ND280mND280mOverview of the activities Overview of the activities

T. Nakaya (Kyoto)

Nov 7, 2006@KEK

2

Outline1. Overall activities (ND280 meeting: 11/7-8)

1. http://www.nd280.org/meetings/nd280200611/

2. Important subjects at this meeting1. UA1 Magnet (CONV, IBR, TB, …)

2. SMRD Installation (CONV., IBR, TB, …)

3. Elec/DAQ/Online/Slow-control/Offline/Software group organization (A special ad hoc committee).

4. Unclear items including schedule conflict (→ CONV, TB)

3. Schedule

4. IPNS ND280 Review (11/27-28)

3

1. Overall activities• Nov. 7, 8 from 8:00 – 22:00.

– http://www.nd280.org/meetings/nd280200611/– Conveners meeting, – Software, – Elec/DAQ, – Technical Board (TB), – SMRD,– TPC, – FGD, – INGRID, – P0D, – ECAL, – Photo-sensor, – Scintillator/Fiber– Magnet

4

1. UA1 Magnet• The magnet must arrive in Japan

before Nov. 2007 (one year from now).– The recovery (sandblasting and

paining) must be finished by the end of June 2007.

– Intensive discussions in the conveners, IBR, TB, special meetings.

• We are working hard for this key component.– Technical aspects– Financial aspects

5CONTROL & SAFETY SYSTEM INSTALLATION

MMS, YOKE, COIL BASKET SUPPORT INSTALLATION

MAGNET ACTIONS Vs TIME

2006 2007 2008 2009

YOKE SHIPMENT

COILS, MMS, BASKET SUPPORT SHIPMENT

PRODUCTION

ACCESS TO THE PIT

DESIGN

RECOVERY

April May June

No south bridge from Nov 2007

Jan Febr March

6

2. SMRD Installation• Two Important milestones

– Survey of the magnet yoke• 8mm thick scintillator modules are required.• Will test the 7mm thick scintillator by the end of this year.

– Installation of the modules after construction of magnet and facility building.

• Mock-up test at LSU and CSU

• Arrangement of the sinitillator modules– Must be optimized for physics case.

• Have an answer by January 2007.

7

3. Elec/DAQ/Online/Slow-control/Offline/Software group organization

• Ad hoc committee met to discuss the group structures. The recommendations are

Electronics[A. Weber]

DAQ/Online[G. Pearce]

Slow-Control[R. Poutissou]

Software/Offline[C. McGrew,

Y. Uchida]

8

4. Unclear items including schedule conflict (→ CONV, TB)

• We also work to identify the unclear items in the TB members.– Common fund items.– Missing items.

• The uncertainty of schedule and conflict also will be discussed in the TB meeting.

9

ND280 Schedule

• It is shown by Tsukamoto-san.– We have only 28 month before we have the beam

• Obviously, the ND280 is a complicated system. We may have many risky aspects in the project (technically, financially, ...). However, so far, we work hard trying to keep schedule including very challenging device.– TPC, ASIC, Elec., Photo-sensor, etc..

=> Need Review !

10

IPNS ND280 Review (11/27-28)Nov. 27th (Mon)• Overview/Introduction 930-1000 ???• 930- 945 General T2K Physics T. Nakaya (15 min.)• 945-1000 Beam line status T. Kobayashi/Y. Yamada/A.K.Ichikawa? (15 m

in.)• ----------------------------------------------------------------------------• 1000-1015 ND280 overview T. Nakaya (15 min.)• 1015-1030 Facility T. Tsukamoto (15 min.)• 1030-1040 (coffee break)• 1040-1130 Physics A. Konaka (50 min.)• 1130-1220 INGRID T. Nakaya (50 min.)• 1220-1330 (Lunch)• 1330-1400 Magnet P. Loverre ? (30min.)• 1400-1450 FGD S. Oser (50 min.)• 1450-1540 TPC D. Karlen and M. Zito (50 min.)• 1540-1555 (coffee break)• 1555-1645 P0D C. Mcgrew/K. McFarland (50 min.)• 1645-1735 ECAL C. Touramanis (50 min.)

11

Nov. 28th (Tue)• 900- 950 SMRD T. Kutter (50 min.)• 900-1040 Photo-Sensor Y. Kudenko/M.Yokoyama (50 mi

n.)• 1040-1050 (coffee break)• 1050-1105 Installation/schedule T. Tsukamoto (15min.)(Electronics/DAQ)• 1105-1135 FGD electronics F. Retiere (30min.)• 1135-1205 TPC electronics Saclay member? (30min.)• 1205-1315 (Lunch)• 1315-1345 Scintillator detecetors A. Weber (30min.)• 1345-1415 DAQ G. Pearce (30min.)

• Closed session 1415-

The review document will be distributed inside the collaboration soon after this T2K meeting.