COSGRAY ROADEXTENSION

City of HilliardOhio Department of Transportation

FRA-COSGRAY ROAD, PID 90989

August 12, 2014

• Lack of north‐south connectivity

• Long queues at intersections today• Contributes to rear‐end collisions

• Congestion predicted to worsen

• Lack of bicycle/pedestrian facilities

EXISTING CONDITIONS

• Improve north‐south connectivity

• Reduce congestion

• Improve safety

• Enhance alternative travel modes

PROJECT PURPOSE

ZONING• Includes Jerman Tract• Retail, office, and recreational land uses

• Zoning approved in 2010 by City and Big Darby Accord

ZONING• Includes Jerman Tract• Retail, office, and recreational land uses

• Zoning approved in 2010 by City and Big Darby Accord

2008/2010:Willoway Wholesale/MJC 

Holdings LLC (Campus at Alton Darby)

2013:Planned Development Company of Ohio (Heritage Preserve)

• Project focuses on transportation network

• Considers stormwater & future development

• Project will not focus on zoning &/or land uses

RECOMMENDED ALTERNATIVE

• “Green” median with bioswales

• Multi‐use paths on both sides and on‐street bike accommodations

• Enhanced pedestrian crossing for regional bike trail

• Roundabout with access to public soccer fields & Jermansite

• Roundabout at Alton & Darby Creek Road intersection

• 35‐mph speed limit

COSGRAY ROAD EXTENSIONTYPICAL ROADWAY ELEVATION VIEW

• Roundabout at Soccer Field/Main Site Drive Intersection• Allows for safe bike/ped crossing of Cosgray Extension• Maximizes median/bioswale length• Slower speeds (20‐25 mph design speed)

• Roundabout at Alton & Darby Creek intersection• Slower speeds (20‐25 mph design speed)• Traditional (4‐leg) intersection on curve not desirable

• Multi‐use path

• Future regional trail connection

• On‐street bicycle facilities

• Split median pedestrian crossings

• Future extensions to Municipal Park & Prairie Oaks Metro Park

PEDESTRIANS & BICYCLES

TYPICAL SPLIT MEDIAN CROSSING ELEVATION VIEW

2834

79

City of Hilliard Big Darby CreekWatershed

Zero Runoff in 2‐YearRain Storm

Runo

ff Storage Volum

e(acre‐feet)

Cosgray Road ExtensionWill Exceed Stormwater Requirements

COSGRAYROAD 

EXTENSION PROJECT

• 2014/2015: Finish environmental studies & preliminary design

• 2015/2016: Final Design

• 2016: Right‐of‐Way Acquisition

• 2017: Construction

*All dates are subject to funding availability. 

NEXT STEPS

• Comments must be received by August 26, 2014• Comments can be provided:

• Comment form  (dropped off at meeting or mailed)

• Email:  lschamp@hilliardohio.gov• Project website:  www.hilliardohio.gov/

PUBLIC COMMENTS

QUESTIONS