Speaker: Racha Chahrour– Hochtief ViCon -How are classic technologies being adopted? -Challenges – experience, software capabilities About the Qatar BIM User Day: Qatar University, HOCHTIEF ViCon and Teesside University proudly take the initiative to facilitate modern and innovative methods in the Gulf construction industry. The focus is Building Information Modeling (BIM), and our aim is to establish a knowledge platform with government, research and industry experts. The User Day aims to help people to share knowledge, discuss new technologies, and identify new potentials for BIM. More information: www.bimuserday.com Follow BUD on Twitter @bimuserday

TRANSCRIPT

1 Dr. Racha Chahrour

HOCHTIEF ViCon

2nd Qatar BIM User Day “Technology is the key to success”

BIM for Project Scheduling and Quantity Take-Off Dr. Racha Chahrour HOCHTIEF ViCon Qatar W.L.L. www.hochtief-vicon.com

2 Dr. Racha Chahrour

HOCHTIEF ViCon

Agenda

1. 4D Model Creation Strategy

2. 4D Scheduling Software

3. Quantity Take Off

4. Summary

3 Dr. Racha Chahrour

HOCHTIEF ViCon

4D Model Creation Strategy

Major Elements

3D Model

Schedule

4D Model

4 Dr. Racha Chahrour

HOCHTIEF ViCon

4D Editors

Program

Imp

ort

C

reate

4D

4D Scheduling Software

Available Software Systems

3D Model

5 Dr. Racha Chahrour

HOCHTIEF ViCon

4D Scheduling Software

Manual Linking in NavisWorks

Structured 3D Selection Sets

Schedule activities Links

6 Dr. Racha Chahrour

HOCHTIEF ViCon

4D Scheduling Software

Rule-based Linking in NavisWorks

Parameter based search sets

Linking rules

Parameter

7 Dr. Racha Chahrour

HOCHTIEF ViCon

4D Scheduling Software

Manual and Rule-based Linking in Synchro

Attributes 3D objects

Attribute scheduling tasks

Linking rules

8 Dr. Racha Chahrour

HOCHTIEF ViCon

4D Scheduling Software

State of the Art Functionalities of 4D Editors

• Import various 3D model formats

• Support major scheduling software

• Construction sequence animation

• Synchronisation of model and program data

• Rule-based activity linking

Visual Schedule

Analysis

9 Dr. Racha Chahrour

HOCHTIEF ViCon

4D Scheduling Software

Limitations of 4D Editors

• Limited export of created 4D model

• Complex and time consuming linking process

• Focus on visual schedule analysis

• High efforts for 4D model updates

No Scheduling

Support

10 Dr. Racha Chahrour

HOCHTIEF ViCon

Quantity Take Off

Model-based Quantities - Creation Strategy / Software

Filled BOQ with model-based Quantities

Specs 3D Model

11 Dr. Racha Chahrour

HOCHTIEF ViCon

• Elements:

• Columns

• Walls

• Ceilings

• Beams

• Quantities with the corresponding structural elements

Quantity Take Off

Structural Elements

12 Dr. Racha Chahrour

HOCHTIEF ViCon

• All openings like doors, windows, ceiling fretworks are subtracted -according to the QRM- of the corresponding structural elements

• If wall and beams intersect, the intersection area is subtracted of the wall

Quantity Take Off

Rules of Measurements

13 Dr. Racha Chahrour

HOCHTIEF ViCon

• Walls, columns and ceilings may have different qualities. e.g. walls:

a. Drywalls

b. Blockwork

c. Concrete

• So different types of walls are displayed in different colours

a. c.

Quantity Take Off

Visualisation of Object Attributes

b.

14 Dr. Racha Chahrour

HOCHTIEF ViCon

• Finishing works can be calculated over the rooms

• A room is bounded by vertical and horizontal structural elements

Quantity Take Off

Finishing Works

15 Dr. Racha Chahrour

HOCHTIEF ViCon

• Full definition of model requirements at project start to ensure re-usage of 3D models

• Definition of the model structure considering construction joints

• Usage of appropriate agreed/standarised description for 3D model elements

• Implementation of rules of measurement to consider small openings

• Easy access to created data for all stakeholders

Quantity Take Off

Process Requirements

16 Dr. Racha Chahrour

HOCHTIEF ViCon

Summary

• Latest technology is generally able to meet common project

requirements

• Rule-based schedule linking would improve performance

• Visualising the construction program improves project communication

among all stakeholders

• Data exchange is limited

• Quantity take off requires accurate, structured and qualified 3D

models

17 Dr. Racha Chahrour

HOCHTIEF ViCon

Dr. Racha Chahrour

BIM Manager

HOCHTIEF ViCon Qatar W.L.L.

www.hochtief-vicon.com

Thank you for your attention!