Advanced RTU Campaign

Technical Resources: Evaluating PerformanceDecember 10, 2013

Page 2: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

Agenda

Overview of the Advanced RTU Campaign

Resources for RTU Evaluation

RTU Evaluation Application

RTU Upgrade Case Study

Better Buildings Alliance1

Page 3: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

Overview of the Advanced RTU Campaign

Marta Milan, Waypoint Buildings Group

Better Buildings Alliance2

Page 4: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

Advanced RTU Campaign (ARC) Overview

National campaign for promotion and support of high-efficiency RTU replacements and retrofits

Partnership between DOE, ASHRAE, RILA, and several supporting organizations

Launched May 30, 2013 and runs through November 2014

Eligible Technologies

High-Efficiency Replacements– For units > 10 years old– CEE Tier 2 and above

Advanced Control Retrofits– For units < 10 years old and > 7 tons– Primarily add variable speed fan control

Better Buildings Alliance3

www.advancedrtu.org

Page 5: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

Benefits of Joining ARC

• Business opportunity – gain credibility from the experiences of a national

campaign

• Leverage DOE technical resources in evaluating savings opportunities

• Qualify for discounts from supporters, including on ASHRAE technical guides

• Stay informed on innovative RTU technologies and resources produced

through the campaign

• Gain recognition, achievement awards, and participate in case studies

based on energy savings

• Save energy and money – Older RTUs can waste from $1,000 to $3,700 per

unit annually, depending on the building size and type

4

Page 6: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

Resources for RTU Evaluation

Michael Deru, National Renewable Energy Laboratory

Better Buildings Alliance5

Page 7: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

Decision Tree for Evaluating RTUs

Better Buildings Alliance6

Questions

to guide

evaluation Resources

Page 8: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

RTU Evaluation Process

1. Initial RTU Inventory: gather basic information in the RTU Inventory Spreadsheet

2. Preliminary Screening: Bin RTUs: retrofit, replacement, needs further analysis, or no action

3. Detailed Inventory: Gather additional information in the RTU Inventory Spreadsheet

4. Field Evaluation: Visual-based field evaluation using the RTU Field Evaluation Checklist

5. Analysis: Energy and economic analyses to make the business case and prioritize actions.

RTU Incentives Database, RTU Comparison Calculator, 179D DOE Calculator, RTU Sizing

Guidance, and ARC Case Studies.

6. Project Planning: Develop a plan for replacements and retrofits. See the list of ARC

Supporting Partners for manufacturers and service providers.

7. Procurement: Prepare a procurement specification(s) with quality installation and quality

maintenance requirements see Procurement Specifications for guidance.

8. Measurement and Verification (M&V): Use the M&V Guidance to determine the appropriate

level of M&V for the project and develop and M&V plan.

Better Buildings Alliance7

Page 9: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

RTU Inventory Spreadsheet

Combines Preliminary

Screening, Detailed Inventory,

and results of Field Evaluation

Meant to be a starting point –

modify to fit your needs

Better Buildings Alliance8

Page 10: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

Preliminary Screening

Better Buildings Alliance9

Gather data from site visit, drawings, asset inventory, etc. May not need all of the fields.

Access general condition and place RTUs into Bins – Replace, Retrofit, Needs Further

Evaluation, No Action

Page 11: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

Preliminary Screening Example

Better Buildings Alliance10

Page 12: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

Detailed Inventory and Field Evaluation

Better Buildings Alliance11

Page 13: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

RTU Field Evaluation Checklist

Better Buildings Alliance12

Visual based inspection,

no measurements required

Need to be familiar with RTUs

but not a trained technician

Page 14: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

RTU Field Evaluation Checklist

Better Buildings Alliance13

Page 15: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

Analysis Resources

RTU Incentives Database, DSIRE,

RTU Comparison Calculator

www.pnnl.gov/uac/

179D DOE Calculatorhttp://apps1.eere.energy.gov/buildings/commercial/179d

Case Studieshttp://www.advancedrtu.org/case-studies--guidance.html

Better Buildings Alliance14

Page 16: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

Planning and Procurement

Project Planning

– This is where you save money

– Avoid costly emergency replacements

– Optimize long-term energy, maintenance, and economic performance

Procurement

– Short and long specifications are coming soon

– Integrate Quality Installation and Quality Maintenance programs• ANSI/ACCA 5 QI – 2010, HVAC Quality Installation Specification

• ANSI/ASHRAE/ACCA Standard 180-2012, Standard Practice for Inspection and Maintenance of Commercial

Building HVAC Systems

Better Buildings Alliance15

Page 17: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

Project Measurement and Verification

Do you need M&V?

– Do you need to determine the project

savings or justify future projects?

What accuracy do you need and how much are

you willing to spend?

– guidance document to help determine the

best approach

Better Buildings Alliance16

Page 18: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

RTU Evaluation Application

Bill Reynolds, Benchmark Group

Better Buildings Alliance17

Page 19: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

Why Establish a Commercial Building Program

1. 51% of RTUs are over ten years old and are nearing the end of their useful age.

2. The majority of RTUs are poorly maintained.

3. There is a lack of control strategies with operating schedules that cause unnecessary

operation.

4. Multitude of problems : 91% had one Problem & 41% had two or more

Source: nbi

Better Buildings Alliance18

new building

institute

Page 20: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

Opportunities for RTU Energy Improvements

1. Retro Commissioning - maintenance, re-establish a baseline

2. Retro Fits – Controls, drives, heat recovery, staging of compressors

3. Replacements – More efficient units, resizing

Better Buildings Alliance19

Page 21: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

Implement a Process

1. Prioritize the buildings to be audited based on age and maintenance records

2. Conduct a RTU survey – condition, age

3. Units that are 10 years and older should be evaluated for replacement

4. Units less than 10 years olds are candidates for retro fits or Retro-Commissioning

5. Provide an Energy Saving Analysis for Return on Investment

6. Based upon the surveys and analysis, schedule the required services to update the systems.

Better Buildings Alliance20

Page 22: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

RTU Upgrade Case Study

JCPenney Store 2921, Flower Mound, Texasand subsequent 126-store rollout including approximately 1300 rooftop units

Better Buildings Alliance21

Ken Logsdon, NexRev

Pat Trlica, NexRev

Page 23: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

VFD Retrofits as RTU Efficiency Upgrade

Better Buildings Alliance22

Most commercial rooftop HVAC units are equipped

with multiple stages of cooling and heating.

In most cases, those units only operate at full-load

conditions less than 5% of the time.

However, the blower fans can only run at full-speed

…. regardless of the “stage” of unit operation.

Retrofitting those unit blower fans with VFD’s

represents a significant energy-saving opportunity.

Page 24: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

Utilize Variable Frequency Drives (VFDs) to

convert RTU blower fan operation from constant

speed to multiple speeds that more closely

match the actual load as indicated by the

thermostat or control system “calls” to the unit.

VFD Retrofits as RTU Efficiency Upgrade

the Concept

Page 25: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

Why do this?

#1 reason = Save Energy

Fan Motor @ 80% Speed uses 47% less power

Fan Motor @ 60% Speed uses 78% less power

VFD Retrofits as RTU Efficiency Upgrade

Page 26: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

90%

80%

70%

60%

50%

100%

40%

30%

20%

10%

100%

6.6%

75.2%

52.8%

35.4%

22.3%

0%

12.9%

90%

80%

70%

60%

50%

100%

Speed

Power

The Fan Affinity Law with regard to Power

Page 27: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

Better Buildings Alliance26

Case Study: Flower Mound, TX

Background:

JCPenney was actively seeking energy efficiency initiatives

Evaluated retrofit product offerings and vendors

Selected by for pilot store

Page 28: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

Case Study: Flower Mound, TX

Better Buildings Alliance27

• Typical Prototype

• Built in 2006

• 100,000 square feet

• 12 RTUs: 2-stg Cool, 1-stg Heat

o Ten (10) 25 ton / 7.5 hp blower

o One (1) 15 ton / 5 hp blowero One (1) 10 ton / 3 hp blower

JCP Store 2921…

Page 29: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

60,000

80,000

100,000

120,000

140,000

160,000

180,000

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

2009 kWh 2010 kWh 2011 kWh

En

tire

Sto

re k

Wh

17%

16%

11%9%

18%

19%

22%

17%

15%16%

16%

Better Buildings Alliance28

Savings = 16%

2011 kWh consumption vs. 2009/2010 Average

VFD Retrofit on January 3, 2011

Case Study: Flower Mound, TX

Page 30: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

Better Buildings Alliance29

Case Study: Flower Mound, TX

Simple Payback… Estimated = 1.57 yrs Actual = 0.66 yrs (8 mos)

Page 31: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

Better Buildings Alliance30

Case Study: Flower Mound, TX

10 point improvement from 65 to 75 in December = Energy Star Certified!

Page 32: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

Better Buildings Alliance31

DrivePak™ Rollout Project

Rollout:

Installation of began in June 2011

Based on pilot store results, rollout schedule was accelerated

Contract awarded to for 126 stores

Project completed in September, approx 1300 units in all

Annualized project results: 12.9% kWh reduction

$2,628,000 avoided cost

Page 33: Advanced RTU Campaign Technical Resources: Evaluating … · 2019-10-26 · Advanced RTU Campaign: Michael Deru, 303-384-7503 michael.deru@nrel.gov Marta Milan, 231-598-2332 martamilan@waypointbuilding.com

Contacts

Advanced RTU Campaign: www.advancedrtu.org

Michael Deru, 303-384-7503 [email protected]

Marta Milan, 231-598-2332 [email protected]

Benchmark Group:

Bill Reynolds, 479-636-5004 [email protected]

NexRev:

Ken Logsdon, 972-303-8502 [email protected]

Pat Trlica, 405-340-1622 [email protected]

JC Penney:

David D. Sergeant, 972.431.1865 [email protected]

Better Buildings Alliance32