MEANS OFFICE BUILDINGPRE-CONSTRUCTION & CONTRACTING SERVICES PROPOSAL

Eddie Aquino, Jimmy Fu, Alvin Sarmiento

Spring 2011

Civil Engineering 239

PROJECT TEAM

Eddie AQUINO PROJECT MANAGER/3D MODELLER

Jimmy FU PROJECT ENGINEER/

CONSTRUCTION SITE LOGISTICS

Alvin SARMIENTO PROJECT ESTIMATOR/SCHEDULER

2

PROJECT REQUIREMENTS Three-story office building w/ underground

garage Concrete waffle slab Spread footings Structural Steel framing with steel deck Penthouse structure CMU Steel joist roof Construction budget 10.5 million – 12 million

PROJECT LOCATION

COMPONENT StreetLooking Southeast

COMPONENT StreetLooking Southwest

PROJECT LOCATION

2.60 Acres IP (PD) URBAN Freeways

3D MODEL

PDF Simulation

Cost Estimates

Timberline Sage Ranked most used estimating software by

ENR

AutoCAD Timberline

Primavera

MS Project

Cost Estimates

Features CSI MasterFormat Provides detailed labor, material, and

equipment cost estimates Provides total cost/unit and total amount

per item

Cost Estimates

Problems Encountered Can not access Division 10-16

Mechanical and Electrical Systems

Cost Estimates

Problems Encountered Final cost estimates from Timberline does

not match cost estimates given in excel sheet

Schedule

MS Project Timeline: January 27, 2011 – January 6,

2012 RS Means 2002 and Golden Bear

Construction Inc. RS Means Office Building Schedule

Superstructure

GarageMeasurement

Daily Output based on RS Means production

Approximate Completion

Structural Steel Columns/Beams 114 Tons 14.4 Tons 8 days

1st FloorMeasurement

Daily Output based on RS Means production

Approximate Completion

Structural Steel Columns/Beams 114 Tons 14.4 Tons 8 days

Metal Deck 18,900 SF 3,500 SF 6 daysConcrete Fill Over Metal Deck 18,900 SF 8,640 SF 3 daysWaffle Slab 18,900 SF 2,380 SF 8 daysFire Proofing 18,900 SF 3,000 SF 7 days

Schedule

Schedule Accuracy of schedule and duration of project

Each activity has a predecessor At any time during schedule, one or more

activities can occur Advantages

Simple to use Disadvantages

Activities may not have any predecessor or successor

CONSTRUCTION SITE

CONSTRUCTION EQUIPMENT

ACTION MOBILE INDUSTRYMODEL 1250 (46’x12’)

LINDEN COMANSALC 500 Series