ounce of Gold
Cash Operating Costs $120 $126
Exploitation Tax 22 16
Capital Cost (initial, sustaining and sunk) 135 111
Total Costs (including sunk costs) $277 $253
Total Cost (excluding sunk costs) $268 $245
Pre-Tax
Internal Rate of Return 20.5% 15.4%
Net Present Value (NPV)
@ 0% discount (billions) $2.77 $1.91
@ 5% discount (billions) $1.29 $0.7870
-
5/11/2014
35
(Final) Feasibility Study (FFS)
The Feasibility Study Report is a decision-making
document based on verified facts and minimum
assumptions (criteria). The report may be used for
several purposes:
Assemble a comprehensive framework of facts.
Present a detailed project description.
Forecast profitability.
Facilitate partners and/or sources of finance.
Basis for detailed engineering.
MCA Project Management in Mine Planning and Design
Open Pit Mine Planning and Design 71
Requirements of a FS to be
bankable
A FS must be;
Credible
Definitive
Relevant
Independent
Open Pit Mine Planning and Design 72
-
5/11/2014
36
Open Pit Mine Planning and
Design
Final Feasibility high level issues Geology and ore reserves - size, shape and depth of the ore, the grade of the
ore and distribution, how homogeneous, any major faults or intrusions and hydrological reports.
Mining method and schedule surface, open cut, underground, annual production rate vs life of mine, phasing of development, envisaged ROM grade, capital equipment and manning levels required. (High production rate, high capital expenditure, shorter mine life what is the optimum?)
Infrastructure requirements - including ancillary buildings, roads, drainage,
tailings disposal, general arrangement drawings of infrastructure layout.
Metallurgy/concentrator/washery design recovery factor, concentrate grade, product quality.
Recommendations for the process plant including:
Flow diagram
Material and water balances
Equipment list (major items) together with budget quotations
General arrangement plan and elections of process plant to scale
1:100
Electrical system (line diagram)
73
Open Pit Mine Planning and
Design
- high level issues continued Infrastructure, water, power, accommodation and environmental issues
source, capital and operating cost, disposal of tailings.
Permits right to mine and discharge waste and make good.
Construction schedule timing, how long to first production the quicker the better.
Logistics - of supply materials, equipment and manpower to site including an investigation of transport modes.
Identification of strategic decisions required - early ordering of long delivery items, early starts to opening of negotiations for right-of-way dispensation etc.
Preliminary programme -for carrying-out the Project.
Construction cost minimum expenditure to get the project operating, which varies depending on type and size of mine. All costs to include transport and commissioning costs, fees and all management costs except for Client's own costs.
Markets and marketing transport to market (FOB or CIF), price for product quality sold, secondary processing costs, adequate demand for product.
Financial analysis put all of the above together to determine if the project is financially viable.
74
-
5/11/2014
37
Combination of many errors in forecasting can be fatal for any project.
Project owner is Pegasus Gold Inc and wrote off US$353.5 million in November 1997 after closing down the project.
This write down of shareholders funds was of balance sheet items amounting to US$122.6 million of acquisition costs, US$49.4 million of deferred preproduction and development expenses and US$181.3 million for property and equipment.
75
Rudenno, 2008
Things can go wrong
Mt Todd gold mine
Open Pit Mine Planning and Design
Case Study Mt Told Gold
Project
Commodity price overoptimism resulted in a
forecast gold price of US$385 per ounce,
including a hedging premium above
expected spot prices.
Spot prices while the project was operating
were about US$315 per ounce and the
hedging premium was small.
76
MCA - Risk Assessment in Mine Planning and Design
Open Pit Mine Planning and Design
-
5/11/2014
38
77
Forecast Actual Change
Reserves grade 1.07g/tAu 0.96g/tAu -10%
Metallurgical recovery of gold 84% 74% -12%
Throughput per year 8 Mt 6.7 Mt - 16%
Crushing costs $1.36/t $2.49/t +83%
Contract mining $1.00/t $1.15/t +15%
Power costs $0.058/kwh $0.075/kwh +29%
Cyanide usage 0.68kg/t 0.86kg/t +26%
Total cash costs $11.86/t $13.58/t +15%
Cash costs per ounce gold
produced
US$287/oz US$415/oz +45%
Gold price US$385 US$315 -18%
Exchange rate, A$1.00=US$ 0.7 0.74 +6%
Case Study Mt Told Gold
Project
MCA - Risk Assessment in Mine Planning and Design Open Pit Mine Planning and Design
Open Pit Mine Planning and Design 78 of 10
NATURE & PURPOSE OF
FEASIBILITY STUDIES IN MINING
Type Scoping Preliminary Feasibility
Audience Internal Technical Mixed Professional External
Exploration Business
Development
Executive
Executives
Joint venture
Extracts to stake
holders
Boards
Financiers
Investors
Consultants
Their Interests Critical factors
Potential
Optimum project scope
Profitability
Cost of next stage
Profitability
Costs
Schedule
Risks, etc
Your Audience
-
5/11/2014
39
Open Pit Mine Planning and Design 79 of 10
Scoping
Study
Preliminary
Feasibility
Feasibility
Study
Project Control
Estimate
Class 1
(+/- 30% - 50%)
Class 2
(+/- 25%)
Class 3
(+/- 10% - 15%)
Class IV
(+/- 5% - 10%)
Order of
magnitude
Capacity factor
estimate
Equipment factor
estimate Forced detail estimate
Definitive;
Fall out detail estimate
Cost Accuracy
Mining is a Business, but risky
Open Pit Mine Planning and Design 80
-
5/11/2014
40
MINING PROJECT RISKS
TECHNICAL RISKS OH&S RISKS
POLITICAL
RISKS
ECONOMIC / FINANCIAL
RISKS
81
Participants discuss these elements of
Risk in Mining Projects.
Open Pit Mine Planning and Design
Conclusion
Strategic planning (SP) involves developing a range
of options, carrying out some form of evaluation,
assessing criteria and decision-making.
Open Pit Mine Planning and Design 82
http://images.google.com/imgres?imgurl=http://www.uniforum.org/publications/ufm/sept96/mining.gif&imgrefurl=http://www.uniforum.org/publications/ufm/sept96/mining.html&h=367&w=341&sz=90&hl=en&start=7&tbnid=G39bOsT-YZHkKM:&tbnh=122&tbnw=113&prev=/images?q=mining&gbv=2&ndsp=18&hl=en&sa=N
-
5/11/2014
41
Activity 2: Individual learning
Refer to worksheet 1
Development of a mining strategy: open pit and/or
underground?
Complete the task and discuss the calculations with the person(s) sitting next to you!
Open Pit Mine Planning and Design 83
Module 2
OPEN PIT OPTIMIZATION
Open Pit Mine Planning and Design 84
What you will learn:
Block Values and Cost calculation
Pit Optimisation techniques
Pit Optimisation Software
-
5/11/2014
42
Block Grade to Block Value
Some factors to consider:
Location of the block relative to the surface effect on
cost
Processing costs my depend on rock type
0.3%Cu -$1.13/t
Dollar Value = Revenue - Costs
86
Dollar Value = Revenues - Costs
Revenues can be calculated from:
Ore tonnages
Grades
Recoveries
Product price
Costs can be calculated from:
Mining cost
Milling cost
Overheads
Open Pit Mine Planning and Design
-
5/11/2014
43
VALUE
= (METAL*RECOVERY*PRICE - ORE*COSTP) - ROCK*COSTM
A Formula for a Block Value used in Whittle
Calculate the value of ore block X:
200 grams of metal
100 tonnes of rock/ore
Metallurgical recovery = 97%
Selling price of metal $10.00 per gram
Cost of processing $12.00
Cost of mining $5.00
BV = [200x0.97x10 100x12 100x5] = $240
X
88
Calculating Costs
Must calculate values for:
Mining Cost per Tonne Mined
Processing Cost per Tonne Processed
Rehabilitation Cost per Tonne of Waste
Selling Cost per Unit of Product
Some Time Costs must be included
Open Pit Mine Planning and Design
-
5/11/2014
44
89
Include
Any cost which is directly proportional to the tonnes
or units of product:
Fuel oil
Wages
Spare parts
Explosives
etc
Include with the appropriate activity
Open Pit Mine Planning and Design
90
Include
Time costs which would stop if mining
stopped:
Site administration
Site infrastructure maintenance
Interest on working capital loan
Fall in resale value of equipment
Capital replacement
Truck purchase (long project)
Open Pit Mine Planning and Design
-
5/11/2014
45
91
What to do with Time Costs
When mill limited
Divide annual time cost by annual mill throughput and add the result to the processing cost
When mining limited
Divide annual time cost by annual mining capacity and add the result to the mining cost N.B. Even add the mill time costs!
When selling limited ...
Open Pit Mine Planning and Design
92
Dont Include
Time costs which continue whether
you continue mining or not
Up-front/sunk costs
Open Pit Mine Planning and Design
-
5/11/2014
46
Activity 3: Individual learning
Refer to worksheet 2
Block Values and Cost Calculation
Complete the task and discuss the calculations with the person(s) sitting next to you!
Open Pit Mine Planning and Design 93
Open Pit Mine Planning and Design 94
Resource Model
Mine survey
Diluted Resource
Ore Reserve estimate
Proved and Probable
Resource estimate
Measured
Indicated
Inferred
Dilution &
ore losses
Beneficiation
factors
Operating
Costs
Economic
Parameters
Resource
Classification
Ore Reserve Model
Mining production
schedule
Beneficiation
product
Potential Ore
Reserve
Overburden
& sub-grade
Process
Parameters
Open pit optimisation
and design
Reserve
Classification
Revenue, cost and
slope parameters
position in mine
planning flow
sheet
Open Pit Optimisation
-
5/11/2014
47
Activity 4 : Individual learning
Refer to worksheet 3
Pit Optimisation Task 1
Complete the task and discuss the calculations with the person(s) sitting next to you!
Open Pit Mine Planning and Design 95
96
Any feasible outline has a Dollar Value. In this context
feasible means that it obeys safe slope requirements
The optimal outline is defined as the one with the highest
dollar value (Profit = Revenue Costs)
Nothing can be added to an optimal outline which will
increase the value without breaking the slope constraints.
Nothing can be removed from an optimal outline which
will increase the value without breaking the slope
constraints.
Definition of the Optimal Outline
Open Pit Mine Planning and Design
-
5/11/2014
48
97
Pit Optimisation Techniques
Moving/Floating/Dynamic Cone Algorithm
Lerchs-Grossmann 2-D Dynamic Programming
Algorithm
LG 3-D Graph Theory Algorithm.
Network Analysis Algorithm
Linear Programming (integer programming)
etc
Open Pit Mine Planning and Design
98
Floating Cone Method
Position an inverted cone, with the required slopes,
on each block with a positive value
If the total value of all blocks in the cone is positive,
mine those blocks
Repeat these steps until no cone has a positive
value
There are two problems
Open Pit Mine Planning and Design
-
5/11/2014
49
99
Floating Cone Method
Open Pit Mine Planning and Design
Courtesy: Kores Corpration
100
Floating Cone- Mining too little
-30
-80 -80
+100 +100
Open Pit Mine Planning and Design
-
5/11/2014
50
101
Floating Cone- Mining too much
Open Pit Mine Planning and Design
102
Lerchs-Grossman Algorithm
Works with block values
Works with block mining precedence
Guarantees to find the three-dimensional
outline with the highest possible value
Open Pit Mine Planning and Design
-
5/11/2014
51
103
Lerchs-Grossman Algorithm
Works with block values
Works with block mining precedence
Guarantees to find the three-dimensional
outline with the highest possible value
Open Pit Mine Planning and Design
104
Lerchs-Grossman Algorithm
Open Pit Mine Planning and Design
-
5/11/2014
52
LG 3d block and graph representation
Orthogonal set of blocks 2 basic geometries to represent open pit
Arrows point to the blocks that first need to be removed to access the underlying block (at the base)
Open Pit Mine Planning and Design 105
106
Final Pit Design composite plan
Open Pit Mine Planning and Design
-
5/11/2014
53
Activity 5 : Individual learning
Refer to worksheet 3
Pit Optimisation Task 2
Follow the example calculation of the LG pit optimisation algorithm
Open Pit Mine Planning and Design 107
The algorithms to determine the final pit
limit assume that an economic value can be
assigned to each block
However, many of the costs are time costs;
it means that assigning them to blocks
requires an assumption about what is the
unitary operation that restricts production
(to express these costs in terms of that
activity)
Precautions with the OP algorithms
1) Ascribing costs to blocks
Open Pit Mine Planning and Design 108
-
5/11/2014
54
To calculate the net value of a block one has
to assume a breakeven cut-off grade
A common assumption is to classify as ore
those blocks with a positive value and waste
those blocks with a negative value. If the
mine is the limiting operation, this misses the
opportunity to create value.
2) Assumption of a breakeven grade
Open Pit Mine Planning and Design 109
There are costs that can not be estimated
without a mining plan. This is the case of waste
material, which has to be placed in a dump and
the cost will depend on the time that this
happens because of the haul distance
This can be solved by iterations!
3) Time value of money
Open Pit Mine Planning and Design 110
-
5/11/2014
55
There are cases where blocks should be
blended with others to be classified as
ore. But that again requires a mining plan in
advance.
This can also be solved by iterations!
4) Blending requirements
Open Pit Mine Planning and Design 111
Major General Mine Design Systems
Fully functional packages (with build-in CAD systems):
VULCAN
DATAMINE/CAE
SURPAC/GEMCOM
MineSight
Minex/Gemcom - WHITTLE
Micromine
CAD overlaying packages:
AutoCAD
SurvCADD/Carlson
LKAB System
Open Pit Mine Planning and Design 112
-
5/11/2014
56
Data Import
Import
+
3D Borehole
Processing
Open Pit Mine Planning and Design 113
Geological Interpretation
Open Pit Mine Planning and Design 114
-
5/11/2014
57
Block Model + Grade Assessment
Block Model with Grade
Open Pit Mine Planning and Design 115
Economical Model - Grade
>>> $Value
>>> Au [g/t]
Value
$$$
Open Pit Mine Planning and Design 116
-
5/11/2014
58
Optimisation/Design
Major optimisation programs based on Lerchs-
Grossman algorithm:
Whittle FX Optimiser (stand alone)
MineMax Planner (stand alone)
Pit Optimizer (Vulcan 3D)
NPV Scheduler (Datamine)
Pit Optimiser (Surpac)
Open Pit Mine Planning and Design 117
Whittle FX
Strategic Mine Planning Software
Import Block Model Pit by Pit Graph
Constrains:
Economical
Geometrical
Operational No access constrains
No haul road/ramp Open Pit Mine Planning and Design 118
-
5/11/2014
59
Optimal Pit
Open Pit Mine Planning and Design 119
Mine Design
Open Pit Mine Planning and Design 120
-
5/11/2014
60
Mine Design
Geomechanics/Geotechnical
Access constraints
Equipment selection
Ventilation network (underground)
Rehabilitation
Environmental constraints
Open Pit Mine Planning and Design 121
Final Optimal Pit
Open Pit Mine Planning and Design 122
-
5/11/2014
61
Final Optimal Pit & Pushbacks
Open Pit Mine Planning and Design 123
Reporting & Evaluation
Open Pit Mine Planning and Design 124
-
5/11/2014
62
Scheduling
Open Pit Mine Planning and Design 125
The Pushbacks Generation
Open Pit Mine Planning and Design 126
-
5/11/2014
63
Optimizing Production
Schedules
Open Pit Mine Planning and Design 127 of 26
Optimizing Production Schedules
+ =
Open Pit Mine Planning and Design 128
-
5/11/2014
64
Activity 6 : Individual learning
Review the following technical paper:
Chanda, E.K., Spencer, E. (1999). Maximising Resource Utilisation in Open Pit Design, in Proc. 28th International Symposium on Computer Applications in the Minerals
Industry, 20-22 October, Colorado School of Mines, pp359-366, (SME-AIME, Littleton).
1) What is unique about the the approach used by the
authors? Open Pit Mine Planning and Design 129
waste dump planning
Open Pit Mine Planning and Design 130
What you will learn:
Principles of dump design and
Dump optimisation
-
5/11/2014
65
Why waste dump planning?
Open Pit Mine Planning and Design 131
A strip ratio of 10:1, say, implies that for every unit of
ore mined, 10 times of waste rock is mined.
The waste rock ends up being stored in a waste
dump
Traditionally little attention has been paid to dump
design and planning, the focus being on planning of
ore extraction
It has been recognised that dump design and
planning is an integral part of pit design.
Rock flow in an open pit mine
Open Pit Mine Planning and Design 132
Yu (2014)
-
5/11/2014
66
133 of 10
Waste Dump Design
Two main approaches:
1) Top-down dumps waste rock is dumped
over an advancing face (angle of repose)
approx 38o from horizontal. After
dumping is complete . The dump is
reshaped to its intended configuration,
usually using bulldozers.
Open Pit Mine Planning and Design
134 of 10
Waste Dump Design
2) Bottom-up storage waste rock
is dumped in series of piles ,
and then spread to form a
relatively thin layer. Also known as paddock dumping.
Open Pit Mine Planning and Design
-
5/11/2014
67
135 of 10
Waste Dump Design
Hybrid dumping whereby top
down used is used to produce
relatively thick layers (10 or 15 m,
say), which are then overlain by
subsequent equally thick layers.
This approach is safer and
requires leas reshaping.
Open Pit Mine Planning and Design
136 of 10
Waste Dump Design
Dump progression with shortest haul first strategy
Open Pit Mine Planning and Design
-
5/11/2014
68
137 of 10
Waste Dump Design
Dump design considering NAF PAF material (Yu 2013)
Open Pit Mine Planning and Design
138 of 10
Waste Dump
Optimisation- how?
MINEMAX Software
Simultaneous pit and waste dump design
Dump modelled as blocks
WHITTLE Software
Dump optimisation as mirror image of open pit
optimisation
XPAC Advanced Destination Scheduler) Software
Module schedules rock placement
Open Pit Mine Planning and Design
-
5/11/2014
69
139 of 10
Waste Dump Optimisation-
Recent Developments
Integrated modelling of dumping system (Yu 2013)
Open Pit Mine Planning and Design
Module 3
PRODUCTION SCHEDULING
Open Pit Mine Planning and Design 140
What you will learn:
Principles of production scheduling
Scheduling Software
-
5/11/2014
70
Mine Scheduling (definition)
A mining schedule, which tell us when things occur, can be constructed by applying
production constraints to the mining
sequence
Basis for preparing and controlling the
mines development and production
A schedule determines the cash flow ($$$)
associated with mining.
Open Pit Mine Planning and Design 141
Typical Timeline
Year
-2 -1 +1 +2
Pre-production
(Development
Construction)
Production
Open Pit Mine Planning and Design 142
-
5/11/2014
71
Inputs
The scope of the work to be done from Mining
Layout Designs
Rates at which this work is normally prepared,
from Key Performance Indicators (KPI)
Labour working hours and rosters from
Strategic Planning module
Plant capacities, from the Strategic Planning
modules
Production schedules, Ore reserves, tonnes and
grades, recoveries and dilutions
Open Pit Mine Planning and Design 143
Types of Mining Schedule
Production schedules
Long Term or Life of Mine (10+ years)
Medium Term (5 years approx.)
Short Term (3 months 2 years)
Extremely Short Term (down to a shift, or for specific jobs)
Exploration drilling schedules
Development schedules
Production drilling schedules
Equipment schedules
Labour schedules
Filling schedules
Consumable schedules
Special project schedules Open Pit Mine Planning and Design 144
-
5/11/2014
72
Scheduling Packages
XPAC
iGannt
MS Project
MS Excel
Whittle 4D
In-house
Open Pit Mine Planning and Design 145
XPAC
Developed by Runge Software
Business focussed mine scheduling application
Specifically developed for forecasting, reserve
database and mine scheduling management of all
types of mineral deposits and mining methods
Easy-to-use tools for the adaptation, analysis and
scheduling of mineral resources
Designed for surface/underground coal mining
Has limitations in underground mining or in pits with
complex geometries
Open Pit Mine Planning and Design 146
-
5/11/2014
73
iGantt
Developed by MineMax
Tool for open-pit and underground production
scheduling
Integrates Gantt chart, 3D visualization and
spreadsheet views of a production schedule
Used for scheduling a single operation or multiple
operations across an enterprise
Open Pit Mine Planning and Design 147
Open Pit Mine Planning and Design 148
-
5/11/2014
74
Open Pit Mine Planning and Design 149
Open Pit Mine Planning and Design 150
-
5/11/2014
75
Financial Technical Model
Plant design
Infrastructure (road, power, water, village, etc.)
Equipment selection
Capitals
Operating costs
Royalty
Tax
Revenue
NCF NPV, IRR, PB, etc.
Open Pit Mine Planning and Design 151
Activity 8 : Individual learning
Refer to worksheet 4
Production Scheduling
Calculate the monthly production figures for a small gold mine
Open Pit Mine Planning and Design 152
-
5/11/2014
76
Module 4
Cut-off grade optimization
Open Pit Mine Planning and Design 153
1. Background
2. The model
3. Example 1: an hypothetical case
4. Example 2: a copper open pit mine
& mill
5. Conclusions
6. References
1. Background
This model was developed in the early
1960s by Ken Lane, a mathematician who
made his professional career in the Rio
Tinto Group
At the time, the model was used in various
mines of Rio Tinto including Palabora
mine in South Africa, and Bougainville
mine in PNG. Open Pit Mine Planning and Design 154
-
5/11/2014
77
2. The model
Qm
Qc
Waste
M
Cut-off gx
Concentrates
Tailings
Ore
C
Qr
R
Slag
Final product
Open Pit Mine Planning and Design 155
M = Mine capacity per period (t of material)
C = Plant capacity per period (t of ore)
R = Refinery capacity per period (t of product)
Qm = Quantity of run-of-mine material (t of material)
Qc = Quantity of ore (t of ore)
Qr = Quantity of final product (t of product) = Qcgy
T = Time to mine, process or refine Qm
P = Profit
Variables used in Lanes Model
Open Pit Mine Planning and Design 156
-
5/11/2014
78
d = annual discount rate
m = mining costs ($/t of material)
c = concentrating costs ($/t of ore)
r = refining and marketing costs ($/t of product)
f = fixed costs, per period ($/period)
s = selling price ($/t of final product)
y = overall metallurgical recovery
Models variables (cont)
Open Pit Mine Planning and Design 157
The profit equation for Qm
TfQmQcQ r- sP mcr
(1a) TfQmQcyg r- sP mc
(1)
As c r
y g Q Q
Open Pit Mine Planning and Design 158
-
5/11/2014
79
Profit from Qm
and Present Value
Qm
Grade
f
gx
Qc
W
V
V = Present value at the beginning of period T
W = Remaining present value after mining Qm
Open Pit Mine Planning and Design 159
Time
P P2 P3 P4 Pn
W
V
T
0
T
d)(1
WPV
(2)
Open Pit Mine Planning and Design 160
-
5/11/2014
80
If time T is small:
(1 + d)T 1 + dT (3)
Replacing in (2):
(4)
Re-arranging:
V(1 + dT) = P + W (5)
T)d(1
WPV
Open Pit Mine Planning and Design 161
Re-arranging:
v = V - W = P - dVT (6)
Where v is the contribution that the
fraction Qm of the ore deposit makes to
the present value of the business
As such, v is the variable to maximise
when choosing the optimum cut-off
grade
Open Pit Mine Planning and Design 162
-
5/11/2014
81
Replacing (1) in (6):
(7)
TVdfQmQcQrsv mcr
But the optimum present value V on the
right side of equation (7) is unknown
until the cut-off grade policy is optimised
This chicken and egg problem is solved
by iterations, using an arbitrary value of
V in the first iteration and stoping when V
converges Open Pit Mine Planning and Design 163
Economic cut-off grades
(7)
In equation (7), time T depends on the
stage that limits the pace at which ore is
mined
That is, the quantities Qm, Qc or Qr and
their respective capacities M, C, or R
This leads to three economic cut-off
grades:
TVdfQmQcQrsv mcr
Open Pit Mine Planning and Design 164
-
5/11/2014
82
a) When the mine imposes a limit (M)
In this case, M
QT m
Replacing this in expression (7):
mcrm QM
VdfmQcQrsv
Max vm 0
g
vm
Open Pit Mine Planning and Design 165
As Qm is given, g only affects Qc and Qr
Then g must be chosen to make (s-r)Qr - cQc
as large as possible
yrsc
gm
cc QcygQr-s
Therefore:
Open Pit Mine Planning and Design 166
-
5/11/2014
83
b) When the plant imposes a limit (M)
In this case, C
QT c
Replacing this in expression (7):
mcrc QmQC
VdfcQrsv
Max vc 0
g
vc
Open Pit Mine Planning and Design 167
In the same way, as Qm is given, g must be
chosen to maximise:
yrsC
Vdfc
gc
cc QC
VdfcygQr-s
Therefore:
Open Pit Mine Planning and Design 168
-
5/11/2014
84
c) When the refinery imposes a limit (R)
In this case, R
QT r
Replacing this in expression (7):
mcrr QmQcQ
R
Vdfrsv
Max vr 0
g
vr
Open Pit Mine Planning and Design 169
In the same way, as Qm
is given, g
must be chosen to maximise:
y
R
Vdfrs
cgr
cc QcygQ
R
Vdfrs
Therefore:
Open Pit Mine Planning and Design 170
-
5/11/2014
85
The operation is sometimes limited by two or
eventually three stages simultaneously
Then, three balancing cut-off grades can be
introduced into the analysis
gmc: Mine-Plant
gmr: Mine-Refinery grc : Refinery-Plant
Balancing cut-off grades
Open Pit Mine Planning and Design 171
gmc fully utilises mine and mill capacities;
that is, maximum stripping ratio at the mine
and throughput at the mill
Mine-mill example
Grade
f
gmc
Qm
gm gc
Open Pit Mine Planning and Design 172
-
5/11/2014
86
Mine capacity: 650,000 t/d
Mill capacity: 150,000 t/d
gm: 0.25 %Cu
gc: 0.65 %Cu
Possible throughputs:
Cut-off % Cu
Mine t/d
Mill t/d
Grade % Cu
0.25 450,000 150,000 0.9
0.50 650,000 150,000 1.2
0.65 650,000 120,000 1.3
0.5 %Cu is a balancing cut-off
Open Pit Mine Planning and Design 173
In summary, Lanes model considers six
cut-off grades:
three economic cut-off grades, and
three balancing cut-off grades
The former depend on economic factors
and capacities whereas the latter are
determined by the grade distribution that
can vary widely throughout irregular ore
bodies
None of these considers mining costs!
Open Pit Mine Planning and Design 174
-
5/11/2014
87
The overall optimum is one of the six cut-
off grades already defined:
1) gm
2) gc
3) gr
4) gmc
5) gmr
6) grc
To assess which one is the optimum it is
best to consider each pair of stages in
turn
Optimum cut-off grades
Open Pit Mine Planning and Design 175
To see which one is the optimum it is best
to plot the value functions considering
each pair of stages in turn
Mine-Concentrator
mcrm QM
VdfmQcQrsv
mcrc QmQC
VdfcQrsv
Open Pit Mine Planning and Design 176
-
5/11/2014
88
g
v
gmc gc gm
Gmc = gm vc vm
g
v
gmc gc gm
Gmc = gmc vc vm
Open Pit Mine Planning and Design 177
g
v
gmc gc gm
Gmc = gc
vc vm
In a similar way, by considering the other
pair of stages, it is possible to obtain Gmr
and Grc
Open Pit Mine Planning and Design 178
-
5/11/2014
89
g
v
gmc gc gm
vc vm
vr
gr gmr grc
The overall optimum cut-off grade is:
G = Middle value (Gmc,Gmr,Grc)
Open Pit Mine Planning and Design 179
Mine capacity (M) = 100
Plant capacity (C) = 50
Refinery capacity (R) = 40
Mining costs (m) = 1
Concentrating costs (c)= 2
Refining costs (r) = 5
Fixed costs (f) = 300
Selling price (s) = 25
Overall recovery (y) = 100 %
Annual discount rate (d)= 15 %
3. Example 1: an hypothetical case
Open Pit Mine Planning and Design 180
-
5/11/2014
90
Grade-tonne relationship
Grade interval
Quantity
0.0 0.1 100
0.1 0.2 100
0.2 0.3 100
. .
.
0.9 1.0 100
1000
g
f(t)
100
0 0.5 1.0
Open Pit Mine Planning and Design 181
Balancing cut-off grades
Cut-off Tonnage Ratios
Mine Mill Grade Ref. M/C M/R C/R
0.0 1000 1000 0.50 500 1.00 2.00 2.00
0.1 1000 900 0.55 495 1.11 2.02 1.82
0.2 1000 800 0.60 480 1.25 2.08 1.66
0.3 1000 700 0.65 455 1.43 2.20 1.54
0.4 1000 600 0.70 420 1.67 2.38 1.43
0.5 1000 500 0.75 375 2.00 2.67 1.33
0.6 1000 400 0.80 320 2.50 3.13 1.25
0.7 1000 300 0.85 255 3.33 3.92 1.18
0.8 1000 200 0.90 180 5.00 5.56 1.11
0.9 1000 100 0.95 95 10.00 10.53 1.05
M/C = 100/50 = 2.00 gmc = 0.50
M/R = 100/40 = 2.50 gmr = 0.45
C/R = 50/40 = 1.25 grc = 0.60
Balancing cut-off grades
Open Pit Mine Planning and Design 182
-
5/11/2014
91
Economic cut-off grades
0.10
yrs
cgm
0.40
yrsC
Vdfc
gc
0.16
yR
Vdfrs
cgr
For V = 0
Open Pit Mine Planning and Design 183
Optimum cut-off grades
Gmc = Mid (0.10, 0.40, 0.50) = 0.40
Gmr = Mid (0.10, 0.16, 0.45) = 0.16
Grc = Mid (0.16, 0.40, 0.60) = 0.40
G = Mid (0.16, 0.40, 0.40) = 0.40
Open Pit Mine Planning and Design 184
-
5/11/2014
92
Intermediate mine plan
Year Cut-off Mine Mill Ref. Profit
1 0.4 83.3 50 35 216.7
2 0.4 83.3 50 35 216.7
. . . . . .
. . . . . .
. . . . . .
12 0.4 83.3 50 35 216.7
P = (25 - 5)35 250 183.3 3001
P = 216.7
PV@12y and 15% = 1174
Open Pit Mine Planning and Design 185
Second iteration
0.10
yrs
cgm
0.58
yrsC
Vdfc
gc
0.25
yR
Vdfrs
cgr
For V = 1174
Open Pit Mine Planning and Design 186
-
5/11/2014
93
Optimum cut-off grades
Gmc = Mid (0.10, 0.50, 0.58) = 0.50
Gmr = Mid (0.10, 0.25, 0.45) = 0.25
Grc = Mid (0.25, 0.58, 0.60) = 0.58
G = Mid (0.25, 0.50, 0.58) = 0.50
Open Pit Mine Planning and Design 187
A new mine plan...
With the new cut-off grade of 0.5, a new
mine plan can be developed but this time
changing the present value from year to year
If annual profits are discounted to time 0 and
added up, it gives another estimate of V
If the difference of the initial and final value
of V exceeds a defined tolerance threshold,
the whole process is repeated
Open Pit Mine Planning and Design 188
-
5/11/2014
94
Annual profit for the first year...
P = (25 - 5)37.5 250 1100 3001
P = 250
PV@ 10y and 15% = 1255
For a 0.5 cut-off grade, the annual profit and
present value is as follow:
Open Pit Mine Planning and Design 189
Optimum mine plan and cut-off grades policy
Year Cut-off Mine Mill Ref. Profit PV
1 0.50 100 50 37.5 250 1255
2 0.50 100 50 37.5 250 1194*
3 0.50 100 50 37.5 250 1123
4 0.50 100 50 37.5 250 1041
5 0.50 100 50 37.5 250 947
6 0.50 100 50 37.5 250 840
7 0.50 100 50 37.5 250 716
8 0.49 97 50 37.1 245 573
9 0.46 93 50 36.5 238 414
10 0.41 89 50 35.9 229 238
11 0.41 21 13 8.8 55 45
* W = V(1+d) - P
W = 1255 1.15 250 = 1194
1000 513 380.8 2517
PV @ 11y and 15%= 1256
Open Pit Mine Planning and Design 190
-
5/11/2014
95
Relevant data: Mine capacity (M) = 18.9 Mt/a
Plant capacity (C) = 7.2 Mt/a
Mining costs (m) = 0.85 $/t material
Milling costs (c) = 3.7 $/t ore
Fixed costs (f) = 3.5 M$/a
Copper price (s) = 2205 $/t Cu ($1.0 /lb)
TC/RC & selling cost (r) = 705 $/t Cu ($0.32 /lb)
Overall recovery (y) = 85 %
Annual discount rate (d) = 10 %
4. Example 2: a copper open pit mine & mill
Open Pit Mine Planning and Design 191
A set of four pushbacks
B
D
C
A
Open Pit Mine Planning and Design 192
-
5/11/2014
96
Input to the model: four scheduled, nested pits
(periods) from a preliminary mine plan
1
1
1
3
2
2
3
4
4
3
PP
Open Pit Mine Planning and Design 193
Grade-tonnage relationship for the four pits
Cut-off Period 1 Period 2 Period 3 Period 4
% Cu Mt % Cu Mt % Cu Mt % Cu Mt % Cu
0.0 20.3 1.05 36.5 0.79 56.3 0.57 80.1 0.59
0.2 18.7 1.13 30.1 0.92 40.8 0.76 60.4 0.77
0.4 15.3 1.32 24.4 1.08 28.5 0.97 50.2 0.87
0.6 12.9 1.47 19.7 1.22 21.7 1.11 38.3 0.98
0.8 11.0 1.61 13.7 1.45 15.1 1.30 22.7 1.18
1.0 8.6 1.80 10.2 1.64 10.0 1.49 14.6 1.35
1.2 7.1 1.95 7.6 1.83 6.9 1.67 9.0 1.49
1.4 5.9 2.08 5.6 2.02 4.4 1.88 5.0 1.65
1.6 4.4 2.27 4.0 2.24 2.7 2.11 2.9 1.75
Open Pit Mine Planning and Design 194
-
5/11/2014
97
Output for a Base case
Year Period 1 Cut-off (% Cu)
Mine (Mt)
Mill Ratio (W/O)
Profit (M$)
PV (M$) (Mt) (% Cu)
1 1 0.85 14.2 7.2 1.67 0.97 110.3 475.5
2 1 0.78 6.1 3.4 1.59 0.82 49.6 412.8
2 2 0.78 9.8 3.8 1.43 1.56 44.8 412.8
3 2 0.72 16.8 7.2 1.37 1.34 81.3 359.6
4 2 0.67 9.9 4.7 1.31 1.13 50.4 314.2
4 3 0.61 6.7 2.5 1.12 1.62 19.4 314.2
5 3 0.61 18.9 7.2 1.12 1.62 56.3 275.8
6 3 0.60 18.6 7.2 1.11 1.58 55.8 247.0
7 3 0.56 12.1 4.9 1.08 1.45 36.5 215.9
7 4 0.56 4.5 2.3 0.96 0.98 14.9 215.9
8 4 0.53 13.6 7.2 0.94 0.89 44.5 186.1
9 4 0.50 13.1 7.2 0.92 0.82 43.3 160.3
10 4 0.47 12.6 7.2 0.91 0.75 42.4 132.9
11 4 0.44 12.1 7.2 0.89 0.68 41.4 103.9
12 4 0.41 11.6 7.2 0.87 0.61 40.2 72.9
13 4 0.37 11.2 7.2 0.86 0.55 38.9 39.9
14 4 0.33 1.5 1.0 0.84 0.50 5.1 5.0
193.2 94.6 1.11 1.04 PV = 475.5
Open Pit Mine Planning and Design 195
Output for an expanded case (Mill from 7.2 to 9.0 Mt/a)
Year Period 1 Cut-off (% Cu)
Mine (Mt)
Mill Ratio (W/O)
Profit (M$)
PV (M$) (Mt) (% Cu)
1 1 0.78 16.3 9.0 1.59 0.81 131.8 521.2
2 1 0.71 4.0 2.3 1.53 0.71 33.1 441.6
2 2 0.67 14.0 6.7 1.30 1.10 71.3 441.6
3 2 0.65 18.5 9.0 1.29 1.05 95.4 381.3
4 2 0.60 4.1 2.2 1.22 0.86 22.1 324.0
4 3 0.45 14.2 6.8 1.00 1.10 46.6 324.0
5 3 0.45 18.9 9.0 1.00 1.10 62.0 287.7
6 3 0.45 18.9 9.0 1.00 1.10 62.0 254.4
7 3 0.45 4.2 2.0 1.00 1.10 13.7 217.9
7 4 0.51 12.9 7.0 0.93 0.84 43.2 217.9
8 4 0.48 15.9 9.0 0.91 0.76 54.1 182.8
9 4 0.45 15.2 9.0 0.89 0.69 52.9 146.9
10 4 0.42 14.6 9.0 0.88 0.62 51.5 108.8
11 4 0.38 14.1 9.0 0.86 0.56 50.0 68.1
12 4 0.34 7.4 4.9 0.84 0.51 26.4 25.0
193.2 103.9 1.06 0.86 PV = 521.2
Open Pit Mine Planning and Design 196
-
5/11/2014
98
Conclusion for this case
The Base Case produces a declining cut-off
grade policy starting at 0.85 %Cu and yielding
a PV of $ 475.5 million
The Expanded Case lowers the initial cut-off
from 0.85 to 0.78 %Cu and increases the PV
by $46 million from $475.5 to $521.2 million
If the expansion capital investment is less than
$46 million, then it is worth going ahead
Open Pit Mine Planning and Design 197
5. Concluding remarks
Lanes cut-off grade model is a first attempt to
define economically what material is ore in a
life-of-mine (LOM) plan
It requires a holistic view of mining in that the
optimisation needs a preliminary LOM plan.
That is, a final pit limit, pushbacks design and
scheduling based on a breakeven cut-off - the
mine or plant cut-off grade, for instance
Open Pit Mine Planning and Design 198
-
5/11/2014
99
Activity 8 : Individual learning
Refer to worksheet 5
Cutoff Grade Optimisation
Follow the calculations to the problems
Open Pit Mine Planning and Design 199
Lanes model considers various variables as
fixed input capacities, and downstream cut-
offs such as metallurgical recovery at the mill
Most recent developments have expanded the
model to include some of these variables and
handle them simultaneously
When the problem becomes too complex, it is
solved using other mathematical tools, integer
linear programming being one of them
Open Pit Mine Planning and Design 200
-
5/11/2014
100
6. References
Kenneth F. Lane - The economic definition of ore, Mining
Journal Books, London 1988
Kenneth F. Lane - Choosing the optimum cut-off grade,
Colorado School of Mines Quarterly. Vol. 59-4, 1964, pp. 811-
829
Blackwell, M. Some aspects of the evaluation and planning of
the Bougainville copper project, Decision-Making in the
Mineral Industry, CIM Special Vol 12, 1971 pp. 261-269
Open Pit Mine Planning and Design 201
Module 5
Mine Planning Software
Open Pit Mine Planning and Design
202
Software Packages
Categories
Capabilities
Providers
-
5/11/2014
101
Common Software Packages
Open Pit Mine Planning and Design
203
Categories of Mining Software
Open Pit Mine Planning and Design
204
-
5/11/2014
102
Mapping Software
Open Pit Mine Planning and Design
205
Geological & Data managent
Open Pit Mine Planning and Design
206
Source: (Sable, 2013)
-
5/11/2014
103
Geological Modelling/
Resource Estimation
Open Pit Mine Planning and Design
207
Drill hole display (Source: Geovia, SUPARC)
Geological Modelling/
Resource Estimation
Open Pit Mine Planning and Design
208
Ore body model(Source: CAE, STUDIO 3)
-
5/11/2014
104
Mine Design
Open Pit Mine Planning and Design
209
Pit Design (Source: Maptek, VULCAN)
Planning and Scheduling
Open Pit Mine Planning and Design
210
Pit Design (Source: Geovia, MineSched)
-
5/11/2014
105
Financial Evaluation
Open Pit Mine Planning and Design
211
Financial Analysis Software (RungePincockMinarco)
Optimisation/Risk Analysis
Open Pit Mine Planning and Design
212
Pit Optimisation (Geovia, WHITTLE)
-
5/11/2014
106
Monitoring & Control
Open Pit Mine Planning and Design
213
Truck Dispatching (Modular Mining System; (DISPATCH)
Simulators
Open Pit Mine Planning and Design
214
Coal Mining Simulator (Immersive Technologies)
-
5/11/2014
107
Virtual Reality
Open Pit Mine Planning and Design
215
ViMine VR Software 3D Ore body model
Summary
Open Pit Mine Planning and Design
216
Advances in Computer technology has
made it possible to model complex mining
environments
Most widely software is for Mine Design &
Planning
Further developments in simulation and
risk modelling
Mining software harmonisation by
suppliers
-
5/11/2014
108
Module 6
mine to mill optimisation
Open Pit Mine Planning and Design
217
Concept embraced and practiced by mining
companies
The philosophy is base on:
Characterise
Track
Measure
Model
Potential to save mining companies thousands of
Dollars
Open Pit Mine Planning and Design 218
Drilling
Blasting
Loading
Hauling
Milling (Crushing, grinding)
Examine total system with regard to cost,
productivity, product quality, optimisation...
Mine production system processes
-
5/11/2014
109
Open Pit Mine Planning and Design 219
Loading: increased fragmentation => higher rate of shovel productivity, hence lower costs per BCM.
Hauling: Truck production per hour will increase with
greater fragmentation due to faster shovel loading rates.
Reduced cycle time.
Crushing: Lower crushing costs result from increased
fragmentation as more material pass through as under
size.
Drilling and blasting costs are harder to relate to
fragmentation).
Open Pit Mine Planning and Design 220
Unit costs as a function of the degree of
fragmentation
Systems optimisation:
Optimum Fragmentation Curves
Degree of fragmentation
Overall Cost Curve
-
5/11/2014
110
Blasthole Drilling
Bore diameter
Hole deviation monitor
Geophysical data
Real time drilling data
Exploration Drilling
Intact rock data
Mineralogy data
Fracture frequency data
Ore body modeling and pit design
Blast Modelling Displacement model Fly rock Heave mechanics
Blast Design
Pattern layout
VOID
Powder factor
Explosive
Muckpile properties
Size distribution* Voids ratio* LCM Visualization Density
S01U264007
0
20
40
60
80
100
120
1 10 100 1000
Size (mm)
Pe
rce
nta
ge
Pa
ssin
g (
%)
S01U264007
35.2Mtpa ROM Target
Excavation/Loading
Digability* Dig rate* Dipper design Power consumption Swing analysis Autonomy
Hauling
Payload data Voids ratio* LCM TKPM rating Autonomy Routing data
Crushing/grinding
Energy data Bond's Work Index Settings
Process
Optimization
Blast design,
Load-Haul
Open Pit Mine Planning and Design 222
Examine individual components and the whole system
Goal: achieving a prescribed level of fragmentation at
minimum cost
In-situ ore with particle size considered to be very large
and reducing to size in the order microns (eg -80 mesh).
Measuring Fragmentation, how?
Diggability (BCM/HR)
Size distribution of muckpile (WIPFrag Software), Split-Desktop software
Photographs are taken from muck pile, digging
face, moving truck, etc.
Optimum Fragmentation
-
5/11/2014
111
Open Pit Mine Planning and Design 223
Fragmentation evaluation
Measurement of parameters- correlate with
fragmentation
Photographs are taken from muck pile, digging face,
moving truck, etc.
Crusher monitoring - energy, feed, product size,
throuputghput
Shovel monitoring- load, wait, down time, swing, power
Drilling and Blasting SubSystem
Open Pit Mine Planning and Design 224
Case Study
-
5/11/2014
112
Open Pit Mine Planning and Design 225
Case Study
Modeling Muck Pile Fragment Size to Optimize
Excavator Productivity in Open Pit Mining
Prominent Hill Copper Mine, South Australia
Open Pit Mine Planning and Design 226
Prominent Hill
-
5/11/2014
113
Open Pit Mine Planning and Design 227
Prominent Hill
Muckpile Image Analysis using SPLIT DESKTOP:
The split desktop system uses digital image
analysis technology to convert an image
captured from a digital camera to a distribution
of defined areas within the photograph.
The software was developed from a system of
manual image analysis where a photographic
image was manually delineated and the diameter
of each particle measured
Open Pit Mine Planning and Design 228
Prominent Hill
Camera
Photo of muckpile
Photo collection and scale placement on flitch face.
-
5/11/2014
114
Open Pit Mine Planning and Design 229
Prominent Hill
Blast master 10040RL
Open Pit Mine Planning and Design 230
Prominent Hill
-
5/11/2014
115
Open Pit Mine Planning and Design 231
Prominent Hill
Open Pit Mine Planning and Design 232
Prominent Hill
Our modelling of the excavator production rates
has suggested that P80 of 800 mm would be the
optimal size to maximise excavator productivity
at 6300 t/hr.
However due to mine machinery and crusher
constraints we believe a revised figure of 600
mm would be more appropriate
-
5/11/2014
116
Module 7
Equipment Selection
Open Pit Mine Planning and Design
233
Simulation modelling using GPSS/H Case Study
Cost Estimation (Capital & Operating)
Study Background
Methodology
Results
Discussion
Conclusion
Recommendations
Simulation and Animation of an
Australian Surface Mine
Open Pit Mine Planning and Design 234
-
5/11/2014
117
Wilcherry Hill Iron Ore Mine
The Wilcherry Hill project is
located 30 km north of the
township of Kimba in South
Australia.
The Wilcherry Hill project
comprises of four tenements
and covers an area of 976
square kilometres.
The tenements are EL4162-
Wilcherry Hill, EL4286-Valley
Dam, EL4421- Peterlumbo,
EL3981-Eurilla Dam.
Open Pit Mine Planning and Design 235
Development at Wilcherry Hill is proposed in three phases; stage 1, 2 and 3.
Stage 1 will be the focus of this project
Comprises mining, crushing and export of Direct Shipping Ore (DSO)
Ore sourced from the upper parts of the mining pits.
Project Development
Open Pit Mine Planning and Design 236
-
5/11/2014
118
Methodology
Aim
Simulation and animation model using the Stage
1 layout of the mine
Determine the optimum number of shovels and
trucks required for this mining scenario
Provide the company with a model they can use
for many what if? scenarios.
Open Pit Mine Planning and Design 237
Programming in GPSS/H
Approximately 1,200 lines of computer code were
used to model this mining scenario
Over 60,000 command lines were used to generate
this animation
Open Pit Mine Planning and Design 238
-
5/11/2014
119
Methodology
GPSS/H Simulation Main Commands
Open Pit Mine Planning and Design 239
Methodology Variables, User Information and Generate
Variables:
REAL &X,&Y,&Z,&A,&B,&C,&D,&E,&F,&G,&H,&I
User Information:
PUTSTRING (' ')
PUTSTRING ('HOW MANY TRUCKS?')
PUTSTRING (' ')
INTEGER &TRUCKS
GETLIST &TRUCKS
Generate:
GENERATE 3,,0,&TRUCKS,,12PH,12PL
Open Pit Mine Planning and Design 240
-
5/11/2014
120
Methodology
Animation
Open Pit Mine Planning and Design 241
Methodology
Mine Layout (Draw, Class and Paths)
Open Pit Mine Planning and Design 242
-
5/11/2014
121
Methodology
Run
Open Pit Mine Planning and Design 243
Methodology
Animation
Open Pit Mine Planning and Design 244
-
5/11/2014
122
Methodology Animation
Open Pit Mine Planning and Design 245
Results
HD 785
EMPTY: 72 t
LOADED: 164 t
LOADED SF: 147.6 t
ORE WEIGHT: 75.6 t
STRUCK BODY CAPACITY: 40 m3
ORE SPECIFIC GRAVITY: 4
FULL STRUCK LOAD ORE WEIGHT: 160 t
HOURS PER SHIFT: 8
Assumptions
Open Pit Mine Planning and Design 246
-
5/11/2014
123
Results
Ore Results
TRUCKS: 3 4 5 6 7
ORE DUMPS PER SHIFT: 9 13 17 20 23 DUMPS
STOCKPILE DEPOSITION PER SHIFT: 1440 2080 2720 3200 3680 T
STOCKPILE WITHDRAWAL RATE: 180 260 340 400 460 T/HR
COMPARISON (IRONCLAD): 291 T/HR
Open Pit Mine Planning and Design 247
Results
Ore Results
Open Pit Mine Planning and Design 248
-
5/11/2014
124
Results
Waste Results
TRUCKS: 3 4 5 6 7
WASTE DUMPS PER SHIFT: 68 87 104 123 142 DUMPS
DUMP DEPOSITION PER SHIFT: 5140.8 6577.2 7862.4 9298.8 10735.2 T
DUMP RATE: 642.6 822.15 982.8 1162.35 1341.9 T/HR
COMPARISON (IRONCLAD): 885 T/HR
Open Pit Mine Planning and Design 249
Results
Waste Results
Open Pit Mine Planning and Design 250
-
5/11/2014
125
Conclusion
GPSS/H Simulation and Animation
Number of shovels: one shovel
Number of trucks: five trucks and possibly an extra standby truck
TALPAC simulations
Number of shovels: one shovel
Number of trucks: six trucks
Open Pit Mine Planning and Design 251
Acknowledgements
Postgraduate Students:
Sophie Mellor
Jian Liu
Open Pit Mine Planning and Design 252
-
5/11/2014
126
Cost Estimation
Capital Costs
Operating Costs
Open Pit Mine Planning and Design
254 of 10
Capital cost estimation: general
considerations
Indicative capital cost estimates
Based on empirical data from other
projects
Estimates are within +/- 30% accuracy
Suitable for scoping or pre-feasibility
studies
Often use rules-of-thumb to estimate
costs
-
5/11/2014
127
Capital cost estimation: general considerations:
Indicative capital cost estimates (cont.)
The sixth-tenths rule (Mular, 1978):
Cost 1 / Cost 2 = (Capacity 1 / Capacity 2)0.6
Capacity 2 and Cost 2 relate to a known similar operation in a similar environment
Capacity 1 relates to the operation being studied
Cost 1 is then estimated
Annualised cost per tonne rule:
Annualised cost per tonne of a known operation
= {Total capital cost} {tonnes per year}
Use this factor directly to estimate capex for another, similar operation.
Open Pit Mine Planning and Design 255
Capital cost estimation: general
considerations
Cost indices
Most cost estimations are based on historical
data available to the estimator.
These data date and cost indices can be used to
update them:
Cost now = {cost then}{cost index now/cost index
then}
Indices available from Cost Guides
Open Pit Mine Planning and Design 256
-
5/11/2014
128
Open Pit Mine Planning and Design
257 of 10
Capital cost estimation: general
considerations
Working capital
This is the capital component of operating
costs needed to support the operation
prior to substantial revenue inflows.
Often underestimated and can result in
project failure.
Sometimes a factor (such as 10% of fixed
capital cost) is applied. However a more
detailed analysis is usually good practice.
258 of 10
Capital cost estimation: general
considerations Options for capital equipment
Contract mining
capital not available;
short duration;
specialist skills required; and/or
specialist equipment required.
Hired equipment
machine only and hirer responsible for fuel, oil, servicing and operation (dry hire); or
full hire (all inclusive), usually hourly rate with standby rate.
Open Pit Mine Planning and Design
-
5/11/2014
129
Capital cost estimation: general
considerations Ownership cost
Fixed cost per hour irrespective of whether
the machine is working or not
It is a function of:
purchase price
cost of any extras
freight charges
tyre costs
resale value
depreciation period
Open Pit Mine Planning and Design 259
Capital cost estimation: general
considerations Ownership cost (cont.)
Straight-line depreciation formula:
D = (P - R) / (N.H) where D is depreciation per
hour, P is purchase price, R is residual value, N is
usefu