Current and Proposed Infrastructure Projects

FORT McMURRAY CONSTRUCTION ASSOCIATION2011 Annual Future Projects Summit

March 31, 2011

BRIAN SOUTAR (780) 422-7461Executive DirectorProject Services Branch, Capital Projects DivisionAlberta Infrastructure

Page 2: Alberta Infrastructure Presentation

GOVERNMENT OF ALBERTA 2011-14 CAPITAL PLAN:• Significant investment in capital will continue: $17.6 billion over 3 years

Capital Plan Details by Category(millions of dollars) 2011-12 2012-13 2013-14 3-year

Estimate Target Target TotalMunicipal infrastructure support 1,628 1,644 1,812 5,084Provincial highway network 1,665 1,354 1,619 4,638Health facilities and equipment 1,022 814 741 2,577Schools 289 238 177 704Post-secondary facilities 251 113 114 478Community facilities 120 130 130 380Water and wastewater management 297 222 232 751Housing 273 130 104 507Government facilities/other capital 1,087 772 659 2,518Total 6,632 5,417 5,588 17,637

Government of Alberta’s Capital Plan

Page 3: Alberta Infrastructure Presentation

GOVERNMENT OF ALBERTA 2011-14 CAPITAL PLAN:• Significant investment in capital will continue: $17.6 billion over 3 years

Capital Plan Details by Category(millions of dollars) 2011-12 2012-13 2013-14 3-year

Estimate Target Target TotalMunicipal infrastructure support 1,628 1,644 1,812 5,084Provincial highway network 1,665 1,354 1,619 4,638Health facilities and equipment 1,022 814 741 2,577Schools 289 238 177 704Post-secondary facilities 251 113 114 478Community facilities 120 130 130 380Water and wastewater management 297 222 232 751Housing 273 130 104 507Government facilities/other capital 1,087 772 659 2,518Total 6,632 5,417 5,588 17,637

Government of Alberta’s Capital Plan

Page 4: Alberta Infrastructure Presentation

GOVERNMENT OF ALBERTA 2011-14 CAPITAL PLAN:• Infrastructure Project Categories

Government of Alberta’s Capital Plan

2011-12 2012-13 2013-14 Total Infrastructure: $ (000)

Schools (project admin. only) 1,000 1,400 600 3,000 Community Facilities 50,000 70,000 60,000 180,000

Govt. Facilities 409,775 202,779 108,867 721,421 Health Facilities 877,945 674,386 618,062 2,170,393

1,338,720 948,565 787,529 3,074,814

Infrastructure 1.3 B 0.9 B 0.9 B 3.1 B Other Ministries 5.3 B 4.5 B 4.7 B 14.5 B

Total 6.6 B 5.4 B 5.6 B 17.6 B

Page 5: Alberta Infrastructure Presentation

ALBERTA INFRASTRUCTUREBUSINESS PLAN GOALS

Safe, innovative and cost effective public infrastructure

• Build relationships

• Integrate design excellence principles

• Work with communities

Page 6: Alberta Infrastructure Presentation

INFRASTRUCTURE PROJECTS:Status: Tender documents in progress

RCMP DetachmentTemporary CellsLocation:MacKenzie Industrial Park• Corner of MacKenzie Crescent and

MacKenzie Boulevard

Current and Proposed Infrastructure Projects

Page 7: Alberta Infrastructure Presentation

Current and Proposed Infrastructure Projects

PARSONS CREEK AND SALINE CREEK PROJECTS:

Fort McMurrayFort McMurray Community:

Parsons Creek Community - Phase I underwaySaline Creek Community

• Affordable housing; • Social infrastructure:

- Schools- Community Health Centres

Page 8: Alberta Infrastructure Presentation

HEALTH PROJECTS:

Status: Design Stage

Fort McMurray Community Health Centre (two clinics)

• Thickwood Community Health Centre

• Timberlea Community Health Centre

Current and Proposed Infrastructure Projects

Page 9: Alberta Infrastructure Presentation

HEALTH PROJECTS:

Status: Design Complete; Now looking for CM services

Northern Lights Regional Health Centre

• Renovations to the Emergency Ward

• Renovations to the Intensive Care Unit

Current and Proposed Infrastructure Projects

Page 10: Alberta Infrastructure Presentation

Upcoming Construction Opportunitiesin Fort McMurray, Grande Prairie and High Prairie

http://alberta.labourmarketlink.com Available to ACA members

Page 11: Alberta Infrastructure Presentation

List of Public & Private Sector Projects in Alberta

Page 12: Alberta Infrastructure Presentation

Other Opportunities