alf scambler aggreko presentation all energy 2016

24
Off Grid Commissioning Power Supply for Renewable Sector Alf Scambler – Renewables Sector Development Manager Northern Europe 1

Upload: buitruc

Post on 14-Feb-2017

223 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Alf Scambler Aggreko presentation All Energy 2016

Off Grid Commissioning Power Supply for Renewable Sector

Alf Scambler – Renewables Sector Development ManagerNorthern Europe

1

Page 2: Alf Scambler Aggreko presentation All Energy 2016

Overview of Aggreko

• Scottish based company with global coverage• Revenue 2015 - £1.561B• Trading profit 2015 - £270M• Employees - 7,300• Operation Centres - 270• Operating Countries - 100 +• Aggreko manufacturing based in Dumbarton

2

Page 3: Alf Scambler Aggreko presentation All Energy 2016

Background to Solution

• Aggreko supplied Power and Load packages to commission Renewables Projects for many years.

• Started in North America with onshore wind, UK in 2009.• Work mainly with equipment manufacturers and developers• Options

– LV supply to keep turbines healthy.– LV static commissioning– HV keeping multiple turbines healthy from single connection

point. – HV rotational commissioning at each turbine.– HV rotational commissioning at single connection point with

multiple turbines running.

3

Page 4: Alf Scambler Aggreko presentation All Energy 2016

Reduced risk to projects

• Possibility of missing the subsidy reduction deadli nes• Developers / Investors

– Reduction / removal of subsidy for the lifetime of project.– Cancellation of whole project due to financial constraints.– Reduced return on investment.– Need to keep turbines healthy and preserve warranty.

• Manufacturers / Contractors– Substantial financial claims / penalties– Loss of customer confidence.– Cancellation of orders– Reduced order pipeline.– Difficulty matching resources to a delayed project time line. 4

Page 5: Alf Scambler Aggreko presentation All Energy 2016

Commissioning Solutions

1) Low voltage solution to do basic commissioning and keep turbines healthy.

2) High voltage solution from central point to enable static commissioning to be completed and keep all turbines healthy.

3) High voltage solution to offer full rotational commissioning of the turbines a) At the base of each turbine b) From a central connection point.

3b offers the most flexible solution. All turbines can be powered up and multiple turbines can be tested simultaneously.

5

Page 6: Alf Scambler Aggreko presentation All Energy 2016

Solution advantages

• Install on time / early to match resources to project deadline.• Enable commissioning phase during peak wind periods.• Removal of project bottlenecks to ensure no penalties.• Testing and commissioning on target – even when grid is

delayed.• Keep turbines healthy until grid is connected.• Confidence for developers to invest.• Confidence that project deadlines can be met.• Keep commissioning team on site to complete the process.• Can enable stage payments to be made.• Revenue generation as soon as grid is connected.

6

Page 7: Alf Scambler Aggreko presentation All Energy 2016

Typical site connection options at various voltages

110V, 240V, 415V, 690 V

11 - 33kV

690V to 33 kV

Page 8: Alf Scambler Aggreko presentation All Energy 2016

Power supplies - Low Voltage @ turbine connection 400 - 690V

Page 9: Alf Scambler Aggreko presentation All Energy 2016

Turbine connection low Voltage Option –110V, 240V,415V, and 690V

Page 10: Alf Scambler Aggreko presentation All Energy 2016

High Voltage connection Load Bank –enables full load test of turbines

10

GEN 2

GEN 1

Load bank CB 1

CB 2

Generator Controller

Generator Controller Step up / down

transformer

Low voltage

High voltage

Page 11: Alf Scambler Aggreko presentation All Energy 2016

HV Package @ 33kV North Rhins

Page 12: Alf Scambler Aggreko presentation All Energy 2016

33kV Full Load Package single turbine

Page 13: Alf Scambler Aggreko presentation All Energy 2016

Grid outages or equipment failure

• O&M phase– Planned or unplanned grid outages, equipment can be kept

healthy from the site HV network enabling maintenance, preservation of warranty and early resumption of power export to grid.

• Failure of transformers or switchgear– Failure of turbine transformer – no export from single turbine.– Failure of export transformer

• no export of power from site• no power to turbine ancillaries.

• Replacement equipment is available to enable business continuity and earn revenue.

• Contingency plans can be provided for your sites

13

Page 14: Alf Scambler Aggreko presentation All Energy 2016

33kV package for turbine ancillary power support during outage 70+ turbines

14

Page 15: Alf Scambler Aggreko presentation All Energy 2016

Wind Farm, Scotland33kV high voltage power connected at the main sub-station and load solution to simulate a full grid connection supply. Our solution enabled both static and rotational commissioning of the turbines, protection of the electrical components, preservation of the turbine warranties and kept the project on course. All from one central connection point.

Rotational Commissioning

Page 16: Alf Scambler Aggreko presentation All Energy 2016

Solar Farm Commissioning

Diesel Generator

~

33kV50Hz

33kV50Hz

415V50Hz

DC / AC

LoadbankController

Grid

Page 17: Alf Scambler Aggreko presentation All Energy 2016

Wind Vs Solar Output Profiles

17

0%

50%

100%

% Wind Farm Power Output

0%

50%

100%

150%

% Solar Farm Power Output

Page 18: Alf Scambler Aggreko presentation All Energy 2016

Innovation – Auto load control(Solar and Wind)

• Manual load matching to Solar output almost impossible• Large power package required to match the solar

generation output.• Load applied to generators from loadbank to match the

likely output from the solar array.• Fuel burn large during periods of low solar output.• Wind Farms, due to their slower ramp rate, are more

manageable under manual operation but require manpower to control.

• Fuel and manpower are significant costs to a commissioning project.

18

Page 19: Alf Scambler Aggreko presentation All Energy 2016

Solution

• Auto load control!• Aggreko have developed an automated load control system for

their commissioning solutions• Can control the fast ramp rate of a solar farm and the slower

ramp rate of a wind farm.• Can be used equally on small scale or large scale projects.• Can be used on other technologies, wave, tidal, etc.• Can also be used to control grid export power under a limited

grid point connection.

19

Page 20: Alf Scambler Aggreko presentation All Energy 2016

Load balance of system (manual control)

0

0.5

1

1.5

2

2.5

3

3.5

4

4.5

5

Low output Med output High output Fuel burn

Generator

Loadbank

Turbine output

20

Loadbank is the fixed point

Page 21: Alf Scambler Aggreko presentation All Energy 2016

Load balance of system (automatic control)

0

1

2

3

4

5

6

Low output Med output High output Fuel burn

Generator

Loadbank

Turbine output

21

Generator load is fixed point

Page 22: Alf Scambler Aggreko presentation All Energy 2016

Benefits

• Keeps power package to a minimum – lower rental costs.• Keeps fuel burn to a minimum – lower fuel costs.• Runs automatically – after commissioning requires minimum

manual intervention – lower manpower costs• System stability improved• Load ramping can be matched to suit technology• If high number of turbines and hence large ancillary load,

turbine(s) can be run to reduce load on generator to supply the base load.

• Results in a cost effective commissioning solution!

22

Page 23: Alf Scambler Aggreko presentation All Energy 2016

More detail?

• Visit us on stand J35• Alf Scambler – Sector Development Manager

Renewables – Northern Europe– [email protected]– www.aggreko.co.uk– 07831 829183 - mobile– 03458 24 7 365 – Rental Centre

23

Page 24: Alf Scambler Aggreko presentation All Energy 2016

Contact Us

Aggreko operates from over 200 locations throughout the world.

For the location nearest you please go to:

www.aggreko.com/contact

Head OfficesUnited Kingdom 03458 24/7/365

Belgium +32 3 8250271 Netherlands +31 88 6441 441

France +33 1 69 73 23 94 Poland +48 608 608 419

Spain +34 902 22 11 01 Germany +49 2362 95 210

Italy +39 02 48 40 491 Ireland +57 866 3233www. aggreko .com