1
BACKGROUND
Article 13, clause no. 13.2 of the Concession Agreement states that:
13.2 Inspection
“During the Construction Period the Independent Engineer shall inspect the Project
Highway at least once a month and make a report of such inspection (the “Inspection
Report”) stating in reasonable detail the defects or deficiencies, if any, with particular
reference to the Scope of the Project and Specifications and Standards. It shall send a
copy of the Inspection Report to the Authority and the Concessionaire within 7 (Seven)
days of such inspection and upon receipt thereof, the Concessionaire shall rectify and
remedy the defects or deficiencies, if any, stated in the Inspection Report. Such
inspection or submission of Inspection Report by the Independent Engineer shall not
relieve or absolve the Concessionaire of its obligation and liabilities hereunder in any
manner whatsoever”.
To comply with the requirement of the above clause of Concession Agreement, a Joint Site
Inspection program of the Project Highway was planned for 22-10-2015 by a joint team
comprising IE and EPC Contractor and the same was informed to the Concessionaire vide this
office letter ref. no. LASA/BK/IE/73426/2015-1047, dated 16/10/2015. During site Inspection,
whole team of IE, Representative of EPC Contractor Mr. Veer Naidu (Project Manager), Mr. V.
Ratnam (Deputy Project Manager, Highway), Mr Adi Narayan (Material Engineer) and other
site engineers were available during site Inspection. Concessionaire’s representative did not
join the Joint Inspection. This Joint Site Inspection Report is based on the findings during site
inspection by the whole team of IE (TL, B/SE, SQME, QS, AHE-2, ABE-2, AQME-2 and
Survey Engineer).
Project Brief
The NH-34 Barasat to Krishnagar Section in the state of West Bengal is located in the
northern part of Metropolitan city Kolkata. It is part of the proposed Barasat to Raiganj section.
The NH-34 is an integral component of the National and Regional road network. The project
highway described in this report is under construction and runs from Km 31.000 to 115.000
between Barasat to Krishnagar on NH 34 in the state of West Bengal.
The completed NH-34 will connect the traffic from Kolkata to Siliguri as well as facilitating the
movements between the State highways (SH), Major district roads (MDR) and other district
roads (ODR). The increase in car ownership, changes in land use and travel patterns have
resulted in congestion on many parts of the State road network including NH-34. The NH-34
currently not only functions as a main corridor to Nepal and Bangladesh but as an urban
collector/distributor between communities, employment and shopping centres.
The alignment traverses through two Districts: North 24 Parganas and Nadia. The terrain
along the project road is generally plain. The predominant land use along the project road is
agricultural with ribbon development near human settlements. At certain locations,
encroachments within the ROW have been observed in the form of Shops, Hotels, Dhabas
and various other commercial establishments. The road passes through towns of Santoshpur-
2
Starting point of the Project Highway (2246’33””, 8830’13”), Kamdebpur (2247’13”,
8830’13”), Amdanga (2234’06”, 8830’27”), Gadamara (2254’00”, 8832’22”), Barajaguli,
Chakdah (2304’52”, 8832’35”), Ranaghat, Phulia, Shantipur (2315’59”, 8826’50”),
Govindapur and Krishnagar(2322’40”, 8829’10”) and end point of the Project Highway
(2355’47”, 8828’08”) etc.
Map Showing Road Alignment of NH-34
I. SCOPE OF WORK
The scope of the Access Controlled Highway Project as detailed in the concession Agreement
shall be broadly classified as follows:
Construction of Four Laning of NH-34 from km 31.000 to km 115.000 (Existing
chainage) or 115.341 (Designed chainage) in the state of West Bengal.
Construction of 2 nos of Major bridges, 5 nos of Minor Bridges, 134 nos of slab culverts
and 17 nos of Pipe culverts on main carriage way under New/widening/ Reconstruction
Scheme as per Schedule B of Concession Agreement.
Construction of 4 nos of ROBs, 1 no of RUB, 2 nos of Vehicular Underpass, 12 major
junctions, 14 nos of minor junctions, 1 no of toll plaza and others Schemed as per
Schedule B and Schedule C of Concession Agreement
During the entire construction period, the Project Highway is to be maintained by the
Concessionaire at his own cost from the appointed date.
Traffic Management and Safety of workers and the road users shall be maintained at all
times in accordance with the relevant IRC and relevant Codes as stipulated in the
Concession Agreement without any deviations.
3
The scope of the work for the Project Highway also includes but not limited to the following:
Road side furniture
Pedestrian Facilities
Highway Lighting Systems
Junctions(Major & Minor)
Tree plantation and landscaping
Truck lay byes & Bus lay byes with bus shelters.
II. SITE INSPECTION
Joint Site inspection was conducted on 16th October, 2015 by the team comprising IE (TL,
B/SE, SQME.QS, AHE-2, ABE-2, AQME-2 and Survey Engineer); and EPC Contractor were
present during site Inspection. The visit was started from Km 115 +000. The inspection
program started at 11:00 AM and concluded at Km 51 +000 on the same day at 4:15PM.As
there was no work from Km 31+000 to 51+000.
III. FINDINGS IN JOINT SITE INSPECTION
There is virtually no highway work due to lack of approved borrow area, except dumping of
sand/sandy soil in some location and GSB and WMM work in some stretches and DBM work
in very few stretches. Some structural works like piling works of ROBs, return walls of box
culverts and pushing of Tunnel at RUB are in progress. Work progress is very slow. The
compliance of comments given by the Independent Engineer in the Reports of previous Joint
Site Inspections was reviewed during this inspection. The works which are under progress
were inspected. The following are the findings:
1. Box Culvert (Km 113+980) RHS
During joint Inspection; it has been observed that shuttering and reinforcement binding for the
box culvert is in progress.
Shuttering and Reinforcement work @ 113+980 Box culvert
4
2. Earth Work from Km 113+200 – Km 113+400 (RHS)
Fine sand (silver sand) filling work for embankment work was in progress from Km 113+200 to
113+400 (RHS). But the work is being done without confinement. EPC contractor is reminded
submit the methodology of embankment work using cohesion less soil and follow procedure
mentioned in IRC SP 58.
Embankment work without confinement from Km113+200 to 113+400 (RHS)
Embankment work without confinement from Km113+200 to 113+400 (RHS)
5
3. Km 113+528 (Jalangi Major Bridge)
The work of this bridge has been stopped since 27-07-2015. Till date, 32/64 piles have been
completed. At present no contractor at site. Kamar infra (contractor) has removed all their
equipment and machineries. At present there are some Sheet pile materials and some liners
are lying at site. EPC Contractor representative said that work in this bridge will be restarted
from 1st week of September after engaging new contractor. But there is no advancement from
the status of previous month. Concessionaire is again instructed to re-start the work of this
bridge at the earliest as the site is dry now.
.
Site clear but no work, no equipment @ Km 113+528 (Jalangi Major Bridge)
4. Km 112+ 247 (RUB)
I. 8 units (6 units for left and 2 units for right tunnel) of tunnel casting have been
completed.
II. CRS approval for pushing tunnel under Railway track has been obtained.
III. Till date 19.00 m of left tunnel pushing under railway track embankment has been
completed.
IV. 11m side pushing of a box was already done previously for clearing space to cast
tunnel.
V. Grouting work to stabilize the original ground (below raft of box) was in progress
6
Pushing of the box under railway track
Boxes of tunnel at RUB are ready for pushing
7
Grouting work in progress
5. Km 111+345 (Krishnagar ROB)
Piling work of A1, A2 and P1 complete. 3/6 pile of P2 completed and cage lowering for P2-
6 was in progress.
One temple is obstructing the piling work of P4 which is to be shifted for smooth
construction of this ROB
Cage lowering at location P2-6 in progress
8
Temple at P4 Work site of Krishnagar ROB ,Km 111+400
6. Km 111+201 (Minor Bridge)
Casting of slab has been completed on 09.09.2015 and after that time, no activities are in
progress. Concessionaire was instructed to continue the work of this culvert.
Minor Bridge at Km 111+201 (LHS structure completed)
7. DBM Work:
i) Km 109+640 –Km 110+140:
At Km 109+640 to 110+240 DBM 1st has been completed. It is observed that core cutting
holes are not filled. EPC Contractor is instructed to fill these holes immediately and core holes
should be filled immediately after cutting in future also. EPC Contractor is planning for 2nd
(Top layer) DBM. Median kerb casting in the location has been completed.
9
ii) Km 101+910 to 102+265, Km 103+360 to Km 103+380: Single layer DBM completed.
iii) Km 102+265 – Km 103+360: Two layer of DBM completed.
The EPC Contractor is also instructed to fill the shoulder portion before allowing traffic in newly
done DBM locations.
Tree plantation has been done on the shoulder (LHS) by “Zilla Parishad “(MG-NREGA) from
Km Km 109+040 –Km 110+140 without any intimation to the Concessionaire, which will
disturb the construction of Project Highway.
Concessionaire is again advised to request the concerned Authority to remove the plantation.
Plantation on shoulder and primed surface
Core filling left in DBM
10
1st Layer DBM completed from Km 109+640 –Km 110+140
8. Madhucon Camp @ 93+000: RE Panel Casting
RE panel casting was in progress. But it has been observed that curing of the casted panels is not
proper and as per submitted methodology. It is instructed to follow the curing process as per submitted
methodology.
Lifting hooks are provided in the casted RE panels, which is not shown in the submitted drawing. It is
instructed to show the lifting hooks in the drawing and submit revised drawing of RE panel.
MTC for galvanization of steel used as hook in the RE panel is not available with the Concessionaire.
Concessionaire is advised to provide MTC of IE for checking.
Curing of RE Panel at Madhucon Camp at Km 93+000
11
RE Panel casting in progress
9. QC Laboratory
Concrete cubes from site (Km 113+358 ROB-M30, RE Panel-M35, Median Kerb from Km
51+880 to 52+010-M20) of age 7 days age were tested and found satisfactory. Result of tests
are enclosed as Appendix: 1-3.
Site Concrete cube testing at QC Lab
12
Site cube testing at QC lab
10. ROB at Km 75+955 (Ranaghat)
Piling work of A1and P1 locations are completed. At P2 location 3/6 of piles completed. At
location A2 pile no. A2-04 was in progress and cage lowering was ongoing.
There is problem in piling at P2-4, P2-5 and P2-6,due to underground 11KV feeder
electrical transmission line. Concessionaire is advised to take up this issue to the
concerned authority at the earliest so the three would be no problem for piling work.
Preparation for load test on test pile was in progress
Cage lowering for pile
13
Reinforcement cage ready for lowering
Preparation for load test on test pile @ Km 75+955 (Ranaghat ROB)
11. Km 66+360 (Chakdah VUP)
Test piling completed on 19-08-2015. One set of machinery for piling is at site. No further
progress can be seen at this location. Representative of EPC Contractor said that the work
is stopped due to overhead electric transmission line and said shifting of electric line will
take about 10 days.
Concessionaire is instructed to talk with local authority to resolve the problem.
14
Preparation for piling work @ Km 66+360 (Chakdah VUP)
Preparation for piling work @ Km 66+360 (Chakdah VUP)
12. Safety
During joint inspection, it is found that the Concessionaire has adopted some safety measures
at site but not sufficient for the safety of workers and safety of road users. Concessionaire is
instructed to install sufficient sign boards at work site as well as along the Project Highway
showing “Work in Progress”, “Man at Work”, “Road Narrows”, “Accisent Prone Zone” etc,as
recommended by safety consultant.Some new safety signboards are installed.
15
Newly installed sign board
Cordoning of work site during piling work at Km 111+345 (Krishnagar ROB)
16
IV. RECOMMENDATION:
The concessionaire has not yet fully addressed/responded/complied the instructions /
comments / suggestions given by the Independent Engineer in previous Joint Inspection
Reports. It is again recommended to address the issues raised by Independent Engineer in
this Joint Site Inspection Report along with previous reports and correct/rectify the deficiencies
at the earliest to achieve the quality works.
Similarly, it is recommended to adopt proper and adequate safety measures for construction
zone as well as construction labours. Similarly, it is advised to strictly follow Safety Manual
submitted by BKEL on 16/02/2013 vide their letter ref. no. BKEL/NH-34/LASA/TL/2013/066
and recommendation of safety Consultant and safety expert.
It is also advised to expedite the work as lot of encumbrance free land (64 Km) is available for
four lanning.
CONTENTS
Background ........................................................................................................................................... 1
I. Scope of Work ............................................................................................................................... 2
II. Site Inspection ............................................................................................................................... 3
III. Findings in Joint Site Inspection ..................................................................................................... 3
1. Box Culvert (Km 113+980) RHS .................................................................................................... 3
4. Km 112+ 247 (RUB) ...................................................................................................................... 5
5. Km 111+345 (Krishnagar ROB) ..................................................................................................... 7
6. Km 111+201 (Minor Bridge) ........................................................................................................... 8
7. DBM Work: .................................................................................................................................... 8
8. Madhucon Camp @ 93+000: RE Panel Casting .......................................................................... 10
9. QC Laboratory ............................................................................................................................. 11
10. ROB at Km 75+955 (Ranaghat) ................................................................................................... 12
11. Km 66+360 (Chakdah VUP) ........................................................................................................ 13
12. Safety .......................................................................................................................................... 14
IV. Recommendation: ........................................................................................................................ 16
National Highways Authority of India
(Ministry of Road Transport & Highways)
Government of India
Four Laning of Barasat-Krishnagar Section of NH-34 from Km 31.000 to Km 115.000 in the State of West Bengal under
NHDP Phase-III on DBFOT (Annuity) Basis
MONTHLY JOINT SITE INSPECTION REPORT
OCTOBER, 2015
LEA Associates South Asia Pvt. Ltd., New Delhi