alf scambler aggreko presentation all energy 2016
TRANSCRIPT
Off Grid Commissioning Power Supply for Renewable Sector
Alf Scambler – Renewables Sector Development ManagerNorthern Europe
1
Overview of Aggreko
• Scottish based company with global coverage• Revenue 2015 - £1.561B• Trading profit 2015 - £270M• Employees - 7,300• Operation Centres - 270• Operating Countries - 100 +• Aggreko manufacturing based in Dumbarton
2
Background to Solution
• Aggreko supplied Power and Load packages to commission Renewables Projects for many years.
• Started in North America with onshore wind, UK in 2009.• Work mainly with equipment manufacturers and developers• Options
– LV supply to keep turbines healthy.– LV static commissioning– HV keeping multiple turbines healthy from single connection
point. – HV rotational commissioning at each turbine.– HV rotational commissioning at single connection point with
multiple turbines running.
3
Reduced risk to projects
• Possibility of missing the subsidy reduction deadli nes• Developers / Investors
– Reduction / removal of subsidy for the lifetime of project.– Cancellation of whole project due to financial constraints.– Reduced return on investment.– Need to keep turbines healthy and preserve warranty.
• Manufacturers / Contractors– Substantial financial claims / penalties– Loss of customer confidence.– Cancellation of orders– Reduced order pipeline.– Difficulty matching resources to a delayed project time line. 4
Commissioning Solutions
1) Low voltage solution to do basic commissioning and keep turbines healthy.
2) High voltage solution from central point to enable static commissioning to be completed and keep all turbines healthy.
3) High voltage solution to offer full rotational commissioning of the turbines a) At the base of each turbine b) From a central connection point.
3b offers the most flexible solution. All turbines can be powered up and multiple turbines can be tested simultaneously.
5
Solution advantages
• Install on time / early to match resources to project deadline.• Enable commissioning phase during peak wind periods.• Removal of project bottlenecks to ensure no penalties.• Testing and commissioning on target – even when grid is
delayed.• Keep turbines healthy until grid is connected.• Confidence for developers to invest.• Confidence that project deadlines can be met.• Keep commissioning team on site to complete the process.• Can enable stage payments to be made.• Revenue generation as soon as grid is connected.
6
Typical site connection options at various voltages
110V, 240V, 415V, 690 V
11 - 33kV
690V to 33 kV
Power supplies - Low Voltage @ turbine connection 400 - 690V
Turbine connection low Voltage Option –110V, 240V,415V, and 690V
High Voltage connection Load Bank –enables full load test of turbines
10
GEN 2
GEN 1
Load bank CB 1
CB 2
Generator Controller
Generator Controller Step up / down
transformer
Low voltage
High voltage
HV Package @ 33kV North Rhins
33kV Full Load Package single turbine
Grid outages or equipment failure
• O&M phase– Planned or unplanned grid outages, equipment can be kept
healthy from the site HV network enabling maintenance, preservation of warranty and early resumption of power export to grid.
• Failure of transformers or switchgear– Failure of turbine transformer – no export from single turbine.– Failure of export transformer
• no export of power from site• no power to turbine ancillaries.
• Replacement equipment is available to enable business continuity and earn revenue.
• Contingency plans can be provided for your sites
13
33kV package for turbine ancillary power support during outage 70+ turbines
14
Wind Farm, Scotland33kV high voltage power connected at the main sub-station and load solution to simulate a full grid connection supply. Our solution enabled both static and rotational commissioning of the turbines, protection of the electrical components, preservation of the turbine warranties and kept the project on course. All from one central connection point.
Rotational Commissioning
Solar Farm Commissioning
Diesel Generator
~
33kV50Hz
33kV50Hz
415V50Hz
DC / AC
LoadbankController
Grid
Wind Vs Solar Output Profiles
17
0%
50%
100%
% Wind Farm Power Output
0%
50%
100%
150%
% Solar Farm Power Output
Innovation – Auto load control(Solar and Wind)
• Manual load matching to Solar output almost impossible• Large power package required to match the solar
generation output.• Load applied to generators from loadbank to match the
likely output from the solar array.• Fuel burn large during periods of low solar output.• Wind Farms, due to their slower ramp rate, are more
manageable under manual operation but require manpower to control.
• Fuel and manpower are significant costs to a commissioning project.
18
Solution
• Auto load control!• Aggreko have developed an automated load control system for
their commissioning solutions• Can control the fast ramp rate of a solar farm and the slower
ramp rate of a wind farm.• Can be used equally on small scale or large scale projects.• Can be used on other technologies, wave, tidal, etc.• Can also be used to control grid export power under a limited
grid point connection.
19
Load balance of system (manual control)
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
5
Low output Med output High output Fuel burn
Generator
Loadbank
Turbine output
20
Loadbank is the fixed point
Load balance of system (automatic control)
0
1
2
3
4
5
6
Low output Med output High output Fuel burn
Generator
Loadbank
Turbine output
21
Generator load is fixed point
Benefits
• Keeps power package to a minimum – lower rental costs.• Keeps fuel burn to a minimum – lower fuel costs.• Runs automatically – after commissioning requires minimum
manual intervention – lower manpower costs• System stability improved• Load ramping can be matched to suit technology• If high number of turbines and hence large ancillary load,
turbine(s) can be run to reduce load on generator to supply the base load.
• Results in a cost effective commissioning solution!
22
More detail?
• Visit us on stand J35• Alf Scambler – Sector Development Manager
Renewables – Northern Europe– [email protected]– www.aggreko.co.uk– 07831 829183 - mobile– 03458 24 7 365 – Rental Centre
23
Contact Us
Aggreko operates from over 200 locations throughout the world.
For the location nearest you please go to:
www.aggreko.com/contact
Head OfficesUnited Kingdom 03458 24/7/365
Belgium +32 3 8250271 Netherlands +31 88 6441 441
France +33 1 69 73 23 94 Poland +48 608 608 419
Spain +34 902 22 11 01 Germany +49 2362 95 210
Italy +39 02 48 40 491 Ireland +57 866 3233www. aggreko .com