Project SLOPE1
WP 7 – Piloting the SLOPE demonstrator
Project SLOPE
T 7.2 – Preparation of Demonstrators
Cork, January 20th, 2016
Gianni Picchi, Raffaele Spinelli, Giovanni AmintiCNR-IVALSA
Technical Meeting, Cork 20.01.2016
Overview
• Status: concluded• Length: until month 19• Involved Partners Leader: CNR Participants: BOKU, COAST, COMPOLAB, GT, GRE, ITENE,
MHG, TRE Aim: Comparison of the current and innovative SLOPE system
for forest survey, harvest and timber supply chain.• Outputs: Deliverables D7.02 (finalized and approved)
Technical Meeting, Cork 20.01.2016
Overview
• The objective of this task is to set up the tests for the new SLOPE system and for comparing it to the main alternative systems (current)
• Suitable demo sites have been identified in Sover (Italy) and Annaberg (Austria)
• Demos and tentative harvest periods have been agreed with landowners and harvesting companies, also according to their specific requirements
• An evaluation methodology had been established
Technical Meeting, Cork 20.01.2016
Technical Meeting, Cork 20.01.2016
Timeline of activities
Pre-demo activities are planned in synergy with other WPs(mainly WP4)
Jan DecApr Jun/Jul Sep/Oct Nov
Pre-test ofmachines
(workshops yards)
2016
May
Pre-test of machines(in forest, single
machines)
Pilot in Montesover
Pilot in Annaberg
Finalconference
(EIMA 2016)
Comparative analysis
Benefit analysis
Technical Meeting, Cork 20.01.2016
not fulfilled 0-2partial fulfilled 3-4
moderate fulfilled 5-6mostly fulfilled 7-8
fully fulfilled 9-10
tree marking degree of fulfilmentcriterion forester/marking spray weighting result/valenceindependence from know-how 10 10 1independence from work experience 8 10 0,8independence from technical skills 10 10 1independence from weather 9 10 0,9cost-efficiency 9 10 0,9independence from power supply 10 5 0,5traceability after logging 3 10 0,3easy legibility 10 5 0,5minimum expenditure of time 8 10 0,8error rate 9 5 0,45usability 9 5 0,45robustness 9 10 0,9
Summe 100 8,5e.g. How important is independence from know-how for the degree of fulfilment of tree marking?
degree of fulfilment
CURRENT SYSTEM
tree marking degree of fulfilmentcriterion forester/visual and RFID marking weighting result/valenceindependence from know-how 5 10 0,5independence from work experience 8 10 0,8independence from technical skills 5 10 0,5independence from weather 5 10 0,5cost-efficiency 2 10 0,2independence from power supply 1 5 0,05traceability after logging 10 10 1easy legibility 5 5 0,25minimum expenditure of time 5 10 0,5error rate 9 5 0,45usability 5 5 0,25robustness 5 10 0,5
Summe 100 5,5
SLOPE
Business processes
Technical Meeting, Cork 20.01.2016
Operations Supervisor
Forest Owner
Customer Harvesting Company
Freight Company
decision about harvesting operation
choosing forest stand
estimation of harvest yield
for calculations
searching for customer, harvesting company and freight company
planning harvesting
operation and transport
harvesting operation
transportation
take over at the mill
evaluation of quality and
quantity
partial paiment of harvesting company
payment of forest owner, final payment of harvesting company, payment of freight company
supervision
supervision
decision about harvesting operation
searching for customer
contract notes customer, harvesting company and freight
company
planning harvesting operation and
transport
harvesting operation
transportation
take over at the mill
choosing forest stand
estimation of harvest yield for
calculations
searching for freight company
searching for harvesting company
payment 30 days after service provision; harvesting
c. is payed by the forest owner, freight c. is payed by the forest owner or by the
customer
economic necessity, decision based on forest management plancutting maturity, composition of
tree species, age class, yield class, volume, stand density, quality
forest management plan (based on inventory data),
experienced estimation
tree species; approximate quantity, quality and price
approximate quantity; mill to supply
harvesting and fright company: contract with companies,
services, period of time, price (€/m3), time limits, terms of
payment, provision in the event of non-compliance
customer: contract involved companies, tree species,
quality, quantity, assortments, price (€/m3), period of time,
terms of payment, provision in the event of non-compliance
compositon of tree species, age class, approximate volume, terrain
conditions, harvesting method, harvesting period, approximate price
area, sea level, weather conditions, tree species, middle
diameter at breast height, approximate volume, surface, inclination, harvesting method
tree selection by expert or forest worker, selection of skid trailsorder, which
forest location and mill, period
of time, quantity, access-
bill millgrading data
dimension data, dimension bill from the mill within 30
days to the employer, payment within another 30
days
access-bill from customer, contact
between transport c. and forest owner
Technical Meeting, Cork 20.01.2016
Processes analysis
Each process will be analyzed by identifying its work elements
working cycle conventional
description
empty run drive till stopping of the carriage
hookfrom the stoppage of the carriage until driving of the carriage
load runfrom starting of the carriage until the stoppage at the landing
land spool out and spool in of the towing rope
unhookfrom setting in motion of the forest worker till spooling in of the towing rope
manipulation with the excavator
warping of the stems when landing is difficult
expiry caused waiting times
carriage is waiting, because the processor driver is still working
interruptions ≤ 15 minutes
working interruptions less or equal 15 minutes
interruptions > 15 minutes
working interruptions superior 15 minutes
working cycle SLOPE
description
empty run drive till stopping of the carriage
hookfrom the stoppage of the carriage until driving of the carriage
load run with RFID reading and weighing by load cell
from starting of the carriage until the stoppage at the landing
land spool out and spool in of the towing rope
unhookfrom setting in motion of the forest worker till spooling in of the towing rope
manipulation with the excavator
warping of the stems when landing is difficult
expiry caused waiting times
carriage is waiting, because the processor driver is still working
interruptions ≤ 15 minutes
working interruptions less or equal 15 minutes
interruptions > 15 minutes
working interruptions superior 15 minutesCable yarder
Process analysis
• Aspects considered Time consumption (overall time needed for machines and operators) Productivity (output according to the elemental unit, e.g. m3, ha, etc) Accuracy (quality of the output, where applicable) Cost calculation (overall cost, including consumable elements) Work load (strain for operators, where applicable)
Technical Meeting, Cork 20.01.2016
EIMA 2016
Bologna (Italy), 10-13 November; Second biggest EU Agro-forest machinery fair; 235,000 visitors (2014 edition); Scientific and technical conferences organized
in collaboration with UNACOMA and ENAMA; Business oriented event, with growing interest
in forest machinery themes and precision forestry/agriculture technologies.
Available Greifenberg stand with intelligent machines prototypes and videos
Technical Meeting, Cork 20.01.2016
BOLOGNA
FI
MI
TN
ROME
Project SLOPE
T7.3 – Trials recommendation and validation cycle
Cork, January 20th, 2016
Kühmaier Martin, Pichler Gerhard, Kastner Maximilian, Stampfer Karl Institute of Forest EngineeringUniversity of Natural Resources and Life Sciences, Vienna
Technical Meeting, Cork 20.01.2016
Contents of the presentation
Technical Meeting, Cork 20.01.2016
1. Overview
2. Introduction
3. Survey site Annaberg
4. Performed activities on the survey site
5. Prospective plans for the harvesting demo
6. Agreement regarding the Austrian Federal
Forests support
1. Overview
• Status: in progress• Length: until month 36• Involved Partners Leader: BOKU Participants: GRAPHITECH, CNR, COMBOLAB, MHG, BOKU,
GRE, TRE, ITENE Aim: Trials and Validation of the SLOPE system on survey
sites in Austria and Italy• Outputs: Deliverables D7.031, D7.032, D7.04 and D7.05
Technical Meeting, Cork 20.01.2016
2. Introduction
• The objective of this task is to validate the new SLOPE system in a mountainous forest scenario
• The new system will be tested in Sover (Italy) in spring 2016 and Annaberg (Austria) in autumn 2016
• The efficiency of the SLOPE system will be measured by methods which were explained in D7.02
• This should lead to the strengths and weaknesses of the new system and support improvement
Technical Meeting, Cork 20.01.2016
Technical Meeting, Cork 20.01.2016
3. Survey site Annaberg
• Study site is located in the Austrian province Salzburg, in the village Annaberg im Lammertal
• Survey area (8 ha) lies on Promberg (905 m - 1144 m)• SLOPE harvesting area (0.42 ha; 1031 m - 1128 m)
3. Survey site Annaberg
• SLOPE harvesting area (0.42 ha; first section): first 200 m x 30 m section is the SLOPE harvesting area UAV+TLS survey was performed in autumn 2015 northwest exposed slope range of 60 % - 100 % small flatter part in the upper sector 30 % - 60 % 90 % spruce; 10 % firs and larches spread over the harvesting area 80 years old stock: 466 m3
number of stems: 345 basal area: 34.8 m2
mean dbh: 33.7 cm mean hight (hLorey): 30.2 m yield class spruce: 15.4 m3/ha/year
Technical Meeting, Cork 20.01.2016
3. Survey site Annaberg
Technical Meeting, Cork 20.01.2016
• SLOPE harvesting area (0.42 ha; first section): Preliminary clearing: Extraction of about 115 RFID marked trees
(150 m3) → this is about a third of the standing trees
• Additional harvesting area ÖBF agreement (second section): Also 200 m x 30 m about half a hectare Same forest stand characteristics Another 115 trees (150 m3)
• In total over the whole harvesting area of 400 m x 30 m about 230 trees (about 300 m3), which must be extracted during the SLOPE demo in autumn 2016 in Austria
Technical Meeting Cork 20.01.2016
Survey areaSLOPE harvesting area
Additional harvesting area ÖBF agreement
4. Performed activities on the survey site
• Selection of the cable line in SAGIS and generating GPS coordinates (survey area, SLOPE harvesting area)
• Marking corner points and borders of the survey area and harvesting area with colour spray on the basis of GPS data in Annaberg
• Marking cable line adapted on terrain conditions with marking tape• Making a complete enumeration for the SLOPE harvesting area
Technical Meeting, Cork 20.01.2016
3. Performed activities on the survey site
Marking harvesting treeswith white colour spray
UAV survey by COASTWAY 05.10.-09.10.2015
TLS survey by TREEMETRICS 02.11.-06.11.2015
Technical Meeting, Cork 20.01.2016
5. Prospective plans for the harvesting demo
• Marking thinning trees with RFID tags (Smartrac Shortdipole Monza 5) and the aid of Treemetrics Forest Application (forest map based on UAV and TLS data)
• Motor-manual felling of the marked trees by forest worker
• Extracting trees with a modified CRG 15 carriage (RFID scanning unit) in combination with a SIBERIAN tower yarder
Technical Meeting, Cork 20.01.2016
• Processing trees with an modified ARBRO (RFID scanning/marking, determining timber quality)
• Performing a time study for the new SLOPE system (modified carriage and processor head) and a cost calculation for the performance evolution
Technical Meeting, Cork 20.01.2016
5. Prospective plans for the harvesting demo
Mid-term Review 2/Jul/15
6. Agreement regarding the Austrian Federal
Forests support
• The Harvesting date must be fixed one month in advance
• Forestry workers of the Austrian Federal Forests will perform the felling operation
• The Austrian Federal Forests will provide a cable yarder operator and a processor operator
• The costs of a normal harvesting operation will be taken over by the Austrian Federal Forests
• Additional costs must be covered by the SLOPE project
Contact info
Martin Kühmaier: martin.kuehmaier@boku.ac.atGerhard Pichler: gerhard.pichler@boku.ac.at
Maximilian Kastner: maximilian.kastner@boku.ac.at
Thank you for your attention!!
Technical Meeting, Cork 20.01.2016
References & Picture sources
Last downloaded on 21.12.2015:• http://www.holz-broeker.de/images/ansicht-luftbild-saegewerk-schnittholz.jpg• http://www.riebli-forst.ch/bilder/maschinen/holz-lkw04_b.jpg• http://www.rfidjournal.com/lib/x/a/assets/2009/11/5350-3.jpg• http://www.dronelife.com/cms/sites/default/files/product/eBee_0.jpg• http://www.woodbusiness.ca/images/heads-arbro.jpg• http://www.sparpointgroup.com/images/uploadedImages/Images/02.10.11.FARO-in-the-woods.png• http://www.blaueberge.at/region-sommer.html#!lightbox[annaberg]/1/• http://www.greifenberg.it/carrellipescanti/crg15s/gallery_2.jpg• http://www.greifenberg.it/teleferiche/siberian/gallery_6.jpg