TERMINAL LEARNING OBJECTIVE

ACTION: Perform COFT Operations

CONDITION: Given a COFT, COFT IUH, and in a classroom environment

STANDARDS: I/O student must demonstrate knowledge of proper COFT training by achieving 80% or higher on the I/O end of course exam and achieve an overall “GO” on all hands on test

COFT SAFETY BRIEFING

SAFETY:

• Tampering with equipment is prohibited and horseplay will not be tolerated

• CVC helmets must be worn in the Crew Station at all times

• No food, drinks, smoking or smokeless tobacco are allowed in the training area

• Use all required references during maintenance and training

• Do not walk on or move any cables, or touch any electrical connections

COFT SAFETY BRIEFING (Con’t)

• Know the location and function of the three Emergency Shutdown Switches

• Know where the fire extinguishers are, how to use them, the location of emergency exits and the Shelter Emergency Shutdown Switches

• Observe all CAUTION and WARNING labels throughout the trainer

• Do not permit any activity in the COFT that is unsafe in the BFV

Risk Assessment Level: Moderate, due to potential for exposed high voltage cables

Environmental Considerations: None

Evaluation: I/O student must demonstrate knowledge of proper COFT training by achieving 80% or higher on the I/O end of course exam and achieve an overall “GO” on all hands on test

ENABLING LEARNING OBJECTIVE A

ACTION: Identify COFT Components and Characteristics

CONDITION: Given a COFT, COFT IUH, and classroom instruction

STANDARDS: Student must adhere to policies and procedures throughout entire I/O course

• Crew Station

• Instructor/Operator Station (IOS)

• Computer Rack

MAJOR COMPONENTS

CREW STATION

INSTRUCTOR OPERATOR STATION (IOS)

COMPUTER RACK

The computer rack consists of the following components:

PrinterModSAF ComputerIOS ComputerIG1 ComputerIG2 ComputerBVE ComputerKVM Switcher

ENABLING LEARNING OBJECTIVE B

ACTION: Perform COFT Power Up

CONDITION: Given a COFT, COFT IUH, and in a classroom environment

STANDARDS: Successfully power up the COFT IAW with IUH

Power Up Procedure

Shelter Preconditioning Procedures

Shelter Door Vent

Fire Protection Panel

Shelter Lighting SwitchesEmergency Light

Power Up Procedure

Shelter Preconditioning Procedures

Door Locking Pin

Air Conditioner Louvers

Hygrometer/Thermometer

Observe the hygrometer/thermometer in the Training Shelter. If the temperature reading is between 60º F and 90ºF (15ºC and 30ºC) and relative humidity is between 20 and 70 percent, refer to (ADD TM #), Unusual Electronic Equipment Power-Up Procedure

Power Up Procedure

A/C Mode Selector

Shelter A/C Mode Selector Switch Setting

Outside Temperatur

e Ranges

ComputerShelter

TrainerShelter

IntecShelter

51AC1 51AC2 51AC3 52AC1 53AC1

-40ºF to -5ºF-40ºC to -20ºC

Vent Heat Cool Heat Heat

-5ºF to 20ºF-20ºC to 6.7ºC

Vent Heat Cool Cool Heat

20ºF to 68ºF-6.7ºC to 20ºC

Cool Vent Cool Cool Heat

68ºF to 80ºF20ºC to 26.7ºC

Cool Vent Cool Cool Cool

80ºF to 125ºF26.7ºC - 51.7ºC

Cool Cool Cool Cool Cool

Humidifier Tank Water Level Gage

Power Up Procedure

Main Circuit Breaker

Circuit Breakers 2 and 6

Power Up Procedure

Main Power 208VAC

MainCircuit Breaker

AC ON Lamp

Power Up Procedure

Key-switch AC ON Lamp

Once the key-switch is turned on, wait until the monitor displays the System Startup screen before continuing

System Start Up

Power Up Procedure

Crew StationAuxiliary Equipment

AC ON Lamps

DC Power Lamps

Power Up Procedure

AC ON Lamp

Crew Station (CFP/ISUW)

Power Up Procedure

AC ON Lamp

AC ON Lamp

Intercom & Test equipment

Crew Compartment Power

Brow Pad

System Start Up

System Start Up

ENABLING LEARNING OBJECTIVE C

ACTION: Manage COFT Time Logbook

CONDITION: Given a COFT, COFT IUH, and in a classroom environment

STANDARDS: Manage system logbook in accordance with IUH TM 9-6930-712-12

COFT TIME LOGBOOK

SIGNATURE

Ernie Lindquist

Ernie Lindquist

Brad Tesch (FSR)

Ernie Lindquist

Ernie Lindquist

Ernie LindquistBrad Tesch (FSR)

Ernie Lindquist

Ernie Lindquist

MIN

30

ACCOUNTABLEFAILURE TIME

HRS

3

5

BLDG 5500LOCATION: Fort Benning

ETM

123.1

128.3

128.3

140.5

140.5

142.3

142.3

152.1

SERIAL NO. 4962

REMARKS

Power up

Power down

Power up

WCB: HE ammo would not selectNotified FSR

Replaced ammo selection switch

Power down

Power upCTD power went down

Notified FSR

Power up

Power down

TIME (00:00)

14:00

19:00

06:00

18:25

11:25

17:00

03:00

09:30

15:00

23:00

COFT SYSTEM LOGDAILY OPERATIONS

DATE(MMDDYY)

01/05/03

01/05/03

01/06/03

01/06/03

01/06/03

01/06/03

01/07/03

01/07/03

01/07/03

01/07/03

DA FORM XXX-A-R

ENABLING LEARNING OBJECTIVE D

ACTION: Perform Instructor Login and Log Off

CONDITION: Given a COFT, COFT IUH, and in a classroom environment

STANDARDS: Successfully perform COFT Instructor Login and Log Off procedures in IAW, IUH TM 9-6930-712-12

System Login

2/8IN A11

INSTRUCTOR LOG OFF

Log Off

ENABLING LEARNING OBJECTIVE E

ACTION: Perform COFT Power-down

CONDITION: Given a COFT, COFT IUH, and in a classroom environment

STANDARDS: Successfully Power-down the COFT, in sequence and in accordance with IUH TM 9-6930-712-12

Power Down Procedure

Quit

Power Down Procedure

Viewgraph J-17

Power Down Procedure

Ensure Power Lamps go off

Last computer Lamp remains on

Power Down Procedure

Main Circuit BreakerCrew Station (CFP/ISUW)

Key-switch

Crew StationAuxiliary Equipment)

TERMINAL LEARNING OBJECTIVE

ACTION: Perform COFT Operations

CONDITION: Given a COFT, COFT IUH, and in a classroom environment

STANDARDS: I/O student must demonstrate knowledge of proper COFT training by achieving 80% or higher on the I/O end of course exam and achieve an overall “GO” on all hands on test

SUMMARY

ELO A: Identify COFT Components and Characteristics

ELO B: Perform COFT Power-up

ELO C: Manage COFT Time Logbook

ELO D: Perform Instructor Logoff

ELO E: Perform COFT Power-down