alternative buffer material project meeting #2 2006-11-30

25
Alternative Buffer Material Project meeting #2 2006-11-30

Upload: jean-fleming

Post on 19-Jan-2016

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Alternative Buffer Material Project meeting #2 2006-11-30

Alternative Buffer Material

Project meeting #22006-11-30

Page 2: Alternative Buffer Material Project meeting #2 2006-11-30

Agenda• 09:00 Welcome and introduction

Project status.Anders Eng, Acuo Engineering

• 09:45 Block Manufacturing.Ulf Nilsson, Clay Technology

• 10:15 Coffee• 10:30 Bentonite characteristics

Dietrich Koch, IKO Minerals

• 11:15 Experiment site visit• 12:00 Lunch• 13:00 Storage (parameters, amount etc)

Anders Eng

• 13:15 Future work, analysesDaniel Svensson, SKB

• - 15:00 Discussions

Page 3: Alternative Buffer Material Project meeting #2 2006-11-30

Talk points

• Project outlines

• Installation

• Current status

• Future work

Page 4: Alternative Buffer Material Project meeting #2 2006-11-30

Talk points

• Project outlines

• Installation

• Current status

• Future work

Page 5: Alternative Buffer Material Project meeting #2 2006-11-30

Project goals

• Verify laboratory results with in situ studies, emphasis on temperature, scale and geochemical conditions.

• Discover possible problems with block manufacturing and handling

• Give further data for verification of thermo-hydro-mechanical (THM) and geochemical models.

Page 6: Alternative Buffer Material Project meeting #2 2006-11-30

International participation

• Participating organizations:• SKB• Andra• BGR• GRS• JAEA• Nagra• Posiva• RAWRA• University of Bern

Page 7: Alternative Buffer Material Project meeting #2 2006-11-30

Experiment design

Experiment design based on LOT experiment with some modifications:• Several materials

• Less instrumentation

• Shorter deposit holes

• Complete package length heated

• Steel pipes

• No inserts or tracers

1 2 34 m4 m

Short time (1-2 years).Heated from start.Artificial saturation from start.

Medium time (2-4 years).Heating starts when buffer is saturated.Artificial saturation from start.

Long time ( 5 years).Heated from start.No artificial saturation.

Page 8: Alternative Buffer Material Project meeting #2 2006-11-30

Materials

Block material:• Ikosorb• Deponit CA-N• Ibeco Seal M-90• Friedland• Asha 505• Calcigel• Febex• Kunigel V1• Callovo Oxfordian

(both discs and remoulded)• Rokle• Mx-80

Granulates:• MX-80• MX-80 with quartz

Total of 14 variations of 11 materials !

Page 9: Alternative Buffer Material Project meeting #2 2006-11-30

Talk points

• Project outlines

• Installation

• Current status

• Future work

Page 10: Alternative Buffer Material Project meeting #2 2006-11-30

Experiment site

Page 11: Alternative Buffer Material Project meeting #2 2006-11-30

Package design

Package parts:• Steel pipe

• Buffer blocks

• Saturation system

• Instrumentation

• Heater system

• ”Backfill”

Page 12: Alternative Buffer Material Project meeting #2 2006-11-30

Steel pipes

• ”Black” steel.

• Bottom plate welded to pipe.

• Welds are pressure leak tested.

• Corrosion prevention at top and bottom.

Page 13: Alternative Buffer Material Project meeting #2 2006-11-30

Buffer blocks

Roughly 100 blocks manufactured

• Block dimensions:– 10 cm high

– Dy = 29 cm

– Di = 11 cm

• Pressure about 100 MPa.

• Density about 2 g/cm3

• 10-12 kg each.

Page 14: Alternative Buffer Material Project meeting #2 2006-11-30

Granulate cage

Problem:Keep granulates in place during installation.

Used tools / materials should not interfere with experiment.

Solution: Steel granulate container.Frame will take force from blocks above.

Same material as heater pipe.

GeoTextile keep granulates in place and allows water passage.

Open at top and bottom for interaction with surrounding blocks.

Page 15: Alternative Buffer Material Project meeting #2 2006-11-30

Granulate cage

Page 16: Alternative Buffer Material Project meeting #2 2006-11-30

Granulate cage

Page 17: Alternative Buffer Material Project meeting #2 2006-11-30

Saturation system

System properties:• Four perforated titanium pipes in each package

• Pipes connected in pair at package bottom – flushing possible.

• 0,1 m between perforation in package 1.

• 1 m between perforations in package 2 & 3.

• Pipes protected by “plastic textile” – prevent holes from clogging with sand.

Page 18: Alternative Buffer Material Project meeting #2 2006-11-30

Sensors

Monitoring temperature and humidity:• Thermocouples

– 20 per package

• Temperature indicators,– 2 between each block.

• Relative humidity sensors– 4 in package number 2.

Page 19: Alternative Buffer Material Project meeting #2 2006-11-30

Sensors

Page 20: Alternative Buffer Material Project meeting #2 2006-11-30

Putting the pieces together

Page 21: Alternative Buffer Material Project meeting #2 2006-11-30

Talk points

• Project outlines

• Installation

• Current status

• Future work

Page 22: Alternative Buffer Material Project meeting #2 2006-11-30

Current status

Project status as of today:

• All three packages assembled and installed in deposit holes.

• Monitoring system completed.

• Remaining buffer blocks are in storage.

Remaining work

• Final assembly of saturation system

• Heater installation

• System startup

Page 23: Alternative Buffer Material Project meeting #2 2006-11-30

Talk points

• Project outlines

• Installation

• Current status

• Future work

Page 24: Alternative Buffer Material Project meeting #2 2006-11-30

Storage

Reference blocks is presently stored on Äspö.

• Temperature above 0°C.

• Temperature variations with season.

• Blocks wrapped in plastic bags and put in boxes.

Other parameters to consider?

• Test program – Daniel Svensson is responsible for planning from SKB side.

Page 25: Alternative Buffer Material Project meeting #2 2006-11-30