Las Cruces , Guatemala Assessment TripLas Cruces Flood Mitigation Project

Las Cruces, Guatemala ,Assessment TripEngineers Without Borders 

Flood Assessment and Mitigation Projectg j

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

Engineers Without Borders (EWB)• From a backyard conversation to 12,000 

b ld idmembers worldwide

• EWB mission statement

• Chicagoland projects

L C G l Fl d A• Las Cruces, Guatemala Flood Assessment 

Changing our World One Community at a TimeChicago Professional ChapterChicago Professional Chapter

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

Concern America, Local Partner

In Las Cruces since 1994 with a focus on:

• Healthcare clinics

T i i f ill h l h• Training of villagers as health promoters

Approached EWB in 2008, f ll i fl d ifollowing a severe flood in Las Cruces

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

Las Cruces GuatemalaLas Cruces, GuatemalaPopulation Apx.17,500

2,800 families2,800 families• Ladinos • Qeqchi • Mam• Mam• Kaqchike

P i il A i lt l &Primarily Agricultural & Ranching Jobs

• PeanutsPeanuts • Sesame

seeds • Papayasp y• Cattle

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

LasDrainage Ditch 

Las Cruces

Main Road

Cavern Entrance

“El Tragante” 

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

October 2008October 2008Tropical 

depressiondepression 

produced 18 days of intense rainfall

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

7,000 residents were 

displaced for a month

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

Flood depths over 10 ft occurred inundatingoccurred, inundating homes up to their roofs

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

Before During

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

Only one well out of 10out of 10

tested did not contain e colicontain e. coli

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

Framework for a SolutionFramework for a Solution

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

M t I t t?Most Important?

l lMaintain a local perspective.

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

• NASA / USGS Shuttle Radar Topography Mission (SRTM)• Aerial and satellite photography • Land cover• Digital Elevation Models (DEMs)

• NASA Tropical Rainfall Measuring Mission (TRMM)

Land cover

• Watersheds

• Tropical 3 hr rainfall (2.5 miles gridded)

• Guatemala Instituto Nacional Sismologia• Monthly rainfall totals (30 miles away)

• Isohyetal maps (regional)

• UN Food and Agricultural Organization

• Soils

• USGS Caribbean Water Science Center

• Inter‐American Bio‐diversity Information Networky

• Google Earth

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

800

Rainfall (mm)

45%of the Average 

600

700 Total Annual Rainfall

i 18 d

500

600 in18 days

400

200

300

100

0

1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

3030 yrs

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

Las

66 i

Las Cruces 66 sq‐mi

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

LLow Spot “Outlet”p

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

Framework for a Solution• Understand the Problem

Was this an extreme event?• Was this an extreme event?

• What’s a typical event?

What event significantly impacts the community?• What event significantly impacts the community?

• Understand the Constraints• Limited engineering alternatives

L k f f di• Lack of funding

• Lack of Resources

Hi t i it i• Historic community issues

• Lack of national support

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

Main R dRoad

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

What’s Next?• Project report (March)

• Fund‐raising

Addi i l• Additional survey

• Final design plans and specificationsFinal design, plans and specifications

• Implementation?

Las Cruces, Guatemala Assessment TripEngineers Without Borders Flood Assessment and Mitigation Project

Changing our World One Community at a TimeChicago Professional Chapter