Port of San Francisco

Crane Cove ParkConstruction Package 2 – Park Improvements

Contract No. 2781

July 12, 2017

PRE - BID Presentation July 12, 2017

Welcome & Introductions Tim Leung – Port Construction & Contracts Manager Steven Reel/Kevin Matsuda – Port Engineer/Project Manager Finbarr Jewell – CMD Compliance Officer Joyce Wong- OEWD Compliance Officer

AGENDA1. Welcome & Introductions – Tim Leung2. Project Overview – Steven Reel3. CMD – Finbarr Jewell4. Highest Prevailing Wage – Anna Liu5. Local Hire – Joyce Wong/Ian Fernando6. Bid Documents – Tim Leung7. Questions

Site Plan

Alternate Bid Items

Local Business Enterprise Goal = 21%

Local Business Enterprise Utilization Tracking System (LBEUTS)

QBD Addendum

ENSUING SITE VISIT699 Illinois Street(PPE Required)