    Save Energy For Benefit of Self and Nation

    MYNTDU LESHKA H. E. PROJECT (3X42MW)JAINTIA HILLS DISTRCT, MEGHALAYA

    PROGRESS OF WORKS

    AS ON MARCH 2012

    COMPLETION DATE:

    UNIT-I - November, 2011UNIT-II - March, 2012UNIT-III - September, 2012

  • 7/30/2019 Myntdu Leshka HE March2012

    2/13

    Save Energy For Benefit of Self and Nation

  • 7/30/2019 Myntdu Leshka HE March2012

    3/13

    Save Energy For Benefit of Self and Nation

    CAUSES OF DELAY

    1. Target Completion period is 5 years is unrealistic and the delay is apparent.

    2. Remoteness of site.

    a. Shortage of skilled man power.b. Slow reaction to construction materials.

    3. Geological Condition.

    a. Delay in foundation excavation of Dam.b. Increase in quantity of concreting.

    4. Seismological Condition

    a. New Dawki faultb. Delay in design.

    5. Water Chemical Condition (Acidity)

    a. In view of acidity of river, special concrete, paints etc. had to be provided after some research and designworks.

    6. Heavy Rainfall (Cherrapunje Belt)

    a. Early rainfall

    b.

    Heavy rainfall causing flood.c. Less working time.

    As a result of Early and Heavy rainfall there has been many floodings in the work site but abnormalflooding had occurred on :-

    a. 8th October, 2009b. 20th May, 2011.

    7. High head of the Project

    a. In view of High head, the machine RPM is fixed at 600.

    b. This result in high pressure etc. develop at the Power House which require utmost care and caution.

  • 7/30/2019 Myntdu Leshka HE March2012

    4/13

    Save Energy For Benefit of Self and Nation

    PHYSICAL PROGRESS OF WORKS OF THEMYNTDU LESHKA HYDRO ELECTRIC PROJECT (3 X 42 MW)

    1. ROADThe constructions of all road works connecting different sites in the Project are completed.

    2. BUILDINGThe constructions of all buildings are completed, except for Permanent Building, Type-IV at Power House Colony where

    the works are in progress.

  • 7/30/2019 Myntdu Leshka HE March2012

    5/13

    Save Energy For Benefit of Self and Nation

    3. DAM-

    Sl.No

    Particularsof Works

    UnitPresentQuantity

    CompletedBalanceQuantity

    Target date ofcompletion

    1 Excavation M3 650000 650000 Completed completed

    2 Concreting M3 332311 331439.00Finishing

    works-

    3ControlRoom

    Completed except for finishing works. -

  • 7/30/2019 Myntdu Leshka HE March2012

    6/13

    Save Energy For Benefit of Self and Nation

    4. SLUICE RADIAL GATES (DAM): All gates completed, except 1(one).

    All hoisting arrangement completed.

    5. TUNNEL/SURGESHAFTSl.No.

    Particulars of Works Unit Present Quantity Completed

    1 HRT M 3313.46 All works completed

    HPT M 314.00 All works completed

    INTAKE GATE No 1 All works completed

    2 SURGE SHAFT M 85 All works completed

    Sl.No.

    Particulars of Works UnitPresentQuantity

    Completed

    1 Sluice Radial Gates Nos. 7

    All Gates are completed and in operation fromboth individual control and remote control

    panel. Gate No.1 is presently used by stop loggate.

  • 7/30/2019 Myntdu Leshka HE March2012

    7/13

    Save Energy For Benefit of Self and Nation

  • 7/30/2019 Myntdu Leshka HE March2012

    8/13

    Save Energy For Benefit of Self and Nation

    6. VAVLE HOUSE & ERECTION OF BUTTERFLY VALVE

    Sl.No

    Particulars of Works UnitPresentQuantity

    CompletedBalanceQuantity

    Target date ofcompletion

    1 Excavation M3 11250.00 11250.00 - Completed

    2 Concreting. M3 698.50 698.50 - Completed

    3 Erection of Butterfly

    ValveNo. Units -I, II, & III are completed.

    Completed

  • 7/30/2019 Myntdu Leshka HE March2012

    9/13

    Save Energy For Benefit of Self and Nation

    7. ANCHORS & SADDLES (3x42 MW)No. of Anchor Blocks: 10

    Sl. No Particulars of Works UnitPresentQuantity

    CompletedBalanceQuantity

    Target date ofcompletion

    1 Excavation (channel)& (Anchors/Saddles) M3 116660.59 116660.59 - Completed

    2 Concreting for Anchors& Saddles.

    M3 27384.993 27384.993 - Completed

    8. PENSTOCK & PIPE LINERSl.No

    Particulars of Works UnitPresentQuantity

    CompletedBalanceQuantity

    Target date ofcompletion

    1 Supply & Fabricationof Penstock Liner MT 3128.913 3128.913 - Completed

    2 Erection of PenstockLiner

    MT 3128.913 3128.913 - Completed

  • 7/30/2019 Myntdu Leshka HE March2012

    10/13

    Save Energy For Benefit of Self and Nation

    9. POWER HOUSE (CIVIL)Civil works All Completed (For Unit- I & II).

    Remaining works (finishing):

    a. Railingb. Lightingc. Lifts

    Sl.No.

    Particulars of Works UnitPresentQuantity

    CompletedBalanceQuantity

    Target date ofcompletion

    1 A. POWER HOUSE

    (i) General Excavation, Pit &

    Tail Race M3

    All works completed Completed

    (ii) Concreting Sub-Structure M3 22000.00 22000.00 0 Completed

    (iii) Concreting Super-Structure

    M3 4050.00 4050.00 0 Completed

    (iv) Concreting of Tail Race M3 20226.739 20226.739 completed Completed

    Draft Tube Gate No. 3

    The erection work andinstallation of draft tube gate forall units is completed. (Hoisting

    arrangement is going on)

    -

  • 7/30/2019 Myntdu Leshka HE March2012

    11/13

    Save Energy For Benefit of Self and Nation

    10. SWITCHYARDErection of Equipment All completed.Cabling works All completed.Charging All completed.

    Sl.No

    Particulars of Works UnitPresentQuantity

    CompletedBalanceQuantity

    Target date ofcompletion

    1 Excavation M3 90997.38 90997.38 Completed

    2Erection of structures equipment M3

    The erection work completed.

    Testing work is in progress

    Completed

    3Inter connecting Line Nos. 7

    Foundation completed,Tower erection completed

    Completed

    4 Cabling Completed Completed

    Testing Completed Completed

    Charging Completed Completed

  • 7/30/2019 Myntdu Leshka HE March2012

    12/13

    Save Energy For Benefit of Self and Nation

    11. POWER HOUSE (ELECTRICAL)a. M/s. Shyama Power

    Erection of all Auxiliaries in Power House is completed.

    Testing of all equipments is in progress for Unit III.

    b. M/s Andritz Hydro Generation started on December 2011 for 1st Unit

    Auxiliaries Cabling & Termination in progress for Unit-III.

    c.

    M/s. Vijai Electricals Erection of Equipment for Unit-III in progress.

    CONCLUSION:

    1. The 1st

    Unit is in generation and as on date more than 16 mu of energy is generated.

    2. Synchronization of Unit II started on 30th

    March 2012.

    3. Target completion date for Unit III is September 2012.