MYNTDU LESHKA H. E. PROJECT (3X42MW)JAINTIA HILLS DISTRCT, MEGHALAYA
PROGRESS OF WORKS
AS ON MARCH 2012
COMPLETION DATE:
UNIT-I - November, 2011UNIT-II - March, 2012UNIT-III - September, 2012
-
7/30/2019 Myntdu Leshka HE March2012
2/13
Save Energy For Benefit of Self and Nation
-
7/30/2019 Myntdu Leshka HE March2012
3/13
Save Energy For Benefit of Self and Nation
CAUSES OF DELAY
1. Target Completion period is 5 years is unrealistic and the delay is apparent.
2. Remoteness of site.
a. Shortage of skilled man power.b. Slow reaction to construction materials.
3. Geological Condition.
a. Delay in foundation excavation of Dam.b. Increase in quantity of concreting.
4. Seismological Condition
a. New Dawki faultb. Delay in design.
5. Water Chemical Condition (Acidity)
a. In view of acidity of river, special concrete, paints etc. had to be provided after some research and designworks.
6. Heavy Rainfall (Cherrapunje Belt)
a. Early rainfall
b.
Heavy rainfall causing flood.c. Less working time.
As a result of Early and Heavy rainfall there has been many floodings in the work site but abnormalflooding had occurred on :-
a. 8th October, 2009b. 20th May, 2011.
7. High head of the Project
a. In view of High head, the machine RPM is fixed at 600.
b. This result in high pressure etc. develop at the Power House which require utmost care and caution.
-
7/30/2019 Myntdu Leshka HE March2012
4/13
Save Energy For Benefit of Self and Nation
PHYSICAL PROGRESS OF WORKS OF THEMYNTDU LESHKA HYDRO ELECTRIC PROJECT (3 X 42 MW)
1. ROADThe constructions of all road works connecting different sites in the Project are completed.
2. BUILDINGThe constructions of all buildings are completed, except for Permanent Building, Type-IV at Power House Colony where
the works are in progress.
-
7/30/2019 Myntdu Leshka HE March2012
5/13
Save Energy For Benefit of Self and Nation
3. DAM-
Sl.No
Particularsof Works
UnitPresentQuantity
CompletedBalanceQuantity
Target date ofcompletion
1 Excavation M3 650000 650000 Completed completed
2 Concreting M3 332311 331439.00Finishing
works-
3ControlRoom
Completed except for finishing works. -
-
7/30/2019 Myntdu Leshka HE March2012
6/13
Save Energy For Benefit of Self and Nation
4. SLUICE RADIAL GATES (DAM): All gates completed, except 1(one).
All hoisting arrangement completed.
5. TUNNEL/SURGESHAFTSl.No.
Particulars of Works Unit Present Quantity Completed
1 HRT M 3313.46 All works completed
HPT M 314.00 All works completed
INTAKE GATE No 1 All works completed
2 SURGE SHAFT M 85 All works completed
Sl.No.
Particulars of Works UnitPresentQuantity
Completed
1 Sluice Radial Gates Nos. 7
All Gates are completed and in operation fromboth individual control and remote control
panel. Gate No.1 is presently used by stop loggate.
-
7/30/2019 Myntdu Leshka HE March2012
7/13
Save Energy For Benefit of Self and Nation
-
7/30/2019 Myntdu Leshka HE March2012
8/13
Save Energy For Benefit of Self and Nation
6. VAVLE HOUSE & ERECTION OF BUTTERFLY VALVE
Sl.No
Particulars of Works UnitPresentQuantity
CompletedBalanceQuantity
Target date ofcompletion
1 Excavation M3 11250.00 11250.00 - Completed
2 Concreting. M3 698.50 698.50 - Completed
3 Erection of Butterfly
ValveNo. Units -I, II, & III are completed.
Completed
-
7/30/2019 Myntdu Leshka HE March2012
9/13
Save Energy For Benefit of Self and Nation
7. ANCHORS & SADDLES (3x42 MW)No. of Anchor Blocks: 10
Sl. No Particulars of Works UnitPresentQuantity
CompletedBalanceQuantity
Target date ofcompletion
1 Excavation (channel)& (Anchors/Saddles) M3 116660.59 116660.59 - Completed
2 Concreting for Anchors& Saddles.
M3 27384.993 27384.993 - Completed
8. PENSTOCK & PIPE LINERSl.No
Particulars of Works UnitPresentQuantity
CompletedBalanceQuantity
Target date ofcompletion
1 Supply & Fabricationof Penstock Liner MT 3128.913 3128.913 - Completed
2 Erection of PenstockLiner
MT 3128.913 3128.913 - Completed
-
7/30/2019 Myntdu Leshka HE March2012
10/13
Save Energy For Benefit of Self and Nation
9. POWER HOUSE (CIVIL)Civil works All Completed (For Unit- I & II).
Remaining works (finishing):
a. Railingb. Lightingc. Lifts
Sl.No.
Particulars of Works UnitPresentQuantity
CompletedBalanceQuantity
Target date ofcompletion
1 A. POWER HOUSE
(i) General Excavation, Pit &
Tail Race M3
All works completed Completed
(ii) Concreting Sub-Structure M3 22000.00 22000.00 0 Completed
(iii) Concreting Super-Structure
M3 4050.00 4050.00 0 Completed
(iv) Concreting of Tail Race M3 20226.739 20226.739 completed Completed
Draft Tube Gate No. 3
The erection work andinstallation of draft tube gate forall units is completed. (Hoisting
arrangement is going on)
-
-
7/30/2019 Myntdu Leshka HE March2012
11/13
Save Energy For Benefit of Self and Nation
10. SWITCHYARDErection of Equipment All completed.Cabling works All completed.Charging All completed.
Sl.No
Particulars of Works UnitPresentQuantity
CompletedBalanceQuantity
Target date ofcompletion
1 Excavation M3 90997.38 90997.38 Completed
2Erection of structures equipment M3
The erection work completed.
Testing work is in progress
Completed
3Inter connecting Line Nos. 7
Foundation completed,Tower erection completed
Completed
4 Cabling Completed Completed
Testing Completed Completed
Charging Completed Completed
-
7/30/2019 Myntdu Leshka HE March2012
12/13
Save Energy For Benefit of Self and Nation
11. POWER HOUSE (ELECTRICAL)a. M/s. Shyama Power
Erection of all Auxiliaries in Power House is completed.
Testing of all equipments is in progress for Unit III.
b. M/s Andritz Hydro Generation started on December 2011 for 1st Unit
Auxiliaries Cabling & Termination in progress for Unit-III.
c.
M/s. Vijai Electricals Erection of Equipment for Unit-III in progress.
CONCLUSION:
1. The 1st
Unit is in generation and as on date more than 16 mu of energy is generated.
2. Synchronization of Unit II started on 30th
March 2012.
3. Target completion date for Unit III is September 2012.
-