    COST ANALYSIS OFCONCRETE ROADS INMUMBAI

    PRESENTED BY,ALOK KUMAR SINGHROLL NO:-08CE-(A)

  • 8/2/2019 Alok Kumar Singh Cost Analysis

    2/17

    Roads are important part of any city. Unlessthey are in healthy condition, the citycannot function properly.

    This paper highlights benefits of cement

    concrete roads and presents a life-cyclecost analysis based on experience ofworking in Mumbai city.

  • 8/2/2019 Alok Kumar Singh Cost Analysis

    3/17

    The original island of Mumbai was only 24

    km long and 4 km wide from Dongri toMalabar Hill.

    Due to low maintenance cost and other

    advantages Municipal Corporation ofGreater Mumbai and Mumbai MetropolitanRegion Development Authority have plans

    for concertizing the entire major roadnetwork in the Mumbai Metropolitan area.

  • 8/2/2019 Alok Kumar Singh Cost Analysis

    4/17

    The total road length in Mumbai is about2000 KM, comprising of 1950 km of BMCmaintained roads and 50 km of statehighways.

    The first concrete road in Mumbai was MarineDrive constructed in the year 1939.

    These roads are of two kinds, namely1.Rigid pavements.

    2.Flexible pavements. Here we determine the cost analysis for these two

    types of roads.

  • 8/2/2019 Alok Kumar Singh Cost Analysis

    5/17

    STABILISED

    SOIL

    6%

    GSB

    17%

    WMM

    15%TACK COAT

    3%

    ASPHALT

    MACADAM

    21%

    DENSE

    BITUMEN

    MACADAM

    21%

    ASPHALT

    CONCRETE

    17%

  • 8/2/2019 Alok Kumar Singh Cost Analysis

    6/17

    Stabilized soil 200 mm =Rs 100 per sqm

    GSB 250 mm (2 layers )=Rs 300 per sqm

    WMM 225 mm =Rs 260 per sqm

    Tack coat (3 times)=Rs 62 per sqm

    Asphalt macadam (75 mm)=Rs 375 per sqmDense bitumen macadam 50m=Rs 375per sqm

    Asphalt concrete (40 mm)=Rs 313 per sqm

    Total =Rs 1770 per sqm

    The cost of above 3.75 m wide pavement willthus be about Rs. 66 Lacks per km

  • 8/2/2019 Alok Kumar Singh Cost Analysis

    7/17

    GSB

    9%WMM

    8%DRY LEAN

    CONCRETE

    M-10

    22%

    CONCRETEOF M-40

    GRADE

    61%

    Sales

  • 8/2/2019 Alok Kumar Singh Cost Analysis

    8/17

    GSB 200 Mm thick (2 layers)=Rs 233 per sqm WMM 150 mm =Rs. 200 per sqm

    Dry lean concreteM-10(150 mm)=Rs.590per sqm

    Concrete of M 40 Grade 300=Rs.1587per sqm

    Total=Rs. 2610 per sqm

    The cost of above Pavement will thus be aboutRs.98 lakhs per km for 3.75 m wide.

  • 8/2/2019 Alok Kumar Singh Cost Analysis

    9/17

    Cost estimate

    Initial cost of flexible pavement=Rs. 66 lakhs/Km Initial cost of rigid pavement=Rs. 98 lakhs/km Initial cost of rigid pavement using 30 % fly ash for

    replacing of cement=Rs. 91 lakhs/km Annual maintenance cost for flexible pavement

    =Rs. 0.25 lakhs/km Renewal of wearing course of flexible pavementevery 5 years=Rs. 12.00 lakhs/km

    Strengthening of road every 10 and 20 years =Rs.14.00 lakhs/ km

    Renewal of wearing course of flexible pavementevery 5,10,15 and 20 years,= Rs. 12.00 lakhs/km Total = Rs. 26 lakhs

  • 8/2/2019 Alok Kumar Singh Cost Analysis

    10/17

    Flexible pavementYEAR

    CONSTRUCTIONCOST

    MAINTENANCECOST

    NPV(1/1.10)

    0 66 - 66.00

    1 - .25 .23

    2 - .26 .21

    3 - .27 .20

    4 - .28 .19

    5 - 15.32 .20

    6 - .31 9.51

    7 - .33 .17

  • 8/2/2019 Alok Kumar Singh Cost Analysis

    11/17

    8 - .35 .169 - .37 .16

    10 - 42.35 16.33

    11 - .41 .1412 - .43 .14

    13 - .45 .13

    14 - .47 .12

    15 - 24.95 5.97

    16 - .52 .11

    17 - .55 .11

    18 - .58 .10

    19 - .61 10

    20 - 68.99 10.25

    TOTALNPV COST

    110.50

  • 8/2/2019 Alok Kumar Singh Cost Analysis

    12/17

    YEARCONSTRUCTIONCOST

    MAINTENANCECOST

    NPV(1/1.10)

    0 98.00 - 98.00

    1 - .1 .09

    2 - .11 .09

    3 - .12 .09

    4 - .13 .09

    5 - .14 .09

    6 - .15 .08

    7 - .16 .08

    8 - .17 .089 - .18 .07

    10 - .19 .07

    11 - .20 .07

    RIGID PAVEMENT

  • 8/2/2019 Alok Kumar Singh Cost Analysis

    13/17

    12 - .22 .0713 - .23 .06

    14 - .24 .06

    15 - .25 .06

    16 - .26 .05

    17 - .27 .05

    18 - .28 .05

    19 - .29 .05

    20 - .30 .04

    99.40

  • 8/2/2019 Alok Kumar Singh Cost Analysis

    14/17

    Saves fuel Long life

    Gain in traffic speed

    Resistant to weather and oil spills Economical

    Environmental friendly

  • 8/2/2019 Alok Kumar Singh Cost Analysis

    15/17

    Initially cost of construction is veryhigh.

    However ,with the price of bitumen

    going up steadily, and the use of flyash in making concrete mixes forpavements the relative cost of these

    two types of pavements could becomequiet comparable.

  • 8/2/2019 Alok Kumar Singh Cost Analysis

    16/17

    Based on the above life cycle cost analysis,Net Present Value (NPV) of flexiblepavement will be about 1.17 % higher thanthe rigid pavement after 20 years.

    Life of concrete pavement will be more than40 years, hence concrete pavement willfurther serve for another 20 years with

    nominal maintenance.