Merancas Classroom Building

Weekly Update May 31, 2019

Merancas Campus

Meetings & Milestones

• This Week:

• Placed Area A and B Slab on Grade• Completed Underground Electrical• Completed Underground Plumbing• Strip Area A and B Forms• Place Area C Forms• Place Stone in Area C• Installed Area C Vapor Barrier • Placed Area C Rebar Mesh• Subcontractor Meeting

• 05/28/19 at 10:00AM

• OACG Meeting• 05/28/19 at 1:30PM

• Balance of Work Re-Bid• 05/29/19 at 2:00PM

Meetings & Milestones

• Next Week:

• Complete Area C Slab on Grade Prep

• Pour Area C Slab on Grade 06/04

• Strip Area C Slab on Grade Forms

• Begin Steel Erection

• Subcontractor Meeting

• 06/04/19 at 10:00AM

• State Construction Meeting

• 06/04/19 at 1:30PM

Progress Photos

Place Area A Slab

on Grade

Progress Photos

Place Area A Slab on

Grade

Progress Photos

Place Area B Slab

on Grade

Progress Photos

Wet Cure Area A

and B

Progress Photos

Area C Slab on

Grade Form Work

Progress Photos

Placed Area C

Stone

Progress Photos

Placed Area C

Vapor Barrier

Progress Photos

Placed Area C

Rebar Mesh

Progress Photos

Area C

Underground

Electrical Conduit

Conclusion of Weekly Update 05/31/2019