Harrisburg Overpass Construction Update April 5, 2016
Activity Progress Since March Meeting • East and West temporary U-Turns are installed.
• East and West through traffic at UPRR shut down & detour installed.
• Project utility work under MSE wall complete. Hughes Street and drainage for bridge remains in progress.
• West MSE wall embankment and lime stabilization complete, started coping work.
• West systems duct bank and manhole installed.
• West footings and columns completed at (Abut. 1, Bent 2, Bent 3)
• West bent cap work started at bents 2 and 3.
• East drill shafts completed (Abut 10, Bent 9, Bent 8)
• East Abutment 10 cap complete
• East Bent 9 footings complete, column work continues. Bent 8 footing work continues.
• East MSE wall foundation and leveling pad work continues.
• Center Bent 4 drill shafts completed, Bent 5 drill shafts continue, Bent 6 drill shafts complete, Bent 7 drill shafts continue.
2
Road Closure of Harrisburg @ UPRR
3
• Began: Sunday, March 13
• Duration: 3 months
• Local Access: Utilize u-turns at
UPRR to access local businesses
Remaining Utility Work (Phase 3) East of Union Pacific Railroad
4
Remaining Utility Work (Phase 3) West of Union Pacific Railroad
5
6
West of Union Pacific Railroad
West of Union Pacific Railroad
7
8
East of Union Pacific Railroad
East of Union Pacific Railroad
9
30 Day Look Ahead
10
West of UPRR
• Finishing MSE walls • Finish bent caps • Install roadway paving • Install bridge railing • Install OCS foundations • Install bridge girders
East of UPRR
• Finish columns and footings • Finish bent caps • Finish MSE embankment backfill • Start lime stabilization • Install MSE wall coping. • Install systems duct bank
Center Over UPRR
• Finish columns and footings • Install bent caps