ams-02 tracker mechanics status of assembly and integration

31
AMS-02 tracker mechanics status of assembly and integration Inner tracker integration completion: - Assembly and cabling - Temperature and magnetic field sensors - Shells closing and flanges mounting - Tooling Preparations for pre-integration: - Test of evaporators (cooling loops) integration + tools - Pre-assembly of outer planes with inner tracker + tools - Cabling issues studies - Jigs for transport and storage at CERN - Tracker configuration for LBBX (TAS) mounting - Integration sequence - Issues to be solved Divic RAPIN, UniGe AMS TIM July 2007

Upload: alden

Post on 11-Jan-2016

49 views

Category:

Documents


0 download

DESCRIPTION

Inner tracker integration completion: - Assembly and cabling - Temperature and magnetic field sensors - Shells closing and flanges mounting - Tooling Preparations for pre-integration: - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: AMS-02  tracker mechanics status of assembly  and  integration

AMS-02 tracker mechanicsstatus of assembly and integration

Inner tracker integration completion: - Assembly and cabling - Temperature and magnetic field sensors - Shells closing and flanges mounting - ToolingPreparations for pre-integration: - Test of evaporators (cooling loops) integration + tools

- Pre-assembly of outer planes with inner tracker + tools - Cabling issues studies - Jigs for transport and storage at CERN

- Tracker configuration for LBBX (TAS) mounting - Integration sequence - Issues to be solved

Divic RAPIN, UniGe AMS TIM July 2007

Page 2: AMS-02  tracker mechanics status of assembly  and  integration

General view of Silicon tracker• 5 planes, 8 layers

• Plane 1, layer 1• Plane 2, layers 2&3• Plane 3, layers 4&5• Plane 4, layers 6&7• Plane 5, layer 8

• 192 ladder modules• 1024 electronic channel/module

200’000 channels

Planes are supported by shells and conical flanges. (not shown)

Page 3: AMS-02  tracker mechanics status of assembly  and  integration

Ladder Assembly (Perugia-Geneva)

• ASSEMBLY• ~ 210 ladders build

• PHASE 2 hybrid box & legs gluing

• EMI SHIELDING ( kapton foil wrapping)

• Full test at each step with RA source and noise control

Page 4: AMS-02  tracker mechanics status of assembly  and  integration

Installation of ladders on support planes (UniGe clean room)

Plane 3 being stored (under Nitrogen)

Details of fixation on both sides

Page 5: AMS-02  tracker mechanics status of assembly  and  integration

Assembly of the inner tracker in the Durga jig

• Set-up for storage & insertion into the magnet.

• Cables must be installed before the supporting shells and extra length must be attached to temporary supports.

Page 6: AMS-02  tracker mechanics status of assembly  and  integration

Tracker with cables but without closing and supporting shells

Temporary storage of cables

384 flat cables from ladders to electronics

Page 7: AMS-02  tracker mechanics status of assembly  and  integration

Temperature (Dallas) and B-field sensors have been tested before closing of the inner tracker (A.Lebedev and U.Roeser)

B-field sensor

T-sensors

Page 8: AMS-02  tracker mechanics status of assembly  and  integration

Closing inner tracker and disconnection from Durga jig

Page 9: AMS-02  tracker mechanics status of assembly  and  integration

Removing inner tracker from Durga assembly jig

Page 10: AMS-02  tracker mechanics status of assembly  and  integration

Complete installation and assembly jigOuter ring assembly

and installation jig

Inner ring assembly and installation jig

Cooling loops are fragile and not self supporting. They need to be kept in jigs for fabrication, storage, transport and assembly

Tests of integration of cooling loops on outer plane (1) and on inner tracker (top)

Page 11: AMS-02  tracker mechanics status of assembly  and  integration

Outer cooling loop on plane 1

Jigs and support pieces were developed in order to manipulate the plane and to install cables and cooling loop at the same time

Page 12: AMS-02  tracker mechanics status of assembly  and  integration

Test integration of the inner cooling loop

Page 13: AMS-02  tracker mechanics status of assembly  and  integration

Test integration of the inner cooling loop

Real life will be less easy due to dimensions of vacuum tank

Page 14: AMS-02  tracker mechanics status of assembly  and  integration

Test integration of the inner cooling

loop

Page 15: AMS-02  tracker mechanics status of assembly  and  integration

Test integration of the inner cooling loop

It fits perfectly

Page 16: AMS-02  tracker mechanics status of assembly  and  integration

Test integration of outer plane on inner tracker (with loops)

Jig for cable storage and crane manipulation of outer planes (compatible with loop)

Page 17: AMS-02  tracker mechanics status of assembly  and  integration

Test integration of outer plane on inner tracker (with loops)

Guiding spacers to prevent damaging contacts between ladders and conical flange during approach of the outer plane.

Device allowing safe and precise approach of the outer plane for the last 25 mm.

Page 18: AMS-02  tracker mechanics status of assembly  and  integration

Study of cabling related issues

Star tracker support region

Tracker feet regions

Page 19: AMS-02  tracker mechanics status of assembly  and  integration

Inner tracker support for storage and transportation (AMS01 test beam frame)

The present state of the tracker (no loops, both outer planes mounted) is convenient for LBBX (TAS) adjustment and installation. (not for transportation)

Page 20: AMS-02  tracker mechanics status of assembly  and  integration

TRACKER (MECHANICAL) INTEGRATION SEQUENCE

(simplified)

- Sequence dictated by topology

- Up or upside down position not specified hereafter

Page 21: AMS-02  tracker mechanics status of assembly  and  integration

Start: four separate boxes

Two outer planes with:- cables, loop, LBBX+fibers

Inner tracker with:- cables, upper inner loop

Lower inner loop

Page 22: AMS-02  tracker mechanics status of assembly  and  integration

Step 1: insertion (lower flange removed)

Page 23: AMS-02  tracker mechanics status of assembly  and  integration

Step 2: four upper feet installation

Next: prepare lower conical flange

Page 24: AMS-02  tracker mechanics status of assembly  and  integration

Step 3: lower conical flange installation

Page 25: AMS-02  tracker mechanics status of assembly  and  integration

Step 4: four lower feet installation

After this operation, tracker and vacuum case can be rotated

Page 26: AMS-02  tracker mechanics status of assembly  and  integration

Step 5: unfold and secure cables (and remove supports)

Prepare lower inner loop

From this step, TOP and BOTTOM operations are independent

Page 27: AMS-02  tracker mechanics status of assembly  and  integration

Step 6: Install lower inner loop

Next: outer planes

Page 28: AMS-02  tracker mechanics status of assembly  and  integration

Step 6: Install outer plane (connect loops)

Page 29: AMS-02  tracker mechanics status of assembly  and  integration

Step 7: unfold and secure cables (and remove supports)

Connect to crates

Page 30: AMS-02  tracker mechanics status of assembly  and  integration

Next operations and open issues

• Cooling loop modification + new connectors (Splinter meeting this TIM)

• VC metrology (Splinter meeting this TIM)

• Balcony design (already started by F.Cadoux) and production (TBD).

• Detailed cable routing (in progress)

• LBBX installation (WW during August).

• Containers for outer planes and covers for inner tracker frame (UniGe)

• Outer planes: Installation of cooling loop, cables and test (UneGe

• Light tightness (UniGe)

• Revision and completion of detailed procedures (E.P. and D.R.)

Page 31: AMS-02  tracker mechanics status of assembly  and  integration

Near future integration operations at UniGe•Design of storage and transport jigs for inner tracker and outer planes (re-use of Alu frame used for AMS01 beam test) (in progress)

•Design and construction of outer plane installation jig.

•Supporting shells installation and remove inner tracker from Durga.

•Pre-assembly of inner evaporator on inner tracker (check mountability).

•Pre-assembly of outer planes (check mountability) on inner tracker.

•Time requested by TAS for laser beam alignment/installation.

•Orbital welding of new connectors is needed for upper/lower inner/outer evaporators (on critical path)

Conclusion of the April 2007 TIM presentation of D.R.