Elmira High School IRM #2 Construction Overview

Community Safety Environmental Protection

Protection of EHS Property

IRM Area of Excavation

Haul Roads mid-June through the end of August

EHS to MSA - 30-40 loads per day

Loading Area for Materials to be Disposed

Offsite Transport and Disposal - 35 loads per day

Dust Monitoring Ambient Air Monitoring

Worker Protective Equipment: Safety glasses, hard hat, steel toe boots, gloves, high-viz, training

Piling will be used to protect structures and ensure soil removal to design limits

Traffic control on/off Main Street Geophysical survey to protect underground

utilities

Dust Control

Excavated soil is covered prior to proper disposal

All equipment is decontaminated before leaving site

Storm sewers protected from debris during construction

Worker Safety