Rob ConnellMay 29, 2002
Retail Sub-Committee Update
2
Objectives
• Update on PTB Synchronization Plan– Status on synchronizing the CR of record
• Provide Update from Previous RMS issues– Portal Performance and Changes– IDR / Non IDR Meter Usage Reports– 867-03 Forwarding Updates
• Information on Enhanced MP EDI Reporting Effort
3
PTB Synchronization Plan
• To address the current market issue with the rep of record getting out of synch between ERCOT, TDSP and CR systems.
• The transition to AREP process identified some of these, and the Move In and Move Out “safety net” processes, market gaps and various system issues have caused many more.
• The objectives of this project are to provide a plan to; – Identify the size of the problem – Provide root causes and options for correcting (if available)– Develop and implement a technical plan to synchronize databases
• The Non-PTB (Over 1 MW) ESI Ids are being addressed through another process
.
4
Market Synchronization Update
• RMS synchronization plan was approved at TAC unanimously
• Kick off Conference Call meeting took place 5/21
a) Minutes distributed 5/22
• Most TDSPs and CRs have identified at least one business and one technical contact to work with ERCOT
• All parties agreed to action plan:
a) Each MP will ensure internal/provider systems are synchronized
b) A test run will occur to ensure queries and file layout are correct
c) This test run begins on May 29th and will complete by June 7th
5
PTB Synchronization Plan - Next Steps
• Market continues to support plan with appropriate technical and business resources being assigned.
• Test files will be processed by ERCOT and finalize format and comparison programs verified.
• ERCOT will work with MPs to correct any file format issues.
• Pull together a detailed project plan to evaluate differences at a point in time and document steps required to correct
• Full data send/analysis will take place once test run is complete
• Report through RMS
6
Questions
7
Portal Performance History (Find ESI IDs) May 29, 2002
Total hits per week
Unsuccessful hitsWeek By Week ESIID Hits Versus Errors
0
5000
10000
15000
20000
25000
W/E1/5
W/E1/12
W/E1/19
W/E1/26
W/E2/2
W/E2/9
W/E2/16
W/E2/23
W/E3/2
W/E3/9
W/E3/16
W/E3/23
W/E3/30
W/E4/6
W/E4/13
W/E4/20
W/E4/26
W/E5/4
W/E5/10
W/E5/18
W/E5/24
Week Ending
Hit
s
24% 14% 31% 22% 26% 28% 16% 5% 13%18% 11% 22% 9%13% 14% 25% 15% 14% 7% 9% 13%
8
Portal Performance Items
• Mux E Way fix from Seebeyond on week of 3/30– Saw a temporary 7 % improvement
• Moved Portal E Ways to New Hardware week of 4/13– Saw a temporary 10 % improvement
• Added components (threads) on 4/25– Showed some very promising improvements
• Additional Architecture change was made 5/21– Removed TCH component competing with batch transactions– Seeing a 30% improvement in errors– Also added “heartbeat” functionality to verify EAI every minute
• Looking at 2 additional improvements currently being tested– Moving Siebel queries directly to Oracle– Improvements in redundancy for find transactions
• Future options also being evaluated– Additional redundant paths for Portal transactions– Continue to analyze errors and respond
9
Questions
10
IDR Meter Usage Report (data submitted 8 weeks following Trade date)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Market CPL Reliant TNMP Oncor WTU
% ID
R in
Lod
esta
r
12-Oct-01
7-Dec-01
1-Feb-02
29-Mar-02
26-Apr-02
24-May-02
11
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
8/3 8/17 8/31 9/14 9/28 10/12 10/26 11/9 11/23 12/7 12/21 1/4 1/18 2/1 2/15 3/1 3/15 3/29 4/12 4/26 5/10 5/24
Date
Per
cen
t
Market
CPL
Reliant
TNMP
Oncor
WTU
IDR Meter Usage Report (as of 5/28/02)Percent of IDR accounts received by ERCOT since August
* NOTE: ERCOT (and REPs) may have received additional non-sequential data (i.e, February data before January data). ERCOT rejects all meter reads that introduce gaps in the database
95% or better expected
63%
12
NIDR Meter Usage Report Percent of NIDR accounts received by ERCOT since August
0.0%
10.0%
20.0%
30.0%
40.0%
50.0%
60.0%
70.0%
80.0%
90.0%
100.0%
8/3 8/17 8/31 9/14 9/28 10/12 10/26 11/9 11/23 12/7 12/21 1/4 1/18 2/1 2/15 3/1 3/15 3/29 4/12 4/26
Last Read Greater Than
Per
cen
tag
e
Market Apr-2002
Market Feb-2002
Market Jan-2002
Market Dec-2001
Market May-2002
95% or better expected
13
Questions
14
867-03 Forward Update
• Data Provided on Existing MP Reports will allow reconciliation
15
867-03 Forward Update
• ERCOT Data for May 1 to May 26, 2002
– 5,557,189 Usage transactions received at ERCOT
– 99.91% forwarded, 5,551,739 transactions
– 5,776 Not forwarded due to invalid forwarding Duns numbers
16
867-03 Forwards – Sample Timings
RUN_DATE TRANS_TYPE TPTNER_ID TRANS_NO Transaction Mapping Status SIID
CPL to ERCOT (AES is FWD Receiver) - Inbound Time of Processing 2:20 PM 5/1/2002ERCOT to AES - Outbound Time of Processing 3:22 PM 5/1/2002
5/1/2002 3:22:02 PM 867_03 8797234681000 946160330020020430221752521940 Accept 10032789481815780
5/1/2002 2:20:51 PM 867_03 007924772 946160330020020430221752521940 Accept 10032789481815780
TNMP to ERCOT (REL RETAIL is FWD Receiver) - Inbound Time of Processing 7:53 AM 5/2/2002ERCOT to REL RETAIL - Outbound Time of Processing 8:13 AM 5/2/2002
5/2/2002 8:13:16 AM 867_03 799530915 20020502867000033 Accept 10400514015920001
5/2/2002 7:53:06 AM 867_03 007929441 20020502867000033 Accept 10400514015920001
REHLP to ERCOT (CALPINE is FWD Receiver) - Inbound Time of Processing 9:48 PM 5/3/2002ERCOT to CALPINE - Outbound Time of Processing 10:16 PM 5/3/2002
5/3/2002 10:16:10 PM 867_03 1127108761000 REL86703A20020501202634 Accept 1008901000140140013100
5/3/2002 9:48:53 PM 867_03 957877905 REL86703A20020501202634 Accept 1008901000140140013100
CPL to ERCOT (CORAL POWER is FWD Receiver) - Inbound Time of Processing 11:30 PM 5/4/2002ERCOT to CORAL POWER - Outbound Time of Processing 11:44 AM 5/4/2002
5/4/2002 11:44:50 AM 867_03 9375172661000 944084541020020503223704326835 Accept 10032789412332150
5/4/2002 11:30:05 AM 867_03 007924772 944084541020020503223704326835 Accept 10032789412332150
CPL to ERCOT (DYNEGY is FWD Receiver) - Inbound Time of Processing 12:56 PM 5/10/2002ERCOT to DYNEGY - Outbound Time of Processing 2:20 PM 5/10/2002
5/10/2002 2:20:41 PM 867_03 009924445 943008693020020509230139716714 Accept 10032789483089721
5/10/2002 12:56:53 PM 867_03 007924772 943008693020020509230139716714 Accept 10032789483089721
17
867-03 Forwarding
• ERCOT believes we are forwarding all 867s that have forwarding information provided
• ERCOT provides 867 forwarding information on the current MP reports to facilitate reconciliation
• ERCOT samples of turn around time are well within protocols
• Next Steps– Should point to point 867 continue?– If MPs believe ERCOT is not properly forwarding 867-03s, provide
Examples for ERCOT to check
18
Questions
19
Questions