Within this project, the motorway M51was built between the E45 inSønderjylland (Southern Jutland) andAlssund, in order to create astructure­enhancing and efficientconnection. For this project, theKliplev Motorway Group (KMG)assigned a european constructioncompany in a so­called public­private­partnership for the construc­tion of the motorway. This newly builtmotorway was erected between2011­2012, has a total length ofabout 28 km and was realizedbetween Kliplev in the west andSønderborg in the east. Overall, twolanes on each side were completed.

Besides the construction of themotorway, seven interchanges aswell as ten crossing municipalconnection roads with a total lengthof 18 km had to be built. Additionally,numerous off­site facilities had to benewly established or modified to thechanged structure. Also, elevenroundabouts and one distributor ringwere constructed within this project.

Due to the high existing complexityand a stipulated construction periodof about two years, it was necessaryto ensure a trouble­free timing andhigh quality requirements on thestructural engineering, the securityand the project documentation.

To support supervisory tasks andconstruction supervision the clientplaced the order with theIngenieurbuero Dr.­Ing. Olaf Schulz.

Ingenieurbüro Dr.­Ing. Olaf Schulz · Roonstraße 11 · D­38102 Braunschweig · www.dr­olaf­schulz.de

Ingenieurbüro Dr.­Ing.Olaf Schulz

Beratende Ingenieure

ClientKliplev MotorwayGroupTime Period2011 bis 2012Motorway4­lanes (28 km)Municipal Roads10 crossing roadstotal length 18 kmCross Sections7 Interchanges11 Roundabouts1 Distributor ringConstruction Types23 Bridges and under­passes, bicycle tunneland openings, rain­water retention basin

Construction Supervision on theMotorway M51 in Denmark ­Kliplev­Sønderborg

WastewaterTreatmentDrainageArea DevelopmentGeo and CanalInformation SystemsExpert OpinionsProject ControllingHealth and SafetyCoordinationRoad ConstructionTransportationSurveyingVisualizationHydraulic Engineering

Scope of Services

• supervision of the technical execution• supervision of the organisational completion• supporting health and safety coordination• counterchecking the building documentation• technical preparation of complex approval processes• documentation of imperfections during construction• improving the flow of information to/from the construction supervisor

Ingenieurbüro Dr.­Ing. Olaf Schulz · Roonstraße 11 · D­38102 Braunschweig · www.dr­olaf­schulz.de

Ingenieurbüro Dr.­Ing.Olaf Schulz

Beratende Ingenieure

Project aims

• compliance within the stipulated construction time and securingeconomical project conditions

• enforcing the aims of the internal quality management• minimizing the operating costs for the pavement, buildings and off­site

facilites of the motorway during the concession term of the public privatepartnership

• minimizing the risk of delivery for the operator on expiration of theconcession term

• recovery of the affected municipal road system within the periodstipulated

• handover of technically high­grade and sustainable buildings to themunicipal payers

WastewaterTreatmentDrainageArea DevelopmentGeo and CanalInformation SystemsExpert OpinionsProject ControllingHealth and SafetyCoordinationRoad ConstructionTransportationSurveyingVisualizationHydraulic Engineering