Summary
Contents
Key Activities
Scope Development
Schedule
Progress Photos
12345
EXTERIOR DESIGN BUILD TEAM I JE DUNN I TREANOR ARCHITECTS I ADG
JULY 2016
OKLAHOMA STATE CAPITOL RESTORATION
Exterior Rehabilitation
EXTERIOR DESIGN BUILD TEAM I JE DUNN I TREANORHL ARCHITECTS I ADG
OKLAHOMA STATE CAPITOL RESTORATION
Exterior Rehabilitation
ContentsSummary
Safety
Progress Photos
Attachments
Roofing Replacement Update
123
JANUARY 2019
1503
9DB
MON
THLY
CON
STRU
CTIO
N PR
OGRE
SS R
EPOR
T
45
STATE CAPITOL RESTORTATE CAPITOL RESTORTATE CAPITOL RESTO
1503
9DB
MON
THLY
CON
STRU
CTIO
N PR
OGRE
SS R
EPOR
T
4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104 I P 405.302.4500 I WWW.JEDUNN.COM
RETURNS TO TABLE OF CONTENTSCLICK HERE
Exterior RehabilitationJE DUNN I TREANORHL ARCHITECTS I ADG
JANUARY 2019
Summary: During the month of January on the Oklahoma Capitol Exterior Restoration Project, exterior tunnel work was completed. Lincoln Boulevard was reopened in mid-January and will be re-striped in early February. The interior finishes in the tunnel will start in 2019, however, the tunnel will remain closed until the new Visitor’s Center is complete. The South Portico door installation was complete in early January ahead of the inauguration of the new Governor. The handrails for the lower South Plaza and the southwest ramp were installed in January. The temporary pedestrian protection was installed for the Southwest entry which allowed it to be re-opened at the end of January. Now that this entry is open, the Southeast entry has been closed while construction for the new Visitor’s Center is in progress. The West Wing South Elevation (Juliette) scaffolding was completely dismantled in January. The West Wing North Elevation (Lima) glass installation on phase 1 was also completed in January, along with the paint and sealant work. Interior storm window installation started at the end of the month and should be complete on phase 1 in early February. Phase 2 glass installation began in late January and will complete at the end of February. All exterior steel and cast iron frame repairs were completed in January. Paint and sealant work is on-going on phase 2 and will be complete at the end of February. The installation of the copper gutter lining is on-going and will be complete in mid-February in time for our final exterior skin punch list in March. The copper roofing replacement work has continued on the south wing. Over the last several weeks we have been working to repair the old and rotting substrate at the main sloped roof as well as the gutterways. New marine grade plywood framing is now complete in the gutterways and new roof drains and piping have been installed. The first sections of flat lock copper have been installed in the southeast (India) gutterway. At the main slope we are replacing all existing plywood. Once the existing plywood is removed, we review the existing substrate with our structural engineer to determine what 1x6 decking has to be replaced due to rotting. A large amount of rotting was found around the skylights of the south wing. This rotting included the 1x6 decking and the wood sleepers that are recessed into the concrete deck. Now that the substrate repairs are wrapping up on the sloped roof and around the skylights, we can begin framing the new skylights in February to receive copper. On the north wing, we expect to begin copper removal of the entire sloped roof at the beginning of February. This will allow us to analyze existing conditions and determine if extensive repairs need to be made to the substrate as we saw on the south wing. Please refer to the subsequent pages of this report to review photos of existing roofing conditions and re-roofing progress.
1503
9DB
MON
THLY
CON
STRU
CTIO
N PR
OGRE
SS R
EPOR
T
4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104 I P 405.302.4500 I WWW.JEDUNN.COM
RETURNS TO TABLE OF CONTENTSCLICK HERE
KeyActivities:
- Echo new historical replica door installation complete - Tunnel phase two exterior work complete - Juliette scaffold demobilization complete - Kilo new historical replica door installation in progress - Lima copper gutter installation in progress - Lima stone restoration complete - South wing re-roofing gutterway framing complete - South wing gutterway flat-lock copper installation in progress - South wing re-roofing substrate repairs & plywood install in progress - West wing clerestory window installation complete - Lightwell excavation/concrete work for new sump pumps in progress - Northeast (Delta) phase 1 retaining wall replacement complete - Northeast phase (Delta) 1 mow strip installation complete - Delta balustrade stone restoration complete - Delta lightwell concrete wall repair prep work in progress - Alpha lightwell concrete wall repairs in progress
Exterior RehabilitationJE DUNN I TREANORHL ARCHITECTS I ADG
JANUARY 2019
1503
9DB
MON
THLY
CON
STRU
CTIO
N PR
OGRE
SS R
EPOR
T
4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104 I P 405.302.4500 I WWW.JEDUNN.COM
RETURNS TO TABLE OF CONTENTSCLICK HERE
Safety:The safety of our workforce and the general public during the course of construction is the most import-ant task that we must deliver. To that end, every craftsmen involved with the project receives a detailed project orientation, and prior to performing any task, the teams develop detailed task specific work plans. These work plans are often called Job Site Analysis (JSA) and assist project teams with analyzing different hazards associated with each work activity prior to beginning work.
Exterior RehabilitationJE DUNN I TREANORHL ARCHITECTS I ADG
JANUARY 2019
Safety Data and Metrics
Orientations Performed through 01.31.19 665
First Aid Incidents for the month of January 0
Recordable Incidents for the month of January 0
Trade Partner Incidents for the month of January 1*
Total Man-Hours for the month of Jan. (hrs.) 6,111
Total Project Man-Hours (hrs.) 177,522
*During the month of January a trade partner had a worker that scraped his hand on a sharpening tool. The worker was wearing
his gloves at the time of the incident as well as his personal protective equipment.
1503
9DB
MON
THLY
CON
STRU
CTIO
N PR
OGRE
SS R
EPOR
T
4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104 I P 405.302.4500 I WWW.JEDUNN.COM
RETURNS TO TABLE OF CONTENTSCLICK HERE
JANUARY 2019 Exterior RehabilitationJE DUNN I TREANORHL ARCHITECTS I ADG
We recently completely another round of rigging training for our exterior restoration trade partners and our roofing crews. This rigging training included using virtual videos to learn proper hand signals as well as actual training on-site using the tower crane. Proper rigging training is important to ensure all materials that are being hoisted are secured properly before being lifted into the air.
Safety Spotlight
1503
9DB
MON
THLY
CON
STRU
CTIO
N PR
OGRE
SS R
EPOR
T
4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104 I P 405.302.4500 I WWW.JEDUNN.COM
RETURNS TO TABLE OF CONTENTSCLICK HERE
JANUARY 2019 Exterior RehabilitationJE DUNN I TREANORHL ARCHITECTS I ADG
Copper Re-roofing Update
Below Photo No. 1 shows a portion of the existing 1x6 wood decking that has had to be replaced on the south wing. This particular section is downslope from the southeast skylights. Photo No. 2 shows the installation of new 1x6 wood decking and plywood.
The following ZFI roof reports document the steps we are taking to make repairs of the existing substrate and also documents an unforeseen anchorage condition at the southeast and southwest gutterways.
Photo No. 1 Photo No. 2
ZFI Engineering Co.
8411 S. Walker Ave.
OKC, OK 73139
Ph: 405.634.3393
Fx: 405.634.6414
www.zfiengr.com
RoofRepairWalk#1(11‐1‐2018)–PreliminaryInformation
Location: South End of Golf Elevation Gutterway (Backside of Parapet) GeneralComments: Existing Deformed Bar Anchors were discovered at the east end of the stone at the southern terminus of the gutterway. They occurred in immediate proximity to a pronounced crack in the limestone. Additional details and recommendations are forthcoming regarding how to treat the anchors and cracking. Mock‐upDiscussion Portions of the list of sleeper replacements/repairs and concrete fill patching below will serve as the mock-ups for their respective repair types. Additional comments in the list below.
Deformed Bar Anchors
Cramp Anchors
Cracked Stone
Roof Repair Walk #1-Preliminary Memo ZFI Project #: 15071-01 November 1, 2018 Page 2 of 3
Location: Golf Elevation and India Elevation Gutterways RepairComments: Damaged or Rotted Sleepers in existing concrete fill. Replace sleepers from 2” to 3” above rotted area down the slope to the termination of the sleeper at the back of the parapet wall. Any concrete fill damaged as part of sleeper repair should be repaired per drawings. Repair list is as follows (sleepers numbered from the south end of the gutterway moving north): GolfElevation IndiaElevation1-4 1-46-10 7-1613-15 1820**, 21-27, 28* 2031-32 2134-36 25-2839 34-38*Mock-up for sleeper repair from damaged area down to parapet wall ** Mock-up for isolated sleeper repair (do NOT repair entire length to wall)
Roof Repair Walk #1-Preliminary Memo ZFI Project #: 15071-01 November 1, 2018 Page 3 of 3
Location: Golf Elevation and India Elevation Gutterways RepairComments: Concrete fill repair (Type 6 per SS003). Perform mock-up repairs on the north side of sleeper #27 on Golf side and both sides as necessary next to sleeper #15 on Golf side.
ZFI Engineering Co.
8411 S. Walker Ave.
OKC, OK 73139
Ph: 405.634.3393
Fx: 405.634.6414
www.zfiengr.com
RoofRepairWalk#2(12‐21‐2018)–DeckingEvaluation
India Slope of Repair Walk #2
Location: South End of South Wing (Gamma and India slopes) GeneralComments: The purpose of this walk was to evaluate the condition of the first expanse of exposed wood decking. At the time of the visit, a significant portion of the south half of the south wing had had the existing copper roofing and plywood underlayment removed. This exposed the 1x6 existing decking for evaluation. Removal of tar paper (between the decking and the plywood) was on-going. The walk consisted of marking (with orange paint) those specific decking boards that needed to be replaced and also general areas of decking that needed replacement. JEDunn was tasked with quantifying the total amount of replaced decking in this walk. Isolated locations requiring additional attachment using Aggre-gator concrete anchors were also noted. Existing nails that had popped up should be driven flush with the decking or supplemented with new nails per the repair documents.
Roof Repair Walk #2 ZFI Project #: 15071-01 December 21, 2018 Page 2 of 6
RepairDiscussion Portions of the decking had been removed in isolated locations and exposed the wood sleepers and concrete fill below. This was primarily at the ridge and at portions of the area that tied into the gutterway behind the east and west parapets. Demolished sleepers will be repaired prior to decking repairs.
Demo’d decking and sleepers @ ridge
Rotted decking at bottom of India Elevation Slope
Roof Repair Walk #2 ZFI Project #: 15071-01 December 21, 2018 Page 3 of 6
Decking appeared to be 1x6 material (~3/4” thick). In general, the decking was in good condition. Isolated areas of rot were encountered (the aforementioned ridge demo location and at the gutterways both pictured above). Split boards were observed in various locations and were typically required to be replaced between sleepers. Splits generally followed the length of the board and tended to originate at nail heads. Occasionally entire lengths of board were called for replacement due to extents of the splits.
Overcutting of the plywood also damaged some decking boards, requiring replacement or additional attachment. All efforts should be made during future demolition operations to avoid overcutting the plywood and damaging the existing decking. Based on this evaluation, there is a high likelihood that damaged decking will be in isolated locations only.
Split boards, typically thru nailhead
Overcut requiring additional attachment of decking to concrete below.
Roof Repair Walk #2 ZFI Project #: 15071-01 December 21, 2018 Page 4 of 6
Some small areas of rot/decay were noted along the limestone at the south edge of the roof. This appeared to be the result of the transition detail between the copper and the limestone at this location.
The following photos are representative examples of the decking repairs noted in the field.
Rotted decking along copper/limestone transition at south end of roof
Decking to be replaced (painted lines).
Additional attachment to sleepers or concrete fill below (painted dots)
Roof Repair Walk #2 ZFI Project #: 15071-01 December 21, 2018 Page 5 of 6
Repairs at south end of Gamma Elevation Slope
Repairs at south end of India Elevation Slope
Decking to be replaced, typ.
Additional attachment to sleepers or concrete fill below
Roof Repair Walk #2 ZFI Project #: 15071-01 December 21, 2018 Page 6 of 6
Extent of repairs on Gamma Slope
RepairComments: The following repair totals were determined by JEDunn personnel. GolfElevation IndiaElevation
121 linear feet of decking repair
168 linear feet of decking repair
24 anchor locations
4 anchor locations
Decking and sleeper repairs should be performed per the documents for ASI 016.
1503
9DB
MON
THLY
CON
STRU
CTIO
N PR
OGRE
SS R
EPOR
T
4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104 I P 405.302.4500 I WWW.JEDUNN.COM
RETURNS TO TABLE OF CONTENTSCLICK HERE
JANUARY 2019 Exterior RehabilitationJE DUNN I TREANORHL ARCHITECTS I ADG
Progress Photos & Field Reports
The photos and field reports attached in the subsequent pages represent progress photos taken during the month of January for the Oklahoma State Capitol Exterior Restoration project.
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 113 - 2018_01-02.docx
Page 1 of 8
FIELD OBSERVATION REPORT REPORT NO: 113 DATE: 1/2/2019
TIME: 1:15 - 2:00 PM DAY OF WEEK: Wednesday
OWNER: OMES TEMP. RANGE: Upper 20s
PROJECT: Oklahoma Capitol Restoration - Exterior Rehabilitation
CAP PROJECT NO: 15039DB
JE DUNN PROJECT NO: 15025800
ADG PROJECT NO: 15-007
TREANORHL PROJECT NO: HP 15.007.00B
ZFI PROJECT NO: 15071-01
ALVINE PROJECT NO: 2014-4286
SRB PROJECT NO: 114801
WEATHER: Clear Overcast Rain Snow Cold
Warm Hot Foggy Windy Ice Other _________
SITE CONDITIONS: Clear Dusty Muddy Other ______________________
PERSONS CONTACTED: None
WORK OBSERVED:
Light fixture installation progressing on east elevation of east wing (Echo).
Door installation progressing on east elevation of east wing (Echo).
Concrete installation progressing at tunnel at circle drive.
Waterproofing installation progressing at tunnel at Lincoln Boulevard.
Roof work progressing on east elevation of south wing (Golf).
Handrail installation progressing at upper stairs at South Plaza.
Roof work progressing on west elevation of south wing (India).
Electrical equipment installation progressing adjacent to ramp at South Plaza.
Scaffold removal progressing on south elevation of west wing (Juliette).
Cast iron frame painting progressing on north elevation of west wing (Lima).
Window component installation progressing on north elevation of west wing (Lima).
Sealant installation progressing at windows on north elevation of west wing (Lima).
ITEMS DISCUSSED:
None
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 113 - 2018_01-02.docx
Page 2 of 8
ACTION REQUIRED:
Sand washed out at concrete sidewalk between ramp and Door 101 due to recent rains. (JE Dunn)
Trench drain grate rusted at north portion of West Plaza. (Streets)
ITEMS TO VERIFY:
None
REMARKS:
None
OBSERVED BY: Peter Breninger (ADG)
COPIES TO: Bobby Snyder (JE Dunn), Geoff Johnson (JE Dunn), Heath Glenn (JE Dunn), Lindsey Ross
(JE Dunn), Lynnsee Boyse (JE Dunn), Mark Maska (JE Dunn), Victor Mendoza (JE Dunn),
JC Witcher (ADG), Robert Meek (ADG), Amelia Hudspeth (TreanorHL), Julia Manglitz
(TreanorHL), Kelsey Liu (TreanorHL), Todd Renyer (TreanorHL), Vance Kelley
(TreanorHL), Mike Thompson (ZFI), Andy Wiese (Alvine), Ed Kongs (Alvine), Sam
Haberman (Alvine), Steve Alvine (Alvine), Gary Noland (Smith Roberts Baldischwiler)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 113 - 2018_01-02.docx
Page 3 of 8
Temporary guardrail in place at roof parapet on east elevation of north wing (Charlie)
Light fixtures in place on granite pedestals on east elevation of east wing (Echo)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 113 - 2018_01-02.docx
Page 4 of 8
Door 104 installation progress on east elevation of east wing (Echo)
Concrete sidewalk and drive progress at tunnel at circle drive
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 113 - 2018_01-02.docx
Page 5 of 8
Waterproofing installation in progress at tunnel at Lincoln Boulevard
Handrail installation progress at upper stair at South Plaza
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 113 - 2018_01-02.docx
Page 6 of 8
Electrical equipment installation progress on north side of ramp at South Plaza
Scaffold removal in progress down to fourth floor on south elevation of west wing (Juliette)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 113 - 2018_01-02.docx
Page 7 of 8
Cast iron frame painting progress at second floor window on north elevation of west wing (Lima)
Window component installation progress on north elevation of west wing (Lima)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 113 - 2018_01-02.docx
Page 8 of 8
Sand washed out at sidewalk on west elevation of south wing (India) due to recent rains.
Cast iron trench drain grate rusted at West Plaza.
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 114 - 2019_01-08.docx
Page 1 of 12
FIELD OBSERVATION REPORT REPORT NO: 114 DATE: 1/8/2019
TIME: 10:45 - 11:45 AM DAY OF WEEK: Tuesday
OWNER: OMES TEMP. RANGE: Upper 40s
PROJECT: Oklahoma Capitol Restoration - Exterior Rehabilitation
CAP PROJECT NO: 15039DB
JE DUNN PROJECT NO: 15025800
ADG PROJECT NO: 15-007
TREANORHL PROJECT NO: HP 15.007.00B
ZFI PROJECT NO: 15071-01
ALVINE PROJECT NO: 2014-4286
SRB PROJECT NO: 114801
WEATHER: Clear Overcast Rain Snow Cold
Warm Hot Foggy Windy Ice Other _________
SITE CONDITIONS: Clear Dusty Muddy Other ______________________
PERSONS CONTACTED: None
WORK OBSERVED:
Retaining wall demolition progressing at northeast portion of site.
Backfill progressing at tunnel at Lincoln Boulevard.
Gutter way work progressing at roof on east elevation of south wing (Golf).
Roof drain piping installation progressing at south wing.
Door installation progressing on south elevation of south wing (Hotel).
Door restoration progressing on south elevation of south wing (Hotel).
Gutter way work progressing at roof on west elevation of south wing (India).
Door installation progressing on west elevation of south wing (India).
Scaffold removal progressing on south elevation of west wing (Juliette).
Handrail installation progressing at West Plaza.
Cast iron frame painting progressing on north elevation of west wing (Lima).
Window component installation progressing on north elevation of west wing (Lima).
Sealant installation progressing at windows on north elevation of west wing (Lima).
Copper installation progressing at gutter on north elevation of west wing (Lima).
Gutter installation progressing at backside of parapet on north elevation of west wing (Lima).
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 114 - 2019_01-08.docx
Page 2 of 12
ITEMS DISCUSSED:
Reviewed gasketing for double doors. Gasketing to be trimmed with straight edge so that doors do
not catch on each other.
Reviewed paint color and finish at interior side of doors and frames of Doors 201, 202, 203, and 204.
Interior side of Doors 202, 203, and 204 and hardware of Doors 202 and 204 to be painted Statuary
Bronze to match color of Door 203. Door 201 paint color and finish to remain.
ACTION REQUIRED:
None
ITEMS TO VERIFY:
None
REMARKS:
OAC Meeting occurred prior to the site visit in the jobsite trailers.
Interior/Exterior Coordination Meeting occurred prior to the site visit in Manhattan’s jobsite office.
OBSERVED BY: Peter Breninger (ADG)
COPIES TO: Bobby Snyder (JE Dunn), Brandon Marriott (JE Dunn), Chris Savoie (JE Dunn), Geoff
Johnson (JE Dunn), Jon Whaley (JE Dunn), Lindsey Ross (JE Dunn), Lynnsee Boyse (JE
Dunn), Mark Maska (JE Dunn), Victor Mendoza (JE Dunn), JC Witcher (ADG), Robert
Meek (ADG), Amelia Hudspeth (TreanorHL), Julia Manglitz (TreanorHL), Kelsey Liu
(TreanorHL), Todd Renyer (TreanorHL), Vance Kelley (TreanorHL), Mike Thompson (ZFI),
Andy Wiese (Alvine), Ed Kongs (Alvine), Sam Haberman (Alvine), Steve Alvine (Alvine),
Gary Noland (Smith Roberts Baldischwiler)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 114 - 2019_01-08.docx
Page 3 of 12
Temporary guardrail installation progress at west and north elevations of north wing (Alpha and Bravo)
Retaining wall demolition in progress at northeast portion of site
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 114 - 2019_01-08.docx
Page 4 of 12
Backfill progress over tunnel at Lincoln Boulevard
Framing in progress at gutter at roof on east elevation of south wing (Golf)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 114 - 2019_01-08.docx
Page 5 of 12
Roof drain piping progress on east elevation of south wing (Golf)
Protection in place under lower skylight to catch debris at south wing roof
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 114 - 2019_01-08.docx
Page 6 of 12
Door 203 installation progress on south elevation of south wing (Hotel)
Door 201 restoration progress on exterior side on south elevation of south wing (Hotel)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 114 - 2019_01-08.docx
Page 7 of 12
Door 201 faux finish and hardware installation progress on interior side on south elevation of south wing
(Hotel)
Roof drain piping progress on west elevation of south wing (India)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 114 - 2019_01-08.docx
Page 8 of 12
Plywood installation in progress at gutter way on west elevation of south wing (India). Deck repairs at
roof shown adjacent to gutter way.
Copper installation in progress at roof drain on west elevation of south wing (India)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 114 - 2019_01-08.docx
Page 9 of 12
Door 101 installation in progress on west elevation of south wing (India)
Scaffold removal in progress down to third floor on south elevation of west wing (Juliette)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 114 - 2019_01-08.docx
Page 10 of 12
Handrail installation in progress at south stair at West Plaza
Cast iron frame painting progress at window on north elevation of west wing (Lima)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 114 - 2019_01-08.docx
Page 11 of 12
Window component installation progress at second floor on north elevation of west wing (Lima)
Sealant installation in progress at third floor window on north elevation of west wing (Lima)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 114 - 2019_01-08.docx
Page 12 of 12
Underlayment installation progress at backside of parapet at gutter on north elevation of west wing
(Lima).
Doors and hardware of Doors 202 and 204 to be painted Statuary Bronze to match color of Door 203.
Door 201 and 203 color and finish to remain as is.
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 115 - 2019_01-15.docx
Page 1 of 14
FIELD OBSERVATION REPORT REPORT NO: 115 DATE: 1/15/2019
TIME: 1:00 - 2:15 PM DAY OF WEEK: Tuesday
OWNER: OMES TEMP. RANGE: Lower 50s
PROJECT: Oklahoma Capitol Restoration - Exterior Rehabilitation
CAP PROJECT NO: 15039DB
JE DUNN PROJECT NO: 15025800
ADG PROJECT NO: 15-007
TREANORHL PROJECT NO: HP 15.007.00B
ZFI PROJECT NO: 15071-01
ALVINE PROJECT NO: 2014-4286
SRB PROJECT NO: 114801
WEATHER: Clear Overcast Rain Snow Cold
Warm Hot Foggy Windy Ice Other _________
SITE CONDITIONS: Clear Dusty Muddy Other ______________________
PERSONS CONTACTED: Brad Slone, Chris Savoie, Geoff Johnson, James Shaw, Lindsey Ross, Lynnsee
Boyse, Mark Maska, Victor Mendoza - JE Dunn
Mike Thompson - ZFI
WORK OBSERVED:
Door installation progressing on west elevation of north wing (Alpha).
Retaining wall demolition progressing at northeast portion of site.
Mow strip installation progressing at northeast portion of site.
Door installation progressing on east elevation of east wing (Echo).
Concrete progressing at Lincoln Boulevard portion of tunnel.
Waterproofing installation progressing at east portion of tunnel.
Work progressing at roof on east elevation of south wing (Golf).
Deck demolition progressing at roof on west elevation of south wing (India).
Concrete fill demolition progressing at roof on west elevation of south wing (India).
Plywood installation progressing at roof on west elevation of south wing (India).
Door installation progressing on west elevation of south wing (India).
Electrical equipment installation progressing adjacent to ramp at South Plaza.
Scaffold removal progressing on south elevation of west wing (Juliette).
Handrail installation progressing at West Plaza.
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 115 - 2019_01-15.docx
Page 2 of 14
Cast iron frame painting progressing on north elevation of west wing (Lima).
Window component installation progressing on north elevation of west wing (Lima).
Sealant installation progressing at windows on north elevation of west wing (Lima).
Cast iron frame repairs progressing on north elevation of west wing (Lima).
Copper installation progressing at gutter on north elevation of west wing (Lima).
ITEMS DISCUSSED:
Meeting to review options for retaining wall over tunnel.
Reviewed options for sleeves in retaining walls for irrigation and lighting.
Reviewed location of retaining walls adjacent to the East Plaza. Retaining walls to line up with flat
portion of stone on battlement wall.
ACTION REQUIRED:
Spot elevations of area at tunnel to be provided to determine design of retaining wall. (JE Dunn)
Proposed locations of site lighting to be provided to determine locations of sleeves in retaining walls.
(ADG)
ITEMS TO VERIFY:
None
REMARKS:
None
OBSERVED BY: Peter Breninger (ADG)
COPIES TO: Bobby Snyder (JE Dunn), Brandon Marriott (JE Dunn), Chris Savoie (JE Dunn), Geoff
Johnson (JE Dunn), Jon Whaley (JE Dunn), Lindsey Ross (JE Dunn), Lynnsee Boyse (JE
Dunn), Mark Maska (JE Dunn), Victor Mendoza (JE Dunn), JC Witcher (ADG), Robert
Meek (ADG), Amelia Hudspeth (TreanorHL), Julia Manglitz (TreanorHL), Kelsey Liu
(TreanorHL), Todd Renyer (TreanorHL), Vance Kelley (TreanorHL), Mike Thompson (ZFI),
Andy Wiese (Alvine), Ed Kongs (Alvine), Sam Haberman (Alvine), Steve Alvine (Alvine),
Gary Noland (Smith Roberts Baldischwiler)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 115 - 2019_01-15.docx
Page 3 of 14
Temporary guardrail installation progress at west and north elevations of north wing (Alpha and Bravo)
Door 001 installation progress on west elevation of north wing (Alpha)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 115 - 2019_01-15.docx
Page 4 of 14
Retaining wall demolition progress at northeast portion of site
Retaining wall demolition progress at northeast portion of site
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 115 - 2019_01-15.docx
Page 5 of 14
Retaining wall demolition progress at northeast portion of site
Doors 103, 104, and 105 installation progress on east elevation of east wing (Echo)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 115 - 2019_01-15.docx
Page 6 of 14
Concrete drive and road in place over tunnel at Lincoln Boulevard. Lincoln Boulevard open to all lanes of
traffic.
Waterproofing installation in progress at east portion of tunnel
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 115 - 2019_01-15.docx
Page 7 of 14
Temporary protection in place at gutter way, skylights, and south portion of roof on east elevation of
south wing (Golf)
Deck demolition in progress at roof on west elevation of south wing (India)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 115 - 2019_01-15.docx
Page 8 of 14
Concrete fill demolition in progress at roof on west elevation of south wing (India)
Plywood installation in progress at roof on west elevation of south wing (India)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 115 - 2019_01-15.docx
Page 9 of 14
Measuring for copper in progress on west elevation of south wing (India)
Temporary protection in place at skylights of roof on west elevation of south wing (India)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 115 - 2019_01-15.docx
Page 10 of 14
Door 101 installation in progress on west elevation of south wing (India)
Sand bags placed adjacent to the sidewalk to prevent washout at the southwest portion of the site
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 115 - 2019_01-15.docx
Page 11 of 14
Wiring pulling and connection in progress at electrical equipment adjacent to ramp at South Plaza
Scaffold removal progress down to second floor window on south elevation of west wing (Juliette)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 115 - 2019_01-15.docx
Page 12 of 14
Handrail installation progress at south stair at West Plaza
Handrail installation progress at north stair at West Plaza
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 115 - 2019_01-15.docx
Page 13 of 14
Cast iron frame painting progress at second floor window on north elevation of west wing (Lima)
Window component installation in progress at first floor window on north elevation of west wing (Lima)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 115 - 2019_01-15.docx
Page 14 of 14
Cast iron frame repair progress at fifth floor window on north elevation of west wing (Lima)
Copper installation in progress at gutter on north elevation of west wing (Lima)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 116 - 2019_01-22.docx
Page 1 of 12
FIELD OBSERVATION REPORT REPORT NO: 116 DATE: 1/22/2019
TIME: 10:00 - 10:45 AM DAY OF WEEK: Tuesday
OWNER: OMES TEMP. RANGE: Lower 50s
PROJECT: Oklahoma Capitol Restoration - Exterior Rehabilitation
CAP PROJECT NO: 15039DB
JE DUNN PROJECT NO: 15025800
ADG PROJECT NO: 15-007
TREANORHL PROJECT NO: HP 15.007.00B
ZFI PROJECT NO: 15071-01
ALVINE PROJECT NO: 2014-4286
SRB PROJECT NO: 114801
WEATHER: Clear Overcast Rain Snow Cold
Warm Hot Foggy Windy Ice Other _________
SITE CONDITIONS: Clear Dusty Muddy Other ______________________
PERSONS CONTACTED: Brandon Marriott, Chris Savoie, Jon Whaley, Lindsey Ross, Lynnsee Boyse, Mark
Maska, Victor Mendoza - JE Dunn
WORK OBSERVED:
Retaining wall work progressing at northeast portion of site.
Mow strip work progressing at northeast portion of site.
Retaining wall work progressing at southeast portion of site.
Concrete work progressing at east parking lot.
Waterproofing installation progressing at east portion of tunnel.
Roof drain piping installation progressing at south wing.
Door installation progressing on west elevation of south wing (India).
Railing installation progressing at ramp at South Plaza.
Electrical equipment installation progressing adjacent to ramp at South Plaza.
Scaffold removal progressing on south elevation of west wing (Juliette).
Handrail installation progressing at West Plaza.
Sealant installation progressing at windows on north elevation of west wing (Lima).
Window component installation progressing on north elevation of west wing (Lima).
Cast iron frame repairs progressing on north elevation of west wing (Lima).
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 116 - 2019_01-22.docx
Page 2 of 12
Copper installation progressing at gutter on north elevation of west wing (Lima).
ITEMS DISCUSSED:
None
ACTION REQUIRED:
None
ITEMS TO VERIFY:
None
REMARKS:
OAC Meeting occurred prior to the site visit in the jobsite trailers.
OBSERVED BY: Peter Breninger (ADG)
COPIES TO: Bobby Snyder (JE Dunn), Brandon Marriott (JE Dunn), Chris Savoie (JE Dunn), Geoff
Johnson (JE Dunn), Jon Whaley (JE Dunn), Lindsey Ross (JE Dunn), Lynnsee Boyse (JE
Dunn), Mark Maska (JE Dunn), Victor Mendoza (JE Dunn), JC Witcher (ADG), Robert
Meek (ADG), Amelia Hudspeth (TreanorHL), Julia Manglitz (TreanorHL), Kelsey Liu
(TreanorHL), Todd Renyer (TreanorHL), Vance Kelley (TreanorHL), Mike Thompson (ZFI),
Andy Wiese (Alvine), Ed Kongs (Alvine), Sam Haberman (Alvine), Steve Alvine (Alvine),
Gary Noland (Smith Roberts Baldischwiler)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 116 - 2019_01-22.docx
Page 3 of 12
Platform demolished in light well on west elevation of north wing (Alpha)
Concrete demolished at base of stairs at North Plaza
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 116 - 2019_01-22.docx
Page 4 of 12
Retaining wall excavation and grading in progress at northeast portion of site
Mow strip formwork installation progress at northeast portion of site adjacent to balustrade
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 116 - 2019_01-22.docx
Page 5 of 12
Retaining wall excavation and grading progress at southeast portion of site
Concrete pour in progress for curb and gutter at east parking lot
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 116 - 2019_01-22.docx
Page 6 of 12
Formwork in place for concrete pour at east parking lot
Waterproofing covered over at east portion of tunnel
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 116 - 2019_01-22.docx
Page 7 of 12
Roof drain piping progress on east elevation of south wing (Golf)
Plywood up in place of Door 201 on south elevation of south wing (Hotel). Door was removed by OMES
and they attempted to reinstall it, then the door fell. The door is not meant to be operated. A to-be-
determined component will be added to the door so that people know it is not to be used.
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 116 - 2019_01-22.docx
Page 8 of 12
Door 101 installation in progress on west elevation of south wing (India). The historic light fixtures have
also been installed at the granite pedestals adjacent to Door 101.
Railing installation in progress at ramp at South Plaza.
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 116 - 2019_01-22.docx
Page 9 of 12
Railing installation in progress at ramp at South Plaza
Wiring connection in progress at electrical equipment adjacent to ramp at South Plaza
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 116 - 2019_01-22.docx
Page 10 of 12
Scaffold removal progress down to second floor windows on south elevation of west wing (Juliette)
Handrail installation progress at north stair at West Plaza
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 116 - 2019_01-22.docx
Page 11 of 12
Sealant installation in progress at fifth floor window on west portion on north elevation of west wing
(Lima)
Window component installation in progress at fifth floor window on east portion on north elevation of
west wing (Lima)
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 116 - 2019_01-22.docx
Page 12 of 12
Cast iron frame repair in progress at third floor window on east portion on north elevation of west wing
(Lima)
Copper installation progress at gutter on north elevation of west wing (Lima)
C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.144 - 2019_01_09.docx Page 1 of 5
FIELD OBSERVATION REPORT REPORT NO: 144 DATE: 01/09/2019 TIME: 11:00 am – 4:30 pm DAY OF WEEK: Wednesday OWNER: OMES TEMP. RANGE: Hi 40s – Lo 50s PROJECT: Oklahoma Capitol Restoration - Exterior Rehabilitation CAP PROJECT NO: 15039DB JE DUNN PROJECT NO: 15025800 ADG PROJECT NO: 15-007 TREANOR PROJECT NO: HP 15.007.00B ZFI PROJECT NO: 15071-01 ALVINE PROJECT NO: 2014-4286 SRB PROJECT NO: 114801 WEATHER: Clear Overcast Rain Snow Cold Warm Hot Foggy Windy Ice Other ___ SITE CONDITIONS: Clear Dusty Muddy Other _________________ PERSONS CONTACTED:
Lynnsee Boyse, Mark Maska, Lindsey Ross, Geoffrey Johnson, Victor Mendoza, Jon Whaley, Brandon Marriott, Chris Savoie (JE Dunn) Eddie Pait, Jerry Barker (Baker Roofing) Lukasz Lesniak (Mark1) Trait Thompson, Doug Kellogg (OMES) Peter Breninger, JC Witcher (ADG) Mike Thompson (ZFI)
WORK OBSERVED:
Gutterway mockup in progress – sheet metal trial layout.
Gutterway framing is complete.
Removal and replacement of over decking has started on the west slope of the south wing.
ITEMS DISCUSSED:
Reglets and coordination with Mark1, particularly the at the pediment.
South wing skylight details and integration with panel installation: Reviewed on ground mockup created by Baker and Ornametals. Connections between top and sidewalls are all acceptable, corners that have blind rivets shall have closed end rivets. Continued discussion about the impact the upslope and downslope details have on the panel layout. (Baker)
C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.144 - 2019_01_09.docx Page 2 of 5
ACTION REQUIRED:
Discuss clip spacing with structural. (TreanorHL)
Trial panel layouts with the skylight upslope and downslope details (TreanorHL) and with proposed changes to those details (Baker). (Baker, TreanorHL)
ITEMS TO VERIFY:
REMARKS:
Appreciation luncheon.
OBSERVED BY: Julia Manglitz, Associate Principal (TreanorHL) COPIES TO: David Mihm (OMES), Doug Kellogg (OMES), Mike Jones (OMES), Trait Thompson
(OMES), Duane Mass (MAI), Jason Cady (MAI), Matthew Radcliffe (MAI), Mark Maska (JE Dunn), Bobby Snyder (JE Dunn), Lindsey Ross (JE Dunn), Lynnsee Boyse (JE Dunn), Geoffrey Johnson (JE Dunn), JC Witcher (ADG), Robert Meek (ADG), Julia Manglitz (TreanorHL), Todd Renyer (TreanorHL), Vance Kelley (TreanorHL), Mike Thompson (ZFI), Steve Ford (ZFI), Andy Wiese (Alvine), Ed Kongs (Alvine), Sam Haberman (Alvine), Steve Alvine (Alvine), Gary Noland (Smith Roberts Baldischwiler)
Gutterway mockup coming out of the roof drain.
C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.144 - 2019_01_09.docx Page 3 of 5
Gap at slope change should be caulked with polyurethane sealant. Check compatibility with both
underlayment materials
Panel clips are specified for use with overdecking to keep transitions between panels spaced and edges
level. All fastners need to be countersunk.
C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.144 - 2019_01_09.docx Page 4 of 5
Side of lower skylight concrete curb exposed by removal of existing copper and substrate.
Location of gutterway cricket ridge is correct, however the blocking needs to extend and bevel cleanly
into the main slope.
C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.144 - 2019_01_09.docx Page 5 of 5
Skylight downslope outside corner preliminary mockup.
Sklyight upslope corner preliminary mockup.
Skylight cricket preliminary mockup.
C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.144 - 2019_01_10.docx Page 1 of 2
FIELD OBSERVATION REPORT REPORT NO: 145 DATE: 01/10/2019 TIME: 8:00 am – 10:00 am DAY OF WEEK: Thursday OWNER: OMES TEMP. RANGE: Lo 40s – Mid 40s PROJECT: Oklahoma Capitol Restoration - Exterior Rehabilitation CAP PROJECT NO: 15039DB JE DUNN PROJECT NO: 15025800 ADG PROJECT NO: 15-007 TREANOR PROJECT NO: HP 15.007.00B ZFI PROJECT NO: 15071-01 ALVINE PROJECT NO: 2014-4286 SRB PROJECT NO: 114801 WEATHER: Clear Overcast Rain Snow Cold Warm Hot Foggy Windy Ice Other ___ SITE CONDITIONS: Clear Dusty Muddy Other _________________ PERSONS CONTACTED:
Lynnsee Boyse, Bobby Snyder, Lindsey Ross, Jon Whaley, Brandon Marriott (JE Dunn) WORK OBSERVED:
ITEMS DISCUSSED:
Overview discussion of copper roofing scope and construction sequence considerations with Jon Whaley and Brandon Marriott, additional JE Dunn personnel for the roofing.
ACTION REQUIRED:
ITEMS TO VERIFY:
REMARKS:
C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.144 - 2019_01_10.docx Page 2 of 2
OBSERVED BY: Julia Manglitz, Associate Principal (TreanorHL) COPIES TO: David Mihm (OMES), Doug Kellogg (OMES), Mike Jones (OMES), Trait Thompson
(OMES), Duane Mass (MAI), Jason Cady (MAI), Matthew Radcliffe (MAI), Mark Maska (JE Dunn), Bobby Snyder (JE Dunn), Lindsey Ross (JE Dunn), Lynnsee Boyse (JE Dunn), Geoffrey Johnson (JE Dunn), JC Witcher (ADG), Robert Meek (ADG), Julia Manglitz (TreanorHL), Todd Renyer (TreanorHL), Vance Kelley (TreanorHL), Mike Thompson (ZFI), Steve Ford (ZFI), Andy Wiese (Alvine), Ed Kongs (Alvine), Sam Haberman (Alvine), Steve Alvine (Alvine), Gary Noland (Smith Roberts Baldischwiler)
1503
9DB
MON
THLY
CON
STRU
CTIO
N PR
OGRE
SS R
EPOR
T
4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104 I P 405.302.4500 I WWW.JEDUNN.COM
RETURNS TO TABLE OF CONTENTSCLICK HERE
JANUARY 2019 Exterior RehabilitationJE DUNN I TREANORHL ARCHITECTS I ADG
Phasing & Schedule Attachments: The following documents are included in the subsequent pages:
- Site Phasing Plan - Site Utilization Plan - Six (6) Week Look Ahead Schedule
1503
9DB
MON
THLY
CON
STRU
CTIO
N PR
OGRE
SS R
EPOR
T
4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104 I P 405.302.4500 I WWW.JEDUNN.COM
RETURNS TO TABLE OF CONTENTSCLICK HERE
JANUARY 2019 Exterior RehabilitationJE DUNN I TREANORHL ARCHITECTS I ADG
Site Phasing Plan:
The site phasing plan is a broad representation of the work flow for the Capitol exterior rehabilitation. Beginning with Alpha (west elevation of the north wing), scaffolding was constructed continuing on to Bravo, Charlie, Delta and Echo. We construct a phase of scaffolding at a time, which is followed by hazardous material removal, window restoration, and stone and lighting repair. As each phase is complet-ed, the scaffolding will be disassembled and reassembled on similar elevations. This site phasing will occur for the duration of the rehabilitation until all work is complete, and the State Capitol is back to its original beauty and functionality.
Trailer Compound
TUNNEL (will continue across Lincoln)
DELTA
FOX TROT
ECHO
KILO
ALPHA
CHARLIE
GOLF
INDIA
HOTEL
JULIETTE
LIMA
BRAVOCOMPLETED
CO
MPLETED
CO
MPLE
TED
COMPLETED
CO
MPLETED
CO
MPLETED
ACTIVE ELEVATIONS
COMPLETED
CO
MPLE
TED
COMPLETED
CO
MPLE
TED
COMPLETED
1503
9DB
MON
THLY
CON
STRU
CTIO
N PR
OGRE
SS R
EPOR
T
4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104 I P 405.302.4500 I WWW.JEDUNN.COM
RETURNS TO TABLE OF CONTENTSCLICK HERE
JANUARY 2019 Exterior RehabilitationJE DUNN I TREANORHL ARCHITECTS I ADG
Site Utilization Plan:
Per our site utilization plan, the JE Dunn trailer compound is the designated area for our staff members,trade partners, and material storage areas. It currently houses four field offices.
Our site fencing is a revolving system that isolates our work area from the public as we move around the Capitol building, helping to ensure a safe work environment.
The gravel lay-down areas are designated paths where machinery, supplies, and equipment are stored and provide a roadway for machinery to move supplies to and from the job site. The gravel will also serve as a protective barrier of the subsurface. Fence gates mark all areas where access can be gained to the job site for material and/or equipmentdeliveries, emergency access, or personnel access. These gates remain closed and are locked every night to ensure a safe work environment.
JED
JED
Activity ID Activity Name RemDur
Start Finish
Oklahoma Legislative SessionsOklahoma Legislative Sessions 85 04-Feb-19 03-Jun-19
.. 85 04-Feb-19 03-Jun-19
.. 85 04-Feb-19 03-Jun-19
CON-30300 2019 Session 85 04-Feb-19* 03-Jun-19
Construction SummaryConstruction Summary 81 26-Feb-18 A 04-Apr-19
.. 81 26-Feb-18 A 04-Apr-19
.. 81 26-Feb-18 A 04-Apr-19
CON-10980 Juliette Facade Repair Duration 17 26-Feb-18 A 30-Jan-19
CON-11000 Lima Facade Repair Duration 81 21-May-18 A 04-Apr-19
ElevationsElevations 59 22-Oct-18 A 04-Apr-19
Juliette- West Wing South FaceJuliette- West Wing South Face 13 12-Nov-18 A 30-Jan-19
ScaffoldScaffold 11 13-Dec-18 A 30-Jan-19
CON-19590 Juliette-Ph 2-Demobilize scaffold and tarp 11 13-Dec-18 A 30-Jan-19
CON-19600 Juliette-Patch scaffold anchor holes 11 13-Dec-18 A 30-Jan-19
InteriorInterior 7 12-Nov-18 A 22-Jan-19
CON-19630 Juliette-Interior Wall Finishes 7 12-Nov-18 A 22-Jan-19
Kilo- West Wing West FaceKilo- West Wing West Face 15 22-Oct-18 A 01-Feb-19
InteriorInterior 15 22-Oct-18 A 01-Feb-19
CON-17830 Kilo-Interior Wall Finishes 15 22-Oct-18 A 01-Feb-19
Lima- West Wing North FaceLima- West Wing North Face 59 30-Nov-18 A 04-Apr-19
ScaffoldScaffold 16 14-Mar-19 04-Apr-19
CON-20170 Lima-Ph 2-Remove temp HVAC in scaffold 1 14-Mar-19 14-Mar-19
CON-20180 Lima-Ph 2-Remove temp power in scaffold 2 14-Mar-19 15-Mar-19
CON-20190 Lima-Ph 2-Demobilize scaffold and tarp 12 18-Mar-19 04-Apr-19
CON-30820 Lima-Ph 2-Scaffold Demobilization Start 0 18-Mar-19
CON-20200 Lima-Patch scaffold anchor holes 1 04-Apr-19 04-Apr-19
InteriorInterior 30 14-Jan-19 A 22-Feb-19
CON-20250 Lima-Remove interior partitions 26 14-Jan-19 A 18-Feb-19
CON-20230 Lima-Interior Wall Finishes 30 14-Jan-19 22-Feb-19
CON-33690 Lima-Deliver Storm Windows 15 14-Jan-19 01-Feb-19
CON-20240 Lima-Interior storm windows 15 04-Feb-19 22-Feb-19
Window FinishesWindow Finishes 31 04-Dec-18 A 25-Feb-19
CON-20540 Lima-Ph 1-Re-install window sashes, panels, and trim 4 04-Dec-18 A 17-Jan-19
CON-32580 Lima-Ph 1-Final Paint Window Frame 7 10-Dec-18 A 22-Jan-19
CON-32590 Lima-Ph 1-Caulk window frames to stone 7 12-Dec-18 A 24-Jan-19
CON-24860 Lima-Ph 2-Re-install window sashes, panels, and trim 22 17-Jan-19 15-Feb-19
CON-20580 Lima-Ph 2-Final Paint Window Frame 20 23-Jan-19 19-Feb-19
CON-20600 Lima-Ph 2-Caulk window frames to stone 20 25-Jan-19 21-Feb-19
CON-20620 Lima-Ph 2-Re-install HVAC louvers 1 22-Feb-19 22-Feb-19
CON-20630 Lima-Window Spray Test 2 22-Feb-19 25-Feb-19
Stone Cleaning & SealantsStone Cleaning & Sealants 9 26-Feb-19 12-Mar-19
CON-20640 Lima-Ph 2-Wash down brick and stone 4 26-Feb-19 04-Mar-19
CON-33830 Lima-Ph 2-Dry Time 5 05-Mar-19 12-Mar-19
Gutter/ParapetGutter/Parapet 30 30-Nov-18 A 25-Feb-19
CON-30140 Lima-Install Metal Wall Panels 30 30-Nov-18 A 22-Feb-19
CON-30050 Lima-Install Underlayment 2 11-Dec-18 A 15-Jan-19
CON-30060 Lima-Install Gutter Liner 25 13-Dec-18 A 15-Feb-19
CON-30120 Lima-Install Hanging Gutter 10 11-Feb-19 22-Feb-19
CON-30150 Lima-Install Metal Wall Panel Trim 7 14-Feb-19 22-Feb-19
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
2019 2
2019 Session
Juliette Facade Repair Duration
Lima Facade Repair Duration
Juliette-Ph 2-Demobilize scaffold and tarp
Juliette-Patch scaffold anchor holes
Juliette-Interior Wall Finishes
Kilo-Interior Wall Finishes
Lima-Ph 2-Remove temp HVAC in scaffold
Lima-Ph 2-Remove temp power in scaffold
Lima-Ph 2-Demobilize scaffold and tarp
Lima-Ph 2-Scaffold Demobilization Start
Lima-Patch scaffold anchor holes
Lima-Remove interior partitions
Lima-Interior Wall Finishes
Lima-Deliver Storm Windows
Lima-Interior storm windows
Lima-Ph 1-Re-install window sashes, panels, and trim
Lima-Ph 1-Final Paint Window Frame
Lima-Ph 1-Caulk window frames to stone
Lima-Ph 2-Re-install window sashes, panels, and trim
Lima-Ph 2-Final Paint Window Frame
Lima-Ph 2-Caulk window frames to stone
Lima-Ph 2-Re-install HVAC louvers
Lima-Window Spray Test
Lima-Ph 2-Wash down brick and stone
Lima-Ph 2-Dry Time
Lima-Install Metal Wall Panels
Lima-Install Underlayment
Lima-Install Gutter Liner
Lima-Install Hanging Gutter
Lima-Install Metal Wall Panel Trim
Remaining Construction
Data Date: 14-Jan-19
Run Date: 22-Jan-19; 08:31
Oklahoma State Capitol Exterior Renovation
Page 1 of 4
Activity ID Activity Name RemDur
Start Finish
CON-30240 Lima-Flood-Test Gutter 1 18-Feb-19 18-Feb-19
CON-30200 Lima-Re-Install Lightning Protection 2 19-Feb-19 20-Feb-19
CON-30170 Lima-Install Lead Tees 1 21-Feb-19 25-Feb-19
Punch & CompletePunch & Complete 15 25-Feb-19 18-Mar-19
CON-30850 Lima-Window Restoration Complete 0 25-Feb-19
CON-22800 Lima Pre-punch 1 26-Feb-19 26-Feb-19
CON-22810 Lima Complete pre-punch list 1 27-Feb-19 27-Feb-19
CON-22820 Lima Punchlist 1 13-Mar-19 13-Mar-19
CON-22830 Lima - Complete punchlist 3 14-Mar-19 18-Mar-19
DoorsDoors 23 24-Jan-19 25-Feb-19
Bravo- North Wing North FaceBravo- North Wing North Face 5 19-Feb-19 25-Feb-19
New Door SequenceNew Door Sequence 5 19-Feb-19 25-Feb-19
CON-27490 Bravo.D106-Install New Frame 2 19-Feb-19 20-Feb-19
CON-27500 Bravo.D106-Install New Door/Hardware 3 21-Feb-19 25-Feb-19
Echo- East Wing East FaceEcho- East Wing East Face 4 24-Jan-19 29-Jan-19
New Door SequenceNew Door Sequence 4 24-Jan-19 29-Jan-19
CON-27730 Echo.D105-Remove Door/Hardware 1 24-Jan-19* 24-Jan-19
CON-27750 Echo.D105-Remove Frame 1 25-Jan-19 25-Jan-19
CON-27760 Echo.D105-Install New Frame 1 28-Jan-19 28-Jan-19
CON-27770 Echo.D105-Install New Door/Hardware 1 29-Jan-19 29-Jan-19
Golf- South Wing West FaceGolf- South Wing West Face 12 01-Feb-19 18-Feb-19
New Door SequenceNew Door Sequence 12 01-Feb-19 18-Feb-19
CON-27820 Golf.D102-Remove Door/Hardware 2 01-Feb-19* 04-Feb-19
CON-27840 Golf.D102-Remove Frame 2 05-Feb-19 06-Feb-19
CON-27850 Golf.D102-Install New Frame 2 07-Feb-19 08-Feb-19
CON-27860 Golf.D102-Install New Door/Hardware 3 11-Feb-19 13-Feb-19
CON-33700 Lightwell-HM Door Frames/Doors (X3) 6 11-Feb-19 18-Feb-19
Kilo- West Wing West FaceKilo- West Wing West Face 8 30-Jan-19 08-Feb-19
New Door SequenceNew Door Sequence 8 30-Jan-19 08-Feb-19
CON-27220 Kilo.D107-Install New Frame 1 30-Jan-19 30-Jan-19
CON-27130 Kilo.D108-Install New Frame 1 31-Jan-19 31-Jan-19
CON-27230 Kilo.D107-Install New Door/Hardware 1 31-Jan-19 31-Jan-19
CON-27140 Kilo.D108-Install New Door/Hardware 1 01-Feb-19 01-Feb-19
CON-27040 Kilo.D109-Install New Frame 1 04-Feb-19 04-Feb-19
CON-27050 Kilo.D109-Install New Door/Hardware 1 05-Feb-19 05-Feb-19
CON-27300 Kilo.D601 & 602 -Remove Frame 1 06-Feb-19 06-Feb-19
CON-27310 Kilo.D601 & 602 -Install New Frame 1 07-Feb-19 07-Feb-19
CON-27320 Kilo.D601 & 602 -Install New Door/Hardware 1 08-Feb-19 08-Feb-19
SiteSite 117 27-Nov-18 A 26-Jun-19
TunnelTunnel 96 17-Dec-18 A 28-May-19
Tunnel RepairsTunnel Repairs 17 15-Jan-19 06-Feb-19
CON-31530 Remove Barriers and Re-Open Lincoln 2 15-Jan-19 16-Jan-19
CON-33380 Remove Temp. Road 3 15-Jan-19 17-Jan-19
CON-31500 Concrete Prep for Sidewalks 2 21-Jan-19 22-Jan-19
CON-31510 Place & Finish Sidewalks 1 23-Jan-19 23-Jan-19
CON-31540 Phase 2 Complete 0 23-Jan-19
CON-31570 Replace Plants, Trees & Sod 7 29-Jan-19 06-Feb-19
CON-33390 Stripings & Markings 2 01-Feb-19 04-Feb-19
Tunnel FinishesTunnel Finishes 96 17-Dec-18 A 28-May-19
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
2019 2
Lima-Flood-Test Gutter
Lima-Re-Install Lightning Protection
Lima-Install Lead Tees
Lima-Window Restoration Complete
Lima Pre-punch
Lima Complete pre-punch list
Lima Punchlist
Lima - Complete punchlist
Bravo.D106-Install New Frame
Bravo.D106-Install New Door/Hardware
Echo.D105-Remove Door/Hardware
Echo.D105-Remove Frame
Echo.D105-Install New Frame
Echo.D105-Install New Door/Hardware
Golf.D102-Remove Door/Hardware
Golf.D102-Remove Frame
Golf.D102-Install New Frame
Golf.D102-Install New Door/Hardware
Lightwell-HM Door Frames/Doors (X3)
Kilo.D107-Install New Frame
Kilo.D108-Install New Frame
Kilo.D107-Install New Door/Hardware
Kilo.D108-Install New Door/Hardware
Kilo.D109-Install New Frame
Kilo.D109-Install New Door/Hardware
Kilo.D601 & 602 -Remove Frame
Kilo.D601 & 602 -Install New Frame
Kilo.D601 & 602 -Install New Door/Hardware
Remove Barriers and Re-Open Lincoln
Remove Temp. Road
Concrete Prep for Sidewalks
Place & Finish Sidewalks
Phase 2 Complete
Replace Plants, Trees & Sod
Stripings & Markings
Remaining Construction
Data Date: 14-Jan-19
Run Date: 22-Jan-19; 08:31
Oklahoma State Capitol Exterior Renovation
Page 2 of 4
Activity ID Activity Name RemDur
Start Finish
CON-32740 Waterproof Slab/Epoxy Coating 3 17-Dec-18 A 16-Jan-19
CON-32750 Frame Walls 15 17-Jan-19 06-Feb-19
CON-32770 OH Rough-In 10 17-Jan-19 30-Jan-19
CON-32780 Sump Pump 5 17-Jan-19 23-Jan-19
CON-32760 In-Wall Rough-In/Wood Bloc king 10 31-Jan-19 13-Feb-19
CON-32790 Frame Ceilings 15 07-Feb-19 27-Feb-19
CON-32820 Hang Walls 10 14-Feb-19 27-Feb-19
CON-32800 Light Fixtures 10 28-Feb-19 13-Mar-19
CON-32810 Hang Ceilings 5 14-Mar-19 20-Mar-19
CON-32830 Tape/Mud/Paint 15 14-Mar-19 03-Apr-19
CON-32840 Ceiling Grid 5 04-Apr-19 10-Apr-19
CON-32850 Handrails 5 04-Apr-19 10-Apr-19
CON-32860 Acoustical Panels 10 04-Apr-19 17-Apr-19
CON-32870 Millwork 20 04-Apr-19 01-May-19
CON-32920 Ceiling Grid Rough-In 5 11-Apr-19 17-Apr-19
CON-32930 Drop Tile 5 18-Apr-19 24-Apr-19
CON-32880 Rubber Stair Treads & Ris ers 3 25-Apr-19 29-Apr-19
CON-32890 Flooring Tile 15 25-Apr-19 15-May-19
CON-32900 Carpet 5 16-May-19 22-May-19
CON-32910 Final Clean 3 23-May-19 28-May-19
CON-32940 Tunnel Finishes Complete 0 28-May-19
Site-LightwellsSite-Lightwells 87 04-Feb-19 05-Jun-19
HardscapeHardscape 87 04-Feb-19 05-Jun-19
CON-33150 Lightwells-Ph 1 (Charlie, Delta, Golf, Foxtrot) -Demo Lightwells 15 04-Feb-19 22-Feb-19
CON-33180 Lightwells-(Golf, Foxtrot) -Pit Slab 1 25-Feb-19 25-Feb-19
CON-33170 Lightwells-(Golf, Foxtrot)-Install Sump Pumps 1 26-Feb-19 26-Feb-19
CON-33480 Lightwells-(Golf, Foxtrot)-Waterproofing 1 26-Feb-19 26-Feb-19
CON-33490 Lightwells-(Golf, Foxtrot)-Topping Slab 1 27-Feb-19 27-Feb-19
CON-33750 Lightwells-(Charlie, Delta) -Form/Pour Concrete Pits 7 19-Mar-19 27-Mar-19
CON-33760 Lightwells-(Charlie, Delta) -Topping Slab 1 28-Mar-19 28-Mar-19
CON-33500 Lightwells-Ph 1 (Charlie, Delta, Golf, Foxtrot) -Wall Coating 15 29-Mar-19 18-Apr-19
CON-33510 Lightwells-Ph 2 (Alpha, Lima, Juliette) -Demo Lightwells 15 05-Apr-19 25-Apr-19
CON-33520 Lightwells-(Juliette)-Form/Pour Concrete Pits 4 26-Apr-19 01-May-19
CON-33530 Lightwells-(Juliette)-Install Sump Pumps 1 02-May-19 02-May-19
CON-33540 Lightwells-(Juliette)-Waterproofing 1 02-May-19 02-May-19
CON-33550 Lightwells-(Juliette)-Topping Slab 1 03-May-19 03-May-19
CON-33770 Lightwells-(Alpha, Lima)-Form/Pour Concrete Pits 5 06-May-19 10-May-19
CON-33780 Lightwells-(Alpha, Lima)-Install Sump Pumps 1 13-May-19 13-May-19
CON-33790 Lightwells-(Alpha, Lima)-Waterproofing 1 13-May-19 13-May-19
CON-33800 Lightwells-(Alpha, Lima)-Topping Slab 1 14-May-19 14-May-19
CON-33560 Lightwells-Ph 2 (Alpha, Lima, Juliette)-Wall Coating 15 15-May-19 05-Jun-19
Site-South RampSite-South Ramp 14 27-Nov-18 A 31-Jan-19
HardscapeHardscape 14 27-Nov-18 A 31-Jan-19
CON-33680 Fabricate Handrails 6 27-Nov-18 A 21-Jan-19
CON-33670 Install Handrails & Guardrails 8 22-Jan-19 31-Jan-19
Site-Northeast Ret Wall/LandscapeSite-Northeast Ret Wall/Landscape 117 08-Jan-19 A 26-Jun-19
HardscapeHardscape 112 08-Jan-19 A 19-Jun-19
CON-23240 NE Wall-Demo Retaining Walls 0 08-Jan-19 A 14-Jan-19
CON-33590 NE Wall-Form/Place New Retaining Wall & Mow Strip 20 14-Jan-19 08-Feb-19
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
2019 2
Waterproof Slab/Epoxy Coating
Frame Walls
OH Rough-In
Sump Pump
In-Wall Rough-In/Wood Bloc king
Frame Ceilings
Hang Walls
Light Fixtures
Hang Ceilings
Tape/Mud/Paint
Ceiling Grid
Handrails
Acoustical Panels
Millwork
Ceiling Grid Rough-In
Drop Tile
Rubber Stair Treads & Ris ers
Flooring Tile
Carpet
Final Clean
Tunnel Finishes Complete
Lightwells-Ph 1 (Charlie, Delta, Golf, Foxtrot) -Demo Lightwells
Lightwells-(Golf, Foxtrot) -Pit Slab
Lightwells-(Golf, Foxtrot)-Install Sump Pumps
Lightwells-(Golf, Foxtrot)-Waterproofing
Lightwells-(Golf, Foxtrot)-Topping Slab
Lightwells-(Charlie, Delta) -Form/Pour Concrete Pits
Lightwells-(Charlie, Delta) -Topping Slab
Lightwells-Ph 1 (Charlie, Delta, Golf, Foxtrot) -Wall Coating
Lightwells-Ph 2 (Alpha, Lima, Juliette) -Demo Lightwells
Lightwells-(Juliette)-Form/Pour Concrete Pits
Lightwells-(Juliette)-Install Sump Pumps
Lightwells-(Juliette)-Waterproofing
Lightwells-(Juliette)-Topping Slab
Lightwells-(Alpha, Lima)-Form/Pour Concrete Pits
Lightwells-(Alpha, Lima)-Install Sump Pumps
Lightwells-(Alpha, Lima)-Waterproofing
Lightwells-(Alpha, Lima)-Topping Slab
Lightwells-Ph 2 (Alpha, Lima, Juliette)-Wall Coating
Fabricate Handrails
Install Handrails & Guardrails
NE Wall-Demo Retaining Walls
NE Wall-Form/Place New Retaining Wall & Mow Strip
Remaining Construction
Data Date: 14-Jan-19
Run Date: 22-Jan-19; 08:31
Oklahoma State Capitol Exterior Renovation
Page 3 of 4
Activity ID Activity Name RemDur
Start Finish
CON-33810 NE Wall-Form/Place New Retaining Wall & Mow Strip (after crane demob) 5 12-Jun-19 19-Jun-19
LandscapeLandscape 97 11-Feb-19 26-Jun-19
CON-23250 NE Wall-Grading & Landscaping 15 11-Feb-19 01-Mar-19
CON-33190 NE Wall-Sump Pump Piping Daylighting 5 11-Feb-19 15-Feb-19
CON-33820 NE Wall-Grading & Landscaping (after crane demob) 5 19-Jun-19 26-Jun-19
Site-East PlazaSite-East Plaza 6 11-Feb-19 18-Feb-19
HardscapeHardscape 6 11-Feb-19 18-Feb-19
CON-33710 E Plaza. North Half-Slab on Grade 3 11-Feb-19 13-Feb-19
CON-33720 E Plaza. South Half-Slab on Grade 3 14-Feb-19 18-Feb-19
Site-North PlazaSite-North Plaza 4 19-Feb-19 22-Feb-19
HardscapeHardscape 4 19-Feb-19 22-Feb-19
CON-33730 N Plaza-Slab on Grade/Fill Exist Vent Shaft 4 19-Feb-19 22-Feb-19
Site-Southeast Ret Wall/LandscapeSite-Southeast Ret Wall/Landscape 13 28-Feb-19 18-Mar-19
HardscapeHardscape 13 28-Feb-19 18-Mar-19
CON-33740 SE Wall-Form/Place Ftgs/New Retaining Wall 13 28-Feb-19 18-Mar-19
Site-Southwest Ret Wall/LandscapeSite-Southwest Ret Wall/Landscape 40 22-Mar-19 16-May-19
HardscapeHardscape 25 22-Mar-19 25-Apr-19
CON-33200 SW Wall-Demo Retaining Walls 5 22-Mar-19 28-Mar-19
CON-33570 SW Wall-Form/Place New Retaining Wall & Mow Strip 20 29-Mar-19 25-Apr-19
LandscapeLandscape 15 26-Apr-19 16-May-19
CON-33220 SW Wall-Grading & Landscaping 15 26-Apr-19 16-May-19
CON-33210 SW Wall-Sump Pump Piping Daylighting 5 26-Apr-19 02-May-19
Site-Northwest Ret Wall/LandscapeSite-Northwest Ret Wall/Landscape 58 05-Apr-19 26-Jun-19
HardscapeHardscape 48 05-Apr-19 12-Jun-19
CON-33230 NW Wall-Demo Retaining Walls 5 05-Apr-19 11-Apr-19
CON-33580 NW Wall-Form/Place New Retaining Wall & Mow Strip 20 15-May-19 12-Jun-19
LandscapeLandscape 10 12-Jun-19 26-Jun-19
CON-33250 NW Wall-Grading & Landscaping 10 12-Jun-19 26-Jun-19
CON-33240 NW Wall-Sump Pump Piping Daylighting 5 12-Jun-19 19-Jun-19
Closeout & WarrantyCloseout & Warranty 317 02-Apr-19 29-Jun-20
.. 60 02-Apr-19 26-Jun-19
.. 60 02-Apr-19 26-Jun-19
CON-10760 Base Job Demobillization 60 02-Apr-19 26-Jun-19
JED-0600 Substantial Completion 0 26-Jun-19
Warranty Review sWarranty Review s 197 20-Sep-19 29-Jun-20
.. 197 20-Sep-19 29-Jun-20
CON-2840 Quarterly Warranty Review #1 2 20-Sep-19 24-Sep-19
CON-2850 Quarterly Warranty Review #2 2 16-Dec-19 18-Dec-19
CON-2860 Quarterly Warranty Review #3 2 11-Mar-20 13-Mar-20
CON-2870 1 Year Warranty Review 2 25-Jun-20 29-Jun-20
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
2019 2
NE Wall-Form/Place New Retaining Wall & Mow Strip (after crane demob)
NE Wall-Grading & Landscaping
NE Wall-Sump Pump Piping Daylighting
NE Wall-Grading & Landscaping (after crane demob)
E Plaza. North Half-Slab on Grade
E Plaza. South Half-Slab on Grade
N Plaza-Slab on Grade/Fill Exist Vent Shaft
SE Wall-Form/Place Ftgs/New Retaining Wall
SW Wall-Demo Retaining Walls
SW Wall-Form/Place New Retaining Wall & Mow Strip
SW Wall-Grading & Landscaping
SW Wall-Sump Pump Piping Daylighting
NW Wall-Demo Retaining Walls
NW Wall-Form/Place New Retaining Wall & Mow Strip
NW Wall-Grading & Landscaping
NW Wall-Sump Pump Piping Daylighting
Base Job Demobillization
Substantial Completion
Quarterly Warranty Review #1
Quarterly War
Remaining Construction
Data Date: 14-Jan-19
Run Date: 22-Jan-19; 08:31
Oklahoma State Capitol Exterior Renovation
Page 4 of 4