african development fund · 2019-06-29 · 31st november 2014 date signed: 31st march 2014...
TRANSCRIPT
AFRICAN DEVELOPMENT FUND
MULTINATIONAL
AFRICAN CAPACITY BUILDING FOUNDATION
FOR THE THIRD STRATEGIC MEDIUM TERM PLAN (SMTP III)
(PCR)
RDGS DEPARTMENT
April 2018
1
I BASIC DATA
A Report data
Report date Date of report: 12 August 2015
Mission date (if field mission) From: 6 July 2015 To: 10 July 2015
B Responsible Bank staff
Positions At approval At completion
Regional Director Ebrima Faal Josephine NGURE
Country Manager Mary MONYAU
Sector Director Vicotr MURINDE John ANYANWU
Sector Manager Bernadette Dia KAMGNIA Noel KULEMEKA
Task Manager Kanny DIALLO Nkoanyane SEBUTSOE
Alternate Task
Manager
PCR Team Leader Bernadette Dia KAMGNIA
PCR Team Members Nkoanyane SEBUTSOE; Mary Manneko
MONYAU
C Project data
Project name: GRANT SUPPORT THE AFRICAN CAPACITY BUILDING FOUNDATION FOR THE THIRD
STRATEGIC MEDIUM TERM PLAN (SMTP III)
Project code: P-Z1-KF0-036 Instrument number(s): ADF GRANT 2100155026866
Project type: PUBLIC SECTOR
PROJECT
Sector: INSTITUTIONAL SUPPORT
Country: MULTINATIONAL Environmental categorization (1-3): 3
Processing milestones – Bank
approved financing only (add/delete
rows depending on the number of
financing sources)
Key Events (Bank approved financing
only)
Disbursement and closing dates (Bank
approved financing only)
Financing source/ instrument1: ADF
Grant 2100155026866
Financing source/ instrument1: ADF
Grant 2100155026866
Financing source/ instrument1: ADF
Grant 2100155026866
Date approved: 17th February 2014 Cancelled amounts: None Original disbursement deadline:
31st November 2014
Date signed: 31st March 2014 Supplementary financing:None Original closing date: 31st December
2014
Date of entry into force: 31st March
2014
Restructuring (specify date & amount
involved): None
Revised (if applicable) disbursement
deadline:31st March 2015
Date effective for 1st disbursement:
08th May 2014
Extensions (specify dates):31st December
2015
Revised (if applicable) closing date: 31
December 2015
PROJECT COMPLETION REPORT FOR PUBLIC SECTOR OPERATIONS (PCR)
2
Date of actual 1st disbursement:
30th May 2014
Financing source/instrument
(add/delete rows depending on the number
of financing sources):
Disbursed amount
(amount, UA):
Percentage
disbursed (%):
Undisbursed
amount (UA):
Percentage
undisbursed (%):
Financing Source/ instrument1:ADF 3,000,000 100% 0 0
Government:
Other (eg. co-financiers). Add rows as
needed
TOTAL 3,000,000 100% 0 0
Co-financiers and other external partners: WORLD BANK, 33 African member countries, South Africa (These are co-
financiers for the overall ACBF SMTP III but not for this specific project).
Executing and implementing agency (ies): THE AFRICAN CAPACITY BUILDING FOUNDATION (ACBF)
D Management review and comments
Report reviewed by Name Date reviewed Comments
Country Manager Damoni KITABIRE
Sector Manager Noel KULEMEKA 21 December
2017
Program was ultimately beneficial as
countries benefited from training and
TA in terms of debt sustainability.
Bank also moved from retail to
wholesale capacity building.
Regional Director (as chair of Country
Team) Josephine NGURE
Sector Director John ANYANWU
II Project performance assessment
A Relevance
1. Relevance of project development objective
Rating* Narrative assessment (max 250 words)
4
The overall goal of the project and ACBF’s Third Strategic Medium Term Plan (SMTP III) is to build capacity of
regional institutions for governance that is effective and translates into real poverty reduction. The Bank’s Ten Year
Strategy (TYS) alludes to the huge capcity building needs the contirnet is faced with and goes on further to allude to
the fact not one capacity building institution can achieve the feat alone. The Bank therefore emphasizes the need for
partnerships in ensuring adequate coverage of capacity development in Africa. This project therefore prioritized the
idea of building partnerships and the Executing agency (ACBF) worked with other implementing partners being
Macroeconomic and Financial Management Instuitute for Eastern and Southern Africa (MEFMI) and the Nigelria
Insitute for Legislative Studies (NILS). The project development objective (PDO) emphasizes effective economic
governance and this is aligned to the Bank’s Knowledge Management Strategy 2015 – 2020 as well as the Capcity
Development Strategy. These two strategies, the KMS and CDS have among their objectives the need to improve the
capacity of regional member countries RMCs to undertake effective policy dialogue. Moreover, the PDO is also
aligned with the Bank group Regional Integration Policy and Strategy (RIPoS) 2014-2023 whose objective is to foster
regional and ultimately continental economic integration through increased effectiveness of Bank Group support to
RMCs, the private sector and sub-regional and regional organizations. To this end, strengthening the capacity of the
African institutions was deemed critical to accelerating the integration agenda lleading to emphasis being placed on
ensuring wide coverage of the project activities through a regional focus by prioritizing regional workshops. By
providing capacity building to RMCs officials the project also satisfied the Bank’s Human Capital Strategy 2014 –
2018 whose aim is is to harness the potential of one billion Africans by building skills and promoting technologies
for equal opportunities and a productive and competitive workforce.
* For all ratings in the PCR use the following scale: 4 (Highly satisfactory), 3 (Satisfactory), 2 (Unsatisfactory), 1 (Highly unsatisfactory)
3
2. Relevance of project design
Rating* Narrative assessment (max 250 words)
3
The project was designed to respond to the needs of the Bank, the Executing Agency as well as the RMCs given that
most RMCs lack are faced with challenges when it comes to economic and financial governance. The capacity of the
ACBF was assessed during project design to gauge its ability to implement the project. It was found that ACBF
possesses competent staff, effective internal controls, and a sound accounting system. This thus assisted in ensuring
that funds are used only for intended purposes; and financial reporting is based on accurate and complete information.
ACBF’s financial management policies, procedures and practices are in full compliance with the International Financial
Reporting Standards (IFRS). Moreover, the procurement rules and processes of the Foundation were put in place with
the support of the AfDB and the World Bank as thus they were found adequate to handle the project’s procurement
activities. By this the project aimed at minimizing delays involved with the prior review requirements necessary under
use of Bank Rules and Procedures for Procurement of Consultants as well as good s and services.
In light of the huge capacity needs facing African countries and the notion that not one institution can meet all these
needs, the project also employed the idea of partnerships as advocated for in the Bank’s TYS, the CDS and KMS. This
helped the Bank move from retail to wholesale provision of support towards capacity building. Due to delays in project
approval the design of the project enabled the executing agency to adjust ther activities along with the sub-grantees to
ensure effective implementation and delivery. The work programme progressed with slight disruptions. Minor
adjustments were made to the results based logical framework (RBLF) during project implementation to ensure
achievement of expected results and their sustainability. Some outputs were revised to those that can be easily
measured. By working with the sub-grantees the project enabled some skills transfer as some of the documents ABCF
uses were shared with the sub-grantees in order for better implementation. This entailed among others the monitoring
and evaluation templates which made supervision easy. The grant also enabled the Bank strengthen its partnership and
collaboration with ACBF in the development of regional public goods on capacity building.
3. Lessons learned related to relevance
Key issues (max 5, add rows as needed)
Lessons learned Target audience
1. Responding to
capcity needs and
priorities of RMCs
With the continuous demand for effective macroeconomic, financial
governance and accountability, and debt management capacities in RMCs, the
Bank and ACBF will continue to respond to the needs and priorities of African
countries in these areas. Partnerships are important as they assist in partenrs
leveraging on each others’ expertise, capacity and comparative advantage.
AfDB, ACBF, RMCs
other partners
2. Increased member
countries’ buy-in,
ownership and use of
macroeconomic,
financial and debt
management solutions
The demand driven and participatory technical and advisory support provided
by MEFMI, contributed significantly to increased buy-in, ownership and use of
policy recommendations, tools and manuals developed by the institution. The
active involvement of the member countries in the diagnostics of the issues as
well as development and roll-out of the possible solutions enhanced knowledge
and skills transfer, ownership and sustainable use of the macroeconomic,
financial and debt sustainability models and instruments.
AfDB, ACBF,
MEFMI other partners
3. Increased
willingness and
commitment of member
countries to contribute
to financing capacity
building intervention
A participatory approach resulted in member countries’ increased willingness
and commitment to the project For instance, MEFMI member countries
contributed 50.2% of the total budget of their current strategy.
The funding provided to NILS served as catalyst to attract additional funding
from the Nigerian government in excess of $400,000 of the project grant. This
was due to project implementation success.
AfDB, ACBF, NILS
other partners
B Effectiveness
1. Progress towards the project’s development objective (project purpose)
Comments
The development objective of the project is to promote effective governance in regional member countries and regional institutions that
translates into real poverty reduction. The project had two componets namely: Component 1: Improving economic and financial
governance in support of regional integration policy formulation and implementation and component 2: Improved transparency and
accountability in the management of public resources in Africa. Through 3 interventions (MEFMI, NILS and AGO), the project has
improved the capabilities (knowledge, skills, systems and processes) of Central Banks, Ministries of Finance/ Economic Planning ,
4
parliaments and parliamentary institutions and other stakeholders in MEFMI and ECOWAS regions in macroeconomic, debt and financial
sector management ; cross-border trade and effective Executive-Legislative relations. Further,the generation of the AGO, has enhanced
stakeholder knowledge and access to research-based information for decision making on financial governance in Africa. Five (5) out of
the 8 results (outcome and output) targets agreed in the Results-Based Monitoring and Evaluation Framework have been achieved.
1. MEFMI
Under Component 1: Improving Economic and Financial Governance in support of Regional Integration, Policy formulation and
Implementation, the following results were achieved:
1.1 Improved Macroeconomic, financial and debt management in the Eastern and Souther Africa Region: MEFMI’s hands-on
technical and advisory support has enabled its member countries to improve their macroeconomic, financial and debt
management capabilities, including: (i) Development of 5 Financial Programming Framework for Botswana, Namibia, Rwanda,
Kenya, Lesotho, (ii) Development of a core Model of Inflation for EAC Countries such as Rwanda; (iii) Development of a
Quarterly GDP and short-term Economic Indicators for Lesotho; (iv) Development of 3 Macroeconomic Modeling and
Forecasting models for Swaziland, Malawi, Mozambique; and v) harmonization of methodologies and construction of analytical
indicators for SADC, SACU and EAC countries
1.2 Strengthened Policy Formulation and Implementation of RECs on Regional Integration and Trade within the MEFMI Region:
MEFMI Conducted 6 seminars: (i) A Seminar on Regional Integration and Trade (30 participants); (ii) – A Course on Economic
Issues in Regional Integration (35 participants); (iii) – A seminar on Deeper Regional Integration Agenda in Africa (30
participants); (iv) Regional workshop on Developments and innovations in payment systems (20 participants); (v) Seminar for
Heads of Payment systems on Leveraging payment systems in Financial Inclusion (13 participants); (vi) Supported the
formulation of debt policies through conducting debt sustainability analysis in Zimbabwe, Tanzania, Zambia and Lesotho.
In addition, 5 In-country missions were conducted: (i) In-country missions to: Central Bank of Swaziland, Bank of Botswana
and Bank of Zambia to provide technical assistance on implementation of the COMESA Framework for Financial Stability
Assessment and reporting requirements; (ii) In-country missions to the National Bank of Rwanda and Bank of Mozambique on
payment systems oversight
1.3 Increased stakeholder knowledge and awareness of Innovative Methods of Financing Infrastructure Development in MEFMI
Region: a High Level Seminar on Sovereign Bond Issuance focusing on Innovative Infrastructure Financing Options was
organized. The seminar deliberated on potential use of several innovative infrastructure financing mechanisms including Public-
Private Partenerships (PPPs), Tapping on Remittances for equity, Diaspora bonds/ remittance backed bonds, Resource for
Infrastructure (RFI) approach, and Annuity Financing Mechanism. Beneficiaries were Ministries of Finance, Central Banks and
Capital Markets Authorities of MEFMI 13 Member states
2. NILS-CAP
NILS-CAP has contributed to improving the knowledge and understanding of policy makers, mainly Legislators, in regional integration
and effective financial governance. The project has also enhanced the skills and competencies of parliamentary staff in the ECOWAS
region to enable them provide effective technical support toward the work of parliamentary institutions. The following are the specific
achievements of the component:
2.1 Improved knowledge and skills of 480 ECOWAS Parliamentary staff in Results Based Monitoring and Evaluation, Speech
Writing and Legislative Research Methodology. The customized national-level training sessions has enhanced the capacity of
parliament officials to provide effective technical support to the legislators.
2.2 Enhanced skills of 153 policy makers including ministers, legislators, MPs, Directors of government ministries and departments
and civil society actors, in cross-border trade and financing framework including Cross- Border trade and opportunities for
trade finance in West Africa.
2.3 Increased knowledge and awareness of 140 policy makers including ministers, legislators, Directors of government ministries
and departments and civil society actors on cross-border trade and financing framework. A two-day regional conference on
regional trade and financing opportunitie was organized by NILs which produced a Communiqué that was widely disseminated
and is expected to have a positive impact on trade policies in the ECOWAS sub-region.
2.4 NILS-CAP supported Legislators and staff from the ECOWAS sub-region to participate in selected international programs and
conferences, learn best practices, and share experiences in developmental issues. 2 officials participated in a course on
Executive-Legislative relations and effective performance organized by the John Hopkins university; 2 officials participated in
an Advanced Legislative Management course, organized by the University of Illinois; 3 Parliamentarians participated in a
Negotiations and Decision Making Strategy course organized by RIPA in London; 2 Parliamentarians participated in a Strategic
Leadership course at Oxford; 1 staff participated in an Outcome-Based Monitoring and Evaluation Course in South Africa; and
4 officials participated in an International Executive Program for Senior Parliamentary Staff organized by McGill University.
5
3. AGO
This aspect of the project was affected by delays in implementation. The process involved recruitment of country research teams (CRTs)
within the 10 pilot countries (Burkina Faso, Ethiopia, Ghana, Kenya, Mali, Mozambique, Rwanda, Senegal, Tanzania, and Uganda) who
would then be tasked with preparing the relavant country’s financial governance report. There were delays in five of the countries and
this led to the overall delay in the publishing of the relevant country assessment reports as well as the Flagship report. Following the
recruitment of the remaining CRTs an inception workshop was conducted end of July 2015. A validation workshop was held in November
2016 to present the findings of the report. This report was finalised by ACBF and was shared with the Bank to provide comments before
its publication. The comments have already been done (July 2017) and the final product is expected from ACBF.
<ENTER HERE>
2 Outcome reporting
Outcome
indicators (as per
RLF; add more rows as
needed)
Baseline
value
(Year)
Most
recent
value
(A)
End
target (B)
(expected
value at project
completion)
Progress
towards
target (% realized)
(A/B)
Narrative assessment (indicative max length: 50 words per outcome)
Core
Sector
Indicato
r (Yes/No)
Outcome 1.No of
Africa capacity
Indicators Report
(ACIR) developed
3 ACIR 4 ACIR 4 ACIR 100% The 4th ACIR was published on 22 December
2014. The ACIRs are currently present on over
90 websites of development institutions and
libraries such as the WBI, AfDB, United States
Agency for International Development
(USAID), Capacity.org, LenCD, Stanford
University. The Library of Congress and over
106 organizations have reproduced the different
versions of the ACI reports on their websites.
Outcome 2:No. of
countries that have
adopted the Private
Capital Monitoring
System(PCMS)
8 9 11 82% The tool is being used by 9 countries, namely
Botswana, Kenya, Lesotho, Malawi,
Mozambique, Rwanda, Swaziland, Tanzania,
Zimbabwe. It has helped member countries to
establish and ascertain the magnitude, scale and
composition of the stocks and flows of foreign
private capital and their impact on the
economies.
Outcome 3: No.
countries whose of
parliamentary
institutions were
supported
0 11 10 110% 12 countries could have been covered but due to
emergence of new cases of EBOLA in one of
the targeted country, 11 were covered.
Rating* (see IPR
methodology) Narrative assessment
4
Even though the PAR put sthe baseline for the ACIR at 1, the actually number of ACIR already produced
were 3 hence the baseline number shoulf have been 3 and not 1. This was realised during the mid-term review
and corrected in the logical framework. In addition, during the mid-term it was discovered “Outcome 2 on
Number of countries rated with more than 39 on the Corruption Perception Index (CPI) for transparency,
accountability and corruption in public sector” would not truly reflect the results of the project and was thus
replaced with “Outcome 2: No. of countries that have adopted the Private Capital Monitoring
System(PCMS).”
6
3 Output reporting
Output indicators (as specified in the RLF; add more rows as
needed)
Most recent
value
(A)
End target
(B)
(expected value at project
completion)
Progress
towards
target (% realized)
(A/B)
Narrative assessment (indicative max length: 50 words per output)
Core
Sector
Indicato
r (Yes/No)
Output 1:No. of
institutions trained
on regional
integration policy
modelling and
forecasting
including gender
using gender-s
ensitive parameters
22 12 183% The interventions have contributed to:
promoting evidence-based policy making;
imparting knowledge on recurrent issues on
regional integration; enhancing capacity to
manage trade arrangements; appreciation of
policy challenges for deeper integration and the
role of different institutions (Central Banks,
Ministries of Finance, Ministries of Planning,
Custom Administration, etc). Out of 893
training beneficiaries, 349 (39%) were women.
Output 2:No.of
RECs assisted to
develop policy
frameworks for the
management of
public private
partnerships
03 02 150% Main beneficiaries are from the Ministries of
Finance, Central Banks and Capital Markets
Authorities.
Output 3: No. Of
legislators and
parliamentary staff
trained in cross
border trade, peace
building and
outcome-based
monitoring and
evaluation
700 450 156% Many of the programs organized by NILS were
over-subscribed. Also, the ECOWAS
Parliament and the Nigerian government
contributed funds to activities of NILS-CAP.
35% of the participants were women
Output 4.1: No. of
Africa Governance
Outlook (AGO)
country reports
published
0 10 0 Work is ongoing in all 10 countries of the
AGO. Out of the ten (10) country reports, five
(5) have been received and under review
(Ghana, Kenya, Uganda, Mali and
Mozambique). The Country Reserach Teams
(CRTs) have been recruited for the drafting of
the remaining country reports and these are
expected end of December 2015.
Output 4.2 Publication of
consolidated report
summarising
findings from the
10 AGO country
reports
1
1 100% Though with a delay, the consolidated report
was finalised by ACBF and has been received
by the Bank to provide final comments before
publication. The country reports will also be
published independent of the consolidated
report.
Rating* (see IPR
methodology) Narrative assessment
3
All the the other outputs were realised on time but one. The AGO component suffered huge delays with
country teams in 5 other countries taking time to be procured. Extension was giaven to allow adequate time
for its completion. Following a validation workshop in November 2016, the consolidated report has been
finalised and shared with the Bank for comments before publication. The other country reports will be
published independent of the coslidated report.
7
4 Development Objective (DO) rating
DO rating (derived from
updated IPR)* Narrative assessment (indicative max length: 250 words
3.5
The project has satisfactorily made strides towards achievement of the PDO, despite facing initial
delays in disbursement of funds and as a result of the outbreak of the Ebola epidemic in West Africa
for some activities. It is also aliogned with the objectives and priorities of ACBF’s SMTP III and the
Bank’s Strategies for the project period. The development objective of promoting effective
governance in regional member countries and regional institutions has been satisfactorily achieved,
since the achievement of outputs and outcomes is deemed satisfactory. Two out of the three outcome
indicators and respective targets—annual and at end of project— have been achieved. The one
outcome that even needed an extension to the project close date was the AGO which suffered from
delays in the setting up of the country research teams (CRTs) in five of the ten countries. However
this activity has since been completed and the report has been shared with the Bank.
5 Beneficiaries (add rows as needed)
Actual (A) Planned (B) Progress towards target (% realized) (A/B)
% of
women
Category (eg. Farmers, students)
MEFMI: 14
countries
14 100% 39 Senior and middle level officials from the Directorates of Ministries of Finance and
Planning, Central Banks and Regulatory
Bodies of the 13 Members States
NILS: 12
countries
10 120% 35 Legislators and staff from the ECOWAS
region
AGO: 10
countries
10 100% n/a Governments of the 10 countries, and
other RMCs
6 Unanticipated or additional outcomes (add rows as needed)
Description Type (eg.
Gender, climate
change, social,
other)
Positive or
negative
Impact on project (High, Medium,
Low)
Reduction in the number of regional parliamentary training
activities due to the Ebola outbreak.
Health Negative NILS-CAP had to cut down on
planned regional level participation
in favour of increased national level
participations.
Extended delay in the delivery of the AGO component Other negative Though completed this activity
delayed the finalisation of the PCR.
7 Lessons learned related to effectiveness (add rows as needed)
Key issues (max 5, add rows as needed) Lessons learned Target audience
1. Flexible design and implementation strategy The flexibility of the Foundation’s grant design and
implementation strategy enabled it to adjust the
project scope and timelines despite the initial delay
in grant approval by the AfDB without any serious
negative impact on the expected results.
AfDB, ACBF other
donors
2. Providng tailor-made capacity building support to
parliamentarians and parliamentary staff
The customized capacity building support
including training favourably responded to the
needs of the beneficiary countries. For example, the
Federal Government of Nigeria provided additional
support to enable more parliamentarians to benefit
from the training. As parliament is the first point of
government scrutiny training parliamentarians
helped them in understanding the various aspects of
their job in oder for increased accountability.
AfDB, ACBF other
donors
8
3. Hands-on technical assistance and project
implementation support provided by ACBF has
enhanced the delivery and impact of the project.
The on-site and remote technical support provided
by ACBF helped in accelerating the delivery and
impact of the poject. In addition to the grant, ACBF
provided technical support to MEFMI and NILs in
project management including M&E , financial
management and procurement which has enabled
the instituions to improve their capabilities which
has translated into timely implementation and
reporting on project results. MEFMI for example
has adopted the Results Measurement Framework
(RMF) developed as part of the project for its
engagement with other donors.
ACBF
AfDB
Project Scope Creep Initial project design assumption of the AGO was
to simply revise existing draft reports and improve
political economy analysis. This was however
subsequently expanded to involve a complete
overhaul of the reports to respond to changes in
data availability.
ACBF
AfDB
CRTs
C Efficiency
1. Timeliness
Planned project duration – years
(A) (as per PAR) Actual implementation time – years
(B) (from effectiveness for 1st disb.) Ratio of planned and actual
implementation time (A/B)
Rating
*
18 months 32 months 0.56 2
Narrative assessment (indicative max length: 250 words)
The initial project start-up delays led to adjustment in the timelines to ensure that expected deliverables and results are
achieved. Subsequently, the Foundation and AfDB discussed and the project duration was adjusted accordingly. Over and
above this one aspect of the project – the AGO – experienced lengthy delays (only being finalised in 2017) and ended up
affecting the overall completion of the project. All the other activities were completed on time as explained in the outputs
section. The delays were as a result of inability to quickly appoint country teams in five countries.
2. Resource use efficiency
Median % physical implementation
of RLF outputs financed by all
financiers (A) (see II.B.3)
Commitment rate (%) (B) (See table 1.C – Total commitment rate of all
financiers)
Ratio of the median percentage
physical implementation and
commitment rate (A/B)
Rating
*
N/A N/A N/A
Narrative assessment (indicative max length: 250 words)
The Foundation has significamtly improved its resource base through diversifying its financing partners. The efficiency indicator
- percentage of total program costs (including knowledge and learning products) to cash outflows - shows improved value of
ACBF’s capacity building support. The over program ratio increased from 83.7% in 2011 to 88.9% in 2014. This ratio was
88.7% as at 31 May 2015. On the other hand, the administrative ratio came down from 16.3% in 2011 to 11.1% in 2014. This is
a demonstration of the continuous improvement in the Foundation’s efficiency in resource use.
3. Cost benefit analysis
Economic Rate of Return
(at appraisal)
Updated Economic Rate of Return
(at completion)
Rating
*
N/A N/A N/A
Narrative assessment (indicative max length: 250 words)
The Economic Rate of Return was not calculated for this project at appraisal.
9
4. Implementation Progress (IP)
IP Rating (derived from
updated IPR) *
Narrative comments (commenting specifically on those IP items that were rated Unsatisfactory or Highly
Unsatisfactory, as per last IPR). (indicative max length: 500 words)
4
(i) Compliance with commitments: The conditions precedent to grant effectiveness, the first disbursement and
conditions required after effectiveness were fulfilled on time. The project was classified as category 3 and
therefore did not warrant any compliance to the Environmental and Social Management Plans as well as social
safeguards.
(ii) Project systems and procedures:
Financial Management: The Implementing Agency (ACBF) continues to have a sound internal control framework
in place. This includes competent staff, effective internal controls, and a sound accounting system. This has
assisted in ensuring that funds are used only for intended purposes; and financial reporting are based on accurate
and complete information. ACBF’s financial management policies, procedures and practices are in full
compliance with the International Financial Reporting Standards (IFRS).
Procurement: The rules and processes of the Foundation were developed with the support of the AfDB and the
World Bank. The resulting procurement activities were in full compliance with the provisions of the grant
agreement as well as the Bank’s rules and procedures. The project files have been maintained consistently with
Bank requirements.
Audit compliance:
(iii) Project implementation and financing: the project suffered a delay in the Bank’s disbursement of the funds
however ACBF and other implementing partners ensured that negative impact is minimal. The overall output
rating is satisfactory (3). The score would have been a 4 if the AGO activity had been implemented successfully
within the project time frame. This has caused a significant delay in preparing this PCR as the activity went even
beyond the 31st December 2015 deadline that was granted as an extension. The validation workshop only took
place in November 2016 and the consolidated report as awell as the country reports are yet to be published. This
has been alluded to in the Section C (i) on timeliness.
5. Lessons learned related to efficiency
Key issues (max 5, add rows as needed) Lessons learned Target audience
1. Implementation of new operating modalities The implementation of new operating modalities
(including relying on mature implementing
partners to undertake some of the activities in their
vicinity in lieu of ACBF fielding a mission, use of
technology for supervision, etc.) has helped reduce
operating costs and improved the timelines for
developing and disseminating strategic knowledge
products. For example, in recognition of the
strategic importance of the 1st US-Africa Summit
that was held in Washington, DC., USA, August 4-
6 2014, the Foundation in collaboration with six
ACBF-supported think tanks (i.e. Botswana
Institute of Development Policy and Analysis
(BIDPA); Institute of Democratic Governance
(IDEG), Ghana; Kenya Institute for Public Policy
and Research Analysis (KIPPRA); Centre
Mauritanien d’Analyse de Politique (CMAP);
Centre D’Etude et de Reinforcement des Capacites
d’Analyse et de Plaidoyer (CERCAP), Mali; and
Programme de Gestion des Politiques
Economiques (GPE-Kinshasa), DRC) drafted
position papers that contributed to the discussion on
the US-Africa relations.
10
D Sustainability
1. Financial sustainability
Rating
* Narrative assessment (indicative max length: 250 words)
3
The capacity challenges of the continent are such that African governments are backing up their demands for ACBF
capacity building support with increased financial contribution. African countries have pledged a total of USD 28.15
million for the SMTP III and already, more than USD 15 million had been disbursed, which is unprecedented in the
history of the Foundation. In addition, the Foundation has consolidated its partnership with the World Bank through a
renewed focus on results. In parallel, the Foundation is diversifying its stream of resources and in August 2014, the
Foundation entered into a partnership with the Bill and Melinda Gates Foundation on the Tobacco Contro Program in
Africa. This partnership is expected to grow and diversify in the coming months and years. Aside this, the Government
of Australia has engaged the Foundation through the provision of the resource facility for the Australia-Africa
Community Engagement Scheme (AACES). The Foundation is also actively re-engaging its traditional bilateral partners
(non-African countries) towards a resumption of their support, while making efforts to reach out to the emerging
economies. The three governance organs of the Foundation (Board of Governors, Executive Board and Secretariat) are
working hand-in-hand to further consolidate the financial sustainability of the Foundation. It is in this regard that the
Board of Governors established in 2013 a Permanent Committee on Resource Mobilization and that resource
mobilization has become a standing agenda item of the Executive Board.
The efficiency indicator- Percentage of total disbursements (including K&L products) to cash outflows - shows improved
value of ACBF’s capacity building support. The overall program ratio increased from 84% in 2011 to 89% in 2014.
This ratio is 89% as at 31 May 2015. On the other hand, the administrative ratio has come down from 16% in 2011 to
11% in 2014. This is a demonstration of continuous improvement of the efficiency of the Foundation.
2. Institutional sustainability and strengthening of capacities
Rating
* Narrative assessment (indicative max length: 250 words)
4
Since 2012, ACBF has been implementing a set of deep reforms aimed at making the Foundation more efficient and
more effective. In November 2013, the Executive Board of the Foundation adopted an additional train of measures which
were implemented in the following 5 areas: Prioritizing and Scaling up operations for Success; Increasing Efficiency;
Strengthening Governance; Increasing focus on Results and Impact; and Working towards the sustainability of the
Foundation. A total of 24 reform actions were identified in these 5 areas and implemented. These included difficult
measures such as separation of half of the staff, pay cuts up to 20% for the remaining staff, operational innovations,
governance tightening, etc. Today, the Foundation has become efficient and significantly effective in its approach to
capacity development.
The reforms conducted have put ACBF in a better position to address the increasing and multi-faceted demand of African
countries for capacity building, generating a capable workforce, and strong institutions. The expected economic growth
in many African countries will lead to further demand for skilled labor force and effective and capable institutions. The
Bank Group’s support to the Foundation’s SMTP III and the region’s capacity building will therefore be sustainable,
given the increasing awareness of countries, RECs and donors for capacity development and efforts to ensure that the
institutional environment is strengthened for economic governance and inclusive growth amidst globalization of trade
and need for Africa to become more competitive. For instance, through support to MEFMI ACBF has contributed to
building capacity in debt sustainability and formulation of debt policies for 4 countries during the contract period. This
has strenthende officials of the given countries in doing meaningfula analysis. Other areas where RMCs capacity was
strenthend include seminars on deeper regional integration agenda in Africa; Regional workshops on developments and
innovations in payment systems; and seminars for heads of payment systems on leveraging payment systems in financial
inclusion. Moreover the implementation of the AU Agenda 2063 requires some capacity imperatives identified by ACBF
and it was agreed with the AUC that the Foundation will be assisting with the implementation of the first ten year
implementation plan of the Agenda.
11
3. Ownership and sustainability of partnerships
Rating
* Narrative assessment (indicative max length: 250 words)
3
ACBF, which was established through a partnership, attaches high importance to building and maintaining strong
partnerships. These partnerships are at the following levels:
At continental level: ACBF has made significant progress in consolidating its partnership with the key pan-
African institutions namely the African Union, the African Development Bank, the NEPAD Agency and the
Economic Commission for Africa, as well as regional institutions such as the Regional Economic Communities
(RECs). This level of partnership places ACBF at the forefront of the definition of the continental agenda for
capacity development;
At country level: ACBF has supported some 45 African countries in one way or the other since its
establishment. In so doing, the Foundation has built strong partnerships with each of these countries. As
reported by the ACBF governors at their 23rd Annual Meeting in Dakar in June 2014, ACBF is the only
organization that really understands their capacity needs and has found the most effective ways to address them.
The steady increase in African financial support to ACBF is a result of a long-standing trust with these
countries;
At global level: ACBF approaches non-African countries and institutions not only from a financial resource
perspective but also to expand its knowledge base and increase its ability to design solutions to the variety of
capacity development issues faced by African countries. Thus, the partnership is built and sustained to take
account of the fact that capacity development is a long term endeavour.
Backed by these critical partnerships, ACBF has been able to offer a participatory and targeted programing as well as
technical support which has enabled the beneficiary institutions abilities to own and drive the interventions as well as
improve the delivery and impact of their activities. The Foundation has stimulated and continues to promote demand
driven capacity building that responds to the needs and priorities of its member countries. In 2014, the Foundation
initiated a new business model for efficiency and effectiveness of operational delivery.The Secretariat entered into
strategic partnership with selected ACBF-supported mature policy think tanks for the supervision of ACBF projects.
Based on its experience and the relevance of its mandate, more strategic partnerships are set with most reliable regional
and continental bodies such as the African Union, the African development bank, the RECs as well as the African
Governments.
4. Environmental and social sustainability
Rating
* Narrative assessment (indicative max length: 250 words)
N/A
The project was classigfied as a Category 3 and thus did not warrant preparation of an Enviromental and Social
Mitigation/Management Plan (ESMP). However, it is geared towards developing capacities of both men, women and
youth for inclusive policy formulation and management. For example, 39% of women have been trained at MEFMI
course and 35% under NILS-CAP. It also seeks to enhance the capabilities of public sector decision makers and non-
state actor to foster evidence-based decision making, transparency and accountability for use of public resource. As part
of the policy making component, ACBF supports the development and deployment of critical capacities for mitigating
fragility and enhancing national development outcomes.
5. Lessons learned related to sustainability
Key issues (max 5, add rows as needed) Lessons learned Target audience
Increased member countries’ interest in targeted
country level interventions including tailor-made
training courses
Continuation of activities after the end of project.
Member countries showed increased interest in the
hands-on country-specific training and technical
support. For example, the in-country training and
technical support provided by MEFMI was over
subscribed.
Both MEFMI and NILS have mainstreamed most
of the activities funded under the AfDB grant into
their programs. These activities are likely to
continue after the end of the project.
AfDB, ACBF and
beneficiary
institutions
12
Responding to priorities and needs of RMCs There is continuous demand for effective
macroeconomic, financial governance and
accountability, and debt management capacities in
RMCs. The ACBF will continue to respond to the
needs and priorities of African countries in these
areas.
AfDB, ACBF,
RMCs other
partners
Increased member countries’ buy-in, ownership and
use of macroeconomic, financial and debt management
solutions
The demand-driven and participatory technical and
advisory support provided by MEFMI, contributed
significantly to increased buy-in, ownership and
use of policy recommendations, tools and manuals
developed by the institution. The active
involvement of the member countries in the
diagnostics of the issues as well as development
and roll-out of the possible solutions enhanced
knowledge and skills transfer, ownership and
sustainable use of the macroeconomic, financial
and debt sustainability models and instruments.
AfDB, ACBF,
MEFMI other
partners
Increased willingness and commitment of member
countries to contribute the financing of capacity
building interventiion
A participatory approach resulted in member
countries’ increased willingness and commitment
to the project For instance, MEFMI member
countries contributed 50.2% of the total budget of
their current strategy.
AfDB, ACBF other
partners
III Performance of stakeholders
1. Bank performance
Rating
* Narrative assessment by the Borrower on the Bank’s performance, as well as any other aspects of the project
(both quantitative and qualitative). See guidance note on issues to cover. (indicative max length: 250 words)
3
The Bank has been timely in responding to issues and challenges that required attention. Through its implementation
support and project monitoring process, the Bank worked closely with ACBF to ensure that the project stays on course
and achieves the intended results despite the initial start-up delays.
The Bank openly discussed with ACBF lessons from the Mid-Term review regarding possible implementation delays
and absorption rate due to the Ebola outbreak in West Africa. Together with the Bank, the Foundation developed
strategies for speeding up implementation and accelerating disbursement.
The Bank’s response to ACBF’s requests has been timely and very helpful for the smooth implementation and
achievement of results.
Comments to be inserted by the Bank on its own performance (both quantitative and qualitative). See guidance note on
issues to cover. (indicative max length: 250 words)
Apart from the delays in the approval of the project and disbursement, the Bank was quite pro-active in ensuring the PDO is met.
This is evident from the adjustments that were done in the Results-Based Logical Framework to ensure that both the outcome and
output indicatros are SMART (specific, measurable, achievable, relevant and timebound). This was done to enable the Bank to be
able to hold the ACBF accountable to meeting the project objectives. The Bank also ensured that procurement and other fiduciary
requiarements conform to the Bank’s Rules and Regulations and use ACBF’s procedures where they are deemed adequate.
Key issues (related to Bank performance, max 5, add rows as needed) Lessons learned
1. Delays in project approval 1. Sticking to timelines is important so as not to meet the
deadlines or milestones as set in the project implementation
plan
2. Flexibility 2. The Bank’s flexibility allowed for changes to be made to the
RBLF to ensure that the outcome and output indicators are
SMART.
13
2. Borrower performance
Rating
* Narrative assessment on the Borrower performance to be inserted by the Bank (both quantitative and
qualitative, depending on available information). See guidance note. (indicative max length: 250 words)
3
ACBF has been quite diligent and the flexibility of their grant design and implementation strategy enabled them to
adjust the project scope and timelines despite the initial delay in grant approval without any serious negative impact on
the expected results. The Foundation continued to improve its project monitoring and evaluation system by ensuring
that its grantees adopt their online monitoring and evaluation tool to enable quick and easy reporting of progress. The
ACBF ensured the project was prepared and implemented in compliance with covenants, agreements and safeguards
agreed with the Bank, and further did very well in terms of its responsiveness to supervision recommendations. ACBF
uses its own policies and procedures in managing financial management aspects of the project, these procedures have
been found to be adequately meeting the Bank’s minimum requirements and thus also conforming to the Bank’s rules of
procedures for project procurement, financial management, and monitoring. The entity uses a computerized accounting
software which permit tracking of funds through the use of system imbedded cash books. Bank account reconciliations
are prepared within a reasonable period after the end of a respective month, and any outstanding items are followed up
in a systematic manner until they clear in subsequent periods
Key issues (related to Borrower performance, max 5, add rows as needed) Lessons learned
1. Flexibility 1. Being flexibile allows for successful project implementation.
Though the Bank disbursement was delayed, ACBF ensured
the activities are delivered timely without much hindrance.
3. Performance of other stakeholders
Rating
* Narrative assessment on the performance of other stakeholders, including co-financiers, contractors and service
providers. See guidance note on issues to cover. (indicative max length: 250 words)
N/A N/A
Key issues (related to performance of
other stakeholders, max 5, add rows as
needed)
Lessons learned (max 5) Target audience (for
lessons learned)
1. 1. 1.
IV Summary of key lessons learned and recommendations
1. Key lessons learned
Key issues (max 5, add rows as needed) Key lessons learned Target audience
1. Increased willingness and commitment of
member countries to contribute to financing
A participatory approach resulted in member
countries’ increased willingness and commitment to
the project For instance, MEFMI member countries
contributed 50.2% of the total budget of their current
strategy.
RMCs, ACBF &
AfDB
2. Flexible design and implementation strategy The flexibility of the Foundation’s grant design and
implementation strategy enabled it to adjust the
project scope and timelines despite the initial delay in
grant approval by the AfDB without any serious
negative impact on the expected results.
ACBF & AfDB
3. Hands-on technical assistance and project
implementation support provided by ACBF has
enhanced the delivery and impact of the project.
The on-site and remote technical support provided by
ACBF helped in accelerating the delivery and impact
of the project. In addition to the grant, ACBF
provided technical support to MEFMI and NILs in
project management including M&E , financial and
procurement which has enabled the instituions to
improve their capabilities which has translated into
timely implementation and reporting on project
results. MEFMI for example has adopted the Results
Measurement Framework (RMF) developed as part of
the project for its engagement with other donors.
ACBF & RMCs
14
4. Responding to priorities and needs of RMCs There is continuous demand for effective
macroeconomic, financial governance and
accountability, and debt management capacities in
RMCs. The ACBF will continue to respond to the
needs and priorities of African countries in these
areas.
ACBF
5. Implementation of new operating modalities The implementation of new operating modalities
(including relying on mature implementing partners
to undertake some of the activities in their vicinity in
lieu of ACBF fielding a mission, use of technology
for supervision, etc.) has helped reduce operating
costs and improved the timeliness for developing and
disseminating of strategic knowledge products. For
example, in recognition of the strategic importance of
the 1st US-Africa Summit that was held in
Washington, DC., USA, August 4-6 2014, the
Foundation in collaboration with six ACBF-
supported think tanks (i.e., Botswana Institute of
Development Policy and Analysis (BIDPA); Institute
of Democratic Governance (IDEG), Ghana; Kenya
Institute for Public Policy and Research Analysis
(KIPPRA); Centre Mauritanien d’Analyse de
Politique (CMAP); Centre D’Etude et de
Reinforcement des Capacites d’Analyse et de
Plaidoyer (CERCAP), Mali; and Programme de
Gestion des Politiques Economiques (GPE-
Kinshasa), DRC) drafted position papers that
contributed to the discussion on the US-Africa
relations.
ACBF
6. Interaction with the ZWFO Constant engagement with the ZWFO has helped in
ensuring that the project is well implemented even
though delays were realised. The comments and
suggestions always made by the ZWFO enable
ECAD to get required answers from the ACBF
when issues are not clear.
AfDB, ZWFO &
ACBF
7. Key recommendations (with particular emphasis on ensuring sustainability of project benefits)
Key issue (max 10, add rows as needed) Key recommendation Responsible Deadline
1. Continue interventions on key areas of capacity
gaps.
2. Need for follow up on capacity building
interventions to ensure sustainablilty.
3. Continue to create awareness on emerging issues.
Develop Aide Memoires for follow up
of interventions.
ACBF, AfDB On-
going
V Overall PCR rating
Dimensions and criteria Rating*
DIMENSION A: RELEVANCE 3.25
Relevance of project development objective (II.A.1) 3.5
Relevance of project design (II.A.2) 3
DIMENSION B: EFFECTIVENESS 3.5
Development Objective (DO) (II.B.4) 3.5
DIMENSION C: EFFICIENCY 3
Timeliness (II.C.1) 2
Resource use efficiency (II.C.2) N/A
Cost-benefit analysis (II.C.3) N/A
Implementation Progress (IP) (II.C.4) 4
15
DIMENSION D: SUSTAINABILITY 3.33
Financial sustainability (II.D.1) 3
Institutional sustainability and strengthening of capacities (II.D.2) 4
Ownership and sustainability of partnerships (II.D.3) 3
Environmental and social sustainability (II.D.4) N/A
AVERAGE OF THE DIMENSION RATINGS 3.27
OVERALL PROJECT COMPLETION RATING (S)
VI Acronyms and abbreviations
Acronym (add rows as needed) Full name
ACBF African Capacity Building Foundation
ACIR Africa Capacity Indicators Report
ADF African Development Fund
AfDB African Development Bank
AGO African Governance Outlook
CDS Capacity Development Strategy
COMESA Common Market for Eastern and Southern Africa
CPI Corruption Perception Index
CRTs Country Research Teams
EAC East African Community
ECAD African Development Institure
ECOWAS Economic Community of West African States
GDP Gross Domestic Product
IFRS International Financial Reporting Standards
KMS Knowledge Management Strategy
M&E Monitoring and Evaluation
MEFMI Macroeconomic and Financial Management Insitute of Eastern and Southern Africa
NILS Nigeria Institute for Legislative Studies
NILS CAP National Institute for Legislative Studies Capacity Building Project
PAR Project Appraisal Report
PCMS Private Capital Monitoring System
PCR Project Completion Report
PDO Project Development Objective
PPPs Public-Private Partenerships
RBLF Results Based Logical Framework
RECs Regional Economic Communities
RMCs Regional Member Countries
RMF Results Management Framework
SACU Southern African Customs Union
SADC Southern African Development Community
SMART Specific, Measurable, Achievable, Relevant and Timebound
SMTP III Third Strategic Medium Term Plan
TYS Ten Year Strategy
UA Units of Account
ZWFO Zimbabwe Field Office
Required attachment: Updated Implementation Progress and Results Report (IPR)– the date should be the same as the PCR
mission.