Treasure Island Development Authority

Treasure Island Development Program

Item 6: 2017 – The Year Ahead

February 7, 2017

Treasure Island Development Authority

• TIDA Board welcomed Sam Moss

• Transferred development parcels in the first subphase areas to TICD

• Secured BCDC Major Permit Approval

• Accepted second Navy land transfer

• Completed demolition of structures on Yerba Buena Island & initiated demolition on Treasure Island

• New westbound Bay Briddge on/off ramps opened

• Initiated formation of public financing districts

• Caltrans opened bike path to YBI

2016 – Events & Milestones

Treasure Island Development Authority

• Anticipate three property

transfers in 2017

• Field work complete in Site 24

• Completion of Site 12 TCRA and

Stage III Removal Actions

• Stage IV work to begin late 2017

or early 2018

Navy Property Transfers

Parcel FOST Date

Parcels Building 233, UC 1 & UC 2 6 Pending

Parcels 30, 30N, 30S, 30W & 31 7 01/31/2017

Parcels 6 & 32 8 07/31/2017

Parcel 24 9 01/30/2018

Parcel 2 10 12/31/2020

Parcels 12A, 12B & Navy

Retained Sites11 12/31/2021

3

Treasure Island Development Authority

• Secure Secure permit approvals for infrastructure improvements

• Secure tentative and final subdivision map approvals

• Draft Public Improvement Agreements

• Prepare design construction documents for open space projects

2017 – Design

Treasure Island Development Authority

Construction Activity – 2017

• Complete demolition in initial Treasure Island sub-phase area

• Initial infrastructure contracts awarded, bid, or advertised• Water reservoir design/build

• Yerba Buena utility/right-of-way infrastructure

• Geotechnical & causeway reconstruction

• Treasure Island utility/right-of-way infrastructure

• Tree removal/relocation/preservation

5

Mobilizing in March

Treasure Island Development Authority

Construction Activity

6

Treasure Island Development Authority

2017 – Planning

• Initiate preparation of Subphase Applications for the balance of Major Phase 1

Treasure Island Development Authority

• Continue planning for congestion management implementation

• Negotiate operating MOUs with AC Transit & WETA

• Begin construction of Southgate/Hillcrest interchange

• Advance design for the westside viaducts

• With SFMTA study/develop parking policies

2017 – TIMMA

Treasure Island Development Authority

• Finalize long-term leases with Treasure Island Enterprises and Treasure Island Sailing Center

• Begin BCDC application process with TIE

2017 – Clipper Cove