Florida Gas Transmission10-Inch Hydrostatic Test

10-Inch Saint Petersburg Lateral PipelineFrom I-275 (Valve 24-102B) to US-19 North of SR 688/Ulmerton Road (Valve 24-103B)

Pinellas County

Who is Florida Gas Transmission (FGT)?

Why is FGT testing?What is the test exactly?When will the test occur?Where will the test take place?How will the test be conducted?How will the test affect me?

Today’s Outline

2

Natural gas transmission company operating a 5,000 mile pipeline system along the Gulf

Provide majority of the natural gas for power generation in Pinellas County

10-inch diameter pipeline serving Tampa area

Customers include: Electric utility companies Local distributors Industrial clients

Florida Gas Transmission Company

3

The U.S. Department of Transportation regulates all interstate pipelines

Testing is federally mandatedBest practice to confirm the safety

and reliability of the pipeline Safety is our #1 priority Ensure continued superb client service

Need for the Test

4

Hydrostatic Test Remove the natural gas from the line• Controlled release vents harmlessly into

atmosphere

• Service is maintained on another system

Test the integrity of the pipeline by filling the line with water• Put the water under pressure for a fixed

period of time

Nature of the Test

5

Hydrotesting the 10-inch lateral systemStandard, common pipeline test

procedureRecent, successful pipeline tests were

completed in:

Pinellas testing has been set for September 2015

Background

Hillsborough Miami-Dade Broward

Palm Beach St. Lucie Martin

6

Public Awareness Campaign

Project Process

Begin Project

Obtain Permits

Prepare System for

Testing

Conduct Hydrotest

End Project

7

TASK DATE

Community Awareness July – October

Permit Applications June – July

System Preparation July – August

Test Preparation August – September

Conduct Hydrotest 28 September 2015

Test window is set: Monday, 28 September 2015 Early morning, midnight – 4:00 a.m.

Project Schedule

8

Total Project Length = 6.1 miles Begin: I-275 at SR 694/Gandy Blvd End: US-19 north of SR 688/Ulmerton Rd

Generally follows 3 roadway alignments: SR 694/Gandy Blvd 78th Ave N US-19 Northbound Frontage Road

Within St. Petersburg, Pinellas Park, Largo, and Unincorporated Pinellas County

Project Location

9

Project Location (con’t)

10

Remove natural gas from the pipeline Completed the week before the hydrotest

Fill the line with waterPressurize the system

Normal operating pressure is 712 PSI Test pressure is up to 1,500 PSI• Relatively short duration (approx. 30 minutes)

Reduce to intermediate pressure at 1,350 PSI•Maintain for 8 hours

How the Test is Performed

11

De-pressurize the lineDrain the water from the systemIf any integrity issues are found:

They are corrected as soon as possible The hydrotest is performed again• Any re-testing will be performed as soon as

possible, during the same hours

Resume normal natural gas service

How the Test is Performed (con’t)

12

Safety is our #1 priorityPerformed extensive test

preparations, including an inspection of the entire system

Any pipe anomalies will be repaired in advance of conducting the hydrotest

For the duration of the high pressure test, as a safety consideration, we plan to isolate sections of the pipeline route from people and traffic

Safety During the Test

13

Advance Preparations Make all key stakeholders aware• Adjacent property owners

• Emergency service providers

•General driving public

Announcements• Flyers, newspaper, website, etc.

Dynamic message signs• 2 weeks in advance

Conducting the Test

14

Night of the Test Begin at midnight Close roads/lanes with barricades Law enforcement support Confirm all-clear along the 6.1-mile

corridor Conduct hydrotest Reopen roadways at approximately 4:00

AM

Conducting the Test (Con’t)

15

General Utility Permit from the Florida Department of Transportation is in process

Officers will be stationed at road and lane closures

Emergency responders will be able to cross as needed

Detours will include signs and officer support

Traffic Control During the Test

16

Detours During the Test - 1

Northbound US-19 at CR 611/49th St N

Exiting from US-19 northbound: 52nd St N 110th Ave N

Entering onto US-19 northbound: CR 611/49th St N SR 688/Ulmerton Rd 58th St N 142nd Ave N

17

Detours During the Test - 2

Northbound US-19 at 110th Ave N

Entering onto US-19 northbound: CR 611/49th St N SR 688/Ulmerton Rd 58th St N 142nd Ave N

18

Detours During the Test - 3

Northbound US-19 at 118th Ave N

Eastbound 118th Ave N: CR 611/49th St N SR 688/Ulmerton Rd 58th St N 142nd Ave N

Westbound 118th Ave N: CR 296/Bryan Dairy Rd SR 693/66th St N

19

Detours During the Test - 4

Northbound US-19 at 126th Ave N

Eastbound 126th Ave N: CR 296/Bryan Dairy Rd SR 693/66th St N

Westbound 126th Ave N: 60th St N SR 688/Ulmerton Rd 62nd St N 142nd Ave N

20

Detours During the Test - 5

Northbound US-19 at SR 688/Ulmerton Rd

Eastbound SR 688/Ulmerton Rd: 58th St N (or SR 693/66th St N) 142nd Ave N

Westbound SR 688/Ulmerton Rd: 58th St N (or 62nd St N) 142nd Ave N

21

Project Location – District 3 / 6

22

Project Location – District 1 / 5

23

Please visit our website:www.fgthydrotest.com

Or contact FGT:Mr. Terry Coleman

2405 Lucien Way, Suite 200Maitland, FL 32751

Toll Free – 844-FGT-INFO (844-348-4636)

Office – 407.838.7054Fax – 407.838.7052

Email – Terry.Coleman@energytransfer.com

For More Information

24

FGT 10-Inch Hydrotest Summary

Federal mandate Testing with water Test will be Monday,

28 September 2015 Midnight – 4:00 AM 5 detours for US-19

northbound (frontage road) intersections

With law enforcement Emergency vehicles

can always cross

25

Thank You