Project Components and Construction ScheduleGREENLINK WEST PROJECT - PUBLIC INPUT WORKSHOP

• Harry Allen 525-kV Switching Station Expansion• Northwest 525/230-kV Substation Expansion• New Amargosa 525/230-kV Collector Station• New Esmeralda 525/230-kV Collector Station• New Fort Churchill-Northwest 525-kV Transmission Line (319 miles)• New Harry Allen-Northwest 525-kV Transmission Line (35 miles)• New Fort Churchill 525/345/230/120-kV Substation• Comstock Meadows 345/120-kV Substation Expansion• New Comstock Meadows-Fort Churchill 345-kV Transmission Line #1 (35 miles)• New Comstock Meadows-Fort Churchill 345-kV Transmission Line #2 (35 miles)• Mira Loma 345/120-kV Substation Expansion• New Fort Churchill-Mira Loma 345/120-kV Transmission Line (45 miles)• Access Roads• Microwave Sites

• Distribution Lines• Fiber Optic Communication Line• Material Yards (for construction only)

H-Frame Structure Lattice Guyed V Structure

Substation

Microwave Structure

• Planned in-service date of December 2026• Construction period is approximately 3 years

Structure ErectionInsulator Assembly

Proposed Project Components

Construction Schedule