Megaprojects - New Psychiatric hospital in Slagelse

Presentation 03.12.2015 by Henrik Bendix Olsen

Hospital projects in Denmark

The kvalitetsfond

constructions are partly

funded by the government

with 60% and regional

funded with 40%.

16 projects with a total cost

of 42 billion ddk.

Hospitals in Region SealandKvalitetsfond projects

Slagelse acute department

Hospital floor space: 11.000 m²

Beds: 85 total consisting of: 50 acute beds, 15

intensive beds and 20 cardiac monitoring beds.

Projekt sum: 0.315 billion ddk.

Occupancy of the hospital – late 2013

Slagelse psychiatric hospital

Hospital floor space: 44.000 m²

Site size: 158.463 m²

Beds: 194 total consisting of: 114 general

psychiatric beds, 50 forensic psychiatric beds

and 30 beds in a high secure ward.

Employees: approx. 650

Projekt sum: 1.2 billion ddk.

Occupancy of the hospital – late 2015

Koege University hospital

Hospital floor space: 189.000 m²

Site size: 275.000 m²

Beds: 900 total

Employees: approx. 4130

Projekt sum: 4 billion ddk.

Occupancy of the hospital – 2022

Special kvalitetsfond demands

Control manual

- Organisation

- Risk management

- Controlling

3D project, IKT

- New technology

Fixed bottomline

- Large reserves

- Change request lists

Networking

- Quarterly rapports

Innovation

Organisation diagram

Advisors

Building owner:

Region Sjælland

Architect (Lead consultant):

Karlsson arkitekter / VLA i/s

Advisors (architect):

Schønherr

Moe

NNE Pharmaplan

Cenergia Energy Consultants

Bartenbach Light Design

Signal

Advisor (building owner):

Kuben Management A/S

Construction/site management:

Rambøll

Security:

Molter Consult

External controlling:

Arkitema Architects

7

Kvalitet og Udvikling – KU Byg – Alleen 15 – 4180 Sorø

7

New Psychiatric hospital in SlagelseTime schedule

Activity Time

General planning (Mangor & Nagel) 2008 to 2009

Advisor to the building owner (Kuben) Primo 2010

Lead consultant choosen by competition (Karlsson architects og Vilhelm Lauritsen architects)

Ultimo 2010

Usergroups, temp. Building program & Kvalitetsfond-application (Karlsson architects and Vilhelm Lauritsen architects)

Primo2011

Kvalitetsfond accept Ultimo2011

Usergroups & planning finished - Ultimo2012

Construction management (Rambøll) Ultimo 2012

Licitation - building Nov. 2012

Construction site and excavation Ultimo2012

Building period 2013 - 2015

Contractor hand over & operation start up Medio 2015

Hand over to psychiatry 1. August 2015

Arial photo 12. november 2015

Main entrance – office building

Entrance area

Office building - atrium

Sports and exercise centre

Patient area

Garden - patient area

Multistimuli-area, General psychiatric

HIS, General psychiatric

17

GAPS – LED lightThe most advanced system in the world

17

LED light:

Dynamic light with the ability to control each roomseparatly.

18

Building integrated art / colours

18

Painter: Malene Landgreen

Author:Ursula Andkjær Olsen

19

Psychiatric bed

19

Billedkunstner: Malene Landgreen

Forfatter:Ursula Andkjær Olsen

LED-belysning indgår som en del af kunststrategien

20

DGNB – pre-certification

20