Oklahoma Dept. of Transportation Public Information MeetingS.H. 51 from Wagoner to the State Line and other projects.April 30th, 2009 Cherokee County

The purpose of the meeting is to inform the public of the Department's scheduled work plan projects within Cherokee and Adair Counties, particularly along SH 51.

Fort Gibson Lake Bridge on S.H. 51 Right of way to be conducted in 2009 Utilities to be conducted in 2010 Construction to start in 2011

Fourteen Mile Creek Bridge on S.H. 51 Right of way to be conducted in 2012 Utilities to be conducted in 2012 Construction to start in 2014

Baron Fork Bridge on S.H. 51 E. of Tahlequah Right of way to be conducted in 2013 Utilities to be conducted in 2013 Construction to start in 2015

S.H. 82 N. of Tahlequah widened to 4 lanes Right of way to be conducted in 2013 Utilities to be conducted in 2014 Construction to start in 2015

Projects to be constructed in Cherokee County