an evaluation of production output for in situ concrete work

398

Upload: phungbao

Post on 01-Jan-2017

222 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: An evaluation of production output for in situ concrete work

Loughborough UniversityInstitutional Repository

An evaluation of productionoutput for in situ concrete

work

This item was submitted to Loughborough University's Institutional Repositoryby the/an author.

Additional Information:

• A Doctoral Thesis. Submitted in partial fulfillment of the requirementsfor the award of Doctor of Philosophy of Loughborough University.

Metadata Record: https://dspace.lboro.ac.uk/2134/7285

Publisher: c© Andrew David Freeman Price

Please cite the published version.

Page 2: An evaluation of production output for in situ concrete work

This item is held in Loughborough University’s Institutional Repository (https://dspace.lboro.ac.uk/) and was harvested from the British Library’s EThOS service (http://www.ethos.bl.uk/). It is made available under the

following Creative Commons Licence conditions.

For the full text of this licence, please go to: http://creativecommons.org/licenses/by-nc-nd/2.5/

Page 3: An evaluation of production output for in situ concrete work

AN EVALUATION OF PROI*JCTION (XJTRJT

FOR IN SII1J COiCEETE WORK

by

ANDRJ DAVID FREEMAN PRICE, B.Sc.

A Doctoral Thesis submitted in partial fulfilment of the requirements

for the award of DOCTOR OF PHILOSOPHY of the LOUGHBOROUGH UNIVERSU!

OF TECHNOLOGY. June 1986.

c ANDRJ DAVID FREEMAN PRICE 1986

Page 4: An evaluation of production output for in situ concrete work

1ABLE OF CONTENTS

Abstract

Declaration

Acknowledgements

List of Sections

List of Appendices

List of Figures

List of Tables

Page

ii

iv

V

viii

xiv

xix

xxv

Sections 1

References and Bibliography 311

(1)

Page 5: An evaluation of production output for in situ concrete work

ABSTRACT

The overall aim of this thesis is to develop reliable methods of

measuring output levels for construction plant and labour, with a

view to establishing realistic output rates for concretingoperations.

This thesis demonstrates that most of the variability in

production rates can be quickly explained, leaving relativelyconstant levels of output f or individual construction operations

(i.e. basic operation times). The primary factors in determiningoutput rates were found to be work rate, delays and waiting causedby poor management, and poor motivation.

The latter two items accounted f or more than fifty per cent ofthe available working time on many sites, whereas work rate varied

only slightly. This last finding may be surprising, but the results

indicated that when work was being done the effort applied appeared

fairly constant to the observer. However, the time spent working was

largely dependent upon the level of motivation induced through the

payment system. Where a combination of good direct supervision andsatisfactory financial incentives were present, high levels of

motivation were observed, conversely, low motivation occurred onsites where minimum day-work payments were present.

Investigations into several construction trades indicate that

work study techniques can be modified to meet the requirements ofmost construction operations, sites and companies, whether the

requirements be a complex synthesis of basic operation times or themore simple determination of site efficiency. The key to this

portability lies in the isolation of basic operation times via theapplication of site efficiency factors.

(Ii)

Page 6: An evaluation of production output for in situ concrete work

In this thesis, primary work study techniques are identified

and discussed. The need for specific construction work studytechniques is shown to be of paramount importance.

The results from over seventy concrete pours are combined andstatistically analysed to produce realistic output rates arid currentlevels of production.

Site factors are combined and statistically analysed to producea relationship between efficiency and level of remuneration.

A comparison is drawn between: the production rates achieved onseveral sites; and the output rates currently being used in the

planning and estimating processes.

(Iii)

Page 7: An evaluation of production output for in situ concrete work

DELABATION

No portion of the research referred to in this thesis has

been submitted in support of an application f or another degree or

qualification at this or any other university or other institution

of learning.

(iv)

Page 8: An evaluation of production output for in situ concrete work

ACKNJLEDGE14ENTS

My sincere thanks goes to Dr Frank Harris for his catalytic

guidance and unfailing support, without which this thesis would not

have been completed.

I know that Anne, my wife, has suffered in many ways

throughout this research; I hope she will now take pride in its

completion for she has been a profound source of' encouragement.

This research has been undertaken within the subject area

Construction Technolor and Management in the Department of' Civil

Engineering at the Loughborough University of' Technology. I am

grateful to my family, friends and colleagues for their support and

constructive advice. In particular I wish to thank Frank Harris,

Margaret Emsley for proof reading the thesis during the final

stages, Vera Cole for mastering the word processor so competently

and cheerfully, Tony Wilson f or help with all computing matters and

Tony Pettitt of the Mathematics Department for advice on all

statistical aspects.

Finally, I wish to express my gratitude to the individuals and

organizations who provided considerable assistance during this

research. The construction industry is often castigated for its

unwillingness to support research, however, I found full co-operation

and openness from the following collaborators.

Cv)

Page 9: An evaluation of production output for in situ concrete work

1.

2.

3.

IL

5.

6.

7.

8.

9.

10.

11.

12.

13.ill.

15.

16.

17.

18.

19.

20.

21.

22.

23.

21k.

25.

26.

21.

28.

29.

30.

Collaborators an& tvoes or contract made available

Thomas Fish & Sons - 2 contracts, mainly foundations

A. Monk & Co. - 3 contracts, motorway, pit head

works, road drainage

French Kier - 1 contract, concrete floors

Wrekin Construction - 1 contract, concrete reservoir

Willett - 1 contract, concrete frame

G. Dew & Co. - 1 contract, concrete reservoir

Mowlem (Northern) - 3 contracts, brickwork to housing

- and a police station

Sindall & Co. - 2 contracts, brickwork to housing

Geo. Hodges - I contract, structural steel-work

Wm. Moss - 1 contract, structural steel-work

Shand Alexander - 2 contracts, earthmoving, structural

steel-work

John Laing Construction - 2 contracts, multi-storey concrete

frames

Wm. Davies - 1 contract, precast concrete

Taylor Woodrow - 1 contract, structural steel-work

B. Roberts - 1 contract, precast concrete

H. & E. Loach - 2 contracts, structural steel and

precast units

Y. S. Lovell Group - 1 contract, reinforced concrete

Trent Concrete - 1 contract, pro-cast concrete units

Crendon Structures - 3 contracts, pre-cast concrete frames

So]. Construction - 1 contract, structural steel-work

Shands Mining - 1 contract, open cast coal mine

D.P. McErlain Ltd. - 1 contract, open cast coal mine

Brown & Davies

(Manchester) - 1 contract, pre-cast concrete frame

Hinks & Frewin (Oxon)

- 1 contract, pre-cast concrete frame

Denham & Cole - 1 contract, pro-cast concrete frame

R.A. Whittacker & Son

(Erection) - 1 contract, structural steel-work

McFarson Construction - I contract, structural steel-work

Bison Concrete - 1 contract, pro-cast concrete

Richard Lees - 2 contracts, pre-cast concrete

J.M. Erections - 1 contract, structural steel-work

(vi)

Page 10: An evaluation of production output for in situ concrete work

Other Collaborators

In the early stages of this research, several organizationswith work study experience and whose work was of a similar natureto construction work were contacted. The following fourteen

organizations made varying contributions to the research.

Contractors with Work Study Data

John Laing Construction Ltd.Winipey Construction Ltd.

Henry Boot Ltd.

Local Authorities

Llncolnshire County Council

Cornwall County CouncilNottinghamshire County Council

Norfolk County Council

Others

Joint Industry Board F or the Electrical Contracting Industry

British Waterways

Building Services Research and Information Association

Building Research AssociationBuilding Advisory Service

Transport and Road Research LaboratoryBircham Newton Training Centre

(vii)

Page 11: An evaluation of production output for in situ concrete work

LIST OF SECTIONS

PageSection

1.0 INTRODUCTION

1.1 INTRODUCTION TO SUBJECT MATTER

1.2 £BJECTIVES

1.2.1 Develoixnent of a Production Analysis

Method Specifically for Construction

Operations

1.2.2 Establishing Realistic Output Rates

1.3 METHODLOGY

1.1 GUIDE TO ThESIS

2.0 WORK SWDY IN PERSPECTIVE

2.1 INTRODUCTION TO WORK STUDY

2.2 HISTORY AND LITERATURE REWIEW

2.2.1 Leonardo da Vinci

2.2.2 Pioneers of' Work Measurement

2.2.3 F.W. Taylor (1856-1915)

2.2.4 F.B. Gilbreth (1868_192 1 ) and L.M. Gilbreth

2.2.5 C.E. Bedaux (1887_191I1)

2.2.6 L.M.C. Tippet

2.2.7 H.B. Maynard

2.2.8 Later Developnents

2.2.9 Recent Trends

(viii)

1

2

5

6

8

10

11

12

12

12

13

15

17

17

18

18

19

Page 12: An evaluation of production output for in situ concrete work

Section Page

2.3 CONSTRUCTION WORK STUDY TODAY 20

2.3.1 John Laing Construction 22

2.3.2 Wimpey Construction 23

2 . 3 . 3 Department of' Transport 24

2.3 .4 Nottinghamshire County Council 24

2.3.5 Joint Industry Board for the 25

Electrical Contracting Industry

2.3 .6 British Waterways Board

21

2.3.7 Building Services Research and 28

Information Service

2.3.8 Building Research Establishment 29

2.3.9 Transpbrt and Road Research Laboratory 30

2.4 CONCLUSIONS 31

3.0 WORK MUD! APPLIED W CONSTRUCTION OPERATIONS 32

3.1 INTROIIJCTION

33

3.2 WORK STUDY IECHN]UES

35

3.2.1 Method Study 36

3.2.2 Work Measurement Techniques 37

3.3 PRESENTATION OF OUTPUT RATES 41

3 .3. 1 Current Methods of Presenting 41

Output Data

3.3.2 Proposed Presentation of 44

Output Data

(Lv)

Page 13: An evaluation of production output for in situ concrete work

Section Page

11.0 A METhOD OF DETERMINING BASIC TIMES FOE IN SITU

138

CONCRETING OPERATIONS

Z1 INTRODUCTION

119

11.2 DATA COLLECTION 51

11.3 BASIC TIMES FOR CONCRETE GANG 56

11.3.1 Analysis of Gang Data 56

11.3.2 Synthetic Data for Concrete Gang 57

13.11 BASIC TIMES FOR TCMER CRANES 61

11.11.1 Analysis of Tower Crane Data 61

11.11.2 Synthetic Data for Tower Crane 63

11.5 BALANCING OF RESCURCES

65

5.0 RE)LTS AND ANALYSIS OF BASIC EMENT TIMES

67

FOR ONCE OPERATIVES

5.1 RESULTS FOR CONCRETE OPERATIVES 68

5.2 METhOD OF ANALYSIS 72

5.3 ANALYSIS OF BASIC ELEMENT TIMES

73

5.3 .1 Introduction 73

5.3.2 Prepare Tools (PRTOOL) 76

5.3.3 Pour Concrete (PcUR) 78

5.3.11 Vibrate Concrete (VISE) 82

5.3.5 Shovel Concrete (SHOVEL)

87

5.3.6 Tanip Concrete (TAMP)

89

5.3.7 Trowel Concrete (TR1EL)

91

5.3.8 Cover Concrete (COVER) 911

5.3.9 Clear Tools Away (CLEAR)

95

5.3.10 General Work (GENERAL) 98

5.13 GENERALIZED CONCRETE ?4JDEL

103

Cx)

Page 14: An evaluation of production output for in situ concrete work

Section Page

6.0 RESULTS AND ANALYSIS OF BASIC ELEMENT TIMES FOR

105

CONCRETE PLANT

6.1 INTRODUCTION

6,2 RESULTS FOR CRANAGE OPERATIONS

106

6.2.1 Basic Element Times for Mobile Cranes

106

6.2.2 Basie Element Times for Tower Cranes 106

6.2.3 Cycle Times f or Mobile Cranes

t09

6.2.1! Cycle Times for Tower Cranes 110

6.2.5 Planning Rates for Cranage Operations 116

6.3 RESULTS FOR PUMPING OPERATIONS

118

6.3 . 1 Actual Times f or Pumping Activities 118

6.3.2 Pumping and Output Rates 118

6.3 . 3 Planning Rates 120

6.1! RESULTS FOR DIRECT PQJR OPERATIONS 121

6.I!.1 Introduction 121

6.1!.2 Planning Rates 121

6.1t.3 Calculation of Planning Rates for Direct Pours 122

7.0 CALCULATING STANDARD TIMES

123

7.1 INTRODUCTION

121!

7.2 TRADITIONAL CALCULATION OF RELAXATION ALLCWANCES

126

7.2.1 Fixed Allowances 126

7.2.2 Variable Allowances

126

7.3 A SYSTEM FOR DETERMINING CONSTRIJ CT ION

129

RELAXATION ALLCMANCES

(xl)

J

Page 15: An evaluation of production output for in situ concrete work

Section Page

7.14 RELAXATION ALLCMANCES FOR 'I1E METABOLIC COST OF WORK

130

7.14.1 Calculation of Actual Work Rate in Terms of

131

Energy Expenditure

7.14.2 Derivation of' Relaxation Formulae 138

for !tabolio Cost

7 .14 .3 Relaxation Allowance Calculation 1140

I or tabolic Work

7.14.14 The Effect of' Idle Time on Metabolic Cost

1141

7.14.5 The Effect of' Combined Work Loads 1143

7.14.6 Relaxation Allowance Calculation 1 1414

for Combined Tasks

7 .5 RELAXATION ALLCIdANCES FOR LOCAL MJSCLE FATJUE

1145

7.5.1 Static Muscle Fatigue 1145

7 .5.2 Relaxation Allowance Calculation 1148

for Local Muscle Fatigue

7.5.3 Relaxation Allowances for Static Loads 1149

7.5.14 Abnormal Postures 152

7 .5.5 Dynamic Muscle Fatigue 155

7 .5 .6 Optimization of' Rest Postures 158

7.6 RELAXATION ALLCMANCE FLCM CHART FOR

160

CONS T1J CT ION OPERATIONS

7.7 CALCULATION OF RELAXATION ALLOcIANCES FOR

162

CONCRETE WORK

8.0 CAL(3LATING PLANNING T3

166

8.1 INTRODUCTION

167

8.2 FACTORS AFFECTING CONSTRUCTION PRODUCTIVITY

167

8.3 SITE FACTORS

170

(xii)

Page 16: An evaluation of production output for in situ concrete work

Section Page

9.0 ACThAL SITE FACTORS

17 4

9.1 INTRODUCTION

175

9.2 MEAJRED SITE FACTORS

175

9.3 ANAI.YSIS OF SITE FACTORS

180

9.l DISCUSSION OF RESULTS

186

10.0 COMPARISON OF ACTUAL SITE FACTORS WITH CONTRACTORS'

188

ESTIMATING DATA

10.1 BUILD UP OF ESTIMATING DATA

1 89

10.2 EXAMFLE OF AN ESTIMATED DURATION BASED ON WORK

190

S'IlJDY DATA

10.3 CONTRACTORS' ESTIMATING DATA

190

10.k COMPARISON OF BASIC OPERATION TIMES WITH

ESTIMATING DATA

11.0 CONCLUSIONS, RECO?VENDATIONS AND FURTHER RESEAR

198

11.1 CONCLUSIONS

199

11 .1 .1 Background and Modification of

201

fraditional Techniques

11.1.2 Determination of Basic Operation Times

202

11.1.3 Determination of Standard Times

203

11.1. 11 Construction Productivity and

2O

Site Factors

11.2 RECOMMENDATIONS

20T

11.3 FURTHER RESEARCH

208

('in)

Page 17: An evaluation of production output for in situ concrete work

LISTOFAPPENDICES

Section Page

APPENDIX A CONSTRUCTION WORK SJD! TERMINOLOGY

209

A.1 INTRODUCTION

210

A.2 CONSTIJCTION WORK SIUDY -- CHAPTER ThREE

211

A.3 CLASSIFICATION OF WORK AND IDLE TIMES

214

-- FIGURE 3.1

A. PROPOSED BUILD UP OF TIME STANDARDS

218

-- FIGURE 3.5

A.5 APICATION OF SITE FACTORS TO BASIC TIMES

-- FIGURE 8.2

221

APPENDIX B LISTING OF MINITAB PROGRAMS

222

B.1 PROGRAM 'ONE.MINEXEC'

223

B.1.1 Prepare Tools

223

B.1.2 Pour Concrete 2211

B.1.3 Vibrate Concrete 225

•B.1.4 Shovel Concrete 226

B.1.5 Tamp Concrete 226

B.1.6 Trc*iel Concrete 226

B. 1 .7 Clear Tools Away 227

B.1.8 Cover Concrete

227

B.1.9 General Work

228

(xiv)

Page 18: An evaluation of production output for in situ concrete work

Section

Page

B.2 PROGRAM 'TESTl.MINEXECt

229

B. 3 PRX RAM 'TES T2. MINEXE C'

23 1

B.k PROGRAM 'TES.MINEXEC'

231

B.5 PROGRAM 'TEST.MINEXEC'

233

(xv)

Page 19: An evaluation of production output for in situ concrete work

Section Page

JPPENDIX C BASIC OPERATION TIMES FOR CONCRETE GAN

235

C.1 INTRODUCTION 236

C.2 BASIC OPERATION TIMES FOR CONCRETE ABS

237

C.2.1 Poured Using a Crane and Skip 238

C.2.2 Poured Using Mobile or Static Pumps 2110

C.2.3 Poured Directly from a Lorry 2112

C.3 BASIC OPERATION TIMES FOR CONCRETE BEAMS 21411

C .3.1 Poured Using a Crane and Skip 245

C.3.2 Poured Using Mobile or Statio Pumps 247

C.3.3 Poured Directly from a Lorry 2119

C.k BASIC OPERATION TIMES FOR CONCRETE WALLS 251

C.14.1 Poured Using a Crane and Skip 252

C.1l.2 Poured using Mobile or Static Pumps 2511

C.5 BASIC OPERATION TIMES FOR CONCRETE COLUMNS

256

C.5.1 Poured Using a Crane and Skip 25?

C.5.2 Poured Using Mobile or Static Pumps 259

(xvi)

Page 20: An evaluation of production output for in situ concrete work

Section Page

APPENDIX D COMPUTER PRINT-OUTS

261

D.1 SELECTED PRINT-CUTS FROM ANALYSIS PROGRAMS

262

D.1.1 Print-Out from Analysis of Preparing Tools

263

D. 1 .2 Print-Out from Analysis of Tamping Concrete

277

D.2 PRINT-CUTS FROM TEST PROGRAMS

281

D.2.1 Print-Out from Program 'TESTl.MINEXEC'

282

D.2.2 Print-Out from Program 'TEST2.MINEXEC'

295

D.2.3 Print-Out from Program 'TEST3.MINEXEC' 300

APPENDIX E OPERATIVE MOTIVATION

311

E.1 INTRODUCTION

312

E.2 REVIEW OF MMOR MJTIVATION THEORIES

312

E.2.1 Maslow's Hierarchy of Needs

314

E.2.2 Achievament Motivation Theory 315

E.2.3 Motivation/Hygiene Theory 316

E.2. 1 Eiuity Theories 317

E.2.5 Expectancy/Valence Theory 318

E.2.6 Relationship between Motivation and Performance 323

E.2.7 Summary of Major Motivation Theories 323

E.3 CONSTIUCTION OPERATIVE !4JTIVATION

324

E.3.1 Firancial Incentives 324

E.3.2 rpes of Incentive Schames 324

E.3.3 Ranking of Operatives' Needs 326

E.3 .4 Construction Operative Performance 328

(ivil)

Page 21: An evaluation of production output for in situ concrete work

Section Page

APPENDIX F BASIC STATISTICAL THEORIES

33 1

F.1 INTRODUCTION 331

F.2 MEASURES OF VARIATION

331

F.2.1 Mean Absolute Deviation 332

F2,2 Variance and Standard Deviation 332

F.3 LINEAR CORRELATION

333

F.k LEAST SQUARES RB3RESSION LINES 336

F.5 COEFFICIE2T OF CORRELATION

337

F.6 ANALYSIS OF VARIANCE 338

F.6.1 Example of Analysis of Variance 339

(xviii)

Page 22: An evaluation of production output for in situ concrete work

LIST OF FIGURES

Figure Page

1.1 Flow Chart of' Research

IT

21

26

36

38

113

115

116

119

53/ 511

55

60

2.1

Contributors to Basic Work Study Principles

2.2

Build Up of' Planning and Estimating Rates

3.1

Standard Flow Chart Symbols

3.2 rpical Rating Assesnents

3.3

Current Build Up of Standard Time

3.11 Classification of Work and Idle Times

3.5

Proposed Build Up of Time Standards•

4.1

Operational Diagram

11.2

Activity Sampling Study Sheet

11.3

Activity Sampling Summary Sheet

11.11

Basic Times for Concrete Gang against

Volume of Concrete for Various Slab Depths

11.5

Total Cycle Time against Distance f or

Various Skip Sizes

11.6 Output Rates during Crane Controlled Time

against: (a) Gang Size and Slab Depth for

Concrete Gang; (b) Cycle Time and Skip Size

for Cranes

611

66

(xix)

Page 23: An evaluation of production output for in situ concrete work

Figure Page

5.1 Time Taken to Prepare Tools against Volume 77

of Concrete

5.2 Time Taken to Pour Concrete against Volume 80

of' Concrete for Slabs

5.3 Time Taken to Pour Concrete against Volume 81

of Concrete for Beams and Walls

5.1 Time Taken to Pour Concrete against Volume 82

of Concrete for Columns

5.5 Time Taken to Vibrate Concrete against Volume 811

of Concrete for Slabs

5.6 Time Taken to Vibrate Concrete against Volume 85

of Concrete for Walls and Beams

5.7 Time Taken to Vibrate Concrete against Volume 86

of Concrete for Columns

5.8 Time Taken to Shovel Concrete against Area 88

of Concrete

5.9 Time Taken to Tamp Concrete against Area of' 90

Concrete

5.10 Time Taken to Double Thel Concrete against 92

Area of' Concrete

5.11 Time Taken to Single Trowel Concrete against 93

Area of Concrete

(xx)

Page 24: An evaluation of production output for in situ concrete work

Figure

5.12

5.13

5.111

5.15

6.1

6.2

6.3

6.11

6.5

7.1

7.2

7.3

7.I

Page

96Time Taken to Clear Tools Away against Volume

of Concrete f or Pumping Methods.

Time Taken to Clear Tools Away against Volume

of Concrete for Skip and Direct Pour Methods

Time Spent on General Work against Time Spent

on Other Activities for Skip Methods

Time Spent on General Work against Time Spent

on Other Activities for Pumped and Direct

Pour Methods

Time Taken to Pour Concrete into Skip against

Skip Size

Time Taken to Lift Full Skip against Skip

Size for Mobile Cranes

Cycle Time against Skip Size f or Mobile Cranes

Time Taken to Lift Full Skip and Return flnpty

Skip against Total Distance Travelled f or

Tower Cranes

Cycle Times against Total Distance

Travelled for Tower Cranes

Typical Relaxation Allowances

Power Required against Velocity f or Body Motion,

from Aberg

Power against Velocity for Object Displacement,

from Aberg

Relaxation Allowances for Metabolic Work

(xxi)

97

101

102

111

112

11.3

1111

115

125

1311

135

139

Page 25: An evaluation of production output for in situ concrete work

Figure

7 .5

7.6

7.7

7.8

7.9

7.10

7.11

7.12

7.13

7.111

7.15

7.16

8.1

8.2

152

153

155

157

Page

1112Relaxation Allowance against Average Work

Rate for Various Percentage Times Spent

Wking

Robmert's Curve

Percentage Relaxation Allc,ances for Various

Combinations of Holding Forces and

Holding Times

Local Muscle Fatigue

Maximum Holding Time against Percentage of

Maximum Force Being Applied

Maximum Holding Time for Various Postures

Relationship between Position of' Load

and Region of Pain

Degree of Dynamic Muscle Fatigue

Relaxation Allowances for Dynamic Muscle

Fatigue

Degree of' Fatigue Reached with Time

Relaxation Allowance Flow Chart

Relaxation Allowance Flow Chart - Example

Work Content and Ineffective Time

Application of Site Factors to Basic Times

1115

1117

1118

150

158

161

163

168

171

(rrH)

Page 26: An evaluation of production output for in situ concrete work

Figure Page

9.1 Total Site Factor against Remuneration 179

10.1 Contractors' Data (hours) against 195

Work Study Durations (hours)

3.k Classification of Work and Idle Times 213

3.5 Proposed Buildup of Time Standards 217

8.7 Application of Site Factors to Basic Times 220

C.1 Concrete Slabs Poured Using a Crane and Skip 239

C..2 Concrete Slabs Poured Using Mobile or Static Pumps 2I1

C.3 Concrete Slabs Poured Directly from a Lorry 2'3

c.1 Concrete Beams Poured Using a Crane and Skip 246

C.5 Concrete Beams Poured .Using Mobile or Static Pumps 2'8

C.6 Concrete Beams Poured Directly from a Lorry 250

C.7 Concrete Walls Poured Using a Crane and Skip 253

C.8 Concrete Walls Poured using Mobile or Static Pumps 255

C.9 Concrete Columns Poured Using a Crane and Skip 258

c.10 Concrete Columns Poured Using Mobile or Static Pumps 260

E.1 Maslow's Hierarcy of Needs 311

E.2 Determinants of E—.P Expectancies 319

(xxiii)

Page 27: An evaluation of production output for in situ concrete work

Figure Page

E.3

Determinants of P—.0 Expectancies 320

E.0

Lawler's Expectancy Motivation Model 322

E.5

Total Site Factor against Pay Riuneration5

329

F. 1

Positive Linear Correlation

33l

F.2

Negative Linear Correlation 33k

F.3

Non-linear Correlation 335

F.1

Uneorrelated Results 335

(xxiv)

Page 28: An evaluation of production output for in situ concrete work

Table

2.1

14.1

14.2

14.3

14,14

14.5

5.1

5.2

5.3

5.14

6.1

6.2

6.3

6.14

7.1

7.2

LIST OF TABLES

Page

15

50

52

- 58

61

61

69

70/7 1

75

1014

101

119

120

121

130

Taylor's Study Results

Concrete Dimensions and Quantities

Activities and Codes for Concreting Operations

Basic Elnent Times f or Concrete Gang

Break Points for Tower Cranes

Mean Elnent Times for Tower Cranes

Codes f or Method and Type of' Pour

Basic Elnent Times for each Concrete Pour

Correlation Coefficients (R)

Generalized Concrete Model

Basic E1nent Times for Mobile Cranes

Basic Elnent Times for Tower Cranes

Mean Times for Pumping Activities

Pumping and Output Rates (rrj3/hr)

Calculation of Standard Times

Work Rate Bench Marks

(m)

Page 29: An evaluation of production output for in situ concrete work

Table Page

7.3

Factors for the Aberg Model 131

7.14

Converted Aberg Formula 132

7.5

Power Relating to Body Posture (A) 136

7.6

Power Relating to Type of ActivIty (B)

136

7.7

Activity Durations and Output Rates 1140

7.8

Information Relating to Total Operation 11414

7'9

Relaxation Allowances for Static Pull

151

and Torque

7.10

Posture Groups 1514

7.11

Relaxation Allowance Calculation f or 1614

Concrete Operatives

7.12

Summary of' Total Site Factors 165

8.1

Description of' Added Work Content and 169

Ineffective Time

8.2

Sample Calculation of Site Factors 173

9.1

Site Factors f or Six Concrete Gangs 176

9.2

Site Factors for Six Formwork Gangs 176

9.3

Site Factors for Six Reinforcement Gangs 177

9.14

Site Factors for Five Steel-work Gangs 177

(xxvi)

Page 30: An evaluation of production output for in situ concrete work

Table Page

9.5 Site Factors for Eight Pre-cast Concrete Gangs 178

9.6 Regression Equations for Stage One

181

9.7 Regression Equations for Stage Two 1 83

9.8 Regression Equations f or Stage Three 185

10.1

Estimated Durations for Pouring Slabs 191

10.2 Estimated Durations for Pouring Walls 192

10. 3

Estimated Durations for Pouring Columns 193

10.4

Site Factors (FT) obtained from 194

Estimating Data

7.12

Summary of Total Site Factors 205

C.1 Basic Operation Times for

Concrete Slabs Poured Using a Crane and Skip 238

C.2 Basic Operation Times for

Concrete Slabs Poured Using Mobile or Static Pumps 240

C.3 Basic Operation Times for

Concrete Slabs Poured Directly frcmi a Lorry 242

0.4 Basic Operation Times f or

Concrete Beams Poured Using a Crane and Skip 245

C.5 Basic Operation Times for

Concrete Beams Poured Using Mobile or Static Pumps 247

(xxvii)

Page 31: An evaluation of production output for in situ concrete work

C. 6

Basic Operation Times for

2119

Concrete Beams Poured Directly from a Lorry

C.?

Basic Operation Times for

252

Concrete Walls Poured Using a Crane and Skip

C. 8

Basic Operation Times for 2511

Concrete Walls Poured using Mobile or Static PumpS

C. 9

Basic Operation Times f or

257

Concrete Columns Poured Using a Crane and Skip

C.1O

Basic Operation Times for

259

Concrete Columns Poured Using Mobile or Static Pumps

E. I

Comparison of Incentive Rankings

32?'

F.1

Example of Analysis of Variance

3311

(xxviii)

Page 32: An evaluation of production output for in situ concrete work

CHAPTER ONE

INTROØJCTICN

Page 33: An evaluation of production output for in situ concrete work

UAPTER ONE

INTRODUCTION

1.1 INTRODUCTION TO SUBJECT MATTER

Information on the production output of construction labour and

plant is not generally available; the main reasons for this lie in

the estimating process. Data used by planners and estimators are

rarely collected from historical records, and it is more usual I or

such personnel to accumulate output knowledge as experience gained

through junior to senior positions in an organization (1.1). In this

way the estimator's store of data is gradually t?tunedt, allowing

sufficient tenders to be won at prices which can earn a profit f or

the comparr. Consequently, much output data is remembered rather

than recorded.

To cope with recent developments in construction plant and

methods, planners and estimators have to interpolate new performance

data from existing sources, for example, the selection of suitable

materials handling equipment and proprietary formwork systems. In

addition, there has also been a significant trend towards sub-

contracting and many firms are having to manage a different type of

work force.

2

Page 34: An evaluation of production output for in situ concrete work

It would, thus, seem logical to encourage the investigation of

some of these developments with the view to defining appropriate

methods of working and establishing the corresponding performance

data. The Dutch, for instance, are already. doing this f or their own

conditions, through the monthly journal BIXJWKOSTEN (1.2), which

establishes and updates "guidance production times" f or construction

operations. Such a store of information would also be helpful to

small contractors and independent bodies.

Work loads are reducing and skilled operatives are leaving the

construction industry to join the manufacturing or service industries

where working conditions and payment levels are considerably higher

(1.3). Consequently, the construction industry is undergoing its

most serious upheaval since the thirties, and the beginning of the

eighties is an ideal time for research into the factors affecting

efficiency.

3

Page 35: An evaluation of production output for in situ concrete work

1.2 OBJECTIVES

It was against this background that the research described in

this thesis was developed, the main objective being the establishment

of realistic output values for a major construction operation.

Concrete work was chosen as the operation to concentrate upon as it

is fundamental to most types of construction work. To achieve this

objective, it was necessary to develop specific measurement

techniques and investigate any factors causing variation in

efficiency levels. This research consequently contains two sub-

objectives, namely: -

(a) the development of a production analysis method

specifically I or construction operations; and

(b) the determination of realistic output rates for

concreting operations.

1.2.1 Deve1opent of a Production Analysis Method Specifically for

Construction Operations

For a production analysis method to be effective it should

involve defining, observing, recording and analysing the operation

under consideration. To transform existing work study techniques

into a form suitable f or construction operations, it is necessary to:

(a) Ascertain the work study techniques currently

being used in the manufacturing and construction

industries.

(b) Classify the types of work and idle times

occurring on construction sites.

(c) Develop existing production analysis techniques

into a form suitable for recording construction

operations.

(d) Rationalize the synthesis of elemental data in the

build up of standard data.

"I

Page 36: An evaluation of production output for in situ concrete work

1.2.2 Establishing. Realistic Outnut Rates

The second sub-objective of this research is to establishrealistic output rates for concreting operations. Owing to the

variation in output rates from site to site, it is not acceptable to

purely concentrate on overall output rates, but detailedconsideration is required for different categories of operative time.

Overall output rates depend upon the "total work content" of theoperations performed. Total work content usually comprises threecategories of' operative time, where: "minimum work content" is a

measure of the time required to complete a task under idealsituations; any extra work periods, caused by practical limitations

or inefficient methods are classified as "added work content"; and

idle periods resulting In lost production are known as "lost time",for example, waiting for concrete to arrive on site.

The measurement of site production concentrates upon the

measurement and analysis of total work content and its constituent

parts, with basic times representing the minimum and added workcontent of each operation, and site factors accounting for any lost

time. Therefore, in order to produce realistic output rates for

concreting operations the following steps are required.

(a) The determination of' minimum and added work contentfor concrete operations.

(b) The measurement of' the variation in minimum and

added work content In relation to the quantity ofwork produced.

(a) The determination and measurement of the maincauses of variation in output rates from site to

site.(d) The investigation of' the factors affecting the

motivation and productivity of operatives.(e) The determination of the appropriate relaxation and

contingency allowances to apply with the data.

5

Page 37: An evaluation of production output for in situ concrete work

1.3

To respond to these objectives, this research primarily comprises

development work and field work. After the initial investigations,irwolving several interviews and a work study literature review, the

remaining research is separated into three phases. Figure 1.1presents a flow chart of the research performed over the three years.

There are three sections to this chart, namely: field work and datacollection; development work carried out in conjunction with the

field work; and a summary of the results relating to each phase of

work. -

6

Page 38: An evaluation of production output for in situ concrete work

FIELD WORK DEVELOPMENT WORK CARRIED RESULTS FROM FIELD ANDAND DATA OUT IN CONJUNCTION WITH DEVELOPMENT WORKCOLLECTION EACH PHASE OF FIELD WORK

Interviews A literature review of An up to date evaluationwork study techniques and of current work studyconstruction methods was techniques and typicalperformed. Data data output rates.collection methods for

- the first phase of sitevisits were devised.

Phase I Major revisions were made Detailed measurement ofof site to recording techniques, work content for the mainvisits enabling the variation operations.

in efficiency levels to The determination of thebe measured. suitability of variousAt this point it was work study techniques.

• necessary to rationalize The concept of using sitethe classification and factors as a measure of'presentation of' work efficiency.study data collection.

Phase II The basic theories Isolation of the mainof site relating to operative causes of lostvisits motivation and relaxation productivity.

allowances were developed. The expansion of dataThe method of measuring collection techniques toefficiency in terms of

also record factorssite factors was posited. influencing operative

motivation andrelaxation allowances.

Phase III A statistical analysis of' The determination of' siteof site work content and lost efficiency levels invisits time was performed. relation to main causes

of' lost production.

Figure I • I Plow Chart of Reasea.rch

Page 39: An evaluation of production output for in situ concrete work

1.11 GUIDE TO THESIS

This thesis contains three main areas of research which can be

summarized as: an investigation into the historical background of

work study and how this has influenced the techniques used in the

construction industry today; an analysis of the time spent working

during concreting operations; and an appraisal of the different

types of lost time. These three areas of' research are now discussed

in more detail.

The first area of research (Chapters Two and Three) reviews the

historical development of work study and investigates the application

of' construction work study within individual organizations. In

addition, several work study techniques are discussed and the methods

currently used to present output data are further developed to

represent construction operations more realistically.

The second section demonstrates how standard times are obtained

f or concrete operations. Chapter Four presents an example of a

typical method used throughout this research to collect work study

data. This example is used to illustrate how basic element times are

measured and how the process of synthesis can be used to determine

basic operation times. The results from over seventy concrete pours

are presented in Chapter Five. These results are used to determine

the basic operation times f or concrete operatives, presented in

Appendix C. The study results and basic operation times for the

main plant items associated with concrete work are presented in

Chapter Six.

Basic times are a measure of' the actual work required to

complete a task. The overall time taken (i.e. standard time) should

include allowances for relaxation periods. Chapter Seven

concentrates on the scientific validation of relaxation allowances

and develops previous research into a more coherent structure

suitable for construction operations. A typical relaxation allowance

is obtained tor concrete operations based on the work done during the

concrete pours.

8

Page 40: An evaluation of production output for in situ concrete work

The final section investigates the variation in performance from

site to site, thus, the emphasis is transferred from work content to

lost time. Chapter Eight discusses the main factors affecting

construction productivity and introduces site factors as a method of

measuring performance. The site factors measured on several sites for

several, trades are presented, analysed and discussed in Chapter Nine.

A comparison is subsequently made in Chapter Ten, between output

rates measured on site and data currently being used by estimators.

The conclusions obtained throughout this report are presented in

Chapter Eleven. Recommendations relating to implementation of the

research findings and further research are also put forward.

Additional information relevant to this research is presented in

six appendices. Important terms used throughout this thesis are

presented in Appendix A. Listings of the Minitab programs used to

analyse the data in Chapter Five are contained in Appendix B. A

selection of computer print-outs are presented in Appendix D, and the

resulting basic operation times f or concrete operatives are presented

in Appendix C. To put the observed variation of operative

performance into perspective, traditional motivation theories are

reviewed in Appendix E. The •theory behind the statistical tests used

in the Minitab analysis is discussed in Appendix F.

9

Page 41: An evaluation of production output for in situ concrete work

CHAPTER TWO

WORK SThDT IN PERSPECTIVE

10

Page 42: An evaluation of production output for in situ concrete work

.QfiAPTER TWO

WORK STUDY IN PERSPECTIVE

2 • 1 INTRODUCTION TO WORK STUDY

It is the responsibility of the management of any organizationto ensure that the available resources are utilized most effectively.

Work study is one management tool which can help to achieve this

objective and is defined in the "British Standard Glossary of Terms

used in work study and organization and methods: BS 3138:1978" as:

"A management service based on those techniques,particularly method study and work measurement,

which are used in the examination of human work Inall its contexts, and which lead to the systematic

investigation of all the resources and factors

which affect the efficiency and economy of the

situation being reviewed, in order to effectimprovement." (2.1)

The objective of any method study is to develop the most

economical method of performing a specified 'task. Work measurement

techniques are used to determine how long a certain task should take

to complete. Two work measurement techniques suited to typical

construction operations are: activity sampling f or groups of workersengaged in constantly changing work patterns; and cumulative timing

for machine dominated operations with repetitive work patterns.

11

Page 43: An evaluation of production output for in situ concrete work

2.2 JISTORY AND LITERATURE REVIEW

One can only make a guess as to the date when the idea of

studying work procedures was initially conceived. However, therelatively advanced construction techniques used thousands of years

ago in the erection of many historic civil engineering structures,for example Stonehenge or the Egyptian pyramids, could only have been

developed from detailed examination of working methods. Initially,

the aim of these early work study techniques was to create viable

methods rather than to devise easier and more effective methods.

2.2.1 J.eonardo da Vinci

The earliest records of work study techniques being applied inan industrial, engineering environment were produced by Leonardo da

Vinci (22)• He built up time standards for shovelling operations,

based on a systematic technique involving the breakdown of work into

elements and allowances made for relaxation periods.

2.2.2 Pioneers of Work Measurement

F.W. Taylor's investigations are the basis for many of today'swork measurement techniques; but prior to Taylor, the records of

individuals such as J.R. Perronet (1708-179k), a French civilengineer, indicate that time studies were performed to determineoutput rates.

Not long after Perronet, secret time trials were advocated by

C. Babbage (1798-187 1), a mathematician, in order to obtain reliable

output data. The secrecy was considered necessary to avoid anydeliberate changes in worker speed as a result of being observed.Secret studies are nowadays unacceptable and also totally unwarrantedthanks to modern techniques such as worker rating.

12

Page 44: An evaluation of production output for in situ concrete work

2.2.3 F.W. Tailor (1856-1C)1)

Frederick Winslow Taylor started his working life as anapprentice machinist, progressing through several supervisory levelsto the position of Chief Engineer at the Midvale Steel Works,

Philadelphia. After holding several other managerial posts heentered the field of management consultanoy.

During the early years of his working life Taylor observed thatthe responsibility for output often lay with the workers, who, in

order to preserve pay and jobs, regularly adjusted their performance.

Thus, Taylor realized that one reason for low productivity was

management's inability to assess what constituted a fair day's work.

Unlike many of' his predecessors, Taylor saw that the benefits

from secret studies were very limited, and on moving into managementhe took the view that the corner-stone of any management scheme

should be the co-operation of' the workforce. Thus, Taylor positedthat:

"the principal objective of management should be

the maximum prosperity for the employer and also

maximum prosperity for each employee". (2.3)

In order to achieve maximum prosperity for all parties the

actual division of profit has to be decided upon. Once this has beendetermined all effort can be directed towards increasing the amount

of profit. To ensure that a company remains viable the overalllabour costs must remain realistic. The combination of high wagesand low labour costs can only be produced when a company is operating

efficiently. To help achieve this situation, Taylor introduced a

scientific style of management based on the following principles.

13

Page 45: An evaluation of production output for in situ concrete work

(a) First. The development of a science for each

element of a man's work, thereby replacing the old

rule-of-thumb methods.

(b) Second. The selection of the best worker for each

particular task and then training, teaching, and

developing the workman; in place of the former

practice of allowing the worker to select his own

task and train himself as best he could.

(a) Third. The development of a spirit of hearty

co-operation between the management and the men in

- the carrying out of the activities in accordance

with the principles of the developed science.

(d) Fourth. The division of the work into almost equal

shares between the management and the workers, each

department taking over the work f or which it is the

better fitted; instead of' the former condition, in

which almost all of the work and the greater part

of the responsibility were thrown on the men. (2.k)

Taylor was mainly concerned with the work measurement branch of

work study and the evaluation of a fair day's performance. His

technique involved: dividing a job into basic movements; classifying

the basic element times; determining the relaxation and contingency

allowances; and calculating a time f or the improved method.

Taylor records a number of investigations in his book Scientific

Management (2.5); the most notable of' these was a study into the

conventional shovelling techniques used at the Bethlehem Steel Works

at the beginning of this century. Taylor discovered that shovels of

the same size were used f or materials varying between 3 and 38 lbs.per load. Further studies indicated that the optimal shovel load

weighed 28 lbs., thus, different shovel sizes were introduced for

different materials. Consequently, a saving of' $78,000 was made per

year by adopting the revised method, as summarized in Table 2.1.

111

Page 46: An evaluation of production output for in situ concrete work

Table 2.1 Taylor' s Study Result 3

Before After

Study Study

Number of workers 500 1O

Tons/man/day 16 59

Earnings/man/day $1.15 $1.88

This simple example illustrated that substantial savings were

possible through studying individual, tasks, and also suggested that

the workers lacked the time, skill and motivation required to

establish the most effective method.

2.2. 11 F.B. Gilbreth(1868-1Q211) andL.M. Gilbreth

Frank Bunker Gil breth was of middle class origin and appeared

destined for university when he discontinued his studies and entered

the building trade as an apprentice builder, at the age of seventeen.

His progress over the next ten years was so rapid that he was

appointed as Chief Superintendent at the relatively young age of

twenty-seven. Between 1895 and 1923 he built up his own construction

company, successfully undertaking work in the United States and Great

Britain. Over the years Gilbreth thrived on reducing the amount of

wasted effort and illogical methods often adopted in the construction

industry. As a result his interests in this area became so strong

that he gave up his construction business to become a management

consultant and, in partnership with his wife, achieved an

international reputation f or his contribution to the science of

motion study.

15

Page 47: An evaluation of production output for in situ concrete work

Mr. and Mrs. Gilbreth were responsible, over a period of time,

for consolidating the scientific approach to management techniques.

Much of their work was founded on F.B. Gilbreth's famous studies on

bricklaying methods (2.6)• After systematically, observing the

working methods employed, he realized that bricklayers usually

adopted one of three sets of' motions, depending on their intent to

work quickly or slowly, or in order to train an apprentice. From

this starting point the number of motions involved was reduced from

1 8 to 5, and, as a direct result of reduced work content, the

bricklayers' productivity substantially increased.

As a consultant Gilbreth continued his method studies in many

different industries. His success in the search for the best way of

performing a task was owed to the simple local system that he

adopted. This involved: "defining" the existing situation;

"analysing" the task using specialized equipment; "examining" the

results; "removing" unnecessary tasks; and "synthesizing" the

remaining activities into a new method. Although these basic

principles were earlier used by Taylor, Gilbreth's main contribution

to work study was to actually lay down detailed instructions on how

the study procedure should be implemented.

The Gilbreths' contribution to work study are diverse; the more

notable ones include: the application of' a motion camera to record

certain tasks; the introduction of' a micro-analysis system, called

'THERBLIGS' (Gilbreth spelt backwards) (2.7), which breaks down all

hand motions into seventeen basic elements; the formulation of' a set

of rules f or the synthesis of' elements known as "Rules f or Motion

Economy and Efficiency"; and the isolation of factors, relating to

the worker and environment, affecting the execution of' a task.

16

Page 48: An evaluation of production output for in situ concrete work

2.2.5 C. E. Bedaux (i887-iq)

Prior to Charles E. Bedaux's (2.8) contribution, time studiesmerely recorded the actual duration of each element. However, Bedauxrecognized that the operatives' speed was an important factor that

should be recorded, along with each element of work, to ensure that thecorrect standard time (measured in 'B' units) was obtained. Basic

performance was taken as 60 'B' units per hour, inclusive of

relaxation allowances; expected performance was taken as 80 'B'

units, for which the worker would receive an additional third of his

basic pay. This subsequently became known as the 6 0/80 scale.

Unfortunately, Bedaux's techniques were largely applied during

the thirties depression and were often abused by management. Thebasic concept behind the Bedaux scale still operates today. However,

the actual rating scale has been superseded by the British Standard

with a rate of 100 representing 'Standard Performance'.

2.2.6 L.H.C. TiDoett

L.H.C.. Tippett (1935), of the British Cotton Industry Research

Board, suggested "a snap reading method of making time studies of

machines and operatives in factory surveys" (2.9). From thisoriginal concept a method known as "ratio delay" was developed by

Morrow (2.10) (19'5), and used to quantify delays incidental toperformance of work. This type of technique is now known as'activity sampling' and its application has been discussed in maIi-articles under the specific names of work sampling, random

observations, activity ratio and ratio delay.

17

Page 49: An evaluation of production output for in situ concrete work

2.2.7 H.B. Maynard

The rapid advances in manufacturing technology immediately afterthe second world war, and the increasing use of assembly lines,resulted in more systematic work procedures. The reduction in the

number of worker and machine motions made it possible for relatively

concise data banks of basic element times to be established. This

was foreseen by Taylor some fifty years previously. However, it was}LB. Maynard (2.11) who developed the concept of predetermined motiontimes into a workable system known as M.T.M. (motion-time-measurement).

2.2.8 Later DeveloD.ents

Since 19110 basic work study principles have not significantlychanged. The majority of later developments are associated with

either the application of work study in different environments or thescientific validation of work study accuracy. This stems from theinflux of industrial scientists brought about by the unusually high

demand f or productions resources and equipment immediately after thesecond world war.

The topics covered by the industrial, scientists dealt with many

problems. However, two distinct spheres of research have evolved.The first is the application of scientific methods involving a

mathematical or statistical process, thus, providing a quantitativebasis for management decisions concerning the organization of'

operations; such techniques are collectively known as 'OperationalResearch'. The second sphere of research is 'Ergonomics', which is

the scientific study of the relationship between man and his working

env irormient.

18

Page 50: An evaluation of production output for in situ concrete work

2.2.9 Recent Trends

In the 1960's and 1970's the world economy was expanding and the

demand for labour was high. The resulting increase in labour costs,and need for higher production levels, encouraged the application of

work study techniques throughout many industries. From the mid-seventies to the present day British industry has been losing its

share of the international market (2.12). To rectify this situation,and preserve British industry, the current government has encouraged

the need for greater efficiency, thus re-stimulating interest in workstudy techniques.

When one considers some of the recent well publicized industrialdisputes, resulting from the pursuit of greater efficiencies, it is

apparent that some basic management principles are being overlooked,or even deliberately ignored. Two prime examples of this are the

dispute at British Leyland arising from the elimination of six

minutes 'washing-up' time, and the year long miners' dispute overpit closures resulting in a devastation of the industry's morale.

As stated previously, Taylor believed that increased productivityshould be achieved via a policy of mutual co-operation between the

workers and management. A colleague of his, H. L. Gantt (1861-1919)

also had very strong views on ethical practice and stated that:

"The control over labour given to management by theapplication of the system which I installed was sofar-reaching that I refused to install it unlessconvinced that the management was such that nounfair advantage would be taken to oppress labour."(2.13)

Manufacturing processes are becoming more automated, particularly

since the introduction of the silicon chip. As a result, work studytechniques are now being used to optimize mechanical efficiency and

reduce the workforce. If the application of work study becomes a

management weapon rather than a tool, similar repercussions to thethirties could arise, with a detrimental affect on the reputation and

acceptability of work study.

19

Page 51: An evaluation of production output for in situ concrete work

2.3 CONSTRUCTION WORI STUDY TODAY

The definition given earlier describes work study as a service

which measures, examines, investigates and improves efficiency.Strange as it may seem, there i a vast difference in application of

this service when the construction and manufacturing industries are

compared.

Work study has most of its roots In the building Industry.However, since Gilbreth, it. has been in the manufacturing industry

that work study has been developed and extensively used to improve

productivity, with the construction industry showing only a tentativeinterest.

The tasks performed within the manufacturing industry are highly

repetitive, especially on assembly line work. This stable

environment has been studied in detail In order to improve

productivity. One result has been the development of a workmeasurement technique called Predetermined Time Motion System (PTMS)

(ie. the synthetic build up of operational time standards bycombining pre-set standard times for each physical movement carried

out). The PTMS technique is not suited to the construction industry,owing to the flexible co-ordination required to perform most

construction operations. The British Leyland dispute on 'washing up

time' also illustrates how far the manufacturing industry will go in

the refinement of workers' physical actions. In stark contrast to

this, the construction worker spends a large proportion of timeengaged in ineffective activities, such as double handling ofmaterials or waiting f or work, often amounting to severs], hours per

day compared with British Leyland's six minutes.

20

Page 52: An evaluation of production output for in situ concrete work

The author initially intended to determine a current state of

the art for construction work study by interviewing several

contractors. Unfortunately, the early investigations indicated that

very few contractors actively used work study, and it was necessary

to contact other organizations, such as Local Authorities, whose work

was of a similar nature to that of the construction industry. The

following fourteen organizations made varying contributions to the

basic principles applled.to construction work study throughout this

research.

Contractors with Work Study Data

John Laing Construction Ltd.

Wixnpey Construction Ltd.

Henry Boot Ltd.

Local Authorities

Lincoinshire County Council

Cornwall County Council

Nottinghamsb.ire County Council

Norfolk County Council

Others

Joint Industry Board for the Electrical Contracting Industry

British Waterways

Building Services Research and Information Association

Building Research Association

Building Advisory Service

Transport and Road Research Laboratory

Birchani Newton Training Centre

Figure 2.i Contributors to Basic Work Stud y PrinciDlea

21

Page 53: An evaluation of production output for in situ concrete work

2.3.1 John Laing Con2truction

At the time of the visit to John Laing Construction Ltd. they

were involved in 220 building contracts, 1k civil engineering and 15

overseas contracts.

John Laing Construction have incorporated work study techniques

into their planning and estimating systems since 1950. The majority

of data collection was done between 1965-1970, resulting in nine data

books containing 380,000 basic element times. These data books cover

the main trades and are categorized as excavation, concrete,

brickwork, joinery and formwork, external works, scaffolding, drain

laying, steel fixing and others.

As a comprehensive library of standard times is available, work

study collection is now on a much smaller scale and mainly used to

settle disputes or investigate new methods. The three main methods

of collecting data are: flyback timing for mechanical operations;

M.T.M. for plant maintenance; and activity sampling f or the

remainder. The factors applied to standard times in order to

determine bonus, estimating and planning rates are usually left to

individual regions.

22

Page 54: An evaluation of production output for in situ concrete work

2.3.2 WlApey Construction

The majority of Wimpey Construction's projects involve the

construction of timber framed houses. However, their work also

includes commercial and industrial type buildings. There are fifteen

operational regions with projects througiout the U.K.; each region is

allocated a work study engineer. The results from any studies are

sent to the main work study department in London, comprising four

work study engineers. Any new studies are directed towards reducing

costs through method improvement, with the results also used to

assist in the setting of planning, estimating and bonus rates.

Rated activity sampling studies are used to collect most of the

data. The relaxation allowances are supplied from the main office

and learning allowances obtained from previous studies. Activities

are generally split up into two areas (i.e. working or ineffective).

Standard times are only derived from the working time plus relaxation

allowances.

Wimpey Construction were very co-operative and forthcoming with

detailed information on studies relating to steel-work erection,

concrete floor slab production, pumping concrete, bricklaying,

transporting concrete, earthmoving, drain laying and the erection of

timber framed houses.

23

Page 55: An evaluation of production output for in situ concrete work

2.3.3 Department of Transport

The Marshall Report (2 114), published in 1970, highlighted thereed for increased professionalism and the better use of modernmanagement techniques by Local Highway Authorities. Also, Report No.

a9 (2.15) of the Prices and Incomes Board in March J7 effectivelyj.mposed upon Highway Authorities the requirement f or operating

j.ncentive bonus schemes based on work study data.

In addition to bonus schemes, several County Councils (2.16)

also use their work study data to determine estimating and planningtimes. This has resulted in the development of a computer based

system, namely RATE (2.17)• The RATE system has cost about £170,000In direct expenditure on research contracts, and is the result of

joint work between the Transport and Road Research Laboratory, the

Working Party on Highway Maintenance, the Department of Transport and

various County Councils. The RATE System consists of a number of

permanent libraries, (a) the Ratebill Library, (b) Operation

Libraries, (c) three Price Files (labour, plant, materials); andproduces Ci) a Bill of Quantities, (ii) the labour, plant andmaterials required.

2.3.11 J1ottInghash1re County Council

The Planning and Transportation Department of NottinghamshlreCounty Council currently uses work study data (2.1 to determineoutput rates f or estimates and to devise bonus schemes, although theemphasis Is mainly on highway maintenance.

Activity sampling and time studies are currently used to update

and expand an existing data bank of standard minute values; these are

stored within a microcomputer based estimating system. The systemhas several functions, including the production of unit rates,

preparation of quotations, production of programme schedules, and thecomparison of alternative methods. The PSM/h.r. (Productive StandardMinutes per hour) are obtained from output and productivity

sta tern ent s resul ti ng in a ty p1 cal value of 110 PSM/hr.

211

Page 56: An evaluation of production output for in situ concrete work

2.3•5 1Qint Industry Board for the Electrica]. Contracting Industry

The Joint Industry Board has produced a "National Library ofWork Study Data" (2.19), this provides a basis I or the estimating,planning and control of the labour element within the electrical

contracting industry.

Rated activity sampling studies are currently used to update and

expand the data bank, with techniques such as synthesis andanalytical estimating used to extend its coverage. The data bank issubdivided into the following sections. The build up of planning arid

estimating rates are illustrated in Figure 2.2.

(1) Work Study D

(a) Method descriptionEach operation contains a detailed method

description upon which the standard times arebased.

(b) Operational StandardsThis section describes how the standard times arecombined to provide operational standards. Thestandard times include a rating factor, occasional

elements, contingency and relaxation allowances.

(U) Planning GuidelinesThe operational standards are used to obtainplanning times by applying allowances for dailywork, ancillary work and manning levels.

(iii) Estimating GuidelinesThis section takes account of' any additional work

caused by site layout and the variation inperformance of individual contractors. The

guideline for general performance adjustment is 75

per cent of standard performance.

25

Page 57: An evaluation of production output for in situ concrete work

U)4)

I-I4)

31

HHH

.p14.'Ida)Ed)

.ri.1.)r4

o - a,.4'

,w ..4Oa,Ca,'-I )-4.4' 0 .0-4.-IC-I a,

HH

z0 a,

UCa,

,-40

a,-.'

4-

4)

Wa)

E0o.p4 .p1 11.1E4J 14

'40)

.p10400o

p-I'414

'-I OHP.i4-I U)

4-''U

Ei1i.2 '

U)4)

'p1'-4

IIU)

4)4)Id4.' Id

— — —

OW.' ,-Iw

•4"I

1.1 rlo .w Id

'0 •rIO4

UI

4-

4)UC

4'Oa,4),-'

+

U4)0Ca,.44 34JoCr.'0.-I

'-Ia,Cm04)•440ala)a)0U-'ora,

4)C

OwwI U a'

mWE

0U

)4 4).1.) ' .0

0 0'4 p.,

4)1 04)

UI •!.) 4)

O'CI .'JC .0

C4)I Ca, 4

--'31 a3CO . )O

1121JjO. .4)

0U)E4

a)m• 4.'

O H .,'P4 • . U).1.' rI 4) 4) 14 1)

Hj

Page 58: An evaluation of production output for in situ concrete work

2.3.6 BritIsh Waterwavs Board

The British Waterways Board employs a direct labour force

throughout the country and has a central work study department.Standard times (2.20) are available f' or repetitive work, Vor examplesheet piling and dredging operations; these are used to evaluatebonus rates and gang sizes. The viability of employing management

consultants to establish standard times for the remaining operationsis currently under consideration. The general procedure used by the

British Waterways Board to determine operational standards issummarized below.

(a) The correct gang size Is established by producing

multiple activity charts showing the amount of timespent working.

(b) Using the correct gang size each individual workelement is performed, timed and rated;

subsequently, the appropriate relaxation allowance

is applied and a standard time obtained.

(c) Allowances f or pre-work and post-work are applied.

(d) The variable elements are recorded on site and atypical site value is determined.

(e) The information is presented In report form, and

includes the standard times, a method statement andthe equipment required.

27

Page 59: An evaluation of production output for in situ concrete work

2.3.7 Building- Serv1ce Research and Information Service (B .3R. I. LI

The B.S.B.LA. have produced an "Estimator's Guide to Labour

Times" (2.21) for heating, ventilating and air conditioning work.This guide is based on data collected from a survey of' thirty-seven

B.S.R.LA. members, combined with the results from earlier studies.

The information is presented as standard times for each item of work

and provides three methods of estimating; namely, "Unit Labour Rate",

"Counted Fitting Method" and "Foot Run Method". Three factors areapplied to take account of different working conditions; these are

listed below.

(a) Task factors

These apply to a relatively short and well defined

piece of work and are applied to the basic timeaccording to height, access, etc.

(b) Site factors

These can apply either to the site as a whole or

some section of it (e.g. 1st Floor, 2nd Floor).

(a) General factors

These cover conditions that might affect labourcosts (e.g. geographical location).

28

Page 60: An evaluation of production output for in situ concrete work

2.3.8 Building Research Establishment

Some research by the Building Research Establishment has been on

projects involving the rationalization of house design (2.22) with

the view to increasing productivity. The rationalized designsachieved continuity of effort from different trades by reducingdelays caused by inter-trade interferences. Full-scale trials,

involving individual mock-up houses, were used to test the results.

The studies were performed using activity sampling recorded oncoded data sheets, with an optical reader used to analyse the dataand present the results. Two of the conclusions drawn from thesestudies were that:

(a) the number of manhours per dwelling had a ratio of3:1 from the highest to the lowest.

(b) factors such as size of dwelling, size of contract,rate of building and number of house types, have no

consistent affect on the variability of manhours

per dwelling when taken individually.

29

Page 61: An evaluation of production output for in situ concrete work

2.3.9 Transoort and Road Research Laboratory

The Transport and Road Research Laboratory have, over the last

ten years, investigated factors affecting the efficiency of bulkearthworks and road paving operations. The section investigatingroad paving operations uses two very different data collectiontechniques, namely CODDLE AND COSSIT, as described below. Similardata collection techniques are also used by the earthworks section.

(1) CODDLE

CODDLE (2.23) is a work study based data collection system that

has developed from hand recorded activity sampling to automatically

recorded cumulative timing. Individual CODDLE studies usually last

for four hours; special events are recorded in a notebook and studydata is recorded on a cassette using a pre .-coded keyboard. The

recorded study data includes file number, activity being performed,

the machine code (or chainage point) and the cumulative time. When a

study has finished, this information is transferred on to nine trackcomputer tape and run through a series of six "SORT" programs with amanual check performed for gross errors.

There have been 150 of these studies recorded although very few

have actually been analysed. The recording instruments used are verybulky at the present and could be improved by the application of the

portable computers.

(ii) COSSIT

COSSIT is a system for transcribing observations made during the

production of road pavements, into a form that matches a model of

pavement construction, and facilitates the storage and analysis ofthe information by computer. This technique is an expansion of theforeman delay survey with each item individually coded, and has been

used to collect data over the full contract duration f or twenty-threesites.

30

Page 62: An evaluation of production output for in situ concrete work

2.k ONcLU8IONZ

The evidence indicates that similar work study techniques areused by various organizations to collect data, but, there is a widevariation in both the presentation and application of results. This

variation often arises because many work study techniques originatefrom the manufacturing industry and have been adopted by the

construction industry without due consideration given to the latter's

needs.

Construction work study is mainly used to determine output rates

for planning, estimating and bonus schemes, and thus involves work

measurement as opposed to method study. The lack of interest in

developing improved construction methods by the construction

industry, consistently perpetuates the status-quo as far astraditional methods are concerned, and in some instances workingmethods have remained the same over the last hundred years or so(2.21k)

In contrast, for example, one of Gilbreth's earlier studies

resulted in the development of a special scaffold system designed to

improve , bricklaying productivity. This scaffold was equipped with abench or shelf for supporting bricks and could be raised short

distances at a time, thus, saving the bricklayer the tiring andunnecessary task of' bending down to pick up bricks or mortar off' the

scaffold floor. However, when one looks around construction sitestoday bricks are often placed in a stack with no assistance from

specially adapted scaffold. This simple example illustrates thelimited advances made with some construction methods since the

beginning of the century, and the improvement required beforeconstruction processes become analogous to the production lines used

in the manufacturing industry.

31

Page 63: An evaluation of production output for in situ concrete work

BAPTER THREE

WORK SLUDY APPLIED TO CONSTRUCTION OPERATIONS

32

Page 64: An evaluation of production output for in situ concrete work

CRAPTEE THREE

3.0 WORE STUDY APPLIED TO CONSTRUCTION OPERATIONS

3.1 INTRODUCTION

With the majority of resources for work study development coming

from the manufacturing industry, the evolved terminology and

techniques are specific to that industry. By careful consideration

and comparison of construction and manufacturing operations work

study techniques can be revised to meet the requirements of the

construction industry.

The direct adoption of manufacturing work study techniques,

combined with the fact that most work study practitioners do not have

a construction background, has certainly curtailed the impact that

work study has had on construction productivity. Also, there are

several other problems, usually associated with the nature of

construction work, which are considered to be the cause of

construction industry's reluctance to implement work study techniques

on a wider scale; these will now be discussed.

Many construction operations last for short periods of time, say

four hours, with a long intervals before any operations are repeated.

Thus, the benefits from construction method studies are not always

immediate.

33

Page 65: An evaluation of production output for in situ concrete work

There are few work study data banks readily available to the

construction industry. Therefore, any contractor wishing to

incorporate work study into . its management structure usually has to

start from scratch, either by establishing a new department or

employing outside work study consultants. The lack of basic data is

a result of contractors who have already gone to the time and expense

of establishing a comprehensive work study library regarding the

information as confidential. The restrictive flow of construction

work study information means that contractors not only have to

collect the data, but they also have to devise suitable methods of

data collection and presentation. This closed door policy has

contributed to the diverse presentation and application of'

construction work study that exists today.

Construction operations, especially those with long durations,

often require expensive items of plant. This plant is often on site

before any study is performed. As on site costs are usually very

high, the decision behind the plant selection is unlikely to be

countermanded, even if a more effective method is found. In addition,

trying new alternatives is not always recommended as the contractor

and operatives may have to repeat the learning process. However, the

benefits resulting from individual studies could be reaped on

subsequent projects. -

Manufacturing operations usually consist of' short cycles of work

performed in a predetermined repetitive sequence: in contrast,

activities involved in construction operations are often varied and

not performed in any predetermined sequence. Thus, construction work

study data collection requires reasonably flexible recording *

techniques. Also, the time lag between performing a study and

implementing any improvements is much more critical for construction

operations as many are "here today and gone tomorrow".

3"

Page 66: An evaluation of production output for in situ concrete work

Over a period of time, very efficient manufacturing processes

have been achieved through a constant detailed refinement of working

methods. The construction industry, by comparison, very often

operates at low levels of productivity. Therefore, any programme

designed to increase construction efficiency should not start with a

detailed refinement of operations but a wholesale change in methods

and attitudes, which requires very different work study techniques to

those currently used In the manufacturing industry.

3.2 WORK STUDY TECIINIOUKS

Work study is the systematic measurement, examination and

Investigation of the current situation in order to effect improvement

via the optimum use of the available resources. Work study can be

divided into two independent activities; namely method study and work

measurement. There are many areas where work study results can be

used to improve the efficiency of a contractor; some of the basic

applications Include:

(a) the calculation of gang sizes;

(b) the determination of job sequences;

(C)

the pre-planning of contracts;

(d) the planning of site layouts;

(e) the setting of bonus rates;

(f) the cost comparison of plant and methods;

(g) the design .of hand tools to reduce work content.

3.2.1 Method Study

Method study is the technique used to systematically record and

analyse existing work procedures, with a view to achieving a

reduction in cost by improvement of the methods under consideration.

Essentially, a method study should comprise the following stages.

35

Page 67: An evaluation of production output for in situ concrete work

(a) Define the problem.

(b) Record the facts.

(c) Analyse the data.

(d) Propose a course of' action.

(e) Put the proposals into effect.

(f) Monitor the consequences.

The above process, as recommended by Harris and McCaff'er (3.1)

and others, is primarily an investigative and reparatory approach;

existing methods are analysed and changed where necessary, with the

effects being monitored. There are three method study techniques

used to portray operations by some visual means; namely:

(1) Flow Charts

Flow charts are used to illustrate the movement of material, or

plant throu&1 a construction process. This involves using symbols on

a plan of the work area and is suited to work of' a cyclic nature.

Figure 3.1 illustrates the five widely recognized symbols presented

inBS 3138: 1979.

SThI3CL ACTIVITI

0 Operation

Inspection

Transportation

Storage

D Delay

7j.gure • I Standard Flow Chart Syhols

36

Page 68: An evaluation of production output for in situ concrete work

(ii) J'rocess Charts

In some situations it is not feasible to represent the flow of'

work on a site plan. For example, where several operations are

confined to one location. If' this is the case, the operation can be

illustrated using a process chart, where the sequence of events is

represented by symbols only. These are man, material, equipment or

outline process charts; the type adopted depends upon the events

under consideration.

(iii) Multiple Activity Charts

Multiple activity charts are used to plot a series of'

interrelated activities against a common time scale, and subsequently

assist in selecting and representing an improved method. The

activities can represent the work done by Individual operatives,

whole gangs or items of' plant.

3.3.2 Work Measurement Techniques

Work measurement is the application of' techniques designed to

establish the time for a qualified worker to carry out a specific

task at a defined level of performance. Work measurement techniques

are, therefore, an integral part of method study during the data

collection phase. The information collected during work measurement

must record the quantity of work produced and the time required to

perform the task.

The work produced during an operation should be measured in

terms of effective output. For example, the measurement of work done

in fixing reinforcement should include the weig1it of steel, the

complexity of reinforcement details and the distance steel is

transported on site.

Time studies are work measurement techniques used to record the

times and rates of working for the elements of a specific job carried

out under specified conditions, and are used to analyse the data soas to obtain the time necessary for carrying out the job at a defined

level of performance. Certain aspects of typical time studies will

now be discussed.

37

Page 69: An evaluation of production output for in situ concrete work

(1) Flyback Timing

The hands of a stop-watch are returned to zero and restarted at

the end of' each element. The time for each element is recorded

directly, along with an assessment of rate.

(ii) Cumulative Timing

The hands of' a stop-watch are not stopped and the actual time at

the end of each element is recorded. Each element is rated and the

duration subsequently obtained by subtraction.

(iii) Activity Samp1ig -

Observations are taken either at set or random intervals on a

group of workers; both the activities being performed and the rate of

work are recorded.

(iv) ting

The objective of any time study is to determine the "realistic

time" required to complete a particular operation. The realistic

time must take into account the effective work rate of the subjects;

this procedure is known as "rating". Rating is, thus, used to assess

the worker's rate of working, relative to the observer's concept of

standard rating. Rate depends upon speed of movement, effort,

dexterity and consistency.

Typical rating assessments, as suggested by BS 3138: 1979, are

presented in Figure 3.2. In practice, however, rating is usually

carried out only on the working activities, with a 1 0 point

graduation scale, ranging between 50 and 130, being adopted.

125 : Very quick, high skill, highly motivated.

100 : Brisk, qualified skill, motivated.

75 : Not fast,average skill, disinterested.

50 : Very slow, unskilled, unmotivated.

Figure .2 Tynica]. Rating Assessments

38

Page 70: An evaluation of production output for in situ concrete work

(vi) Foreman Delay Survey

Borcherding and Tucker (3.2) In the U.S.A., and subsequentlyEaston (33) in Australia, have shown that the foremen delay survey

is a useful management tool designed to determine which factors,other than operative performance, affect productivity. For example,waiting for materials or plant breakdown. Foreman delay surveys arebased on operative feedback. They are, therefore, dependent upon theco-operation of the foreman; who identifies, quantifies and records

the lost time f or each day. Subsuently, the results can be used to

improve working methods and monitor revised methods. Although

foremen delay surveys can monitor a whole project on a regular basis,

and provide up to date information on certain organizational delays,there are also several disadvantages which Influenced the decisionnot to incorporate this technique in the data collection program used

in this research; these are listed below.

(a) The foremen will tend to include the lost timecaused by poor operative motivation with the delaysassociated with management organization.

(b) The overall accuracy of the study will always be indoubt because the times are all estimated by the

foreman.

(c) It was anticipated that the foremen's co-operationduring this research would not extend to work notdirectly associated with his job.

(d) Foremen usually only spend part of the working day

on site, thus, missing a large proportion of thedelays.

(e) The technique only allows for large delays to be

recorded, however, short delays or interruptionsare just as important.

39

Page 71: An evaluation of production output for in situ concrete work

In addition to time study techniques, there are several

analytical processes which form an important part of any workmeasurement exercise, These will now be discussed.

(1) Synthesis

Basic operation times can be determined by combining previously

established elemental times. This work measurement technique isknown as synthesis, and is used extensively in the analysis section

of this thesis. One advantage of using synthetic data is that slightvariations in working method can be accounted f or by adding oromitting the appropriate basic element times.

(ii) Predetermined Motion Tie Sste (Pt1TS)Predetermined motion time systems are the synthetic build u p of

basic operational times from previously set standards representingbasic human movements or mental tasks. This technique is suitable

for many manufacturing operations where a limited number of movements

are regularly repeated. However, it is not suited to mostconstruction operations owing to the flexible working motions

involved.

(iii) Analytical EstimatiigAnalytical estimating is the determination of operational times

partially from knowledge and experience of similar types of work, andis, therefore, very useful where only some of the basic element timesare available.

110

Page 72: An evaluation of production output for in situ concrete work

3.3 PRESENTATION OF (JTPUT RATES

Reasonable access to construction output rates, including some

based on work study techniques, has been provided by organizations

within both the public and private sectors. However, the huge

variation in presentation of data has been somewhat disappointing.

This may be partly attributable to the exclusive organization of each

construction project, and individual contractors ensuring that their

records are of limited use to fellow bidders, competitors and

customers. So it is clear that such data gathered from various

sources are unlikely to be comparable, unless, they are standardized

by some unified approach.

3.3.1 Current Methods oLPresenting OutDut Data

Output rates can be presented as basic times, standard times or

planning times, depending upon their intended use. The basic

principle, as laid down in ES 3138: 1979, is to obtain the basic

element times to which factors are applied in order to obtain

planning times. The British Standard was written to cover a wide

range of industries, resulting in numerous policy and contingency

allowances, many of which are not appropriate to the construction

industry.

Most of the organizations visited build up their standard times

as shown in Figure 3.3, but differ in the application of policy

allowances used to obtain planning times. The flexibility that

presently exists makes it all too easy for existing inefficiencies to

be transferred to future work via these policy allowances. This

often occurs when future policy allowances are determined by dividing

the working day duration by the average value of work, expressed as

standard time, currently being performed per day. This obviously

results in a realistic policy allowance, but does not facilitate the

improvement of productivity by the location of inefficiencies.

11

Page 73: An evaluation of production output for in situ concrete work

In this respect it seems that the British situation is quite

disorganized when compared with others on the continent For

example, Dutch contractors have formed a progressive co-operative,

with the charter to provide a pool of output times linked to

construction methods. These are updated and published monthly for

guidance of the industry and its customers by the journal BOLJWKOSTEN.

12

Page 74: An evaluation of production output for in situ concrete work

Selected basic times

Contingecy allowancefor

Relaxa-tion

(a) Fatigue allowance

(b) Personal needsallowance

Outside work i Inside work (b) (c) (c) Environmentalallowance

Selected basic Work Relaxa-times contin- tion

gency allowan

a) (b) (c)

(a) Fatigue allowance

(b) Personal needsallowance

(c) Environmentalallowance

Work content in standard

Delayunits of work contingency

allowance

STANDARD TIME

Build—up of standard time for operator controlled work

Machine controlled Itime ]

Basic cycle time

Standard cycle time

Standard time

Build-up of standard time for single operator single machine1machine controlled work with no unoccupied time

Figure 3.3 Current Build-up of Standard Time

Page 75: An evaluation of production output for in situ concrete work

3.3.2 ProDosed Presentation of Output Data

The main deficiencies in current methods of presenting output

data are: the failure to accurately represent the various individual

elements relating to complete operations; and the lack of flexibility

in representing various levels of performance. The proposed method

of presenting output data aims to reduce these deficiencies, by

careful consideration of the types of work and idle time occurring

during the working day. During this rationalization of construction

time standards, it was ensured that: the proposed system related

closely to current methods of presentation; and the terminology

complied with the British Standard, whilst concentrating on the

sections relevant to the construction industry.

The working day f or most construction work can be broken down in

terms of working time, diverted time, idle time and absence time, as

illustrated in Figure 3.11. Consuently, construction operations are

classified as unrestricted, semi-restricted or restricted, depending

upon the type of idle time involved. The terms used in Figure 3.11

and Figure 3.5 are defined in Appendix A.

In order to comply with current work study terminology, output

rates have to be expressed as basic operation times. Thus, the

build up of time standards, as illustrated in Figure 3.5, was

developed by combining Figures 3.3 and 3.11. The total basic time for

an operation includes basic times f' or excess and ancillary work in

addition to the main work elements. The only idle time included in

the total basic time are allowances f or internal delays (i.e.

unavoidable idle periods). A method of determining basic operation

times for concrete work is described at length in Chapter Four.

1114

Page 76: An evaluation of production output for in situ concrete work

WORKING DAYAND

OVERTIME

II IABSENCE TIME

ATTENDANCE TIME EXhA

I

BREAKS BREAKS

WORKING TIME DIVERTED TIME IDLE TIME

IIINSIDE OUIDE

machine controlledtime

riELEMENT EXCESS ANCILLARY

TIME TIME TIME

I 1RELAXATION DELAY

I II1•ALL CMANCE ADDITIONAL EXTERNAL INTERNAL

I I DELAY DELAY

UNRESTRICTED OPERATIONS

SEMIRESTRICTED OPERATIONS

RESTRICTED OPERATIONS

Flgure1.1I Classification of Work and Idle Times.

NOTE: Bold type indicates terms which are also used in Figure 8.2.

Page 77: An evaluation of production output for in situ concrete work

BASIC TIME BASIC TIMEEXCESS ANCILLARY

ASSEMBLE BASICELEMENT TIMESTO OBTAIN BASICOPERATION TIME

BASIC TIMEFOR

CONTINGENCY WORK

BASIC TIMEUNRESTRICTEDOPERATION

INTERNAL DELAYALL ANCES

BASIC TIMERESTRICEDOPERATION

TOTAL BASICTIME

PERSONAL BASICNEEDS FATIGUE

FIXED

ENV IORON MENTALSTRAIN

IVARIABLE

SITE FACTORS

Ft EL AXAT ION

(F1xF2xF3xF1)

ALLOdANCES

TOTAL PLANNING

TOTAL STANDARD

TIME

TIME

Figure .cProosed Build Un of Time Standards..

Page 78: An evaluation of production output for in situ concrete work

Standard times are obtained by combining basic times with

relaxation allowances; this process is discussed in Chapter Five.

Standard times are only applicable to sufficiently motivated

operatives working on well organized sites, This ideal combination

is not always the case, and planning times often have to account for

large periods of idle time. The majority of idle time associated

with construction work relates to individual sites. Hence, site

factors are used to represent lost time, as explained in Chapter

Eight.

Page 79: An evaluation of production output for in situ concrete work

CHAPTER FOUR

A METhOD OF DETERMINING BASIC TIM FOR

IN 8110 CONCRETING OPERATIONS

18

Page 80: An evaluation of production output for in situ concrete work

CHAPTER FOUR

A METHCH) OF DETERMINING BASIC TIMES FOR

Th SITU CONCRETINGOPERATIONS

11.1 INTRODUCTION

The following example illustrates the recording methods usedduring this research. The operation involves using a crane and skipto pour concrete into two columns, two roof slabs, and inf ill

concrete between several pre-cast concrete units. The dimensions andquantities of work encompassed are presented in Table 1L.1, and theoperation is illustrated in Figure ).1.

Figure .1 Operational Diagra

Page 81: An evaluation of production output for in situ concrete work

Vertical = 1O.Om

Horizontal 37.Om)

Total = 38.5m

Table 11.1 Concrete Di.enzionm and Quantities

POUR DIMENSIONS

Slab I width 2.Om; area = 88.3m2 ; volume = 29.9m3

Slab 2 width = 2.Cn; area 1O.6m2 ; volume = 3.7m3

total volume 33.6m3

Columns (O.5m x O.5m x 3.8m) x 2; volume

Joints (O.15m x O.O5ni x 3.6m) x 12; volume O.3

total volume 2.2m3

Average distance travelled by skip:

Capacity of concrete lorries 53

Capacity of skip 1m3

The example is now divided into three sections: the first

illustrates the procedure used to collect the data on site; the

second describes how this is translated into basic times for the

operation; and the final section demonstrates how these times can

be used in the synthetic build up of planning times for other

operations.

50

Page 82: An evaluation of production output for in situ concrete work

It.2 DATA COLLECTION

Flyback timing was found to have two main drawbacks: (a) it wasnot possible to realistically observe more than one cycle of work at

a time, for example, the measurement of haul trucks involves several

simultaneous cycles; and (b) it was not possible to use one stop-wat'ch

and combine activity sampling with flyback timing. To overcome theseproblems, cumulative timing was used to record operations of a

cyclical nature. To simplify the subsequent analysis, the divisions

on the stop watch were in hundredths of a minute rather than seconds.

In the manufacturing industry activity sampling observations are

taken at predetermined random intervals, to ensure that the regular

pattern of the work does not influence the study. When dealing with

operatives on the site there is generally a natural random pattern in

the work, consequently, activity sampling can be carried out at set

intervals for the majority of labour dominated operations.

Data for concrete operations were collected on a speciallyadapted activity sampling sheets, as illustrated in Figure 1 .2, whichcomprise the following sections.

(1) Activit Sa*p1inActivity sampling proved successful for recording groups of

workers engaged in constantly changing work patterns. After many

trials, the procedure finally adopted required an observation to be

taken of each operative every five minutes; the activity and rate of

work being recorded in the first nine columns. The list of activitycodes used in this study are presented in Table .2.

(ii) Cuwilative TimingCumulative timing proved more appropriate f or machine dominated

operations, where activities were commonly performed in a regular

pattern. As the work done by the crane was of a cyclical nature,

cumulative times were simply taken at the start and finish of theloading and unloading of the skip. These results being entered inthe last five columns of Figure 4.2.

51

Page 83: An evaluation of production output for in situ concrete work

(iii) 9mIIent

Important events not recorded in the activity sampling or

cumulative timing sections were noted in the comments column. For

example, delays caused by the late arrival of concrete.

Table 1 .2 Activities axxl Codes

for Concreting ODerations

cODE I- ACTIV ITY

0

Break

1

Away

2

Walk

3

Talk

14 Recover

5

Walt

6

General

7

Other work

8

Internal delay

9

Prepare work area

10

Clear away

11

Carry

12

Search

13

Instructions/Drawing

111 Redo work

15

Clean shutters

16

Pour concrete

17

Vibrate

18

Shovel

19

Tarn p

20

Trowel

21

Cover

22

Jack Hammer

52

Page 84: An evaluation of production output for in situ concrete work

Figure 4.2 Activity Sampling Study Sheet

Additional Activities Break Points Comments

31 Concrete Joints in P.C.IJ. BP1 Skip arrives at lorry area Start roof slabs at 1.30 pm

lOT Transfer tools EP Skip leaves lorry area and finish at 4.50 i

lGc Pour concrete to columns EP Skip arrives at pour area Start columns at 4.50 pin and

17c Vthrate columns s Skip leaves pour area finish at 5.30 pm

Weather:- Wet/Cold/Calm -- _________________________ -

Date:- 14 March 1983

- REC. Andrew Price- - - - - -_______________________________

TIME Man 1 Man 2 Man 3 Man 4 Cumulative Timing (mins)Act Rate Act. Rate Act. Rate Act. Rate Comments PLANT:- TOWER CRANE

1.30 16 100 9 110 9. 100 9 110 Delays Note. Start @ 1.0 (=0.0 ______

35 9 90 18 100 5 9 90 Start slaJ BP1 BP2 BP3 BP4

40 18 100 31 110 9 110 9 100 Crane wail ci (1.30h)* 1.09 9.30 9.75

45 18 100 31 110 5 - 19 110 2 10.80 11.90 12.75 12.95

50 18 110 18 90 17 90 4 1 lift fo 3 13.90 15.25 16.15 16.40

55 1.8 110 9 90 lOT 3.00 17 110 joinersx 4 17.25 x 21.80 22.40 22.80

2-00 10 100 lOT 100 6 50 18 110 wait for 5 23.80 24.90 25.60 26.10

05 18 120 31 100 17 60 19 .110 concrete 26.60 27.60 Lift fo. joiner'_______ - - - - - - - - 4.13 Inins - _______ _______ _______ ______

10 16 100 31 70 18 100 4 6 (slab2) 36.00 36.10

15 18 100 31 100 18 100 31 100 Cont.slab 2 34.00 34.90 35.80 3..n2

20 20 100 5 5 1 8 37.20 38.00 38.70 38.90

25 20 110 31 100 6 100 5 9 39.90 40.60 41.60 41.75

2-30 20 110 31 100 5 - 18 -2. 43.90 x Lift fo brickl vers

35 20 90 3.1 100 17 100 6 100 17.9mi 10 60.50 61.60 62.30 62.50

40 20 100 31 110 17 (10 19 50 IT (2 oads to lab 2)

45 20 120 31 110 16 110 19 100 Cont. slal 13 9.70 10.80 11.90 12.15

__________ - - - - - 1 - __________ _________ _________ _________

50 20 110 31 110 17 110 19 90 14 13.25 14.50 15.15 15.40

55 20 100 5 17 110 18 110 15 16.60 17.00 18.30 18.70

3-00 4 - 31 90 17 110 18 100 wait for l9.8O ______ ______ ______

05 - - concrete 16 i . (2 oads to lab 2) ______

10 20 110 31 110 17 110 19 100 cont.slabl 18 32.25 * 34.30 34.80 35.10- waitfor

15 20 110 31 100 17 80 18 1(0 conc.gang 36.30 37.40 37.80 1L....

20 20 100 4 17 80 19 100 0.45 inins .2g.. 39.20 43.90 4420

25 20 110 31 110 17 110 17 100 21 45.10 46.20 47.00 47.20

30 20 110 31 110 5 - 18 100 rica to 22 48.40 48.90 49.85 50.20

35 20 110 31 90 17 100 4 - changeov •j_ 51.30 52.30 52.90 53.40

40 20 110 4 17 110 6 90 - 24 54.25 55.35 56.40 56.80

waitfor *

45 19 100 18 100 17 100 6 100 conCrete* 25 57.80 Lift f r brick ayers

50 19 100 18 100 17 110 19 110 13.4 mm.. 25 11.20 12.60 13.20 13.95

55 - - 26 15.00 16.50 18.60 18.95

27 19.75 21.00 21.90 22.15- a - - - - - - -

Page 85: An evaluation of production output for in situ concrete work

Figure 4.2 Activity Sampling Study Sheet Continued

Additional Activities Break Points

16c Pour concrete to columns BP1 Skip arrives at lorry area Pour Dimensions17c Vibrate columns P2 Skip leaves lorry area L w

P3 Skip arrives at pour area Slab 1 2 . Om x 44 • 2m x 034m

BP4 Skip leaves pour area Slab 2 2•Om x 53m x O35rn

Columns (O•5m x 0 . 5m x 38m)x2- Joints (015v005 x 3 • 6) 12- ___________________________ -

Skip us3- - - a -

Man 1 Man 2 Man 3 Man 4 - Cumulative Timing Cams)

TINE - Coients PLANT:- TOWER CRANE

Act.Rab ct. Rate ct. Rate Act. Rate ______ ______________________________

3.55 20 90 31 110 13 110 18 100

BP1 BP2 BP3 BP4

4.00 20 100 31 110 17 100 1 Wait for - _______ ______ _______ ______

05 20 100 6 80 16 100 1 - concrete 28 23 • 25 24.25 25.40 25•70_______ - 51 29 27.30X 3340 35'O0 3540

10 31 100 6 80 17 110 1 -

15 18 100 4 17 90 5 30 36 • 60 374O 38•00 38.50______ --31 3960 40•lO 412O 42.90

20 18 100 16 100 17 100 1 - ________ _______ ________ _______32 4325 44.10 4490 4560

25X 1O0555 - __ ____

30 5 5 5 5 33 47 • 05 48•05 48•60 49.50

35 20 110 5 5 5 - 34 . 53 • 5 31.25 518O 52.90_______ - - - Wait for

53•50X Lifts or Brick ayers

40 20 110 5 5 - 5 -_______ - - - -287 nunS

s 22 . 20 ) Not Re orded

45 20 110 5 5 - 5 - - ________ _______ _______ _______

50 5 5 525.8O _____ _____ _____

55 20 110 5 17 100 18 ioo 37 Cols _______ _______ _______

5.00 20 100 19 100 17c 100 16c 100 t5.00 p.m 38 Cols ______ ______ ______

05 j— -j -: j 2 U 39 Joints________ - - - - coflcrete - _______ _______ _______ _______

10 20 110 19 110 17c 100 16c 100 COl5 - ________ _______ _______ _______

15 20 100 4 17c 100 NOT - a bla k space ndicates missing________ obse_ ation.

20 __ __ __ __

25 21. 100 17c 100 18 100 21 100 _______ _______ _______ _______

30 21 100 17c 100 18 100 21 100 - ________ _______ _______ _______

__ Man Man 6 Man 7 Man 8t 5.15.p

5.15 21 100 21 120 2]. 120 21 120 4 more - _______ ______ _______ ______

20 4 21 90 21 90 21 90 wen 1p - _______ ______ ______ ______to cover

25 21 100 21 100 21 110 21 120 concrete - ________ _______ _______ _______

30 21 100 21 110 21 100 21 90

- - - - - - -

Page 86: An evaluation of production output for in situ concrete work

4-)a)a)

rI.1.)

4*

B

4* U)

EU)

oxN -

II'

U) C

.141

'IC)

>,414*4*

C

B

U)(N

14

144*

..1

.4C)

Ce

.4.1BE

12)0U) U)- C

nil B

ItIU) an

0) - p

on ,

4114.4W E.

9

CC.141.4

41U4

1.1

- — — — — — — - — — — — -- — — —Na'rU)

_____ - N

00+0

— CNN *0-, NON*0O -

U (N C) N(N *0 0NUUN 1)Z H.4 N N (N m N -. - m m

X a'

3 U)

— — - - — — — — — — — — — - — — — — —0

-. mm m m *0 0 a' 0 mm mOm *0- E-' + + N.U ill 0No -I) EUU

— o+ ------ —Il0 •

4 00 0 00 (Nm 000 NO 0

1.1 N (N N N (N (N N (N (N N N N N N

- -----a' a' a' a' a' a' a' 0' 0* a' 0*0*0* 0*

— — - — — — — — — — — — — — — — — —

(S3/VZ)) U) 0 0 Il) m C' N U) U • It) IU (N (N It) -. N IQ 0) C C) N

U) () (N N N (N0 I

(3x) U)In 0 0 II) m 0) N It) U) m U) 0 -r WWTSWg N N t). N*D . m

(Ioxv7) 00 0 UI U) 00 0 U) U) U) 0 U) 0 0m N N - N N ' a' -' - - '* ('I0 WTtT2eAO - -

— — — — — — — — — — — — — — — — —

(N m 0 0 (NO (NO) UI m 0 Om 0 0 .-U ebiey ° 9999°' 2929999 2

0

- 0W N ..-a - ------ -- - U) N

U) 0 - -W -4.111 -.- - -- - - --

11 0 (N (N N N N U) a m .-. U) *0CH- ---------

- ill 0 .. N . - N NO 0*

- -- ---

0 N (NWE U)

- ------

-

o ...I - -- - --- -- - --.14.1 - -4JW 0 -

*0

- ----------EmE 0 - -.0 U)

(N C' - 0) - -

0 U) U)

8

— ___sgicis •S'103

0)0 N.

a,;In(N 4+0 +1(1om lfllI)mU) UlU)U) U)

II II14

C)

14

>'14 C)

-I.4 4*o 4.1

.1

4 0)

Page 87: An evaluation of production output for in situ concrete work

1 3 BASIC TIMES FOR CONCRETE GANG

1L3 . 1 Analysis of Gang Data

The activity sampling analysis sheet, illustrated in Figure 1.3,

is used to calculate the standard times for this study, and is

completed as follows.

(a) The activity sampling results, obtained from the

study sheets, are transferred into column Cl, this

is done by summating the number of occasions each

activity occurs at the specified rates. For

practical reasons, the rating values are recorded

in steps of ten units. For example, It can be

seen from Figure 1.3 that the activity "pour"

occurs on four occasions at standard rate 100 and

once at a rate of 110. In this example, the

activities for the slabs are separated from the

column activities. From these values, the average

rate (C2) can be obtained f or each activity.

(b) Overall time (C3) is the number of occasions each

activity occurs multiplied by the observation

interval (0.1.). Basic time (CIU 18 the productof the overall time (C3) and average rate (C2)

divided by 100. The basic time per unit (C6) is

equal to C1/C5. The quantities in this example

are two slabs, two columns and some mt ill work.

But, in the following synthetic build up of times

the units of work are area and volume of concrete.

(c) The total relaxation allowance (Cli), for each

activity, Includes allowances for basic needs

(C7), standing (C8), posture (C9) and load (dO).

More detailed information on relaxation allowances

is presented in Chapter Seven.

56

Page 88: An evaluation of production output for in situ concrete work

(d) Standard time (C12) is expressed per.unit of work,

and is calculated from the basic time (C6) plusthe appropriate relaxation allowance (C6 x

Cil/ICO).

(e) Site factors are calculated at the bottom of

Figure i.3. These are applied to the basic time 8

and realistic planning times are obtained.

J .3 .2 SynthetIc Data for Concrete Gang

In practice the shape and size of a concrete pour might varyfrom the example shown. Therefore, for a more general application of

the data, it is necessary to relate the basic element times to a set

of common variables. For example,, a floor slab might have a large

surface area and be shallow, while a foundation base or column

usually exhibits the opposite characteristics; clearly, area andvolume are important controlling variables. In order to establish

the relationships between these variables and the basic times, overseventy concrete pours are combined and statistically analysed in

later chapters. However, for simplicity, only the data relating to

the two roof slabs are used to demonstrate the principles of

synthesis.

(1) BasIc E1eient TIRes for Concrete Gang

The following example describes the synthetic build up of basicoperation times, based upon basic element times for the concrete gang.

The elements relating to volume of concrete are pour and vibrate;those relating to area are shovel, tamp, trowel and cover. The time

spent on general work is allocated in proportion to the time spent on

each of these six elements, as shown in activities d" to "1" in

Table 11.3. The preparation, clearing and transferring of tools

relate to the number of occasions they are each performed.

57

Page 89: An evaluation of production output for in situ concrete work

Table 1l. Basic Elent Times for Concrete Gang

Activity Variable Basic Genera]. B.T. Un.its B.T. + G.Time (G.) + G. Unitmine mine

a Prepare Occasions 110 - - 1 110 mine

Tools

b Clear Occasions 20 - - - 1 20 inins

Tools

o Transfer Occasions 15 - - 3 5 mine

Tools

d PourConcrete Volume 25 1.1 26.6 33.6m3 0.792

k .38min/m3

e VibrateConcrete Volume 115 5.0 120.5 33.6m3 3.586

f ShovelConcrete Area 123 5.3 128.3 98.9m2 1.300

g TampConcrete Area 69 3.0 72.0 98 . 9n12 0.728

11.61

h Trowel mm/n?

Concrete Area 1117 6.11 153.11 98.9 1112 1.550

i CoverConcrete Area 98 11.2 102.2 98.9 1112 1.0311

___ - ___ ___ ______

Page 90: An evaluation of production output for in situ concrete work

(ii) Basic Operation Tlaes

The 25 minutes spent on. general work, activity code b, are added

to elements (d) to (1) in the ratio of' the time spent on each. This

gives a basic time, for each activity, inclusive of excess work.

Therefore, the basic operation time for a concrete pour can be

expressed as follows.

Basic Time

60 + 11.38 Vol. + 3.61 Area ...Equation 4.1

First Pour

Basic Time = 5 + 4.38 Vol. + 4.61 Area ...Equation 11.2

Subsequent Pours

The basic operation times obtained using Equations 11.1 and lI.2

include time spent trowelling and covering the concrete. These are

not always required, therefore, the appropriate equation should be

selected from the following.

Basic time 60 + 4.38 Vol. + 4.61 Area (trowel and cover)

in man = 60 + 4.38 Vol. + Area (trowel but not cover)

minutes bO + 4.38 Vol. + Area (cover but not trowel)

60 + 4.38 Vol. + 2.02 Area (neither trowel nor cover)

To illustrate how the slab depth can affect the basic time per

cubic metre, area is replaced in Equation 4.1 by volume and depth.

Thus, resulting in Equation 11.3 which is represented graphically in

Figure 4.4.

Basic Time 60 + 4.38V + 11.61 V ...Equation 4.3

D

or

Basic Time = 60 + 50.5V

= 60 + 22.8V

= 60 + 15.9V

when D = .10m

when D = 0,25m

when D = O.11Om

V = volume in m3.

D = depth in m.

59

Page 91: An evaluation of production output for in situ concrete work

0

U

0

0)

r-.

rn

EcoW

HW

0z0

"0

0IJJ

0>

If)I

-o

-J(1W)0

0-LiJ<

00ZLL.0uJOF-

uJ

0

(/)0LLIO

0

0>

• . •

...............J. ; .

QEEEEEEEDEEEEEEE+ <00O00-J .-. , Ott) 0 It) 0

. Z ........... c.Jr')

II

m :0

o o 0 0 0

0 0o 0 - Il) 0

U,

r) C'J C'.J

S3LL 3SV8

Page 92: An evaluation of production output for in situ concrete work

11. 11 BASIC TIMES FOR TOWER CRANES

ii. 1i.1 Analysis of Tower Crane Data

In this example, the work done by the tower crane is of a cyclic

nature. The work elements contained within each cycle are defined as

the time between the break points presented in Table k.1I.

Table . Break Points for Tower Cranes

Break Points Code

(Figure 1.2)

Skip arrives at lorry area BP1

Skip leaves lorry area BP2

Skip arrives at pour area BP3

Skip leaves pour area BP1I

The mean element times for the tower crane are obtained from the

cumulative timing results presented in Figure. l.2.

Table .5 Mean Element TiRes for Tower Cranes

Elements Break Mean Element

Points Time (mins)

A Pour into skip BP2-BP1 1.02

B Lift full skip BP3-BP2 0.81

C Pour into shutters BP1I-BP3 O.12

B Return empty skip BP1-BPk 1.02

TOTAL 3.27

61

Page 93: An evaluation of production output for in situ concrete work

Total Working Time = Mean Element Time x Skip Loads

(T.W.T.) = 3.27 x 311

111.2 minutes

In addition to the working cycle, the crane was subjected to

delays; for example, waiting f or concrete lorries or being diverted

onto other work. These delays were recorded in the comments section

in Figure 11.2, and can be summarized as follows.

(1) External delays caused b concrete lorries

Wait for concrete lorries 0.00 + 11.13 + 17.90 + 5.91 +

(for each lorry) 3.30 + 13.110 + 5.10 + 28.70

Total External Delays = 78.110 mine.

(T.E.D.)

Average delay per lorry = 78.40 = 9.8 mine.

8

Average delay per skip = 9.8 x skip size ...Equation 11.4

lorry size

(ii) Internal delays caused by interference

Wait f or concrete gang

Diverted onto other work

Internal Delay (I.D.)

Internal Delay

Allowance

Internal Delay

Allowance

= 0.115 + 8.21 8.7 mine.

= 3.6 mine.

= 12.3 mine.

= I.D.

T.E.D. + T.W.T.

= 12.3 x 100 = 7%

78.110+ 111.2

In this example, internal delays are seven per cent of total

basic time and total external delays.

62

Page 94: An evaluation of production output for in situ concrete work

11. 11.2 5nthetic Data for Tower Crane

To synthesize data suitable for other pours, it is necessary tocombine basic element times with delays for the tower crane. Forexample: for a given skip size, the pouring times remain fairly

constant over a series of pours, but travel time depends upon the

distance between pick up point to discharge area.

Pour into skip and shutters = 1.02 + 0.112 = 1.1111 mins.Lift and return skip = 0.81 + 1.02 = 1.83 nuns.

The average distance between the pour location and concrete

lorries was 38.5 metres, therefore, the 'no delay cycle time' can be

expressed in general terms, Equation 11.5.

No delay cycle time = 1.11 11 + 1.83 x D D = distance concrete

38.5 is conveyed (in.)

1.1111+ D ...Equation 11.5

21.0

The total basic crane time per cycle (TBCT) includes the time toplace the concrete, plus delays caused by waiting for concretelorries; .and giving assistance to other gangs when concrete is

available. Thus, the basic time per cycle (mins.) can be obtained

from the following equations.

TBCT pour into + Travel time + Externa Internal

per = J skip and for skip Delay x delay

cycle I_shutters J

allowance

IBCTpercycle

= r 1.1111 + Distance + 9.8 x Skip sizel x LOT mins.

L21.0 Lorry size]

.....Fquation 11.6

The relationship presented in Equation 11.6 is used to plot

Figure 11.5. The crane time per cycle can be obtained for aiy skipsize, or distance hoisted, given that the time to load and unload

concrete is 1.1111 minutes and the delay per lorry is 9.8 minutes.

63

Page 95: An evaluation of production output for in situ concrete work

0tx

E

N(I)0

(I)rf)

0

2UJ0

% '' ' ' ' - .% :%% ? uo:

\ \ \%, \ \ \%:%::t ' : : L .,

% %%: % : . : :

\ \\\ \ \ \ +%% :' :

: %% '% :

\.\.\...\...\....\.• ..................+

\ \\\\\\o (I)

S0 I-

0z0

00

cc

o(I)

-o

Li

w00

(I)

0

0

Lii

001

./.....

\JLLii

ZVLj

' :C..........

• : w• . :1-.>- .

• • •% : IV)

: :

E• : : z

coE

...I......\........IIOV) : : :

: F-ck:OLii

Lii ..>m................

• cz

0) N- CO U)

0

SU!W 3V1LL 313A3 1VIOI

Page 96: An evaluation of production output for in situ concrete work

l.5 BALANCING OF RESOURCES

The concrete gang works.in conjunction with the tower crane.

Consequently, the pouring, shovelling, vibrating, tamping and

trowelling are usually all done during the machine controlled time:

the preparation and transfer of tools are often performed outside the

machine controlled time. Thus, using Equation 11.2, the basic time

f or the crane controlled work (BTCC) is expressed as shown below.

BTCC Vol (11.38 +3.57) mins. ...Equation 11.7

d

Where d is the depth of the slab in metres.

To ensure that the size of the concrete gang is balanced with

the crane, the output rates during the basic machine controlled time

are equated to give the optimum gang size.

Output rate Skip size (in3 ) x 60 (m3/hr)

f or crane 1BCT ...Equation 11.8

Output rate = Volume x Gang Size x 60 (m3/hr)

f or men BTCC ...Equation 11.9

Equations 11.8 and 11.9 are combined to produce Equation 11.10 and

Figure 11.7, both of which can be used to determine the optimum gang

size.

Gang size Skip Size x BTCC

IBCT Volume

...Equation 11.10

65

Page 97: An evaluation of production output for in situ concrete work

LLJEEEE

• W11"rT1"i•:c3Q00l,o / / / / I

x O.tnO r I I I I I

I

-o

Li

• H

NN

. .:;.LLJcDO)

ckz

/1

iiiii

ZZo4LJLjJ

JFLJ0oauJ-J L&.

cj

V)OQ::

ZcDO

o

ij(()Oo.

0I—.0

pp. '-I-

0 0 o o o aLt•) c.I 1

no w lfldlflO

Page 98: An evaluation of production output for in situ concrete work

HLPTER FIVE

REJLTS AND ANL!SIS OF BASIC EMENT TIMES

FOR CONCRETE OPERATIVES

67

Page 99: An evaluation of production output for in situ concrete work

CRAPTEL FIVE

RESULTS AND ANALYSIS OF BASIC ELEMENT TIMES

FOR CONCRETE OPERATIVES

5.1 RESULTS FOR CONCRETE OPERATIVES

The build up of synthetic data from one study was illustrated by

an example presented in Chapter Four. In order to establish the

reliability of the assumptions made in this example, the results from

seventy concrete pours are combined and analysed. The analysis is

performed on the PRIME mainframe computer using a statistical package

called Minitab (5.1).

The results for each concrete pour are presented in Table 5.2.

The basic element times for each pour, obtained from activity

sampling performed on site, are presented in columns C3 to Cli; the

concrete dimensions are presented in columns C13 to CiT.

Table 5.1 gives the codes for the different methods of placing

concrete, and the codes f or the different types of pour. These codes

are respectively entered into columns C2 and C12 of Table 5.2. The

information presented in Table 5.2 was transferred on to the Prime

computer and saved in the file 'data', thus, enabling a statistical

analysis to be performed using the Minitab package. This analysis

tests the assumptions made in Chapter Four during the build up of

synthetic data, modifies these assumptions where appropriate and

establishes a model for calculating basic times f or concreting

operations.

68

Page 100: An evaluation of production output for in situ concrete work

Table 5 • I Code3 for Method and Type of Pour

PLLEMEHT METhOD TYPE OF POUR

Code Method (C2) Code Type (C12)

1 Direct pour I Slab

2 0.5 Cu. m. skip 2 Beam

3 Pnp 3 Wall

1.0 cu. m. skip Columns

69

Page 101: An evaluation of production output for in situ concrete work

Table 5.2 BaSic Element Times for each Concrete Pour

BASIC NT TI)€S (MINS) CONCRETE DI)€NSIONS

I I 1 . 1 I I I I I I I I ICl I C21 C3 I Ck C5 I C6 C7 I C8 I C9 CIOl Cli C12 C13 I Clk C15 I C16 Ci?II I I I I I I I I I I I

I I I I I I I - I I ISM PTIPIVISITITIG CT CT VI NIL I A ID7 E ROIOIIIIIIAIR(E LO 0! 01 lIE P I EUT EOIUIBIOIMIOIN EO VP LI DIN I E I PD H PLI RI RI VI P1 WI E ALl E E Ut TI 43 I A I TTO ASI latE! IEIR PSIR MI HIT I I

IDRI luLl ILIAI El IH I IN El I El I I I LI I0 I I I I I I I I (m3) I Cm) I Cm) I Cm2 ) I (a)

I I I I I I1 1 21 5 8 16 1 30 28 I 0 I I 16 1 6.10 I 4.90 4.90 24.30 I 0.252 1 11 9 12 28 I *4 214 I 0 1 • • 1 6.10 I 4.90 4.90 I 211.30 0.253 1 • 9 15 2* I 36 29 I 19 10 20 1 7.30 I 14.90 14.90 I 24.30 0.304 1 ' I 9 18 38 39 30 36 • I 21 1 7.30 I 5.40 5.40 I 29.20 0.255 1 I 4 19 9 60 I 25 29 0 I • I • 1 6.10 I 14.9 04.90 I 214.30 0.256 2 ' III 12 19 I 23 32 I 18 10 3 1 3.10 4.50 14.50 I 20.60 0.157 2 I 29 29 1* 0 I 6 32 16 • 20 3 2.01 0.25 I 10.7 I 2.68 0.758 2 I 20 24 39 26 140 3 7 25 2 6.20 1.11 I 26.2 I 29.10 0.209 1 • 51 79 51 40 130 9 • 2 17.0 0.65 38.8 I 25.20 0.60

10 I 2 38 ' I • 22 14 15 I 32 10 • 3 20.9 0.50 17.14 I 8.70 2.4011 2 15 15 211 211 I 27 1414 I 21 I 16 1 9.10 11.50 9.001140.5010.2212 2 5 10 I 23 8 I *2 16 143 ' 16 1 6.00 I 14.50 5.30 21.9 00.2013 2 11 65 101 30 I 79 150 54 • 43 1 9.10 4.50 9.00 140.50 0.2214 2 16 101 16 0 I 3 I 0 I 14 2 1 2.001 0.60 0.70 0.140 5.0015 I 2 12 5 20 0 I 9 ' 0 I 4 2 11 2.00 0.60 0.7 0 I 0.140 5.0016 4 45 37 1175 0 I 26 15 26 I 15 28 3 23.2 0.50 5.35 I 2.80 6.3017 14 1 • I 12 15 22 I 33 65 16 I I I 1 2.30 I 2.00 2.00 9.20 I 0.2518 14 10 I 3 I 16 26 I 28 37 10 I I • 1 2.3 0 2.00 4.50 9.20 0.2519 I 15 5 37 63 I 42 65 20 t • • 1 6.20 I 5.00 5.00 214.80 I 0.2520 14 40 I 43 I173 7 1 29 10 35 I I • 3 23.2 0.50 5.35 1 2.80 I 6.3021 4 • I 67 • 68 I 60 82 95 I 10 I 79 1 21.0 I 5.35 5.72 I 30.70 0.6822 4 20 I 36 i 0 I 27 12 10 I • • 3 23.2 0.50 5.35 I 2.80 6.3023 11 0 I 12 I 2* 6 I 20 40 15 I • • 1 2.40 I 2.00 2.00 4.00 0.60214 14 20 18 15 9 I 23 113 21 • • 1 2.40 2.001 2.001 4.00 0.6026 3 • 123 216 192 1309 • 120 1 72 • 1 66.0 23.3 I 12.3 I 285.0 0.2327 11 20 I 36 156 0 I 28 6 21 I * 18 3 23.2 0.50 I 5.35 I 2.80 6.3028 14 30 36 51 0115 18 01 • 24 1 2.00 0.3010.30 1.60 6.3030 1 ' 214 30 15 I 33 50 36 I I 1 4.80 2.00 I 4.004 8.00 0.6032 3 • 65 130*0 I 50 55 • I 55 15 3 28.5 0.30 I 32.6 I 9.80 3.5033 1 • 10 • 1110 1185 55 20 • 1 17.5 5.50 I 14.8 I 81.40 0.2039 3 30 2* 6 61 64 I • 8' ' • 1 9.55 5.101 9.60 49.00 0.19140 I 3 I 30 17 1 314 50 I • 19 ' 1 11.41 5.10 I 9.60 1 149.00 0.09

Page 102: An evaluation of production output for in situ concrete work

Table 5.2 Basic Element Times for each Concrete Pour :- Continued

- _________

BASIC €IT TIMES CHINS) CONCRETE DIMENSIONS

I I I I I I I I I I - I I I ICl I C21 C3 I C4 CS I C6 I C7 I C8 I C9 I C101 Cli C12 C13 I Ci* C15 ( C16 I CIT

I I I I I I 1 I I I I I I

I I I I I I I I I I - I I I ISIHIPTIPIVISITITIOICTICT VI WIL I AIDTIEIROIOIIIRIAIRIEILOIOT 01 lIE I RI EUITIEO I UI BI 01 14, 01 IIEOI V P L D I N I E I PDIRIPLIRIRIVIPIWIEI*LIE £ U Tb I A IT1101*51 ILl El (EIRIRSIR H HIT I IN

I D R I I T L I I L. I Li E I H INI IEI tEl I I ILl I0 1 I I I I I I I I I (&) I Cm) I (.) I (a') I (a)

I I I I I - I I -141 3130 211 * 143 531 • 18114112 1 6.7115.1019.601 119.00 0.14142 3 I 201 111 I • 67 50 • 10 • 8 1 5.50 1 5.101 9.601 49.00 0.11143 3 I 20 I 22 1 *8 52 13 I • 9 1 7.90 I 5.10 1 9.60 I 49.00 0.161414 31 201 37 I • 80 83 121 9 1 ' 1 12.14 1 5.50 I 9.50 I 52.00 0.2345 1 I 10 I 39 a 9 16 I a 0 14 I a 1 23.0 I 3.10 I 3.50 I 10.90 2.10'e i a 17.5 19 11 i 30 15 I • a 6.00 I 2.00 I 10.0 I 20.00 0.20149 1 I 5 I 30 a 50 20 • a • 2 18.0 I 3.70 3.50 12.90 I 1.4050 1 I SI 181 28 i 24 291 • 8 a • 2 12.01 1.10 12.1 13.30 0.9051 2 I 10 I 10 20 0 I 0 a 0 • I • 4 0.95 I 0.50 0.50 0.25 3.8052 14 I 60 I 45 11145 I *0 90 80 20 20 • 1 34.0 1 2.00 119.5 97.00 0.3553 14 I • I 25 1116. 123 69 11147 25 I 12 I 98 1 33.6 I 3.00 33.0 98.90 0.35514 2 I 10 15 30 0 i o • o • a 4 1.80 I 0.50 1.00 0.50 3.8055 14

I 40 1115 1285 1180 195 (295 65 • 80 1 65.0 I 8.00 29.0 1714.00 0.3756 2 I 15 I 5 I 10 i o I 0 a I a a 14 0.95 1 0.50 0.50 0.25 3.8057 2 I 15 I 5 I 20 I 0 0 • I I a 4 0.95 I 0.50 0.50 0.25 3.8058 11 I 40 40 95 85 50 50 50 a • 1 25.3 7.50 8.00 60.00 0.4259 2 22 I 50 135 I 0 0 I 40 a a 14.70 0.70 2.50 0.25 3.8060 11 20 I 20 80 *5 85 1 • 45 t 151 a 12.5 4.80 10.5 I 50.00 0.2562 3 10 I 85 I 75 I 50 175 I • 60 25 a 1 30.7 6.50 15.7 I 1c2.3 0.3063 a I 95 1120 75 155 I • 80 45 a i 28.5 6.50 12.5 I 81.140 0.3564 3 10 I 75 I 75 85 180 • 105 I 42 I a i 30.6 6.00 15.5 I 92.70 0.3365 3 9 I 15 I 15 I 10 I

a 0 25 I • 4 1.06 0.145 1.05 I 0.47 2.2566 3 15 I 45 I 45 I 30 130 I • 50 145 I * 1 16.5 6.50 7.70 I 50.00 0.3367 3 20 I 85 1105 I 80 1180 a 60 145 I • 1 30.3 6.50 15.5 1101.00 0.3068 11 10 I 5 I 30 50 1001 • 151 10 • 1 15.7 14.80 12.5 60.00 0.2669 14 10 1 27 I 27 I 0 5.5 a 0 5 I I 8 1.85 0.6? 1.2* I 0.82 2.257 j 4 a I 18 I 5 I 10 10 0 • a 2 1.00 0.30 9.60 I 2.90 0.3571 8 • I 10 5 I 10 10 I 10 0 • I 2 1.00 0.30 I 9.60 I 2.90 0.3572 14 101 15 I 30 30 80 • 10 15 I • 1 15.7 4.80 12.5 I 60.00 0.2673 14 I 0 I 55 I 65 I 0 0 I 10 10 a 8 1.86 0.80 1.145 1.16 2.25711 3 45 I 45 I 145 I 45 105 I • 1 25 a a 37.0 10.4 10.5 1105.00 0.31175 14 I 0 I 30 I 15 I 0 5 I a I 10 a a i 0.60 0.20 I 0.60 I 0.214 2.14076 14 I 20 I 20 25 i 25 60 I a I a • 1 15.0 5.140 I 11.3 I 60.80 0.2577 14 15 I 10 15 i O s I ' I 5 a I 14 0.90 0.20 I 0.60 I 0.36 2.14078 * 15 I 55 1165 1125 135 I • I 35 I a I 1 41.0 9.50 I 18.4 I 136.0 0.3079 14 0 I 5 I 10 1 0 0 I • I 0 I a 14 0.30 0.20 I 0.60 I 0.12 2.14080 8 0 I 25 I 15 I 0 5 I • I 0 a I 3 1.70 0.69 0.15 4.60 I 2.4081 14 I I 40 I 70 1 5 10 I a 30 • I I 3 13.0 0.20 I 111.14 2.88 I 4.50

- F-.

Page 103: An evaluation of production output for in situ concrete work

5.2 METhOD OF ANALYSIS

The following analysis combines the results from the seventy

concrete pours presented in Table 5.2, and tests the assumptions madein the example used in Chapter Four. From the results of this

analysis a more detailed model, which can be used to calculate basictimes for a wide range of concreting operations, is constructed. The

earlier example presented in Chapter Four assumes that:

(a) the basic element times relating to the volume of

concrete are pour and vibrate;

(b) the basic element times relating to area are

shovel, tamp, trowel and cover;

(c) the basic element times for preparing, clearing and

transferring of tools depends upon the number of

occasions each is performed; and

(d) the time spent on general work relates to the timetaken to pour, vibrate, shovel, tamp, trowel and

cover the concrete.

These assumptions may be translated into the following

mathematical expression. In the analysis of basic element times thevalidity of this expression is established and values are determined

for constants a, b, c, d, e, f, g, h, I and j.

BasicTime aN+bNi + cN2+Vx(d+ e)x(1+j)(manhours) +Ax( f+g+ h+I)x( i+j)

Where: NNiN2

VA

a, b, e

d, ef, g, h, I

j

= number of times the tools are prepared= nunber of times the tools are cleared away= number of times the tools are transferred

= vole of concrete

area of concrete

= basic times per occasion to prepare, clear

and transfer toolsbasic times per cubic metre to pour and vibrate

= basic times per square metre to shovel, tamp,trowel, and cover,

allcMance for general work

72

Page 104: An evaluation of production output for in situ concrete work

5.3 ANALYSIS OF BASIC KLIENT TIMES

5.3.1 IntroductIon

The following Investigation could have been based on a multiple

regression analysis using the pour dimensions against either:

(a) the total basic times for individual studies,obtained by summating columns C3 to Cli in Table

5.2; or(b) the individual basic element times, le. treating

columns C3 to Cli separately.

The majority of concrete pours have at least one activity which

is not performed, for example trowel and cover. If the former

approach is adopted In the analysis, the obtained correlationcoefficients would be affected, and the resulting model would notaccurately represent operations where some activities are not

performed. Thus, the following analysis is based upon individualbasic element times; the resulting equations are used to build thegeneralized concrete model.

The first stage in testing the earlier assumptions is to analyse

each activity separately (i.e. data in columns C3 to Cli), this

involves using eight individual Minitab programs. The program

investigating the general activity includes the findings of the firsteight programs, To check the reliability of the resulting model, a

final set of programscompares the predicted times with the ieasuredtimes. The results , obtained from these individual programs are

discussed in the remainder of this chapter and program listings are

presented in Appendix B. Extracts from the computer print-outs are

presented in Appendix D. These include the results from the twoprograms analysing the preparation of tools and the tamping of'

concrete, and print-outs from the programs checking the analysis.

73

Page 105: An evaluation of production output for in situ concrete work

There are four main progressive steps in this section of theanalysis; these come under the headings of correlation, graphs, oneway anova test and multiple regression analysis. The theories behindthese steps are summarized in Appendix F. The whole analysis is

primarily investigative, and to account for the trends indicated in

each step, the analysis can either omit the next step or backtrack toone of the previous steps.

In controlled laboratory tests correlation coefficients between

either: 0.90 and 1.00; or -0.90 and -1.00, are often required.However, values as low as 0.60 are often acceptable in the field ofhunan sciences. For this type of research correlation coefficientsaround: ±0.90 are very high; 0.80 are good but indicate that theremay be an additional variable which has some influence and also

requires consideration; 0.70 are reasonable but indicates there may

be two groups of results; 0.50 are considered to be too low to provea direct relationship but do indicate a trend.

The first stage in the analysis is to correlate the individualbasic element times with volume, area, and depth of concrete; the

results are shown in Table 5.3. In the pours studied there is some

correlation betieen volume, area and depth, therefore, checks are

carried out throughout the analysis to ensure that any cross-

correlation is taken into account.

vi

Page 106: An evaluation of production output for in situ concrete work

Table 5. Correlation Coefficients (fi)

Volune Area Depth General

Prepare tools 0.503 0.368 0.061 0.2111

Pour 0.795 0.66 1 -0.043 0.8011

Vibrate 0.8111 0.591 0.192 0.639

Shovel 0.786 0.889 _0.1186 0.6118

Tamp 0.80T 0.928 -0.1114 0.8(6

Trowel 0.572 0.831 -0.356 0.582

Genera]. 0.695 0.693 _0.2116

Clear tools 0.731 0.660 -0.208 0.8111

Cover 0.716 0.669 -0.225 0.693

Volume --- 0.831 -0.116 0.695

Area --- --- -0.450 0.693

Depth --- --- 0.21l6

75

Page 107: An evaluation of production output for in situ concrete work

5.3.2 Prepare Tools (PRTOOL)

(1) CorrelationThe correlation coefficients (R) in Table 5.3 indicate that

there is little correlation between the time taken to prepare tools

and either the volume, depth or area of concrete.

(ii) graphsThe Minitab plots of time taken to prepare tools against volume

and area, using codes for the method of placement and type of pour,

show considerable scatter with no obvious grouping of results.

(iii) AnovaIn the first anova test, the times for preparing tools are

separated into groups depending on the method of placement; the results

indicate that there is no significant difference between the groups.

The second anova test indicates that for the half cubic metre skipmethod the time taken to prepare tools per cubic metre is greater

than the times required for the other methods. This is probably

because small volumes of concrete are usually associated with this

method.

(iv) Kegression An1ysisRegression analyses are performed on volume, and volume with

area; the resulting equations are presented below. There is littledifference between the two correlation coefficients, hence, therelationship based on volume alone is used to plot Figure 5.1, andsubsequently adopted in the generalized concrete model. The

correlation coeffients for this activity are the lowest obtained in

the analysis and only indicate a trend. There may be other

variables, such as site layout, which exhibit a greater influence on

the time taken to prepare tools. Taken in isolation, the resulting

equation may appear inaccurate but it is combined with eight othersat a later stage.

PETOOLS = 11.8 + 0.5811 VOLUME - 0.0345 AREA = 25.7 ALL POURSPRTOOLS 11.7 + 0.501 VOLUME 25.3 ALL PCURS

76

Page 108: An evaluation of production output for in situ concrete work

60

50

40

30

20

10

0

Cl,C

E0)-J0

uJ

U

0

0F-

Ui

liME TO PREPARE TOOLSAGAINST VOLUME OF CONCRETE

0 10 20 30 40 50 60 70VOLUME OF CONCRETE cu. m.

IFIGURE 5.11

Page 109: An evaluation of production output for in situ concrete work

5.3.3 Pour Concrete (POUR)

(I) Correlation

The overall correlation between the time required to pourconcrete and the volume of' concrete is very good, resulting in avalue of 0.7 95.

(ii) Graphs

The initial Minitab plot of time taken to pour concrete against

volume has some scatter associated with both the method of placementand the type of pour.

(iii) Anova TestsThe first anova test indicates a difference in the basic element

time caused by the method of' placement; this results in a F statistic

of 2.19. A more significant difference is obtained In the anova testbased on the type of pour, resulting in a F statistic of 13.10. As

the results for walls and beams are similar, they are combined f or a

third anova test; the resulting F statistic Is 19.95.

(iv) Graphs

The results from the anova tests show that there is a

significant difference between the basic element times f or different

types of pour. Three graphs are plotted to investigate this further:Figure 5.2 plots time taken to pour concrete against volume for

slabs; Figure 5.3 plots time taken to pour concrete against volume

f' or beams and walls. These two figures have little scatter and theresults are consistent with the previous steps in the analysis.

The values for columns are plotted in Figure 5.1 and large

variations in times are indicated. For example, the time taken topour columns with two cubic metres of concrete varies from 5 minutes

to 55 mInutes, This discrepancy results from an earlier decision to

combine the times f' or several columns poured together in order toimprove the accuracy of the activity sampling. Consequently, if the

pour times are divided by the appropriate number of columns; theresulting times for pouring individual, columns vary between 5 and 15minutes.

78 -

Page 110: An evaluation of production output for in situ concrete work

Cv) Regression Analysis

The three equations resulting from the regression analysis are

presented below. If the columns are treated as individual items the low

coefficient would significantly increase. However, the adopted

expression combines columns, ensuring that the resulting equation is

consistent with those obtained for the other activities.

PAJR = 5.15 + 1.67 VOLUME

= 69.8

aABS

POUR= 16.10+ 1.18 VOLUME

B2 = 61.1k

BEAMS AND WALLS

PIJJR 2.79 + 9.65 VLUME

B2 = 36.8 CLUMNS

79

Page 111: An evaluation of production output for in situ concrete work

CI,C

EUiF-LU

0z00

000F-zLi

LU

F-

TIME TAKEN TO POUR CONCRETEAGAiNST VOLUME OF CONCRETE

FOR SLABS

140

120

7100-...... . .

X/

x /80-.:../..................................

>( /

60. ..............................

/

,/40-.

X

x I:20- j...)<..)(............................................................................

,F <' xxx x____________ _________________________ : ____________________________________________________

0 10 20 30 40 50 60 70VOLUME OF CONCRETE cu. m.

-

[RCUREJ

Page 112: An evaluation of production output for in situ concrete work

TIME TAKEN TO POUR CONCRE1 EAGAINST VOLUME OF CONCRETE

FOR BEAMS AND WALLS

70

60

C1•)

ELU 50F-LU

0z00

00

zLU

F--

LU

F-

20

100 5 10 15 20 25 30

VOLUME OF CONCRETE cu. m.

IFIGURE 5.3]

Page 113: An evaluation of production output for in situ concrete work

55

50

45

ci,C

E40

LU

LU

o 35z00

00

F-25zLU

LU

F-

15

IC

5

liME TAKEN TO POUR CONCRETEAGAINST VOLUME OF CONCRETE

FOR COLUMNS

0 1 2 3 4 5

VOLUME OF CONCRETE cu. m.

IFIGURE 5:j

Page 114: An evaluation of production output for in situ concrete work

5.3.J Yibrate Concrete 1VThR1

(1) CorrelationThere is very good correlation between vibration time and the

volume of concrete, resulting in a correlation coefficient of 0.8111.However, it is also necessary to investigate the variations caused by

the type of pour.

(ii) GraphsThe initial Minitab plot of vibration against volume indicates

that there is a significant difference between -the times for columnsand the rest of the data.

(ill) Anova TestThe anova test confirms that there is a significant difference

between the vibration times per metre cubed for various shapes ofpour. The times are therefore separated into different groups f' or:

slabs, walls or beams, and columns.

(iv) Regression AnalysisThe subsequent regression analysis shows that within each of the

above categories there is high correlation between the vibrationtimes and volume of concrete, resulting in correlation coefficients

of' 0.91, 0.92 and 0.90 respectively. The relationships established

from the regression analysis are presented below; Figures 5.5, 5.6

and 5.7 are plots of vibration times against volume of concrete-forthe different types of pour. -

VIBRATE = 3.116 V(LUME R2 = 82.8

aVIBRATE = 5.69 VOLUME R2 = 8k.6

WALLS AND BEAK

VIBRATE = 22.80 VOLUME R2 = 81.0

COLUMNS

83

Page 115: An evaluation of production output for in situ concrete work

300

250

200

150

100

50

0

TIME TAKEN TO VIBRATE CONCRETEAGAINST VOLUME OF CONCRETE

FOR SLABS

U)

ELiJF-Ui

0z00U

03>0I-zLi

U

F:

0 10 20 30 40 50 60 70VOLUME OF CONCRETE cu. m.

f1CURE 5.5J

Page 116: An evaluation of production output for in situ concrete work

liME TAKEN TO VIBRATE CONCRETEAGAINST VOLUME OF CONCRETE

FOR WALLS AND BEAMS

180

160

cu 140

E

LU120

0z0o 100

LU

> 80

z

6

LU

f— 40

20

a

5 10 15 20 25 30VOLUME OF CONCRETE cu. m.

IF1CURE 5.61

Page 117: An evaluation of production output for in situ concrete work

liME TAKEN TO VIBRATE CONCRETEAGAINST VOLUME OF CONCRETE

FOR COLUMNS

140

120

0)

E 100Lii

0z

80

ni> 60

zLiici:

40w

I-

20

00 1 2 3 4 5

VOLUME OF CONCRETE cu. m.

IFIGURE 5.71

Page 118: An evaluation of production output for in situ concrete work

5.3.5 Shovel Concrete (SHOVEL)

(1) Correlation

The correlation between time spent shovelling concrete and both

area and volume are good, giving respective correlation coefficients

of 0.889 and 0.786. However, there is also some negative correlation

between time and the depth of concrete, -0.Ji86.

(ii) GraDh

The initial Minitab plots of shovel against area, volume and

depth indicate that the time taken to shovel concrete relates best to

the area of concrete, as illustrated in Figure 5.8.

(iii) Anova Test

The one way anova test, of time required to shovel per square

metre against type of pour, confirms that the depth of concrete has

no significant affect.

(iv) Regression Analysis

There is very little increase in the R2 value when depth is

included in the regression analysis, therefore, the relationship

between shovel and area, as shown below, is adopted.

SHOVEL 8.07 + 0.737 AREA R2 79.0 ALL PCURS

87

Page 119: An evaluation of production output for in situ concrete work

liME TAKEN TO SHOVEL CONCRETEAGAINST AREA OF CONCRETE

200

180

160C,,

E140

LUF-LU

0z 12000-J

>00IC,,

80

zLU

60

LU

F-

40

20

a0 50 100 150 200 250 300

AREA OF CONCRETE sq,u. m.

[FiGURE 5.81

Page 120: An evaluation of production output for in situ concrete work

5.3.6 Tamp Concrete (TAI1PI

(1) CorrelatIon

There 18 very good correlation between the time required to tamp

and area of concrete, resulting in a correlation coefficient of

0.928. There is also some correlation between tamp arid both volume

and depth of concrete.

(ii) GraphB

Figure 5.9 plot8 the time spent tamping concrete against area of

concrete; as there is very little scatter no ariova tests are

required.

(iii) Regression An1ysis

The regression analysis of tamp and area produces a R 2 value of

8.3. When depth Is also Included there Is no significant increase

in the R2 value, hence, the following equation is adopted.

TAMP = 10.7 + 1.12 AREA 86.2 ALL PCURS

89

Page 121: An evaluation of production output for in situ concrete work

TiME TAKEN TO TAMP CONCRETEAGAINST AREA OF CONCRETE

350

300

C',

' 250

UF-U

0200

00

150

zuJ

100

F-

50

00 50 100 150 200 250 300

AREA OF CONCRETE.scp. rn.

IF1GURE 5.9]

Page 122: An evaluation of production output for in situ concrete work

5.3.7 Trowel Concrete fTRCMEL)

(1) CorrelationThe correlation between the time spent trowelling and the area

of concrete is 0.831.

(ii) Grar,hsThe Idinitab plot of trowelling time against area suggests that

there are two significantly different groups of results. When the

results are investigated further, It becomes obvious that the mainInfluencing factor is the quality of finish required. The quality of

finish varies considerably between sites, from concrete reservoirs

requiring double trowelling to car parks where no trowelling is

necessary. Hence, for the trowelling activities the pours areclassified as:

(a) very good finish with repeat trowelling;

(b) trowelled once f or a normal finish; or

(c) no trowelling required. -

(iii) AnovaThe anova test used on the first two groups of pours Indicates a

significant difference In the trowelling times per square metre, asillustrated by Figures 5.10 and 5.11.

(lv) IngressIon ArtysisThe equations resulting from the regression analysis are

presented below. The high intercept on the y axis is caused by theextra work often required around the edge of the slab when a goodfinish is necessary.

TR(YV1EL 27.6 + 2.79 AREA R2 81.6 DOUBLE TB(ELThJEL = 1.51 AREA = 88. SINGLE TREL

91

Page 123: An evaluation of production output for in situ concrete work

TIME TAKEN TO DOUBLE TROWEL CONCRETEAGAINST AREA OF CONCRETE

160

140

Cl,C

120ILIHUJ

0z

100

F- 800F-zuJ

4:F- 60

H

40

200 10 20 30 40 50

AREA OF CONCRETEsqu. m.

(FiGURE 5.101

Page 124: An evaluation of production output for in situ concrete work

TIME TAKEN TO SINGLE TROWEL CONCRETEAGAINST AREA OF CONCRETE

300

250

Cl)C

EbJ

200

Uz00-J

1500

I—

z10

U

F-

50

00 50 100 150 200

AREA OF CONCRETE squ. m.

IF1GURE 5.11J

Page 125: An evaluation of production output for in situ concrete work

5.3.8 Cover Concrete (COVERI

(1) CorrelatjQfl

The correlation coefficients for the time required to cover

concrete against area, volume and depth are 0.66 9, 0.7 16 and -0.225,

respectively. It is initially assumed that the time relates to the

area of concrete covered, and increases as the depth of concrete

becomes larger. However, the correlation coefficient f or the

resulting regression equation (COVER 7.81 + 0.1190 AREA + 1.115

DEPTH) shows no improvement on the correlation coefficient, 0.669,

obtained using area alone.

(ii) Graoha

The Minitab plot of time spent covering concrete per square

metre against depth indicates a linear relationship expressed as:

COVER/AREA = 1(1 + K2.DEPTH

Where Ki = Y Intercept

1(2 = Gradient

Alternatively, this can be written as

COVER = K1.AREA + K2.VOLU!€

(iii) egestoi Ani1yi1js

A regression analysis is carried out to determine 1(1 and 1(2,

resulting in the equation presented below. The correlation

coefficient, 0.7112, for this equation is an improvement on the

coefficent, 0.669, obtained when area is the only variable.

COVER = 8.62 + 0.861 VOLUME + 0.202 AREA R2 = 55.2 ALL POURS

911

Page 126: An evaluation of production output for in situ concrete work

5.3.9 Clear Tools Aw,y (CLEAR)

(1) Correlation

The correlation coefficients f or clear tools away, with volume,

area and depth, are 0.731, 0.660 and -0.208, respectively. These are

very similar values to those obtained for covering concrete.

(ii) Graphs

The initial Minitab plot of time spent clearing tools away

against volume of concrete clearly shows two separate groups of

results; those for pumping concrete and those for other methods of

placement, as plotted in Figures 5.12 and 5.13.

(in) Inova Tests

Four one way anova tests are used to investigate how both

methods of placement and type of' pour affect the time required to

clear the tools away. The results agree with the grouping indicated

by the figures.

(iv) Regression Arlsis

The data is separated into the two groups and a regression

analysis carried out on both, resulting in the following equations.

When area is also included in the regression analysis the R2 values

are not significantly increased.

CLEAR = 6.83 + 0.310 VUME = i8.1 OTHERS

CLEAR = 16.20 + 0.859 Vct.UME 61i.J FUMP

95

Page 127: An evaluation of production output for in situ concrete work

80

70

0,. 60E

50(I-i-J0

uJ-J00F-zw

Li

I-

10

0

40

30

20

liME TAKEN TO CLEAR TOOLS AWAYAGAINST VOLUME OF CONCRETE

FOR PUMPING METHODS

0 10 20 30 40 50 60 70VOLUME OF CONCRETE Cu. m.

IFICURE 5.12J

Page 128: An evaluation of production output for in situ concrete work

20

18

0,. 16E

<14(I,-J00F--

12

w-J0

0F- 10zLiJ

8P

6

4.

liME TAKEN TO CLEAR TOOLS AWAYAGAINST VOLUME OF CONCRETE.

FOR SKIP AND DIRECT POUR METHODS

0 5 10 15 20 25 30 35

VOLUME OF CONCRETE cu. m.

F1GURE 5.13 I

Page 129: An evaluation of production output for in situ concrete work

5.3.10 General Work (GKNERAL)

In order to determine variables influencing the amount of

general work, two separate investigations are carried out. The

variables used in the first Investigation are volume, area and depth

of pour. In the second investigation, the total times spent on the

main activities, excluding general work, are taken as the main

variables.

(I) fiRST INVESTIGATION

(1) CorrelationThe correlation coefficients f or general work against area,

volume and depth are 0.693, 0.695 and -0.2146 respectively.

(ii) GraDhaThe initial Minitab plots, of general work against volume, area

and depth of concrete, all contain a large degree of scatter with no

apparent grouping of results.

(iii) Anova TeatsAn anova test is performed on the method of placement and

general work per cubic metre. At this stage there Is no significant

difference between these groups, although the indications are thatthe times f or the half' cubic metre skip are slightly higher.

(iv) Regression Analysis -The regression analysis, using both area and depth as variables,

results in a correlation coefficient of 0.670. This is a slightreduction on the value of 0.6 93 obtained when area is the onlyvariable.

GENERAL = 7.149 + 0.379 AREA + 0.995 DEPTH = 148.5

ALL POURS

GENERAL = 9.59 + 0.36 1 AREA = 148.1

ALL POURS

98

Page 130: An evaluation of production output for in situ concrete work

(II) SECOND INYESTIGAION

In order to determine the activities most closely correlated to the

quantity of genera]. work, the total times are calculated for the

following groups of activities.

C20 : Pour, vibrate, shovel, tamp, trowel.

C21 : Prepare tools, clear tools, cover.

C112 : All the above activities.

(1) CorrelatIon

The correlation coefficients obtained for the groups are:

0.769 for C20; 0.559 for C21; and 0.790 for C2. These values are a

significant Improvement on those obtained in the first Investigation.

(ii) Regression Analysis

The correlation coefficients, obtained f or the following

regression equations, Indicate that it Is more appropriate to combine

the two groups of activities (ie. C12).

GENERAL 1.81 + 0,0998 x C20 + 0.0576 x C21 R2 = 59.3 ALL PC.URS

GENERAL 0.70 + O.0919 x C1 2 R2 = 62.5 ALL POURS

99

Page 131: An evaluation of production output for in situ concrete work

(III) COMBINATION OF INVESTIGATIONS ONE AND TWO

To enable the allowance for general work to be applied as a

percentage of the time spent on other activities, the regression

analysis is repeated with the intercept set to zero. Also, the

activity times are divided into two groups and plotted in Figures

5.9 and 5.15: the times for methods using a skip are put into the

first group; the times for methods using either direct placement

or pumping are put into the second group. A final regression

analysis is performed on these two groups, resulting in the following

equations with improved correlation coefficients; these are adopted

in the generalized concrete modeL

GENERAL = 0.13 00 x C112 R2 80.1 SKIP

GENERAL = 0.0175 x C112 = 62.1 DIRECT + PUMP

100

Page 132: An evaluation of production output for in situ concrete work

E

0

-J

uJzUJ0

z0

F-zLiJ0

UJ

F-

120

100

80

60

40

20

0

TIME SPENT ON GENERAL WORK AGAINSTTIME SPENT ON OTHER ACTIVR1ES

FOR SKIP METHODS

0 200 400 600 800 1000

TIME SPENT ON OTHER ACTIVITIES mins.

{1CURE 5.14J

Page 133: An evaluation of production output for in situ concrete work

TiME SPENT ONTiME SPENT

FOR PUMPED AN

GENERAL WORK AGAINSTON OTHER AC11Vfl1ESD DIRECT POUR METHODS

80

70

cE

F°40

0z0F-Z 30Ui0Cl)

Ui

1— 20

10

0

0 200 400 600 800 1000 1200TIME SPENT ON OTHER ACTIVES mins.

[FiGURE 5.15]

Page 134: An evaluation of production output for in situ concrete work

5. 1$ GENERALIZED CONCRETE MODEL

The additional times required to prepare the work area and clear

away the pipeline used in pumping operations are the only significant

variations in individual basic times associated with the method of

placement. Most of the variations in basic times are caused by theshape of pour, hence, basic operation times are presented separately

f or slabs, beams, walls and columns. The generalized concrete modelalso allows vibration, trowelling and covering to be treated as

optional activities.

The regression equations obtained in the main analysis are

summarized in Table 5.1$. However, before these relationships wereused to produce the basic operation times presented in the AppendixC, a check was carried out to ensure that the values measured on sitecorresponded to those predicted by the model. The four programs

used to check the model are listed in Appendix B with the resultspresented in Appendix D. The first two programs (i.e. !TEST1.MINEXECI

and 'TFST2.MINEXEC') checked the expressions for the individual

activities, for example pouring concrete. The third and fourth

programs (i.e. 'TFST3.MINEXEC' and 'TEST II.MINEXEC t ) used the

generalized concrete model to calculate a basic time for each

operation. The correlation between the values obtained from the

model and the times measured on site was very hig1i (i.e. 0.962). Itcan, therefore, be concluded that the generalized model accuratelyrepresents the seventy concrete pours measured on site.

103

Page 135: An evaluation of production output for in situ concrete work

Table 5.Ij Gerra11zed Concrete Model

OPERATION UATION CORRELATION VARIABLECOEFFICIENT

PRTOOLS 11.70 + 0.501 x V R 0.50 ALL POURS0. 27<R<O.67

POUR 5.45 + 1.670 x V R = 0.84 LABS072<R<O.91

POUR = 16.10 + 1.180 XV R 0.60 BEA AND WALLS0. 43<R<O. 93

POUR = 4.7,9 + 9.650 x V R 0.61- COLUMNSO.12<R<0.86

VIBRATE = 3.46 x V - R 0.91 JABS0. 83<R<0. 95

VIBRATE = 5.69 x V R = 0.92 WALLS AND BEAO.76<R<O. 98

VIBRATE 22.80 x V R 0.90 COLUMNSO.72<R<O. 97

SHOVEL = 8.07 + 0.737 x A R e 0.89 ALL POURS0. 83<R<O. 93

TAMP = 10.7 + 1.120 X A R = 0.93 ALL POURS0. 89<R<0. 95

TROWEL 27.6 + 2.7,90 x A R 0.90 DOUBLE 'IRCMFL0.70<R<O.97

TRMEL = 1.510 x A R 0.94 SINGLE TRWEL0. 86<R<O. 98

COVER 8.62 + 0.861 x V R 0.74 ALL POURS

+ 0.202 x A O.43<R<O.89

CLEAR = 6.83 + 0.310 x V R = 0.69 OThERS• O.38(R<O.86CLEAR = 16.20 + 0.859 x V R = 0.80 POMP

O.31XR<O. 95

GENERAL = 0.1300 x C42 R = 0.895 SKIPO.77<R<O.95

GENERAL = 0.0775 x c42 R = 0.768 DIRECT AND POMP0.611<R<O. 88

When: VA

Cl2R

A<R<B

= VCLU}f= AREA= JM OF ACTIVITIES EXCLUDING GENERAL= CORRELATION COEFFICIENTWHERE A AND B ARE 95% CONFIDENCE LIMITS FOR R

104

Page 136: An evaluation of production output for in situ concrete work

CHAPTER SIl

REJLTS AND ANILYSIS OF BASIC EP4ERT TIMES

FOR CONCRETE ffJ ANT

105

Page 137: An evaluation of production output for in situ concrete work

£HAPTER Six

RESULTS AND ANALYSIS OF BASIC ELEMENT TThES

FOR CONCRETE PLANT

6.2 INTRODUCTION

The generalized concrete model (Table 5.k) can be used to

calculate basic times for the work performed by the operatives.

However, in order to obtain realistic output rates for concreting

operations, basic times f or the site transportation of concrete have

to be calculated. The site transportation of concrete can be

separated into three operations (i.e. cranage, pumping and dir'ect

pour). In this chapter the results of studies on these three

operations are presented and basic times are established.

6.2 RESULTS FOR CRANAGE OPERATIONS

Cycle times are obtained from studies carried out on seven sites

for a variety of cranage operations. The results f or mobile cranes

and tower cranes are analysed and presented separately. The work

performed by cranes during concrete operations is usually cyclic and

can be represented by the following elements:

(a) pour concrete into skip;

(b) lift full skip to the required location;

(c) pour concrete into shutters;

(d) return empty skip.

106

Page 138: An evaluation of production output for in situ concrete work

6.2.1 Basic Element Times for; Mobile Cranes

Table 6.1 contains the basic element times from sixteen studies

on mobile cranes used to pour concrete slabs, beams, walls and

col uinns.

Table 6.1 Basic Element Times for Mobile Cranes

Basic Element Times

Skip (mins) Total

Size ______ ______ ______ ______ Cycle Coents

(m3 ) Pour Lift pour Return (mins)

Into Into

Skip Skip Shutter Skip

0.38 0.3k 0.52 0.21' 0.57 1.6k Sinai]. slab

0.38 0.59 0.66 3.22 0.92 5.39 k.2m high wall

0.38 0.67 0.kO 1.10 0.113 2.60 Beam,slab,wall

0.38 0.58 0.3k 0.55 0.116 1.93 Ground beam

0.90 0.95 0.60 0.6k 0.36 2.55 Large wall

0.90 0.96 0.5k 071 0.42 2.63 Large wall

0.90 1.20 0.80 2.83' 047 5.30 Small slab

0.90 0.97 0.52 0.95' 0.50 2.9k Small slab

0.90 0.90 1.27 1.05 0.5k 3.76 Columns

0.90 1.01 0.76 1.81 0.62 11.20 Large base

0.90 1.111 1.03 1.10 0.76 11.03 Large base

0.50 0.68 0.61 0.59' 0.52 2.J10 Roof slab

0.50 0.70 0.61 0.72k0.118 2.51 Roof slab

0.50 0.8k 0.56 1.16 0.60 3.16 Wall

0.50 0.58 0.56 1.36 0.58 3.08 Wall

0.50 0.118 0.56 1.11 0.62 2.77 Wall

NOTE: • Denotes slabs

107

Page 139: An evaluation of production output for in situ concrete work

6.2.2 Basic Element Times for Tower Cranes

Table 6.2 contains the basic element times obtained from

thirteen studies on tower cranes, To simplify the work cycle, the -

total distance travelled by the skip is taken as the sum of both

vertical and horizontal distances.

Table 6.2 Basic Element Times for Tower Cranes

Skip Basic Element Times Total Times Distances

Size (miris) (mins) Travelled (m)

Pour Lift Pour Return Lift Total

Into Into

(m3) Skip Skip Shutter Skip Return Cycle }loriz. Vert. Tota

0.75 1.20 1.88 0.58' 1.78 3.66 5.111! 5.0 83.0 '176

0.8 1! 1.01 0.73 0.110* 1.( 1.79 3.26 19.6 10.0 59

0.8 1! 1.22 0.66 0.111* .0.88 1.51! 3.17 12.3 10.0 115

0.8 1! 1.02 081 0.112* 1.02 1.83 3.21 18.5 10.0 57

0.8 1! 0.92 0.118 0.52' 0.78 1.26 2.70 17.5 5.0 115

0.81! 1.08 0.61 0.85' 0.50 1.11 3.01! 13.5 5.0 37

0.81! 1 .09 0.50 0.57k 0.115 0.95 2.61 10.3 5.0 31

1.00 1.25 2.13 2.110 0.97 3.10 6.75 35.0 20.5 111

1.00 1.16 0.92 0.56' 1.11 2.03 3.75 30.0 15.5 91

1.00 1.16 0.89 0.77' 1.02 1.91 3.84 25.0 15.5 81

1.00 0.97 2.2 1! 1.51! 1.20 3.111! 5.95 110.0 23.5 121

1.00 1.03 1.117 0.1111* 1.11 2.58 11.05 36.0 15.5 103

0.50 0.85 1.69 0.56' 1.22 2.91 11.32 50.0 12.5 125

NOTE: * Denotes slabs

108

Page 140: An evaluation of production output for in situ concrete work

The basic element times presented in Table 6.1 relate to mobile

crane and are used to plot Figures 6.1, 6.2 and 6.3. The basic

element times presented in Table 6.2 relate to tower cranes and are

used to plot Figures 6.1, 6.4 and 6.5. Some of the activity timesare combined f or mobile and tower cranes; for example, "pour Into

skip" and "pour into shutters".

6.2.3 Cycle Ti.es for Mobile Cranes

(I) Pour into SkiDThe time taken to pour concrete into the skip depends upon the

skip size and can be obtained from Figure 6.1.

(U) Lift Full SkipThe time required to lift the skip also depends upon the skip

size and can be obtained from Figure 6.2.

(iii) Pour into ShuttersA large proportion of the time spent pouring concrete Into the

shutters Involves positioning the skip, consequently, the basic

element time relates to the type of pour. The average values for

several types of pour are:

Slabs = 1. mins.Others = 1.26 mins.

(iv) leturn e*ptiv skinThe average basic time taken to return the empty skip for short

distances is:

Return skip = 0.55 mine.

(v) Calculation of Cycle TinesThe above basic element times are combined and the results used

to plot Figure 6.3, from which total cycle times can be obtained.

109

Page 141: An evaluation of production output for in situ concrete work

62. Cycle Tie8 for Tower Cranea

The tower crane basic times for "pour concrete into skip" and

"pour concrete into shuttersW are combined with the values for mobile

cranes.

(1) Travel Ti.es

The travel times (full and empty) relate to the distance

travelled by the skip and are plotted on Figure 6.li. To obtain the

travel times when the crane rotates, the circular distance travelled

by the skip is used (i.e. not just the distance between the load and

discharge areas). If the total distance travelled is less than

thirty metres, the tower crane action is similar to that of a mobile

crane and the travel time for mobile cranes are used.

(ii) Calculation of Cycle Tiez

Figure 6.5 combines the basic element times for tower cranes,

taking into account the skip size and distance travelled, and can be

used to determine cycle times.

110

Page 142: An evaluation of production output for in situ concrete work

z

UiF-U

0z00Df)Oz

ZcLLiJ

F-

U

F-

UiNI

cc)

0

I-I-

FlCo

w

'0

0

0

N0

co:ido

LiM

da.(n

0

d

0

I-

d

0

.x •x•x

.t.+..+.-.

X : .

.

+f

CI') 'LiJz Z

-o,--oo

cTwoO

—J

I- C *

ci 01 I- 0 0 0

08U!W 3V1IJ iflOd

Page 143: An evaluation of production output for in situ concrete work

N (0 * Nd d d

GU!W 3VNLL ONIUI1.

C4

(0

w

'0Li..

0)0

U:?0

0

E

LJN

ncf,c0

c/-i

0

d

0

0

0

z

jJ-a3

PwZ5

<2H11)

U

Hz

Page 144: An evaluation of production output for in situ concrete work

wN(1)

0/LiJz

F-ct

404

w

F-

U

U-Jm0

2

I-.

I',

U

'0Li..

N0

Edo

uJNi

da.

(1)

0

F')d

ci0

1•

d

0

\N

.\.\!:

2•

1 1 •1•\4.\4.\

• a

0

• 000

Ifl r') in c.1

r)

•SUW 31'NLL 313A

Page 145: An evaluation of production output for in situ concrete work

0

(0w

co b-

U0z

Z-'V)<OLJ

icJI—LLJ

0—<I--LLO-Jo

z LiLi<Li

lJLLJck:

I—Li

• .

+

+

• . .

OILJJm

_J • .-

0

U')>-

a°LJ

IJ

F-0

0

0

0

0LA 'A LA if) If)

ci d

su'ui 3ILL 13AVL

Page 146: An evaluation of production output for in situ concrete work

0

It)

Ij.I

0LI-

0

-J-JLiJ

F-

uJ0z

C/)0

-J

F-

F-1/)z

404

Id

F-

Id

E

00

000

0CD

0

If)>-

0Li-J

Li

I-Li0

0CJ

0(0

'$ . !.

VL\N I\. \:\N• L •\\ •

S :': \

z

''

(_)

Li.J :\\

F- •:

21

\\\\

1 1 '\I:

<F—

I0

CD it, U)

it, U CJ

IC;

c.1

SU!UJ JVNII 310A3

0

0c.4

Page 147: An evaluation of production output for in situ concrete work

6.2.5 P].anning Rates for Cranae Operations

Output rates for most cranage operations can be calculated fromthe following cçuation, where cycle time is obtained from the

appropriate figure.

Output rate for crane Skip Size x 60 (m3/hr)

Basic Cycle Time

The main external delays to the overall operation are caused by

the non-arrival of concrete. On the sites studied the ready mixed

concrete lorries were found to be on average seven minutes late,

owing to a variety of reasons. It is not always suitable to apply

this delay as a site factor, or percentage, as the applied value

depends on the basic cycle time. The delays per skip cycle caused by

the non-arrival of concrete can be expressed as shown below.

Cycle delay = Average Delay x Skip SizeLorry Size

116

Page 148: An evaluation of production output for in situ concrete work

Consider the following two examples, where the average delay per

lorry load is seven minutes.

(a) A tower crane with a half cubic metre skip and anaverage cycle time of five minutes would have abasic output rate of six cubic metres per hour

(from Figure 6.5). If the capacity of the concrete

lorry was five cubic metres the delay to each cyclewould be:

cycle delay = 7 x 0.5 = 0.7 inins.5

percentage delay = 0.7x 100 = 11%

5

(a) A mobile crane with a 0.90 cubic metre skip wouldhave an average cycle time of 3.1 minutes and a

basic output rate of 17.k cubic metres per hour

(from Figure 6.3.). If the capacity of the

concrete lorry was five cubic metres, the delay toeach cycle would be:

cycle delay = 7 x 0.9 = 1.26 xnins.

5percentage delay 1.26 x 100 = 141%

- 3.1

These two examples illustrate that f or the same average lorry

delay the percentage delay can vary considerably f or different

operations. However, in practice the average lorry delays can becontrolled by management, thus reducing the very high percentage

delays. The planning rate for cranes should include site factors F3and F14 in addition to the waiting time caused by arr delays and canbe expressed as shown below.

Planning rate = Skip Size x 60 x 1 (m3/hr)

for cranes (Basic Cycle Time + Waiting) (F3 x F14)

117

Page 149: An evaluation of production output for in situ concrete work

6.3 RESULTS FOR PUMPING OPERATIONS

6.3.1 Actual Times for Pumping ActivitiesThe results presented in Table 6.3 were collected from several.

sites, using cumulative timing techniques. In all of the studies the

maximum concrete slump was 75 mm. The actual pumping times are per

lorry load and involve the following activities:

(a) pumping concrete;

(b) waiting for lorries to change around;

(a) waiting for lorries to arrive;

Cd) pump moving position; -

(e) waiting for men to perform the last operation.

6.3.2 Pumning and Outout RatesIn all operations the pumping distances are well within the

capabilities of the pump. The main cause of variation in the timespent actually pumping concrete is the pipe diameter, with distance

having little effect. Thus, the results in Table 6.11 are presentedseparately for 1 50mm. and 100mm. diameter pipes, and give values f orthe following activities.

(1) Pumoing RatesThe pumping times in Table 6.11 represent the pump capabilities

and are determined by taking the weighted mean pumping times fromTable 6.3.

(ii) Pump. Change and Move Rates -These rates include the time to: pump the concrete; change the

lorries around; and move the pump when necessary. If an operation iswell organized, as in the first three studies, 1.93 minutes are

required to change the lorries around, and 0.07 minutes per cubic

metre are required to move the concrete pump. Consequently, the mean

pumping rates, inclusive of' 'change' and 'move' activities, arecalculated and presented in Table 6.11.

(iii) Outout RatesThe minimum, maximum and mean output rates are calculated

from the total times presented in Table 6.3.

118

Page 150: An evaluation of production output for in situ concrete work

+3

•• 0 H

4) Nm .,-i • 0 in in c'.j 0 in in in in 0

.,-i H '- - in - c'j .- . -

0000000000000000cj000

• P m0000-0000-0000'.o0c'J0

4) -..(fl0i00in004 oOczOO

0 0 - -. '.o C'.J C in1

4 t P 000-.00000

aU,

(flcV)CflO000U, ________ _________________________

14 0. P3 IflO..00OOC'.J

0 0 '. 0 '.0 '. 00' -0'I- % •- •-

P3 JC'.JC'.JC'.J(43 •o r

14 C'.J(Y)

U,•.000ZO C\J '-

-3

L qi • '.0 '0 '.0 '.0 • '.0 '.0 '0 '.0 '.0o0 in,-3-3 C)

• • 0000000000• inOoIn000000I --

'- c'.j i-n .- in '.o i- a 04.)

0

UI

o-i-I 04)-'-4U, 0.Øo 04-s

. 0. ØV

bØ'r4 C)

,-4-.-•I 04-) 0>, 0. -4 (I) C)

C)

o 0..z 0 £ 0i-4 .)04-i

0

0 0 4 -i-4

L.43 OId >-400 00004-40 aC) 4.) -4 4.) 4.) 4) q-1H 5.

s. •4) 0. 0 0. 0. 0. .,

0) 03 0)0

C) C) 4)0)4)430000000-4.-1r1-r$

E-IE-4 140

II II II II II II II

C)0

•'-Iid0.4)W 4343 0 0 .rl U)0 00 09-I

U,4)0z

Page 151: An evaluation of production output for in situ concrete work

6.3.3 Planning Rates

Most of the observed pumping operations involved concrete

volumes between 2k and 5k cubic metres. The values presented inTable 6.3 show that. these quantities can easily be pumped within two

hours. Thus, actual output rates are often limited by the performance

of the concrete gang rather than the pump. On larger pours kOm3/hr

can be used as a planning rate, but allowances for starting up thework and cleaning the pump should be taken into account.

- Table 6 . Pumping aM Output Rates (m3/hrl

Rates (m3/br) 15 diameter 1O diameter

pipes pipes

Pumping Rate 52.5 38.2

Pump, Change and Move Rate 37.9 29.8

Minimum Output Rate 25.5 11.1Maximum Output Rate 35.3 25.9

Mean Output Rate 3O.1 17.1

120

Page 152: An evaluation of production output for in situ concrete work

6.11 RESULTS FOR DIRECT POUR OPERATIONS

6.11.1 Introduction

Large quantities of concrete can be poured directly from ready-mix lorries in a relatively short period of time, consequently the

operatives' rate of placement is usually the controlling factor.However, direct placement of concrete is not normally used f or

columns or walls.

6.11.2 Planning Rates

Planning rates for pouring concrete directly from ready-mix

lorries should be determined from the basic operation times for theconcrete gang. However, on some sites it may be necessary for thelorries to transport the concrete over considerable distances,

therefore, the resulting basic time for the concrete gang should be

compared with the basic time for the lorries. Concrete was poureddirectly from lorries in twelve of the pours presented in Table 5.2.The following basic elements have been extrapolated from these pours

and can be used to calculate basic operatidn times for lorries.

(a) The basic time required to discharge one load ofsix cubic metres into a slab or base is seven

minutes.

(b) The basic time required to discharge one load ofsix cubic metres into a beam is eighteen minutes.

(c) The basic time required to manoeuvre between

discharge points, in the same locality, is two

minutes.

(d) The basic time required to prepare for the firstload and clean down afterwards is five minutes.

121

Page 153: An evaluation of production output for in situ concrete work

18 cu. m.

10 sq. in.

Direct pour

3 men

6

21 nuns.

12 mins.

- 5 mins.

38 mins.

6. JI.3 Calculation of PlaziningRates for Direct Pours

The following example calculates the planning rate for pouring

an in situ concrete beam using the direct pour method. The basic

times for the concrete gang are obtained from Appendix C, and the

basic times for the lorries are obtained from the previous page.

(1) ODeration Information

Volume of concrete

Area of concrete

Method

Gang size

Number of lorry manoeuvres

(ii) Basio Times for Concrete Gang

Basic Operation Time

(Table C6 in Appendix C)

Duration 305/3

= 305 man mins.

= 102 mins.

(iii) Basic Time for Lorry

Discharge concrete

Manoeuvre lorry.

Prepare/cl ean down

Total Basic Time

(18 x 7)/6

2x6

The above calculation shows that the time spent pouring the beam

by the concrete gang is larger than the time spent on site by the

ready-mix lorry. The planning time is determined by applying a site

factor (see Chapter Eight) to the concrete gang's duration.

i.e. Planning Time = 102 x Site Factor

122

Page 154: An evaluation of production output for in situ concrete work

CHAPTER 8EY

CALCULATING STANDARD TII4ES

123

Page 155: An evaluation of production output for in situ concrete work

CHAPTER SEVEN

CALCULATING STANDARD TI)IES

7.1 INTRODUCTION

To establish a library of standard times based on work studytechniques, it is necessary to predetermine what allowances should be

applied to the basic element times. The most common of these is therelaxation allowance, but, there is a gross disparity in the values

being awarded by different firms f or the same relaxation factor

(7.1). Generally, the origins of relaxation allowances for

construction work are unknown and the values used are sometimes simply

borrowed from similar manufacturing situations. Such ambiguityclearly highlights not only the need f' or the standardization of restallowances, but also f or an in depth review of the theoretical

validation behind them. For example, the relaxation allowances f or

construction work, as recommended by Harris and McCaff'er (7.2),presented in Figure 7.1, are typical but as yet unproven values.

This chapter reviews traditional methods of calculating

relaxation allowances and investigates the ambiguities which arise

when the results are applied to construction operations. A systemmore appropriate to construction operations is developed and

summarized in Figure 7.15. This system is based on several ergonomictheories; these are discussed and developed further with constructionoperations in mind.

12k

Page 156: An evaluation of production output for in situ concrete work

ii lII

11o II

t4.,

It) ' I

— O i-

4)4) ouMI

4)

Ie('4bI 4)

.'. I •.-iI4.) I WI

I•r4)) WIU)r-lI 01

-

C0

>1 .i-I

4).

I

I-I

CM

• 0 0I-I r.I

4)4)

•i-I 4)

4)0,- 4.) 4)

I)4J

I-)U

U)4)

I

.1—I

0

U) <IWI

If) I44)

.i .4

HI I._)b

U)

O MIt)

TIN

—p.) 0,

4)•1.)

(PI

.

• o

It) 4)0

CM

In.i-I CN• 0 C

4.) 4.) (0U) N l

1•

• 0 0

4)0 114.)C r1 4) 4)

•00 Z 0

) 4)

U .) U) 04.)

U.1•rIo o

.IZ U4J

r CN

U)C

C •rIr) 4.)

Page 157: An evaluation of production output for in situ concrete work

The later discussion of site factors presented in Chapter Nine

shows that the motivation of construction operatives often producesidle periods exceeding the required relaxation period. However,relaxation allowances are still a very important aspect of

construction planning as they indicate optimal levels of performance.

7.2 TRADITIONAL CALCULATION OF RELAXATION ALLOWANCES

Relaxation allowances are normally applied individually to the

basic time of each work element; the resulting standard element timesare combined and standard times for the complete operations are

obtained. Most relaxation allowances fall into the categories of

either 'fixed allowances' or 'variable allowances'.

7.2.1 Fixed AllowaneeB

Fixed allowances take into account the operatives "personal

needs" and "basic fatigue", and are considered a minimum requirement.The personal needs allowance is applied to every task and enables the

worker to attend to activities such as washing or obtaining a drink;

a typical value is six per cent of the basic time. The basic fatigueallowance is the minimum value required to accommodate moderateexpenditure and to alleviate monotorr; a typical value is four per

cent f or a worker who is seated and engaged on light work with normal

movements in good working conditions. - The majority of tasks in the

construction industry are usually allocated a fixed allowance of ten

per cent of basic time, with only a few requiring more than seventeen

per cent.

7.2.2 Yariable Allowances

Very often fixed allowances, alone, are not sufficient to

protect the long and short term health of the worker. This problem

is overcome by supplementing the fixed allowance with a "variableallowance", corn pri sing: "additional fatigue allowances" whereadditional inputs of physical or mental work arise; and

126

Page 158: An evaluation of production output for in situ concrete work

"environmental allowances" to account for azr adverse working

conditions. Additional fatigue allowances are applied on anelemental basis, whereas, environmental allowances are usually

applied on a daily basis.

A traditional method of calculating standard times for a typical

concreting operation is presented in Table 7.1. The relaxation

allowances applied in this example are based on values recommended by

LAMSAC (73). The total relaxation allowance comprises factors for

the following.

a) Basic Allowance.

b) Standing or Sitting Allowance.

e) Posture and Movnent.

d) Energy Output.

Table 7.1 Calculation of Standard Ti.es

Basic Relaxation Allowance (%) Standard

Time a b c d Total Time

(miris) (mins)

L EMEN TS

General Work 25 10 2 0 1 13 28.2

Prepare Tools 110 10 2 0 1 13 115.2

Clear Tools Away 20 10 2 0 1 13 22.6

Pour Concrete 25 10 2 0 1 13 28.3

Vibrate Concrete 115 10 2 0 11 16 133.3

Shovel Concrete 123 10 2 2 6 20 1117.6

Tamp Concrete 69 10 2 3 Ii 19 82.1

Trowel Concrete 97 10 2 is 11 20 176.11

Cover Concrete 98 10 2 0 1 13 110.7

TOTAL 662 17 7711.11

12T

Page 159: An evaluation of production output for in situ concrete work

When traditional systems for determining relaxation allowances

are compared with classic ergonomic theories several inconsistenciesoccur. These inconsistancies can result from either the method used

to build up relaxation allowances or their subsequent application.

Most discrepancies resulting from the build up of relaxationallowances arise because the calculations are performed on an

elemental basis. For example: the personal needs factor represents

a minimum period of time and, therefore, should not be applied to

individual elements but to complete operations; no account is takenof the opportunity to recover during waiting periods or whilst

performing elements requiring little effort; the effort factor does

not take into account which part of the body is being used or thenumber of times an operation is perfromed; and allowances are

sometimes made f or factors having no affect on overall fatigue.

The majority of manufacturing operations involve elements of'

work requiring uniform levels of effort with very few interruptions,and as a result these discrepancies have little or no affect. In

contrast, construction operations often involve work elementsrequiring considerably different levels of effort with regular

interruptions; consequently, the discrepancies cannot be ignored. It

is for this reason that a detailed investigation is performed toestablish a more theoretical valid system for determiningconstruction relaxation allowances.

128

Page 160: An evaluation of production output for in situ concrete work

7.3 A STSTEM FOR DETERNINING CONSTRUCTION RELAXATION ALLOWANCES

At this stage it is important to emphasize that relaxation

allowances are applied to ensure that the worker has time to attendto personal needs, whilst ensuring ability to recover from the

metabolic, mental and postural cost of the work. The previouslydiscussed discrepancies arise because these two types of allowances

are combined on an elemental basis. For this reason "basicallowances" are now treated as a minimum level of relaxation; with

"health and safety" allowances accounting for mental cost,environmental cost, metabolic cost and local muscle fatigue, as

summarized below.

(1) Mental Cost (concentration or boredom)Some tasks require minimal muscular activity or energy

expenditure but can still cause some fatigue; for example, mentaltiredness. The construction operations under consideration are

predominantly physical, therefore, a detailed investigation intorelaxation allowances f or mental fatigue is not required.

(ii) Environmental CostEnvironmental allowances are used to allow for abnormal working

conditions resulting from the affect of weather, dust, fumes or

noises. Basic allowances are often increased to accommodate anyadverse environmental conditions.

(ill) Metabolic CostLarge loads applied to the body as a whole over a period of time

cause a debit from the metabolic store, and relaxation periods are

required to replenish it.

(iv) Local Muscle FatigueLocal muscle fatigue occurs with little metabolic cost when

either poor postures are adopted, or small loads are consistentlyapplied to the same group of muscles. Local muscle fatigue can beeither static or dynamic depending upon the frequency of' loading.

129

Page 161: An evaluation of production output for in situ concrete work

7. RaAXATION ALLOWANCES FOR T METABOLIc COST OF WO

When loads are applied to the body as a whole, it is possible to

determine the metabolic cost in terms of enerr output by measuring

the oxygen consumption over a period of time (7.). previousresearch (7.5) has shown that over an eight hour working day an

acceptable work level is approximately equivalent to a third of the

maximum oxygen intake rate cvo2 per hour). The variation inrecommended values arises because it is not actual fatigue that can

be measured, but the sensation of' fatigue which depends upon thelevel of drive or motivation present.

Research by Astrand (7.6) indicated that the maximum oxygen

intake ranged between 2.29 and 3.17 litres per minute (i.e. on

average 2.73 litres per minute) for a variety of' building operatives.One litre of oxygen consumed per minute is equivalent to 350 watts,

therefore, the acceptable work level over an eight hour day is

approximately 300 watts (0.333 x 350 x 2.73). The bench marks for

various types of activities presented in Table 7.2 have been

established (7.7) by the direct measurement of oxygen intake whilstperforming each activity.

Table 7.2 Work Rate Bench Marks

Activity

Acceptable Work Level (A.W.L.)Relaxation Rate standing (LR.)Relaxation Rate sitting (R.R.)

Dangerous Work Rate (D.W.R.)

Watts

300

130105750

130

Page 162: An evaluation of production output for in situ concrete work

7 . .1 Calculation. of Actual Work Rate in Ter.z of Energy Exnenditure

In order to calculate relaxation allowances for metabolic tasks,

it is necessary to compare the actual energy used with the acceptable

work leveL This can be doi by: direct measurement of the volume of

oxygen consumed; adopting existing bench marks; or using existing

models. Existing energy bench marks should be adopted wherever

possible. However, when these are not available one of the following

models could be used. The direct measurement of oxygen consumed

during a specific task is difficult to achieve and, therefore, should

only be used in special circumstances. -

(i) The Aberg Model

The Aberg Model (7.8) takes the form of

(vo2 ) consumed Basic Metabolism (Ki)

+ Posture (K2)

+ Body Motion (K3+Klt)

+ Load Motion (K5+K5+K7+K8)

Table 7 . Factors for the Aberg Model

Factor Power Activity

xl 85 watts Basic metabolism

K2 29 watts Sitting For a

3 watts Standing j body

56 watts Standing bent mass of

K3 205 watts/(m/sec) Walking 70 kg.

Ku 790 watts/(xn/sec) Bend + rise

K5 65 watts/kg/(m/seo) Horizontal arm work

K6 3 watts/kg/Cm/see) Horizontal carrying

K7 119 watts/kg/(m/sec) Lift up

K8 82 watts/kg/(ni/sec) Lift down

131

Page 163: An evaluation of production output for in situ concrete work

The Aberg Model was originally presented as a general formula in

Imperial Units. This general formula has been converted into S.L

units, and separated into the body and load motions associated with

construction operations. The converted results are presented in

Table 7.3 and 7.k, and used to plot Figures 7.2 and 7.3. The power

expended when the body is stationary with no loads applied is equal

to Ki plus K2: power expended whilst standing is 119 watts (i.e. 85

+ 314): power expended whilst sitting is 11 14 watts (i.e. 85 + 29).

Table 7 . Converted -lberg Formula

(a) Carry an object

P = 119 + L(205+3W)

(b) Lift an object stationary body seated

P=11k+I19WL LiftUp

= 1114 + 82WL Lift Down

= 1114 + 65WL Lift Horizontal

(a) Lift object and body

P = 119 + L(790+119W) Lift Up

P = 119 + L(790+82W) Lift Down

(d) Body motion and light loads

Determine power by using the above

equations but with W=O.

Where:

P represents power in watts.

L represents velocity in metres per second.

W represents weight in kilograms.

132

Page 164: An evaluation of production output for in situ concrete work

Power relating to both basic metabolic rate (i.e. Ki) arid body

motion (i.e. K2 to Kk) can be obtained from Figure 7.2. For example,

the power consumed whilst walking at O.k metres per second is

approximately 170 watts, as illustrated by the chain-line on Figure

7.2.

Power relating to load motion (ie. K5 to K8) can be obtained

from Figure 7.3, reading in an anti-clockwise direction. For

example, the power required to lift a 50kg weight at a speed of one

metre per second is 5.95 kilowatts, as illustrated by the chain line

on Figure 7.3. To determine the total metabolic cost (or total

power) the values obtained from Figures 7.2 and 7.3 should be

combined. The right-hand side of Figure 7.3 was drawn for lifting

objects upwards, with power obtained from the Y-axis. The left-handside of Figure 7.3 can be used to determine the power consumed whilstlowering objects or moving them horizontally.

133 -

Page 165: An evaluation of production output for in situ concrete work

>-F-09Li

F-V)z

0

z0b

0

I-

NU

0cnU0

a,0

0-o00

cD4cD

I-a)a

onz•s.

cnu

0

CsJ0

U.

0

0<LiO—Li>Qr

>-

d09Lu>

Li

00

-J

z

A0I

0uJ

c•o :

• .4.Z :

o___z

• 1 . IH•

•.... 0:-J

0 0 0 0 0 o b0 0 0

S4OM eJ3MOd

Page 166: An evaluation of production output for in situ concrete work

0

Li

2<>-F-0

9Li>F-U)z

0

Ui

0cL

0U-

zUi

Ui0

0If)CD

Li

(:3L&

Cs4

In

-0

i

>-0

LU>

Lfl

0

D

ftLU

02o

Page 167: An evaluation of production output for in situ concrete work

(ii) The Suitzer aM. Rettinger Model

The Spitzer and Hettinger model (79) comprises three sections

and takes the form of the following equation. The 76.7 watts is an

allowance for basic metabolism. Factors "A" and "B" represent the

power elements relating to body posture and type of activity, and are

obtained from Tables 7.5 and 7.6, respectively.

Total Power = (A + B + 76.7) watts.

Table 7.5 Power Relating to Body Posture (A)

Body Posture Power (Watts)

Sitting 21

Kneeling 36

Squatting 36

Standing 112

Bent over 55

Walking 118 to 21111

Climbing unlaiden 52 per metre rise

Table 7.6 Power Relating to Type of Activity (Bi

Power (Watts)

Activity Grade of activity

Light Mediun Heavy

Hand work 21-42 I2-63 63811

One arm work 119-814 8't.-118 118-153

Both arts work 105-1tO 11101711 17112O9

Body work 1711-279 279 1118 1118_592

592-8 01

Very heavy

136

Page 168: An evaluation of production output for in situ concrete work

(iii) The Pandolf ModelGivord. and Goldman (7.10) developed an empirical relationship for

energy expenditure prediction as a function of speed, external load,

body weight, grade and terrain. This relationship was limited tospeeds ranging from 0.7 to 2.5 metres per second. However, Pandoif' et

a]. (7.11) subsequently developed the following relationship for wider

application.

M 1.5W + 2.0(W+L)(L/W)2 + n(W+L)(15V2 + 0.35VG)

Where: - M = metabolic rate, watts.

W subject weight, kg.L external load, kg.

= terrain factor (1 for treadmill).V = velocity rn/sec.

G = slope.

The above expression can be simplified by considering a standard

worker of 70kg, and assuming that positive and negative gradients

cancel each other out. Two of the variables are, thus, elimirated

and the following equation obtaird.

M = 1.5x70 + 2.0(70i. L)(L/70) 2 + n(70+L)(1.5V2 + 0)

M = 105 + 2 . 0(70+L)(L/70) 2 + n(70+L)1.5V2

The Aberg, Spitzer and Hettinger, and Pandoif models can all be

use to determir the metabolic work rate associated with various

tasks. However, the model selected often depends upon the type of

operation and the information available. The Aberg model is bestsuited to singLe activities wnere detailed information relating to

the applied load and velocity of' movement are available. The Spitzerand Hettinger model is best suited to operations where the tasks can

be classified as light, medium or heavy work. The Pandoif' model isonly suited to operations involving the horizontal transportation ofloads.

137

Page 169: An evaluation of production output for in situ concrete work

7..2 Derivation of Re1ax ptjonFprmu1pe for Metabo1icCot

The methods discussed previously can be used to determine the

metabolic cost of individual work elements. Construction operations,

however, usually involve several activities with varying work loads.

To calculate relaxation allowances for these operations, it is

necessary to combine the metabolic cost of the individual elements

over a minimum period of say thirty minutes. The resulting mean work

rate (M.W.R.) is subsequently equated to the acceptable work load

level (LW.L.), and the appropriate relaxation allowance obtained.

To simplify the procedure of calculating relaxation allowances,

Equations 7.1 and 7.2 can be adopted. These equations are derived by

equating the energy expenditure during both the working and

relaxation periods to the acceptable work level (Table 7.2). The

resulting equations are used to plot Figure 7.1k (Wt = working time,

Rt = relaxation time).

Work + Relaxation = Acceptable Work Level

(14. W. R.)Wt + (R.R.)Rt = (A.W.L.)(Wt+Rt)

(M.W.R.)Wt + (R.R.)Rt

300(Wt+Rt)

But Relaxation Allowance (R.A.) = Rt/Wt (xl00%)Thus Rt = Wt(R.A.)

Substituting f or Rt

(M.W.R.)Wt

-3 00 C R. A.)

+ (R.R.)Wt(R.A.)

+ (R.R)(R.A.)

R. A.

300( Wt + Wt(R.A.) )

300 - M.W.R.

(M.W.R.) - 300x 100%

300 -. (R.R)

The relaxation rate (R.R.) is obtained from existing benchmarks,

using Table 7.2, and substituted into the above equation, hence:

Seated Relaxation .. R.A. 0.513(M.W.R.) - 15k Equation 7.1

R.R. = 105 )

Standing Relaxation .. R.A. = 0.588(M.W.R.) - 176 Equation 7.2

C RR. 130 )

138

Page 170: An evaluation of production output for in situ concrete work

0N I

L4J

(:1

Li

0ILlCD

00(0

0-I-a

In-I—,a

uJ

Q10

0

z

oLd

00

0In1')

0

0-J0

w

2'I,U0z

9-J

z0

x-JU

00

00 0 0 0 0'1) 0 it) 0 U)c'J c'1

°4 3ONVMOTIV NOIIVXV13èI

Page 171: An evaluation of production output for in situ concrete work

7. k .3 Relaxation Allowance Calculation for Metabolic Work

The following example calculates relaxation allowances for

an operation involving metabolic work. The operation under

consideration involves six activities each having different durations

and work rates, as summarized in Table 7.7.

Table 7.7 Activity Durationz and Output Ratea

ACTIVITY DURATION WORK ENERGY

B. T. RATE EXPENDI[1JRE

(mins) (watts) (joules)

1 20 350 7000

2 30 1150 13500

3 10 500 5000

11 30 150 11500

5 5 200 1000

6 110 1100 16000

TOTAL 135 --- 117000

The relaxation allowance for the above operation is determined

by calculating the mean work rate, and substituting the obtained

value into Equation 7.2, as shown below.

MEAN WORK RATE

. . 14. W. R.

Standing Relaxation R.A.

R.A.

BASIC TINE

STANDARD TI!€

TOTAL ENERGY EXPENDITURE

TOTAL DURATION

= 117000 = 3118 watts

135

0.588 (M.W.E.) - 176 Equation 7.2

28.6%

= T.B.T. 135 mina.

= 135 x 1.286 174 nuns.

1110

Page 172: An evaluation of production output for in situ concrete work

7.11.11 The Effect of Idle Time on Metabolic Cost

In the previous example a relaxation allowance is calculated fora typical operation. Depending upon the level of efficiency this

operation may be subjected to delays of varying duration. During

these periods some recovery can take place, thus, reducing the

additional period required f or relaxation. Rather than repeat the

calculations for every combination of work and idle time, it ispossible to calculate the reduced relaxation allowance from a

generalized equation.

The generalized relaxation equation is derived by calculatingthe mean work rate inclusive of delays (M.W.R.), and substituting the

obtained value into Equation 7.2. The mean work rate is calculated

by combining the non-delay work rate (LB.) with the recovery rate

(R.R. is equal to 130 watts when standing). If "a" represents thepercentage of overall time spent working, the mean work rate can be

obtained from the following equation.

Mean work rate (M.W. B.) = (W.R.)a + 130(1 00-a) watts100

Standing Relaxation R.A. 0.588( M.W.R. ) - 176 ...Equation 7.2

Substituting for (M.W.R.)

R.A. = 0.588( (W.R.)a + 130(100-a) ) - 176

100

Figure 7.5 was plotted from the above equation and can be used

to determine the required relaxation allowance, if work rate and

percentage of time spent working are known. The relaxation allowanceshould be applied to both working and idle times, as shown below.

BASIC TIME (B. T.) = W0RKI TIME + IDLE TIME

STANDARD TIME (S. T.) = ( B. T. ) x (100 + R. A. )100

1I1

Page 173: An evaluation of production output for in situ concrete work

0 0 0 0 0 00 0 0 0 014) t') C'1

°4 33NVMOT1V NOLLVXV1JeJ

2LiH-

z

Lii

LiiLJ

<(I)LiiF-

(I)—ZI—

<LU00

UJzOLUzo

:i(f)

<0

Zck0<

x

—JLi

I olz

111N1

IE ri ii i] 11 r;i ri ri ii 'WII3I ii 1J LJ Li 1i 1i Li i olIa lIo101

00

U,0-4-'0

0z

000N-

zLdI

Lii

0z

DD

))

Page 174: An evaluation of production output for in situ concrete work

7..5 The Effect of Combined Work Loads

Most construction operations include both work and idle periods

resulting from a combination of individual tasks. In order todetermine the appropriate relaxation allowance for complete

operations, it is necessary to combine the partial relaxation

allowances for the individual tasks. This procedure is illustrated

for an operation with the following constituent parts.

(a) In the first task "a" per cent of the basic time(B.T.1) is spent working at a rate of A watts,

resulting in a required partial relaxationallowance of per cent, obtained from either

Figure 7.11 or Equation 7.2.

(b) In the second task "b" per cent of the basic time(B.T.2) is spent working at a rate of B watts,

resulting in a required partial relaxation

allowance of ftyft per cent, obtained from either

Figure 7.11 or Equation 7.2.

Cc) In the third task "o" per cent of the basic timeGB.T.3) is spent working at a rate of C watts,

resulting in a required partial relaxationallowance of per cent, obtained from either

Figure 7.11 or Equation 7.2.

TOTAL BASIC TIME C B.T.1 + B.T.2 +,B.T.3 )

TOTAL RELAXATION TIME = x(B.T.1) + y(B.T.2) + z(B.T.3)

TOTAL RELAXATION ALLCMANCE: TOTAL RELAXATION TIMETOTAL BASIC TIME

T.R.A. x(B.T.1) + y(B.T.2) + z(B.T.3)

( B.T.1 + B.T.2 + B.T.3 )... Fquation 7.3

I 13

Page 175: An evaluation of production output for in situ concrete work

7 .J$ .6 Relaxation Allowance Calculation for Conibined Taska

The following exanple illustrates how the relationship expressed

in Equation 7.3 can be used to calculate the relaxation allowance for

an operation comprising the three tasks sunmarized in Table 7.8.

iable 7.8 Information Relating to Total Operation

Task Duration Work Rate % Time spent Partial R. A.

mins watts working standing Figure 7 .5

1 20 600 80 20 122%

2 kO 525 70 30 63%

3 30 365 100 0 39%

T.R.A.

. T. R. A. =

x(B.T.1) + y(B.T.2) + z(B.T.3)

( B.T.1 + B.T.2 + B.T.3 )

Equation 7.3

122(20) + 63(kO) + 39(30)

( 20 + 110 + 30 )

68%

BASIC TIME

T.B.T. = 90 minutes

STANDARD TIME

90 x 1.68 = 151 minutes

11111

Page 176: An evaluation of production output for in situ concrete work

800

C,,IDz00

400

zw1•-C,z

200-J0

>(

0

7.5 RELAXATION ALLOWANCES FOR LOCAL WSCLE FATIGUE

Local muscle fatigue usually occurs at low levels of ener

output where loads are applied to a localized group of muscles.Local muscle fatigue can be either static. or dynamic, depending upon

the frequency of' loading.

7.5.1 £tatle Muscle Fatigue

Rohmert (7.12) established an empirical relationship betweenapplied static force, expressed as a percentage of maximum force, and

maximum holding time. This relationship is represented by Equation

7.1 and illustrated in Figure 7.6. Rot1mert also showed that up to

fifteen per cent of' the maximum force could be held indefinitely, andthat the maximum force could not be held for more than six seconds.

Tniax 126 - 36 + 6 - 90 ... Equation 7.1

p p2 p3

where: Tmax = Maximum Holding Time (seconds)p = Applied Force / Maximum Force

0.2 0.4 0.6 0.8 1

FRACTION OF MAXIMUM FORCE p=f/fmax

FIgure 7.6 Rohmert's Cury

S 145

Page 177: An evaluation of production output for in situ concrete work

Rohmert went on to produce a solution for calculating the

relaxation allowance required to compensate for local muscle fatigue,

given the holding time and the percentage of the maximum force

developed. The relationships between recovery time, loading time,

maximum holding time, applied force and maximum force are presented

in Equation 7.5 and illustrated by Figure 7.7.

Tree = 18( T )1•(P-O.15)°5 Equation 7.5

T Tmax

where: P = Applied Force/Maximum Force

Tmax = Max holding time (m.iris.)

Tree = Recovery time (mins.)

T = Loading time (mins.)

116

Page 178: An evaluation of production output for in situ concrete work

10

2

0

.5

4J

C

E

U

P

0z

O-J04I

PERCENTAGE RELAXATiON ALLOWANCES FORVARIOUS COMBINA11ONS OF

HOLDING FORCES AND HOLDING TIMES

0 20 40 60 80 100

FORCE DEVELOPED, percentage of maximum force

[GURE 7.7J

Page 179: An evaluation of production output for in situ concrete work

7.5.2 Relaxation Allowance Calculation for Local Muscle Fatigue

If a force with a maximum holding time (Tmax) of three minutes

is applied f or one minute (T), the appropriate relaxation allowance

(R.A.) is obtained from Figures 7.6 and 7.7, as shown below.

T = 1 mm = 60 sees.

Tmax = 3 mm = 180 sees.P = 30% From Figure 7.6

R.A. = 200% From Figure 7.7

In some construction operations a rest period is automatically

available after a load has been encountered. If this rest period is

less than the required relaxation period, the maximum strength is

subsequently reduced. Thus, the above method of calculating

relaxation allowances is an over-estimate because it is not necessary

to fully return to the maximum starting strength before resuming

work.

Figure 7.8 illustrates the relationships between fatigue,recovery and time. If the full recovery period is not taken, there

will be a residual degree of fatigue when work is restarted. The

affect of' several short "work-recovery" cycles is similar to that of

dynamic muscle fatigue, and the relaxation allowance calculations are

even more complex.

CUMULATIVE TIME

Figure 7.8 Degree of Local Muscle Fatimie

1 l8

Page 180: An evaluation of production output for in situ concrete work

7.5.3 Relaxation Allowances for. Static Loads

Corlett (7.13) investigated the relationships between holdingtime in minutes and the percentage of maximum force being applied,for both static pull and static torque experienced during normal

postures. The equations Corlett produced as 'best fit' lines for hisexperimental data are presented below.

Logey = 3.32 - 0.Ol2x for static pull

Log5y = 2.52 - 0.0l3x for static torquex=%of maximal force

y = holding time (mins.)

The above equations, Corlett's experimental results and thetheoretical relationships as developed by Honed and Rohrnert are all

plotted in Figure 7.9. The following conclusions are drawn from acomparison of these theoretical and experimental results.

(a) Corlett's experimental results for static torquesare closer to Rohmert's equation than those

produced by the above equations.

(b) Corlett states that the results are "by no means

asymptotic to the Y axis, even at 10% of the

force". However, this probably arises becauseinsufficient data were obtained, for example, only

one point is plotted for loads less than 15% ofthe maximum. Also, no correction is taken for the

affect of body weight.

(c) Corlett's experimental results show a distinct

difference between static torque and static pull.This suggests that the relationship between time

and load is dependent on the type of muscleloading, although Rohmert states that this is not

so. Using Corlett's experimental results, the

relaxation allowances obtained from Figure 7.7

vary considerably for different muscle groups, asillustrated by the following example.

1 1$9

Page 181: An evaluation of production output for in situ concrete work

0)r-Z

IJ-

________ -I 0I 0)

I) : Io

.:

ill , 0.Jt...L,'.L.o1'-

:,iI:' ill

: i:T'J"

/ III Li...

11/0

Z2Li_.- : ._-. : r 00 _________ - __..__..-i

I.

___ ) _/_______ - - - - /

d' . X . /. 0

• 1•0

. /

/

•00 0 0 0 00 0 0 00 U, 0c1 I--

XD W± 'sallo33s NI 31111 ONICflOH 11flV4IXV11

0LU-V)

I- (I)V)OLiJzzIk:<LiJi

<LLJLi LU

Li

–I-xo

Page 182: An evaluation of production output for in situ concrete work

Consequently, Corletthas presented insufficient data to

conclusively prove that there is a significant difference betweenstatic pull and static torque. Therefore, the relationships produced

by Rohmert for calculating maximum holding times (Equation 7.k) and

the appropriate relaxation allowances (E4uation 7.5) have been

adopted in this reseach. The following example calculates relaxation

allc*iances for static pull and static torque.

The relaxation allowances f or two loading conditions are

determined. The first case considers a static pull load with maximumholding time of' 250 seconds being applied f or 30 seconds. The secondcase involves a static torque load with maximum holding time of 250seconds being applied for 30 seconds. The applied forces are

initially obtained from Corlett's "best-fit" lines presented in

Figure 7.9, and the relaxation allowances subsequently obtained from

Figure 7.7. Also, the applied forces and corresponding relaxationallowances are obtained using Robinert's curves.

Table 7 • 9 Relaxation. Allowances for Static Pull and Torque

Corlett Rolanert

Centa Static Torque Static Pu]].

DuratIon 30 seconds .30 seconds 30 seconds

Maximum holding time 250 seconds 250 seconds 250 secondsApplied force, Figure 7.9 27% 6% 2I%

Relaxation allance 5O 25 25%from Figure 7 .7

151

Page 183: An evaluation of production output for in situ concrete work

30

28

26

24

22

20

_ 18C

316

14

12

10

6

4

2

7.5.i Abnormal Postures

In certain tasks, it is necessary for the operative to adoptawkward postures and, thus, experience local muscle fatigue. Themost recent work done in this area has been the development of the

OWAS (7.111) group of postures. These are illustrated in Figure 7.10,

and the maximum holding times are given for typical postures adopted

whilst performing a simple tapping task. The postures are classified

by the location of the task being performed in terms of thepercentage of maximum working height and distance. The postures are

numbered (1 to 16) and the actual location of the task being

performed is illustrated, along with the region of pain, in Figure7.11. I .

0 123-45678910 11121141516

Figure 7.1 0 Maximum Holding Time for Yariouz Postures

152

Page 184: An evaluation of production output for in situ concrete work

8 14

Figure 7 - li_Relationship between Position of Load and Region of Pain

Figures 7.10 and 7.11 show that, for certain postures, body

weight can be more significant than the actual task being performed,

and that for different postures different muscle groups are critical.Rohniert's method of calculating relaxation allowances uses holdingtime and force developed (expressed as a percentage of the maximum

force), thus, the holding times in Figure 7.10 can be used tocalculate relaxation allowances for different types of posture.

To determine the relaxation allowance required when static loadand poor posture are both present, the force developed by the static

load and an equivalent force developed by the posture should becombined and used with Figure 7.7. To simplify this procedure, theholding times f or various postures have already been converted into

an equivalent developed forces and presented in Table 7.10. The OWASpostures (1 to 16) are divided into seven groups depending on the

maximum holding time. Figure 7.6 is used to convert these holdingtimes into an equivalent percentage of the maximum developed Vorces.

153

Page 185: An evaluation of production output for in situ concrete work

Table 7.10 Posture GrouDs

New OW AS Holding F/Fmax.Group Postures Tinie(mins)

A 1 30 11B 2 21 13C 3 13 16D 1,5,6 8 18E 7,8,9 5 23F 10 to 15 3.5 28

G 16 1.5 36

.The maximum holding times presented in Table 7.10 are obtaird

from research relating to the OWAS group of postures (7.15). These

results are for the same light tapping task performed in various

postures. The equivalent percentages of maximum force (F/Fmax) being

applied are caused by the adopted posture and the appropriate values

are obtained from Figure 7.6. When calculating relaxation

allowances, this equivalent , force (F/Finax) can be used either on its

own or combined with static loads.

1511

Page 186: An evaluation of production output for in situ concrete work

I

7.5.5 DYnamic. Muscle Fatigue

Dynamic muscle fatigue is usually associated with tasks

involving repeated loading cycles. The relaxation period required

for dynamic muscle fatigue is dependent upon both the degree of

fatigue reached during the loaded part of the work cycle and the

recovery available during the unloaded periods.

NOTE: C = contractionr = relaxation

Figure 7.12 Degree of Dynaic MuBole Fatigue

The recovery time for both static and dynamic work depends uponthe degree of fatigue reached (ie. the percentage reduction in

maximum load). Therefore, it is necessary to classify dynamic workin terms of' the ratio of "load time:uriload time", as well as the

percentage maximum force being applied. In Rohmert's formula,

Equation 7.6, these are represented by Neff. f or the number of

completed cycles and Nel. for fifteen per cent of the maximum numberof cycles.

155

Page 187: An evaluation of production output for in situ concrete work

REFA (7.16) have produced the simplest solution for determining

relaxation allowances associated with dynamic work. This involves

classifying the task in terms of steps In strain, and relating the

required relaxation allowance to the duration of uninterrupted work,

as shown in Figure 7.13.

heavy dynamic R.A. = 1.9(t) 0•l45 (Neff. - 1) 1OC

muscular work Nel.

...Equation 7.6

Note:

t = duration of working period (construction)

Neff. niber of ccnpleted cycles

Nel. = fifteen per' cent of the maximum number

of cycles.

156

Page 188: An evaluation of production output for in situ concrete work

RELAXATION ALLOWANCES FORDYNAMIC MUSCLE FATIGUE

200

180

160

LU

140

-J< 120z0

100-JU

80

zLU0 . 60U0

40

20

00 1 2 3 4 5 6

STEPS IN STRAIN

IFICURE 7.13 I

Page 189: An evaluation of production output for in situ concrete work

7.5.6 Optfmfat1on of Rest Pauses

The degree of fatigue reached during both static and dynamic work

depends upon the frequency of loading, therefore, it may be possible

to increase productivity by optimizing rest pauses. The relationship

between degree of fatigue and time is illustrated in Figure 7.1k for

two similar tasks with different rest pause arrangements.

10

8

(I)

cE

L1J 60z

0z

>(

2

00 10 20 30 40 50

PERCENTAGE OF MAXIMUM FORCE BEING APPLIED, P

Figure 7. 1 Degree of Fatigue Reached with Time

158

Page 190: An evaluation of production output for in situ concrete work

In Rohmert's investigation (7.17) into the optimization of rest

pauses, he posited that short but frequent breaks are more economic

than infrequent but longer breaks as:

(a) "it ensures short working periods with a smallaverage degree of fatigue as well as the frequent

experience of the high rate of recovery at the

beginning of a break."

(b) "well as by a psychological output-increasing

- effect while working up to a scheduled break."

On inspection those two statements by Rohmert appear to be

founded on unsound logic, thus, putting into doubt the possiblebenefits to be obtained from short regular breaks.

Firstly, Figure 7.1 14 indicates that a high rate of recovery can

only be obtained when a high degree of fatigue has been reached. Asfrequent breaks reduce the level of fatigue at the end of each work

cycle, only low rates of recovery can be achieved. Also, if short

breaks are taken there will still be some residual fatigue at the

beginning of the next work cycle, and the rate of increase in fatigue

will be greater.

Rohmert's second statement also fails to correspond to the

actions of a typical construction operative, as there is a definite

winding down period before and after official breaks on the majority

of sites.

159

Page 191: An evaluation of production output for in situ concrete work

7.6 RELAXATION ALLOWANCE FLOW CHART FOR CONSTRUCTION OPERATIONS

The previous sections In this chapter present the theoretical

background to the figures and equations used for the calculation of

construction relaxation allowances. The following flow chart has been

developed in order to simplify the choice of appropriate figures orequations used when calculating relaxation allowances. As a note of

caution, once this flow chart has been used and the relaxation

allowances calculated, a check should be performed to ensure that the

value obtained is not less than the basic allowance.

160

Page 192: An evaluation of production output for in situ concrete work

Is the load appliedto the whole body?

[YESF I N]

ILMETABCLIC COST LOCAL t4JS(E FATIGUE

What is the loading type?

Are existing benchj -' I

marks suitable? ] DYNAMIC ______ J STATICdue toJ 1_due to:

YES [NO] iii i i r—

I

Heavy Light IBad L jApplied- work, work.] L!ture.I

Can existingmodels be used?

LYEVIOI [on A$ ____ ___

From direct

measuranentj Determine posture Determinetype from Fig 7.10 F/Fmax frcin

_________________ and hence the Figure 7.6Determine work equivalent F/Fmax or Equation

-j rate, in watts from Table 7.10. 7.I.for each activity.

Is idle timepart of theoperation? The F/Fmax values for

posture and load are_____ _____ added together when

YES -j NO] applied to the samemuscle group.

Determinethe Is relaxation _____________________

partial relaxation taken standing Determine relaxation

alliance from or sitting? allc*jance from eitherFigure 7.5. Figure 7.7 or

I

Equation 7.5.

Determine the rlf sitting] If standingtotal relaxation use use

a1liance from Equation 7.1.] Equation 7.2.Fivation 7.3.

Fjgure 7.15 Relaxation Allcrance Flcw Chart

Page 193: An evaluation of production output for in situ concrete work

77 CALCULATION OF RELAXATION ALLOWANCES FOR CONCRETE WORK

The following example calculates a general relaxation allowancefor the majority of concreting operations1 this is based upon theresults from seventy concrete pours presented in Table 5.2. The

basic times for each element of concrete work are summated andpresented in Table 7.11. The percentage time spent on each activity

is subsequently calculated and used to determine a standardrelaxation allowance for most concreting operations. Figure 7.16

illustrates the path taken on the relaxation allowance flow chartrelating to most concrete operations. Loading is generally applied

to the body as a whole rather than any individual muscle group,therefore, the metabolic cost of the work is the main criterion. As

there are no existing bench marks, the power output is determinedfrom the Spitzer and Hettinger model (Tables 7.5 and 7.6). The

resulting relaxation allowance is twenty per cent of the basic time,

slightly higher than the seventeen per cent obtained in Table 7.1

using more traditional methods. Although some subjective assessmentis required the values can be checked by performing the individualtasks and recording the oxygen consumed over set periods. Asensitivity analysis is performed in Table 7.11 in order to

determine how relaxation allowances are influenced by errors made inthe assessment of the power associated with individual activities.

In this sensitivity analysis a ten per cent error is applied to twoactivities (i.e. vibrate concrete and cover concrete). Consequently,

a ten per cent error in the assessment of power consumed duringvibration changes the relaxation allowance by 18 per cent; and a ten

per cent error in the assessment of power consumed whilst coveringconcrete changes the relaxation allowance by 2 per cent.

162

Page 194: An evaluation of production output for in situ concrete work

DYNAMIC

STATICdue to: due to:

Heavy Light

Bad Appliedwork, work. Posture. Load.

NOYES

Is the load appliedto the whole body?

EIIHOCOST LOCAL MJSCLE FAT]'OUE

What is the loading type?

Are existing benchmarks suitable?

1YES I NO I

Can existing[de1s be used?

YES

From directmeasur n ent.

Determine workrate, in watts

for each activity.

Is idle tiupart of theoperation?

Use UseEquation Equation

7.6. 7.7.

Determine posture Determinetype frcm Fig 7.10 F/Fmax frcmand hence the Figure 7.6equivalent F/Fmax or Equationfrom Table 7.10. 7.1,

The F/Fmax values forposture and load areadded together whenapplied to the samemuscle group.

Determine the Is relaxationpartial relaxation taken standing

allcwance from or sitting?Figure 7.5.

Determine the If sitting If standingtotal relaxation use use

a1lance from Equation 7.1. Equation 7.2.Fquation 7.3.

Determine relaxationallcanoe from eitherFigure 7.7 orEquation 7.5.

jgur e 7.16 Rel axa ti on All c ance Fl -- Chart-.- Rxm nie

Page 195: An evaluation of production output for in situ concrete work

Table 7.11 Relaxation Jllowarice Calculation, for Concrete ODeratives

Activity Total. PercentagE Power (watts) T x P.T.

Basic Times A B TOTAL 100

Times P.T. (T)

(nuns.)

Prepare Tools 953 6 - 150 1 110 367 22.02

Pour Concrete 2112 12 112 17 11 293 35.16

Vibrate Concrete 311113 20 56 1711 307 61.110

Shovel Concrete 23110 111 87 209 373 52.22

Tamp Concrete 3536 21 87 209 373 78.33

Trowel Concrete 2096 12 36 130 2113 29.16

General Work 1606 9 150 1110 367 33.03

Clear Tools Away 568 3 150 140 367 11.01

Cover Concrete 561 3 150 1110 367 11.01

TOTAL 17215 100 333.311

SENSITIVITY ANALYSISASJME 10% ERROR IN PCWER ASSESSMENT

ABOVE EXAMR.E IN VIBRATE ACTIVITY IN COVER ACTIVITY

ERROR 61.110 x 0.1 11.01 x 0.1= 6.1i = 1.10

M.W.R. 333.311+6.1k 333.311 + 1.10M.W.R 333.311 watts = 3391I8 watts 3311.1111 watts

R.A. O.586(M.W.R.)-176LA. O.588(333.3 11)-176 O.588(339.1i8-176 0.558(3311.1111).176

R.A 20% 23.6% 20.65%E1ROR 1$ 3%

Note: A Power relating to body posture, from Table 7 .5.

B Power relating to type of activity, frc*n Table 7.6.

C Basic metabolin (76.7 watts).

T Total per relating to individual activities,

from Spitzer and Hettinger (A + B + C).

1611

Page 196: An evaluation of production output for in situ concrete work

It was observed in this research, however, that there was a

considerable amount of' idle time associated with construction

operations which is available as a substitute for relaxation

allowances. The site factors dealing with this aspect, presented in

Chapter Nine (Tables 9.1 to 9.5), can be used to compare theoretical

relaxation allowances and actual idle time. These total site

factors, inclusive of official breaks, are presented in Table 7.12.

The values show that actual Idle periods for the In situ concrete

gang greatly exceed the relaxation required.

Table 7.12 Summary of Total Site Factors

Trade Maximum Minimum

Site Factor Site Factor

In situ concrete 2.98 1.42

Formwork 2.50 1.27

Reinforcement 1.75 1.16

Structural steel-work 1.5k 1.23

Pre-cast concrete 1 .47 1 .29

Relaxation allowances have long been the traditional method of

establishing standard times for production planning and estimating in

the manufacturing industry. However, the above figures indicate that

relaxation allowances appear to have little relevance to performance

in the construction industry as there is a considerable amount

lost time caused by other factors. The method devised during this

research, and presented in Chapter EIght, uses site factors to

accommodate lost time in the setting of planning rates. These site

factors should always be checked to ensure that the appropriate

relaxation periods are available.

165 -

Page 197: An evaluation of production output for in situ concrete work

CHAPTER EIGHT

CALJLATING PLANNING TINES

166

Page 198: An evaluation of production output for in situ concrete work

CHAPTER EIGHT

CALCULATING PLANNING TIMES

8.1 INTRODUCTION

The previous chapter illustrates how allowances for the physicalcost of work should be applied to basic time in order to establish astandard time f or a specific task. In practice, standard time is

rarely achieved as the actual relaxation period taken often exceedsthe time required f or recovery. Thus, planning time should take into

account the basic operation time and an allowance for the factors

affecting productivity.

8.2 FACTORS AFFECTING CONSTRUCTION PRODUCTIVITY

The "Real Work Content" of any operation is the least possible

time it can be completed in. However, at the design and planningstages mistakes can be made,, resulting in an "Added Work Content"

even before the job has even started. Also, while the work is in

progress management and operatives can cause idle periods, Le.

"Ineffective Time". Therefore, the total number of man hours for an

operation can be classified as shown in Figure 8.1 and described in

Table 8.1.

167

Page 199: An evaluation of production output for in situ concrete work

C

C00

'-4

.4-,0

g)

4.'UC)

I4.U.'wwCEH--4

'-I

4.'

o .r4

.r4

HO

ao

Real WorkContent

DesignAddedWorkContent

MethodAddedWorkContent

ManagementIneffective

Time

OperativeIneffective

Time

Figure 8.1 Work Content and Ineffective Time

Page 200: An evaluation of production output for in situ concrete work

Table 8.1 Description of Added Work Content and.Ineffective TiAe

Added Work Content Caused B y Design Errors Will Occur If:(a) the structure Is designed such that the most

economical construction methods cannot be used;

(b) there is a wide variety in the type of units oronly short production runs are possible;

(c) a material is not up to the correct specificationsand therefore difficult to work with;

Cd) the specifications are too high and excess work isrequired to achieve them.

Idded Work Content Caused By Method_Of Working Will Occur if:(a) the incorrect size or type of' plant Is selected;

(b) the site layout causes wasted effort by the

incorrect positioning of site accommodation,

batching plants, material stores and workshops;

Ineffective Time Will Occur If' ManageNent Fails To En&re That

(a) operatives are given the opportunity to acquireskill and speed by standardizing temporary works

or providing continuity of operations;

(b) the work does not come up to the clients

specification;

(C) the order of work is planned in detail eliminating

waiting time;(d) the materials are on site where and when they are

required;

(e) the plant is kept free from breakdowns by regular

maintenance;

(f) worker fatigue is kept to a minimum by good

working conditions;

(g) the correct safety precautions are taken.Worker Ineffective Ti.e Will Occur If:

(a) the operatives are not fully motivated, resulting

in extended breaks, excess relaxation ordeliberately working at a reduced rate;

(b) work has to be repeated due to bad workmanship;Cc) the operatives do not observe current safety

regulations.

169

Page 201: An evaluation of production output for in situ concrete work

The site manager can, by applying accurate planning techniques,

reduce the element of lost time under his control; but it is

important to realize that even if all the waiting time is eliminated,

the planned output rates will only be achieved if the labour force is

sufficiently motivated. The proposed build up of construction

planning times, from basic operation times and site factors,

incorporates the concept of adding various inefficiencies onto the

real. work content, as illustrated by Figure 8.1.

8.3 SITE FACTORS

To accommodate various levels of efficiency, adjustments are

made to total basic time for changes in work rate, idle or wasted

time and breaks. In this research these adjustments are expressed

as factors, and can be determined from activity sampling or

cumulative timing results. The relationships between the working

day, site factors and total basic time are illustrated In Figure 8.2

and expressed in Equation 8.1.

170

Page 202: An evaluation of production output for in situ concrete work

BASIC INTERNAL

TIME DELAY

BT ID

TOTAL BASIC WORKRATE

TIME TIME I

EXT ERN AL

WORKING TIME DELAY RaAX.ATION

WT

ED

R

ATTENDANCE TIME

AT

WORKING HCJJRS

EXTRA

BREAKS

EB

OFFICIAL

BREAKS

WH

WORKING DAT

WD

Figure 8.2 ADDlication of Site Factors to Basic Tines

Page 203: An evaluation of production output for in situ concrete work

The relationship between working day (WD) and total basic time

(TBT) is, therefore, expressed as:

WD = ThT x Fl x F2 x F3 x F1 ...Equation 5.l

Given that:

Fl = TBT (THIS IS NOT A SITE FACTOR BUT

BT RELATES TO ThE OPERATION)

F1=WT

WORK RATE

TBT

F2 =AT WT +W + R

IDLE TIME

WT WT

F3 WE

EXTRA BREAKS

AT

F1 = WD

ABSEE

WE

The procedure for building up planning times from basic element

times, allowing f' or different site conditions, is summarized below.

(a) Determine the basic operation time by combining

the basic element times, .work contingency

allowances and internal delay allowances where

appropriate.

(b) Determine the basic operation time for site

ancillary work.

(c) In order to obtain standard time, calculate and

apply the relaxation allowances to the basic time,

takingof account any internal delay allowancealready incorporated.

(d) In order to obtain planning times, apply the total

site factor ( FT Fl x F2 x F3 x F 1 ) to the basic

time.

172

Page 204: An evaluation of production output for in situ concrete work

This relationship between working day (W.D.) and total basic

time (T.B.T.), as expressed in Fi.ivation 8.1, is used in Chapter Nine

to quantify the efficiency of several sites in terms of site factors.

The values are subsequently applied to the general concrete model

(Table 5.6) and compared with estimators' data as a means of

validating the modeL

The following example illustrates how the site factors were

calculated f or the Formwork gang on Site 3 (as presented in Table

p 9.2). The average durations f' or each activity were determined from

several days of activity sampling.

Table 8.2 Saple Calculation of Site Factors

Activity Duration Site Factors

Hours

Working Day 8.50

Official Breaks 1.35 FIt = WD/Wli = 1.i9

Working Hours 7.50

Extra Breaks 1.61 F3 = AT/WT = 1.29

Attendance Time 5.54

External Delay + Relaxation 1.77 F2 = AT/WT = 1.117

Working Time 3.77

Work Rate 0.37 Fl WT/TBT 1.11

Total Basic Time 3.110

- 173

Page 205: An evaluation of production output for in situ concrete work

CHAPTER NINE

ACTUAL SITE FACTOES

17k

Page 206: An evaluation of production output for in situ concrete work

CHAPTER NINE

AC1JAL SITE FACTORS

9.1 INTRtI$JCTION

The build up of planning times, from basic element times and

site factors, is discussed in Chapters Seven and Eight. In this

chapter site factors obtained from several sites are presented for in

situ concrete, formwork, reinforcement, structural steel-work and

precast concrete gangs. The main causes of variation in gang

performance are ascertained and the relevance of site factors in

determining production times f or construction operations

dnonstra ted.

9.2 MELJRED SITE FACTORS

Studies, on eleven constructions sites were carried out on the

above trades in order to determine actual site factors. Summaries of

the observed site factors are presented in Tables 9.1 to 9.5. The

data are set out in relation to the level of remuneration to

illustrate the marked impact that this single variable appears to

have on the site factor values. The rates of pay quoted have been

adjusted for a base year of 1983 using Baxter Indices.

175

Page 207: An evaluation of production output for in situ concrete work

Table Q .1 Sitejactora for Six Concrete Gang

SITE PAY Fl F2 F3 Fk FT

£/Hr

1 3.78 0.98 1.26 1.0k 1.14 1.1t6

2 2.51 1.05 1.72 1.12 1.18 2.39

3 2.03 1.02 1.86 1.32 1.19 2.98

14 2.80 1.03 1.28 1.01 1.22 1.62

14 2.80 1.10 1.32 1.01 1.22 1.79

5 2.87 1.07 1.145 1.05 1.22 1.99

Table 9.2 Site Factors for Six Forwork Gangs

SITE PAY Fl F2 F3 FJ4 FT

LI Hr

-

1 14.1414 0.98 1.10 1.03 1.114 1.27

2 3.90 1.03 1.314 1.19 1.18 1.914

3 3.614 1.11 1.147 1.29 1.19 2.50

ii 14.22 1.00 1.10 1.01 1.18 1.31

Il 2.53 1.09 1.36 1.02 1.22 1.814

5 3.10 1.00 1.31 1.02 1.22 1.63

______I_

176

Page 208: An evaluation of production output for in situ concrete work

Table Q • Site Factors for Six Reinforceient Gangs

SITE PAY Fl F2 F3 F4 FT

£/Hr

1 11.22 0.96 1.03 1.03 1.11 ii6

2 11.00 0.96 1.O'T 1.08 1.18 1.31

3 3.00 0.96 1.18 1.30 1.19 1.75

3.08 1.01 1.20 1.03 1.22 1.52

11 3.08 1.01 1.18 1.02 1.22 1.118

5 3.25 1.02 1.19 1. 1.22 1.57

Table g. Site Factors for Five Structural Steel-work Gangs

SITE PAY Fl Fl F2 F3 F11 FT

6 1LCO 1.29 1.00 1.12 1.111 1.11 1.k2

7 3.50 1.14 1.00 1.21 1.16 1.10 1.5k

8 3.70 1.36 1.00 1.01 1.11 1.10 1.23

9 11.00 1.28 1.00 1.18 1.10 1.11 1.kl

10 3.70 1.37 1.00 1.28 1.05 1.12 1.51

177

Page 209: An evaluation of production output for in situ concrete work

Table Q.c Site Factors for. Eight Pro-cast Concrete Gangs

SITE PAY Fl Fl F2 F3 Fl FT

£/Hr

11 1.12 1.00 1.09 1.05 1.11 1.29

12 3.50 1.23 1.00 1.23 1.09 1.10 1.117

13 3.60 1.110 1.00 1.12 1.13 1.12 1.112

111 3.110 1.28 1.00 1.15 1.10 1.12 1.112

15 11.20 1.29 1.00 1.11 1.11 1.10 1.36

16 11.50 1.22 1.00 1.13 1.111 1.10 1.112

17 11.50 1.29 1.00 1.06 1.17 1.11 1.38

18 11.50 1.15 1.00 1.10 1.12 1.12 1.38

178

Page 210: An evaluation of production output for in situ concrete work

TOTAL SITE FACTOR AGAINST REMUNERATION

3-

2.8 -

2 .6-

2.4-

2 .2-

UJF--(-n-J

1.8-F-

1.6-

1.4-

1.2-

1-2

LegendL CONCRETE GANGS

X FORMWORK GANGS

.0 STEELWORKCANCS

REINFORCEMENT GANGS

.... PRE-CAST CONCRETE GANGS

.........................................................

.........................................................X

x

..

.................: .

........................................

xx:0

2.5 3 3.5

4 4.5REMUNERATION /l-1r.

[FiGURE 941

Page 211: An evaluation of production output for in situ concrete work

9.3 ANALYSIS OF SITE FACTORS

There are numerous variables affecting operative performance;

however, the following analysis concentrates on the relationship

between total site factor (FT) and hourly pay (P) for five trades, as

illustrated in Figure 9.1, which indicates an inverse relationshipbetween performance and remuneration independent of trade. Three

types of relationship are thus investigated in each stage of the

analysis; namely straig1it line, inverse and log.

There are two points on Figure 9.1, relating to joiners, which

deviate considerably from the trend. Consequently, the followinganalysis has three stages: the first omits these two points from the

analysis; the second includes these two points; the third includes

these two points and investigates possible causes of the divergence.

In each stage the relationship between total site factor and hourlypay investigated by regression analysis using the Minitab package.

The resulting equations and coefficients of determination (R 2) are

presented for the individual stages in the analysis.

(1) Stage One

In Figure 9.1 total site factors (FT) are plotted against hourlypay, for the thirty-one gangs. The two points with large deviationare excluded from this stage of the analysis. Initially, a straight

line relationship is investigated resulting In a correlation

coefficient (R) of -O.8. Secondly, two inverse relationships are

used, thus improving the correlation to 0.9314. Finally, simple log

relationships are Investigated with the best correlation coefficient

being 0.938. The regression equations and correlation coefficients

resulting from this stage of the analysis are presented in Table 9.6.

As there is only a slight Improvement in correlation when logs are

introduced, the following equation is selected to represent the

relationship between total site factors and pay.

FT = 0.863 + 7.88/P2R = 0.9314

180

Page 212: An evaluation of production output for in situ concrete work

Table g .6 Reresion Equations for - Stage One

Fquation8 Coefficient of

DeterRirtion (R2)

FT = 3.05 - 0.413 P 65.0%

FT = 0.105 + 5.01/P 81.14%

FT = 0.863 + 7.88/P287.3%

FT = 3.143 - 3.41 Log P 73.5%

FT = 3.143 + 1.71 Log(1/P2 ) 73.5%

Log FT = 0.636 - 0.826 Log P 79.7%

Log FT = 0.636 + 0.1413 Log(1/P2 ) 79.7%

Correlation Coefficients CR)

PAY 1/P 1/P2 Log P Log 1/P2

Log FT -0.8514 0.922 0.938 -0.893 0.893

FT -0.806 0.902 0.9314 -0.857 0.857

181

Page 213: An evaluation of production output for in situ concrete work

(U) Stage Two

The equation resulting from the first stage of the analysis

closely represents the data used. The second stage is performed to

determine the relationship best representing all thirty-one gangs.

The two stray points in Figure 9.1 now are included. The result is a

reduction in the correlation coefficients obtained: -0.702 for the

straight line relationship; 0.7 92 for the inverse relationship; and

0.791 for the log relationship. The resulting regression equations

and correlation coefficients are presented in Table 9.7. The

equation presented below is selected to represent the relationship

between total site factor and remuneration.

FT = 0.955 + 7.12/P2R = 0.792

182

Page 214: An evaluation of production output for in situ concrete work

Table gy Regression Eauations for. Stage Two

Equations Coefficient of

Determination CR2)

FT = 3.05 - 0.kOO P 119.2%

FT 0.231 + 11.75/P 59.1%

FT 0.955 + 7.112/P2 62.9%

FT = 3.110 - 3.2T Log p 511.3%

FT = 3.110 + 1.6 11 Log 1/P2511.3%

Log FT = 0.628 - 0.789 Log P 58.5%

Correlation Coefficients (R)

PAY FT 1/P 1/P2 Log P Log 1/P2

Log FT 0.7110 - 0.783 0.791 -0.765 0.765

FT -0.702 - 0.769 0.792 -0.737 0.737

183

Page 215: An evaluation of production output for in situ concrete work

(iii) Sta&e Three

The two points exhibiting excessive divergence in Figure 9.1 areassociated with the forinwork gangs. This divergence represents areduction In performance when compared with other gangs. On

inspection of Tables 9.1 to 9.5, this divergence appears to be caused

by the large pay differential between the concretors and joiners on

the same site. Thus, it Is postulated that the low productivity of

concrete gangs receiving minimum payments reduces the efficiency of

joiners receiving substantially I:iIgher wages. As the work done byreinforcement fixers, steel erectors and pre-cast concrete erectors

is of an independent subcontract nature, they are not significantly

affected by pay differentials.

Stage three of the analysis Investigates this divergence with

the objective of establishing a realistic relationship, betweenperformance and remuneration, which takes into account the pay

differential between joiners and concretors on the same site.

The correlation coefficient for the straight line relationshipis now 0.713; this Is only a slight improvement on the value obtained

In stage two. The correlation for the inverse relationship is now0.866, this lies half-way between the corresponding values obtained

in stages one and two. The best correlation from the simple logrelationships Is now O.8O1, again this is half-way between the two

corresponding values obtained in the previous stages. The regression

equations and correlation coefficients, obtained during stage three

of the analysis, are presented In Table 9.8. The following equationsare selected to represent the relationship between total site factors

and remuneration.

Joiners FT 0.883 + 7.52/P2 + 2.29/Pc2R = 0.866

Other Gangs FT = 0.883 + 7.52/P2

Note: P = Level of pay (i/br)

Pc = Difference between joiners and concretors

pay on the same site.

1811

Page 216: An evaluation of production output for in situ concrete work

Table 9.8 Regression Eauation for. Stage Three

Equations Coefficient of

Determination (R2

FT 3.0k - 0.0j P + 0.05 Pc 50.9

FT 0.195 + 1 .79/P + 0.045 11 Pc 60.8

FT 0.925 + 7.118/P2 + 0.045 Pc 611.11

FT 0.168 + JI.79/P + 0.728 Pc 66.7

FT 0.158 + '1.79/P + 2.23/Pc 270.8

FT 0.895 + 7.50/P2 + 0.7'15/Po 70.6

FT 0.883 + 7.52/P2 + 2.29/Pc275.0

FT 0.1173 + 11.111/P - 003511 (P-Pci-i) 60.1

FT 0.50 + 11.2 11/P - 0.0066 (P-Pc+1) 260.7

FT 1.15 + 6.91/P2 - 0.0366 (P-Pci-i) 63.8

FT = 1.15 + 6.6 11/P2 - 0.007 (P-Pci-i) 264.6

Log FT 0.630 - 0.760 Log P - 0.032k Log (P-Pci-i) 58.9

Log FT = 06211 - 0.796 Log P + 0.0682 Log (1+Pc) 61.11

185

Page 217: An evaluation of production output for in situ concrete work

9.11 DISCUSSIOL OF RESULTS

The very high correlation obtained in the analysis shows that avery good relationship exists between total site factor arid hourly

pay, as represented by the following equation.

FT = 0.663 + 7.88/P2 R = 0a9314

However, this relationship is sometimes affected by the level ofpay received by other gangs, particularly in the case of joiners.

Figure 9.1 shows that the above relationship holds true for the five

trades studied, with some grouping of results. For example, concreteoperatives generally received the lowest level of pay, and are thus

grouped towards the left in Figure 9.1, but are still represented by

the above equation.

Other factors, such as site conditions, level of' directsupervision or site organization, can affect motivation. However,

the high correlation obtained in the analysis justifies this rather

simplistic expression used to represent the relationship betweenincentives and motivation. The analysis has produced a basic

equation with very good correlation, however, the inclusion of any

additional factors would complicate the resulting expression withoutany significant improvement in the correlation.

Figure 8.1 shows the different types of' ineffective time andwork content contained in the total time taken to perform most

construction operations. Real work content is the least possible

time a task can be completed in. Added work content relatesto

decisions made during the design or planning stages, and is a measure

of additional work performed. Ineffective time comprises idle

periods caused by both management and operatives.

When determining overall efficiency levels all four additionsto the real work content should be considered. Losses caused by

management can contribute to three of' the five sections in Figure8.1, consequently, the quality of site management and level of site

186

Page 218: An evaluation of production output for in situ concrete work

supervision are important variables affecting site productivity.However, this research focuses upon total ineffective time, as

opposed to added work content.

On construction sites lost production can be caused bydesigners, site management and operatives, but it is very difficultto allocate arw loss to one particular source. Management and

operative ineffective times are often intertwined and difficult toseparate. For example, when an operation is delayed owing to poor

management, say waiting f or materials, the operatives have two options;they can wait for the material to arrive or continue on some other

task. Well motivated operatives can, therefore, reduce the ineffectivetime caused by site management by diverting onto other work.

In this chapter a relationship between remuneration level andtotal ineffective time is established. rhe remuneration level isnot only a measure of operative motivation but also indirectly

corresponds to the level of site supervision. It was observed

that operatives receiving higher rates of pay were prepared to be

subjected to higher levels of direct site supervision. And, it is a

fair assumption that management paying high rates consider their

operatives a valuable asset requiring full attention and good

supervision; conversely, it does not cost the contractor a

considerable amount if operatives receiving minimum rates are not

fully utilised.

The high correlation obtained between basic time and work

content for concrete operatives, see Chapter Five, indicates thatthe main variations in output rates are associated with ineffective

time. On construction sites, the majority of managerial efforts are

directed towards the optimization of' site profitability rather than

increasing individual operation efficiency, and it is often necessaryfor site managers to sacrifice operational efficiency in order to

complete critical operations, For example, during the constructionof a multistorey building, concrete may be poured using either cranesor pumps, but, the deciding factor is usually not the work contentinvolved in the two methods, but the difference between overall pour'

times.

18T

Page 219: An evaluation of production output for in situ concrete work

CRAPTER TER

COMPARISON OF ACTUAL SITE FACTORS WITH

CONTRACTORS' ESTIMATING DATA

188

Page 220: An evaluation of production output for in situ concrete work

CHAPTER TEN

COMPARISON OF ACTUAL SITE FACTORS WITH

CONTRACTORS' ESTIMATING DATA

10.1 BUILD UP ESTIMATING DATA

The basic operation times obtained by synthesizing elements

using the equations on page 10k represent the irreducible time of

concrete work in man. niinutes. However, to enable basic operation

times to be compared with realistic estimating data, adjustments

have to made for ancillary work, site efficiency and bonus rates.

Weather, holidays and overheads are also generally included in the

labour cost element of arr estimate.

189

Page 221: An evaluation of production output for in situ concrete work

10.2 EXAMPLE OF AN ESTIMATE!) DURATION BASED ON WORK SJDY DATA

The following estimate of duration is for pouring a concrete

slab (200mm deep, with an area of fifty square metres and a volume of

ten cubic metres) using a crane and skip. The duration calculated

below is presented in Table 10.1, along with values for other pours.

The basic operation time for this operation is obtained from Table Cl

in Appendix C.

Basic Operation Time (B.O.T.)

395 man-minutes

Estimate Duration (E.D.)

B.0.T. x FT

60The average value of the observed total site factors for the

concrete operatives is 2.OZ, from Table 9.1.

Estimate Duration (E.D.) = 395 x 2.011

60

E.D. = 13.11 man-hours

10.3 CONTRACTORS' ESTIMATING DATA

Estimating data has been obtained from several sources, these

are: four' contractors (Cl - C11); two local authorities (Li - L2); andthree published sources (i.e. •Griffiths' building price book (10.1),

Spence Geddes' estimating f or building and civil engineering works

(10.2), and Comprehensive Builders Price Book (iO3)• These valuesare used to estimate the time required to pour concrete for slabs,walls and columns, the results are presented in Tables 10.1, 10,2 and

1 0.3. These durations are inclusive of non-productive time, butexclusive of weather allowances.

190

Page 222: An evaluation of production output for in situ concrete work

0OO 0000 nc000

C) CJ Lfl - Cr) C%J C\4 tn -

(-I r r

o cj o - t en o 000

d - en '- en i-n • ir. en tLAefl'o C'J .A0c)c) cncOcflO

- '- '- c en '•- c'J '- c'J -

0000 0000 00tn 0000o cj - co o - d o 0' en C%j

oCn0 Q%IC1Cfl

'- C%J '- In IA - (%J - C1 en

0000 0000 0000 0000ddad

(-i ø (J (J 00 IA 0

. H t- I- i-u en e- C%J i-fl - i-fl Cr)00

000 (i (%J C,J C%J CJcXC

,-cfl.-(JV..

IA000 0000 0000 00i-v t'-'- c%j IA C%J '- . '.00% C%J IA '

'- '-

IA000 0000 OiAOO 00000 In . • • • • • a • •

1 C) C'JIAOIA 0000 Lfl00- i-u IA - en 'o (1 IL\ en '.o 0'

I-I- '- ._

0'. '.oC 9000

0 C) CJ IA - - IA '- I C\i '.0 C'.J

O - c'.i i en i-fl IA i-u IA'- '-

IA000 0000 L('I00 0000

r . . . . . . . . . a • . a • a

C) c0t--

-(fl1A -Cu-'.o

>4 0C'.J 0ii0'. '.00ncJ c'.J cj cu en .. 0 0' 0' 0 en 00%.0 -

(-I Q' '.o CJ en IA '.0 .- C\J LA - -0 d d '. Cr) 0% IA 0% '.0

'- i-u en en - - i-u

— — —

m IA000 0000 oLnoo 0000

') ,J 0 - i-u en - Cu - Cu c'.J C'.JS..-

XZ1 (1 0000 0000 Lfli-fl00 0000H 0 t000 IA000 CJvoOLA

'— '- Cu en - i-u en - -

- 0

0 0 0 0 08 0 0 0 0

S.- i-u .-

Page 223: An evaluation of production output for in situ concrete work

t.. 0 0 - CJ e-

C.) Cd . CJ CT) LA C\J In LA

xcO i0O

0 .- - d c...

' ' C\J C%J LA - cn .o

rn0CJ ocoLccn cOLACnO coincn0

S • • • S • S S • S • S S • •

C, - 05 • OI 0. . O

v-CJ CJCJ CJ-CJ

5- 5-

0 LA IA 0 LA LA LA LA LA LA 0 LA 0 IA 0E- .4 • • • • S S 5 5 S S

H 0. In CJ O C%j C\J - - C\J LA -. C'.J

5- Cu Cu Al Alc.) 0 ____ _______ ________ 5- _______

5- lI III' lull

Ill pill uul liii

000 000 CJIA--CT)oczt-

5- 5- Al 5- Al Al

C') OLALA OLAOtn t.-IflIfl

CT) . • . . . . . . . . . . . .

0 C.) IA .- Al IA Al LA -. - ..o Al IA In

5- - In 5- cu . cu

000 s-s-0O s-s-0s LflIfl-Er4 CJ • . . . • . • S S •

Z C.) Cu In LA Al LA 0 LA 0 LA LA LA 0 LA 0' s ss Al e-s Al

0000 LAOLALA LAOLALA

5- . S S • S • • • S • • • .

0 000 -LAC- -LACJ-

5- '- Al In '-Cu In '-cu In

LAD—LA LA—-5-

. . S • • • S S • S S

CT) CT) CT) ', C' Al IA -. ('I

5- 5-

t-CT)rflC'J rncncu'- LAInCflgx 5-'- cu '- Al CT) cu In Cu cn

000 0000 0000 0000

m . • . . . . . . . . . . . .C') .- Al In LA Al LA 0 LA LA 0 IA LA LA 0 LA LA

Z 0 '- 5- 5_ 5-5-. 5-5- Cu

C0• 9 9C0•9 0 a

H g . %O 0 cu LA 0 LA Al IA Cu s-cu cn o5- 5-5- 5-

.4

-s 0 0 0 0c'J

H - . .0 0 0 0

Page 224: An evaluation of production output for in situ concrete work

P4 LA LA 0 LA 0cJ C' cfl

'- U-

('J . - 0 .-I-I . S • S

cn o C3 O LAT- U--

C%J 'O

C' cos- CU rn

t_ 0 0 0 0cY 'o CU

r- T (U00

I I I I I

cn .o CU CUS • • S S

C.) - CU LAU--

0 0 0 0 00 • . . .

0 C) CU . CU '.o- U--

00 (j U U- U--

CU . . . .z C) t- CU fl0 ____0

U- CU 'OU- S • S • S

C) CU in 0 inU--

- LA LA C'S S • S •

CU cv tA '0

U- T ci CU in

0(zlEl

in 0 0 0 0a . • . •

C) 0 CU in00

Page 225: An evaluation of production output for in situ concrete work

Table 10.11 Ratio of Estimated Durations to Basic Operation Times

CONTRACTORS LOCAL PUBLISHEDAUTHORITIES DATA

Cl C2 C3 0k Li L2 G SG CBP

DEPTH ABS(mm)

100 1.57 2.39 2.32 2.50 2.3k 7.76 9.61 5.96 5.117

200 2.30 2.95 2.95 3.149 2.92 10.1111 111.88 10.06 5.11

1400 2.99 3.58 3.91 4.16 3.0k 13.03 10.35 8.80 5.08

1000 3.19 5.53 5.53 5.98 3.110 15.23 13.36 111.36 5.81

WIDTH WALLS(mm)

100 ' 3.711 1.69 11.25 3.110 - 7.65 8.53 9.67 5.67

200 11.99 2.50 6.23 i.k8 - 11.16 12.33 17.33 7.31

1400 14.82 3.2k 5.63 5.31 - 111.65 16.72 13.CYT 6.55

800 14.66 3.0k 11.82 5.02 - 13.68 15.03 12.13 6.28

VOLUME - COLUMNS(in 3)

<1.0 2.00 0.81 2.16 1.110 - 3.51 5.06 3.1414 5.04

2.0 3.06 0.914 3.60 2.311 - 5.110 8.146 5.72 14.05

3.0 3.71 1.13 11. 141 3.08 - 6.61 10.37 6.98 11.96

14.0 11.01 1.21 l.71 3.31 - 7.06 11.11 7.119 5.31

MEAN 3.142 2. 141 1I.37 3.71 2.93 9.68 11.23 9.65 5.56

Page 226: An evaluation of production output for in situ concrete work

FIGURE 10.1 CONTRACTORS' DATA hoursAGAINST WORK STUDY DURATIONS hours

120

100

80

aC,,

160

40

20

o.t0

-I.,..........................Q.. ......................................

1 I......................................................................................

± 4

-E

,

±. .4

:CONTRACTORS

.X CONTRACTOR C2

0 CONTRACTOR C3

+ CONTRACTOR C4

10 20 30 40 50 60 70 80

WORK STUDY DURATIONS

Page 227: An evaluation of production output for in situ concrete work

10. 11 COMPARISON OF BASIC OPERATION TIMES WITH ESTIMATING DATA

A comparison can be made between basic operation times andestimated durations by using the values presented in Tables 10.1,

10.2 and 10.3. The estimated durations obtained from the

contractors' data are approximately three times higher than the

basic operation times, Table 10.11. This indicates that the two

sources are compatible and the main differences arises because:

Ci) The results obtained from the sites visited indicate thatsite factors (FT) ranging between 1.16 and 2.98 should beapplied to convert basic operation times into realistic

planning times.

(ii) The basic times for concrete operations are based upon the

work done by the concrete gang. However, the estimateddurations include any general operatives servicing this

gang.

(iii) The actual cost of an operation represents a combinationof the time taken and the cost of labour inclusive of

bonus paid. However, estimates are usually based upon the

operatives basic wage, and consequently the estimated

duration is larger than the actual.

(iv) The ratio of contractors' estimated durations to basicoperation times increases as the size of' pour increases,

Table 10.11. The shape of most concrete pours corresponds•to the smaller pours in Tables 10.1 to 10.3, thus, the

duration f or the majority of pours is accurately predictedusing the contractors' own data. However, the rates used

by contractors do not accurately predict output rates f' or

the larger and more unusual pours, as illustrated by the

large differences between the contractors' data for pours

greater than forty cubic meters, Figure 10.1. Equally,

because the generalized model is mainly based on smallpours, care is needed when extrapolating planning timesfor large pours.

Page 228: An evaluation of production output for in situ concrete work

Bonus rates are normally paid at a third of the operatives'basic pay. To illustrate the degree of correlation between the twogroups of results, a site factor of 2.5 is applied to the work study

data and the obtained durations are plotted, on Figure 10.1, against

the contractors' durations which are based upon the estimated

durations minus a third to allow f or bonus incentives.

In contrast to the good correlation between the work study dataand contractors' data, the durations estimated from traditional

published sources (i.e. Griffiths' and Spence Ceddes') are three

times greater than the contractors'. Also, resea.roh by Fleming (b04)

shows that there has been little change in these published rates

since 1900. This obviously puts the credibility of such sources intoquestion. However, the values obtained from the first edition of

Comprehensive Builders' Prices Book are more realistic.

Most of the work undertaken by local authorities' own workforce

involves highway maintenance and small remedial work, with any largestructural projects being put out to tender, conseqently, suitable

estimating data were only obtained from two local authorities. Theserates indicated a wide variability in data used by the two local

authori ties.

197

Page 229: An evaluation of production output for in situ concrete work

APTER ftv

CON cLUSIONS, EEOI41ENDATIONS AND

FUBTUER RESEARR

198

Page 230: An evaluation of production output for in situ concrete work

CHAPTEW ELEVEN

CONCLUSION$, RECOMMENDATIONS AND FURTHER RESEARCH

11.1 CONCLUSIONS

In this thesis the author has sought to describe the development

of construction work study and its constituent parts. One of the

main findings was that work study techniques could be modified to

meet t.he requirements of most construction operations, sites and

companies, whether the requirements were complex synthesis of basic

operation times or the more simple determination of site efficiency.

The ey to this portability lay in the isolation of basic operation

times via the application of' site efficiency factors.

The author has also demonstrated that most of the variability in

production rates can be quickly explained, leaving relatively

constant levels of' output for individual construction operations

(i.e. basic operation times). On construction sites lost production

can be caused by designers, site management and operatives, but it is

very difticult to allocate any loss to one particular source.

Management and operative ineffective times are often intertwined and

difficult to separate. For example, when an operation is delayed

owing to poor management, say waiting t or materials, the operatives

have two options; they can wait f or the material to arrive or

continue on some other task. Well motivated operatives can,

therefore, reduce the ineffective time caused by site management by

diverting onto other work.

199

Page 231: An evaluation of production output for in situ concrete work

Figure 8.1 contains five sections and shows the different types

of ineffective time and work content contained in the total time

taken to perform most construction operations. Real work content

represents the least possible time a task can be completed in. Added

work content relates to decisions made during the design or planning

stages (i.e. design added work content and method added work

content), and is a measure of additional work performed. Ineffective

time comprises idle periods caused by both management and operatives

(i.e. management ineffective time and operative ineffective time).

When determining overall efficiency levels aU four additions to

the real work content should be considered. Losses caused by

management mainly contribute to three of these additions (design

added work content, method added work content and management

ineffective time), consequently, the quality of site management and

level of site supervision are important variables affecting site

productivity. However, this research focuses upon total ineffective

time and operative motivation, as opposed to added work content and

degree of management controL In contrast, research by Homer (11.1)

in the Department of Civil Engineering at Dundee University

concentrated upon the relationship between degree of management

control and site productivity. One of Homer's main findings was the

indication that, at low levels of management control, there was a

positive relationship between productivity and the degree of control.

In addition to the development of construction work study and

the measurement of site efficiency, realistic output rates have

been determined for a wide range of concreting operations. The

conclusions resulting from these three objectives have been discussed

throughout this thesis. They are now collectively summarized and

presented in four sections.

200

Page 232: An evaluation of production output for in situ concrete work

11 • 1.1 Background and Modification of Traditional Techniques

The first section, comprising Chapters Two and Three, contained

a review of the historical background to work study and an

investigation into how this Influenced the techniques currently used

within the construction industry. The evidence indicated that,although similar work study techniques were used by various

organizations to collect data, a wide variation existed in both thepresentation and application of the results. This variation often

arose because many work study techniques originated from thejnanufacturing industry and were adopted by the construction industry

without adequate consideration given to the latter's needs.

Contractors mainly used work study to determine outputrates f or planning, estimating and bonus schemes, thus, work

measurement techniques were more popular than method studies. Thelack of drive in developing improved construction methods has

perpetuated the status-quo as far as traditional construction methods

are concerned, and in some instances working methods have remainedthe same over the last hundred years or so

The main deficiencies in current methods of presenting outputdata were found to be: the failure to accurately represent the

various individual elements relating to complete operations; and thelack of flexibility when dealing with different levels of operative

performance. In order to reduce these deficiencies, the differenttypes of work and idle time usually associated with construction work

were carefully considered in the development of a more systematical

approach to the presentation of output data. During thisrationalization of construction time standards, it was also ensuredthat the developed method of' presentating data was compatible with

current methods and complied with the relevant terminology used inthe British Standard. The working day was broken down in terms of

working time, diverted time, Idle time and absence time, as

illustrated in Figure 3.k. Consequently, construction operationswere classified as unrestricted, semi-restricted or restricted,depending upon the type of' idle time involved.

201

Page 233: An evaluation of production output for in situ concrete work

11.1.2 Determination of Basic Operation Times

The second section demonstrated how basic times were obtained

f or concreting operations, beginning with the results from just onestudy and subsequently expanded to include results from over seventy

concrete pow's. The results from the single study were used to

illustrate the data collection process adopted throughout this

research, along with the process of synthesizing basic operationtimes. In addition, the data obtained from several pours were used

to determine basic operation times for major items of constructionplant.

The example presented in Chapter Four provided the author withthe framework to derive a systematical approacri in the development ofconstruction work study. The framework comprised several sub-systems

which were described and modified throughout this thesis. The mainsub-systems were work measurement, relaxation allowances, operative

motivation and site factors.

The work measurement techniques applied during data collectionwere mainly activity sampling and cumulative timing, as described in

Chapter Four. Activity sampling proved successful when recording

groups of workers engaged in constantly changing work patterns.After many trials, the adopted procedure involved taking observationsevery five minutes with the activity and work rate being recorded.

The intervals between observations were reduced where smaller gangs

were involved. Cumulative timing proved more appropriate f or machine

dominated operations where activities were commonly performed in

regular patterns. To simplify the whole procedure, data for concrete

operations were recorded on specially adapted activity sampling

sheets, and the initial analyses were performed on activity sampling

summary sheets, as illustrated by Figures and,1h3.

- 202

Page 234: An evaluation of production output for in situ concrete work

11.1.3 Determination of Standard Times

It is impossible to establish a library of standard times

without predetermining what allowances should be applied to the basictimes. In work study data based libraries one of' the most commonfactors is the relaxation allowance. However, even in the

manufacturing industry where there is a relatively limited number of

operations, a gross disparity exists between the relaxationallowances being awarded f or the same type of task.

The validity of traditional methods used to calculate relaxation

allowances was investigated, and a system more appropriate toconstruction operations was developed. In the first instance, this

involved a review of the theoretical basis of existing methods andconcentrated upon the two types of fatigue pertinent to construction

operations (i.e. metabolic and local muscle). Standard times f or

concreting operations were subsequently obtained by combining basic

times and relaxation allowances.

A flow chart was developed in order to simplify the methods usedto calculate construction relaxation allowances. This flow chart was

used to establish w'hich equations and figures, presented in Chapter

Seven, were applicable to concreting operations. The results from

all the concrete pours were then used to determine a generalrelaxation allowance for concrete operatives. The value obtainedusing the new approach was found to be. twenty per cent of the basic

time, as opposed to the seventeen per cent obtained using a more

traditional approach. Consequently, the standard time for ary

concreting operation was found to be equal to the basic time plus

twenty per cent f or relaxation.

Standard times were only applicable to sufficiently motivatedoperatives working on well organized operations. On several of the

construction sites, this idea]. combination was not always the case,and planning times often had to account f' or large periods of idle

time. The majority of idle time associated with construction workrelated to individual sites, hence, site factors were used to

represent lost time, as explained in Chapter Eight.

203

Page 235: An evaluation of production output for in situ concrete work

11.1. 11 Construction Productivit y aI Site Factors

The final section investigated the variation in performance fromsite to site with the emphasis being transferred from work content tolost time. On the construction sites visited, there was a 'wide

variety of' payment schemes in existence, (for example, the level ofremuneration for concrete operatives varied between 2.03 £/hr and

3.78 £/hr). As a result some operatives were highly motivated whilstothers had little or no motivation. Standard times, by definition,

only apply to uninterrupted work performed by well motivated

operatives. Therefore, some form of' adjustment, other than the

addition of relaxation allowances, was required to convert basictimes into realistic construction planning and estimating data. When

applied to construction operations standard times lose some of theirtraditional meaning, however, they still have an important role to

play as they indicate optimal levels of performance.

The main possible causes of lost construction production wereinitially discussed in terms of work content and ineffective time,

and the concept, of' using site factors to account for lost production

or as a measure of performance, was introduced. It was observed

that there was a considerable amount of idle time associated with

construction operations which were available as a substitute f' or

relaxation allowances. The site factors dealing with this aspect,presented in Chapter Nine (Tables 9.1 to 9.5), were compared with

theoretical relaxation allowances. These total site factors,

inclusive of' official breaks, were presented in Table 7.12. Thevalues showed that actual idle periods for the in situ concrete gangs

greatly exceeded the relaxation required. The site factors, presented

in Figure 9.1, also suggested that the idle periods associated with

operations performed by more high)y motivated operatives (eg. the

pre.-cast concrete gangs) did not greatly exceed the requiredrelaxation allowances.

20 1

Page 236: An evaluation of production output for in situ concrete work

Table 7.12 S"' y ofTotal Site Factors

Trade Maximum Minimum

Site Factor Site Factor

In situ concrete 2.98

Formwork 2.50 1.27

Reinforcement 1.75 1.16

Structural steel-work 1.51 1.23

Pre-cast concrete 1.7 -1.29

Relaxation allowances have long been the traditional method of

establishing standard times I or production planning and estimating in

the manufacturing industry. However, the above figures indicate that

relaxation allowances appear to have little relevance to performance

in the construction industry as there is a considerable amount of'

lost time caused by other factors. The method devised, and presented

in Chapter Eight, uses site factors to accommodate lost time in the

setting of planning rates. Before these site factors are applied,

they should always be checked to ensure that the appropriate

relaxation periods are available.

The high correlation obtained between basic time and work

content for concrete operatives, see Chapter Five, indicated that the

main variations in output rates were associated with ineffective -

time. In Chapter Nine, a relationship between remuneration level and

total ineffective time was established. The very high correlation

obtained In the analysis (R = 093 lØ showed that a very good

relationship existed between total site factor and hourly pay.

However, this relationship was slightly affected by the level of' pay

received by other gangs, but Figure 9.1 showed that the relationship

represented all five trades studied.

The high correlation obtained justifies this rather simplistic

expression used to represent the relationship between incentives and

motivation. Other factors, such as site conditions, level of direct

205

Page 237: An evaluation of production output for in situ concrete work

supervision or site organization, do affect motivation; but furtherwork would be needed to fully understand the relationship between

these additional variables.

On construction sites, the majority of managerial efforts are

directed towards the optimization of site profitability rather thanincreasing individual operation efficiency, and it is often necessary

for site managers to sacrifice operational efficiency In order tocomplete critical operations. For example, during the construction

of a multistorey building, concrete may be poured using either cranesor pumps, however, the deciding factor Is usually not the work content

involved in the two methods, but the difference between overall pourtimes.

The remuneration levels were not only a measure of operative

motivation but also indirectly corresponded to the level of sitesupervision. It was observed that operatives receiving higher rates

of pay were preparea to be subjected to higher levels of direct sitesupervision. And1 it is a fair assumption that management paying

high rates consider their operatives a valuable asset requiring fullattention and good supervision; conversely, it does not cost the

contractor a considerable amount if operatives receiving minimumrates are not fully utilized.

Estimating data were obtained from several sources (i.e. four

contractors, two local authorities, and three published sources). Inorder to compared these values with the work study-data, they were

used to estimate the time required to pour concrete f or slabs, wallsand columns. The estimated durations obtained from the contractors'

data were found to be compatible with he work study data. However,the durations estimated from traditional published sources (i.e.

Griffiths' and Spence Geddes') were found to be three times greaterthan the contractors' values. Also, research by Fleming (1)

shows that there has been little change in these published ratessince j900. This obviously puts the credibility of such sources into

question. However, the values obtained from the first edition ofComprehensive Builders' Prices Book were found to be more realistic.

206

Page 238: An evaluation of production output for in situ concrete work

11.2 RECOMMENDATIONS

As far as the future is concerned, more people working

independently in industry, but pooling their information in a

standardized form, would provide a forum for an exchange of

information on methods of working with the hope of improving

construction productivity.

Initially, construction work study is likely to more effective

if the applications are directed towards work improvement on

individual sites, rather than the collection of output rates. Only

when it becomes clear that more efficient methods of working are

possible, will feedback data begin to be pooled for subsequent use.

In the manufacturing industry most operations are performed in a

predefined order with delays and interruptions easily avoided, and as

a result output levels can be accurately predicted. In this type of

environment bonus schemes can be effectively introduced and operative

motivation easily controlled. In general, incentive schemes improve

the operatives' motivation and encourages them to reduce the amount

of idle time. The majority of incentive schemes in the manufacturing

industry are based on standard times obtained from a combination of

basic times and relaxation allowances. However, owing to the

excessive idle periods on many construction sites this combination is

not applicable when calculating realistic planning rates. The

combination of basic times and site factors, as developed in this

research, is more appropriate and also provides the site manager with

a measure of' site performance. The construction Industry should be

made aware of the large variation that currently exists between sites

and encouraged to make better use of' incentive schemes with the view

to improving operative motivation and Increasing productivity.

The comparison made, in Chapter Ten, between productivity

achieved on construction sites and output rates presented in

published sources, highlights the need for more realistic output

rates to be assembled and made available to general users.

207

Page 239: An evaluation of production output for in situ concrete work

11.3 FURTHER RESEARCH

Throughout this thesis, the author has made several

recommendations for further research and development, these are now

summarized and others added.

The establishment of basic operation times usually involves on

site measurement followed by a detailed analysis, and can often be a

very tedious and time consuming process. Current research (11.2) in

the Department of Civil Engineering at Loughborough University is

aimed at improving the situation by utilizing portable microcomputers

such as the EPSON and APRICOT. The format presented in Figure 14.2

has been adopted on the EPSON for work measurement on site, and the

initial stage of any subsequent analysis is performed on the APRICOT

and follows the format shown in Figure 14.3. In addition to the

reduction in time spent collecting and analysing data, the use of

computers should encourage a more standardized approach.

It has been demonstrated, by concentrating upon the work

performed by the operatives, that the variability between the basic

times for different methods of placing concrete was relatively low,

and that lost time was a good measure of efficiency. 1n other

operations, such as falsework erection, work content often depends on

the adopted method, and thus, efficiency is a combination of work

content and lost time. Further research is, therefore, required into

work content before absolute levels of efficiency can be determined

f or all construction trades. The author also recognizes the need for

more research on the productivity of materials handling systems (i.e.

pumps, cranes) before any statisticallyvalid conclusions can be

drawn.

In this research a relationship between level of remuneration

and site efficiency was established f or several trades. Research by

Homer indicated a relationship between degree of management control

ans site efficiency. If' a relationship between overall management

control, level of direct site supervision and level of remuneration

were to be measured the compatibility between these two could be

firmly established.

208

Page 240: An evaluation of production output for in situ concrete work

APPENDIX A

CONSTRUCTION WORX STUD! TERMINOLOGY

209

Page 241: An evaluation of production output for in situ concrete work

AFFENDIX &

CONSTRUCTION WORK STUDY TERMINOLOGY

Li INTRODUCTION

This appendix contains definitions relating to the terminology

used within this thesis and is sub-divided into four sections. The

definitions in the first section relate to the terminology used in

the general discussion of construction work study as presented in

Chapter Three. The remaining sections are directly associated with

the terminology used in Figures 3.1k, 3.5 and 8.2.

210

Page 242: An evaluation of production output for in situ concrete work

A.2 CONSTRUCTION WORK STUDL - CHAPTER THREE

Work Study A management service based on those

techniques, particularly method study and workmeasurement, which are used in the examination

of human work in all its contexts, and whichlead to the systematic investigation of all

the resources and factors which affect the

efficiency and economy of the situation beingreviewed, in order to effect improvement.

Method Study The systematic recording and critical

examination of existing and proposed ways ofdoing work, as a means of developing and

applying easier and more effective methods andreducing costs.

Work Measurement The application of techniques designed toestablish the time for a qualified worker to

carry out a specific job at a defined level ofperformance.

Ti.e Study A work measurement technique for recording the

times and rates of' working for the elements of'

a specific job carried out under. specifiedconditions, and for analysing the data inorder to obtain the time necessary for

carrying out the job at a defined level of

performance.

211 -

Page 243: An evaluation of production output for in situ concrete work

Flyback Timing The hands of the stop-watch are returned to

zero and restarted at the end of each element.The time icr each element is recorded

directly, along with an assessment of' rate.

Cumulative Timing The hands of the stop-watch are not stoppedbut the actual time at the end of each elementis recorded. Each element is rated and the

duration subsequently obtained by subtraction.

Activity Sampling Observations are taken either at set or random

Intervals on a group of' workers, with both theactivities being performed and the rate of'

work recorded.

Rating Rating is used to assess the worker's rate of

working relative to the observer's concept ofstandard rating (rate depends upon speed of

movement, effort, dexterity and consistency).

212

Page 244: An evaluation of production output for in situ concrete work

WORKING DAYAND

OVERTIME

ABSENCE TIMEATTENDANcE TIME l

ErIRA OFFiCIAL_________________ ___________________ BJWAS DREAXS

WORKING DIVERTED TIME - IDLE TIME

I ___________I I _________

INSIDE OUTSIDE Imachine controlled RAIATION DELAY

time

II I I I I

ELEMENT EXCESS ANCILLARY ALLCMANCE ADDITIONAL EXTERNAL ThTEUILTIME TIME TIME DELAY DELAY

UNRESTRICTED OPERATIONS

SEMIRFTRICTED OPERATIONS

RFTRICTED OPERATIONS

Figure Claaaification of Work and Idle Times.

NOTE: Bold type indicates tenns which are also used in Figure 8.2.

Page 245: An evaluation of production output for in situ concrete work

A.3 CLASSIFICATION OF WORK AND IDLE TIMES - FIGURE

Working Day The official daily hours beyond which overtime

is paid. The working day comprises both

absence and attendance time.

Absence Time The period of the working day when the

- operative is absent from work.

Attendance Time The period of the working day that the

operative spends at his place of work. There

are three types of attendance time, namely

working, diverted and idle time.

Working Time The actual time taken to carry out the work,

and includes the following.

Inside Machine The work which can be performed within the

Controlled Time mactime controlled time.

Outside Machine The work which must be done outside the

Controlled Time machine controlled time.

Element Time The time spent on productive work elements.

Excess Time The additional time caused by a deviation from

the specified method or materials.

211

Page 246: An evaluation of production output for in situ concrete work

Ancillary Time The remaining time which cannot be classified

as productive or excess but is necessary for

the completion of' an operation.

Diverted Time The time the worker is engaged on otheroperations.

Idle Time The period of attendance time not spentworking. It can take the form of' relaxationor delays.

Relaxation Allowance An additional time to the basic time intendedto provide the worker the opportunity torecover from the physiological and

psychological effects of carrying out

work under specified conditions and to allow

attention to personal needs.

Additional Relaxation The time taken over and above the officialrelaxation when there is work available.

Delays Periods of time when the operative isavailable for work but is prevented from doingso by the lack of work or materials.

External Delays The delays caused by factors outside theoperatives' control (eg. waiting for concrete).

Internal Delays The unavoidable delays which occur when anoperative is working within a gang or with amachine.

Official Breaks The time officially set aside f or tea breaks

but does not include lunch breaks.

215

Page 247: An evaluation of production output for in situ concrete work

Extra Breaks The periods during which the worker is not

available for work owing to additional breaks,early finishes or late starts.

Unrestricted An operation in which the output is solely

Operation controlled by the operative (eg. fixingreinforcement).

Senai-restricted An operation which can be affected by externalOperation delays (eg. waiting f or concrete).

Restricted An operation in which the output is affectedOperation by internal delays (eg. waiting for an

excavator to finish before laying pipes).

216

Page 248: An evaluation of production output for in situ concrete work

BASIC TIME BASIC TIMEEXCESS ANCILLARY

ASSEMELE BASICELEMENT TIMESTO OBTAIN BASICOPERATION TII

BASIC TIMEFOR

CONTINGENCY WORK

BASIC TIlEU NRETh ICTED

OPERATION

INTERNAL DELAYALL 0.1 ANCES

BASIC TIlERESTRICEDOPERATION

TOTAL BASICTIME

PERSONAL BASICNEEDS FAT]I]UE

I-F IXED

ENVIORONMENTALSTRAIN

IVARIABLE

SITE FACTORS

RELAXATION(Fl xF 2xF 3xF It)

ALL0.IANCES

TOTAL PLANNING

TOTAL STANDARDTIME

TIlE

Figure .5 Pr000ed Build ho of Time Standards

Page 249: An evaluation of production output for in situ concrete work

A. J1 PROPOSED BUILD UP OF TIME STANDARDS -- FIGURE

Element A distinct part of a specified operation

selected for convenience of observation and

analysis. (Types: repe ti tive, occasional,

constant, variable, manual, machi ne,

governing, foreign).

Operation

Basic Element Time

Basic Operation Time

A unit of work used for planning or control

purposes based on a combination of elements.

The time required to perform an element of

work at standard rate.

The time required to complete an operation at

standard rate.

Standard Rate The average rate at which qualified workers

will perform, so long as they are sufficiently

motivated and carry out the work to the

specified method.

Standard Time The total time required to complete a job at

standard performance. It includes basic time,

contingency allowances and relaxation

allowances.

Contingency Allowance A small allowance of time which may be

included in the total basic time to meet

legitimate and expected items of work or

delays. Their precise measurement is often

uneconomical because of their infrequent or

irregular occurrence.

218

Page 250: An evaluation of production output for in situ concrete work

Basic Excess Tine This is the additional work caused by the

deviation from the standard method and can be

attributed to either the operation or the

site. (e.g. the time spent carrying

reinforcement which has been unloaded in the

wrong area).

Basic Ancillary Ti.e This is the necessary work which is part of an

operation (e.g. maintenance of plant), or site

organization (e.g. walking to canteen) and

cannot appropriately be classified asproductive.

Policy Allowance Under exceptional circumstances an additional

allowance applied to the standard time in

order to provide a satisfactory level of

ear z'ii ngs.

219

Page 251: An evaluation of production output for in situ concrete work

AT

BASIC INTERNAL

TIME DELAY

BT ID

TOTAL BASIC WORKRATE

TIME TIME I

EXTERN AL

WORKING TIME I DELAY RAXATIQN

WT I ED R

EXTRA

ATTEThANCE TIME I BREAKS

OFFICIAL

WORKI? HCURS I BREAKS

WH -

WORKING DAY

WD

Figure 8.2 Application of Site Factors to Basic Tines

Page 252: An evaluation of production output for in situ concrete work

A.5 APPLICATION OF SITE FACTORS TO BASIC_TIMESL - FIGURE 8.2

(1) Internal. Delay s (Interference)This is the time when the operative is prevented from working

owing to the nature of the task. This is generally of a low order

when dealing with construction operatives as there is invariably someother work available. Internal delays become significant when

machines are involved and the operatives or machine have enforcedidle periods.

(ii) Work Rate Tine

The main cause of variation in work rate is the skill of the

operative. As most operations occur on a regular basis and are

performed by experienced workers there is generally little variationin rating levels. However, when an operation of a complex nature

occurs, the variation can be very high because the operative is in a

learning situation.

(iii) External DelaysThese occur I or a wide variety of reasons and are mainly caused

by poor site organization. They often lie outside the control of the

operations involved, for example waiting for materials.

(iv) Relaxation

When work is available the only viable reason for not doing itis the motivation of the operative. Official relaxation allowances

are normally provided and can be taken during other periods of lost

time.

(v) Extra BreaksThe periods during which the worker is not available for work

owing to additional breaks, early finishes or late starts, and isrelated to iow motivation but is within the control of site

management.

(vi) Official BreaksThe periods officially allocated to tea breaks but does not

include lunch breaks.

221

Page 253: An evaluation of production output for in situ concrete work

APPENDIX B

LISTING OF MINIT4%B PROGRAMS

222

Page 254: An evaluation of production output for in situ concrete work

B.l PROGRAM 'C1E.MINEXEC'

B.l.l PREPARE TOOLS

RETR 'data'CON STCORE Cl-Cl?ONEWAY C16 C2ONEWAY C17 C2ONEWAY C13 C2ONEWAY C16 C12ONEWAY C17 C12ONEWAY C13 C12OMIT '' C3 C2 , C63 C62ONEWAYC63 C62PLOT C3 C13PLOT C3 C16L}LOT C3 C13 C2.LFLOT C3 C16 C12LPLOT C3 C13 C12OMIT '' C3 C2 , C63 C62ONEWAYC63 C62CORE C3 C13RER C3 I C13MEAN C3LFLOT C3 C16 C2RB3R C3 2 C13 C16CORE C3 C13 ci6LET C30=C3/C13OMIT '' C30 C2 , C90 C62ONEWAY-C90 C62TABLE C2 C12;DATA C3;MEANS C3.CHOOSE I C12 C3 C13 , C21 C22 C23PLOT 022 C23RE3R 022 1 023CHOOSE 3 C12 C3 013 , C21 C22 C23PLOT C22 C23RØ3R 022 1 C23CHOOSE 11 C12 C3 C13 , C21 C22 023PLOT C22 C23RBR C22 I C23

223

Page 255: An evaluation of production output for in situ concrete work

B.1.2 IQUR CONCRETE

RETR 'data'CON STCORR C1 C13LFLOT C1 C13, C2FLOTC1C13RR C I C13LET C20=Ck/C13OMIT 'a' C20 C2 , C80 C62ONEWAYC8O C62CHOOSE 2 C2 Ck C13, C21 C22 C23RER C22 I C23CORE C22 C23PLOT C22 C23CORR Ck C13LPLOT C C13, C12PLOT Ck C13RERCk1C13LET C20=CIUC13OMIT '' C20 C12 , 8O C72ONEWAYC8O C72CHOOSE 1 C12 Cle C13, C21 C22 C23RB3R C22 1 C23CORE C22 C23PLOT C22 C23CHOOSE 2 C12 Ck C13, C21 C22 C23RER C22 1 C23CORE C22 C23PLOT C22 CCHOOSE 3 C12 CII C13, C21 C22 C23RE13R C22 1 C23CORE C22 C23PLOT C22 C23CHOOSE I C12 CII C13, C21 C22 C23REXR C22 1 C23CORR C22 C23PLOT C22 C23REDO 3 C12 2 C12LET C20=CII/C13OMIT '*' C20 C12 , 8O C72ONEWAY C80 C72CHOOSE 2 C12 CII C13, C21 C22 C23RR C22 1 C23CORR C22 C23PLOT C22 C23CHOOSE 1 C12 CII C13, C21 C22 C23RE3R C22 1 C23CORE C22 C23PLOT C22 C23LET C22C22/C3OLET C23:C23/C30gJ C22 1 C23

PLOT C22 C23

2211

Page 256: An evaluation of production output for in situ concrete work

C21 C22 C23

C21 C22 C23

C21 C22 C23

C21 C22 C23

C21 C22 C23

B.1.3 .YIBRATE CONCRETE

RETR 'data'CON STCORE C5 C13LFLOT C5 C13, C12PLOT C5 C13RR C5 I C13LET C2005/C13OMIT '' C20 C12 , C80 C72ONEWAY-C80 C72NOCOQiCOSE 1 C12 C5 C13,RR C22 1 C23CORE C22 C23PLOT C22 C23CON SREXR C22 1 C23CHOOSE 2 C12 C5 C13,RFR C22 1 C23CORE C22 C23PLOT C22 C23CHOOSE 3 C12 C5 C13,RER C22 1 C23CORR C22 C23PLOT C22 C23CHOOSE 1 C12 C5 C13,R3R C22 1 C23CORR C22 C23PLOT C22 C23NOOREGR C22 1 C23REDO 2 C12 , 3 C12CHOOSE 3 C12 C5 C13,CORR C22 C23PLOT C22 C23CONSRER C22 1 C23NOORFZ3R C22 1 C23CORR C22 C23PLOT C22 C23

225

Page 257: An evaluation of production output for in situ concrete work

B.1. 1 &OY CONCRETE

RETR 'data'CON STCORE C6 C13 C16 C17R3R C6 2 C16 C17PLOT C6 C13PLOT C6 C16PLOT C6 C17R3R C6 1 C16LET C3O=C6/C16OMIT "' C30 C12 , C90 C72ONEWAY C90 C72

B.1.5 TAMP CONCRETE

RETR 'data'CON STCORE C7 C13 C•16 C17RF3R C7 2 C16 C17PLOT C7 C13PLOT C'T ci6PLOT C7 C17RR C7 1 C16

B. 1 .6 CONCRETE

RETR 'data'CON STCORR c8 C13 C16 Cl?RE3R C8 2 C16 C17PLOT C8 C13PLOT C8 C16PLOT C8 Cl?REflR C8 1 C16RECO 0 C18 2 C18WRITE C18OMIT " C8 C18 , C68 C7 8ONEWAYC68 C78LET C68 C8/Ci6OMIT 'a' C8 C18, C68 C78ONFMAYC68 C78LPLOTC8O36OC13O8OC18CHOOSE 1 C18 C8 C16 , C20 C21 C22OMIT i c18 C8 Ci6 , C23 C211 C25PLOT C21 C22PLOT C2k C25R3R C21 1 C22RR C2l 1 C25cORE C21 C22CORE C2 1 C25NOCORER C2 11 1 C25

226

Page 258: An evaluation of production output for in situ concrete work

B.1.7 CLEAR TOOLS AWAY

RETR 'data'CON STCORE dO C13 C16 C17REX3R ClO 2 C16 C17REGE dO 2 C13 C16RB3R dO 2 C13 Cl?PLOT dO C13PLOT ClO C16PLOT do C17LET CkO=C1O/C13OMIT " dO C2 , C70 C62ONEWAY-C70 C62OMITI*?CIOC2,C95C62ONEWAY-C95 C62OMIT "' C1O C12 , C95 C72ONEWAY- C95 C72OMIT *1 co C12 , C70 C72ONEWAY-C7O C72LPLOT do C13 C2LPLOT cia C13 C12REDO 1 2 C2 k C2CHOOSE k C2 dO C13 , C21 C22 C23PLOT C22 C23REGR C22 I C23CORE C22 C23MEAN C2CHOOSE 3 C2 C1O C13 , C21 C22 C23PLOT C22 C23RB3R C22 I C23CORR C22 C23MEAN C2

B.1.8 COVER CONCRETE

RETE 'data'CON STCORE Cli C13 C16 C17REGR Cli 1 C16REGR Cli 2 C16 Cl?REX3R Cli 2 C16 C13LFLOT Cii C13 C12LPLOT CII C16 C12LPLOT Cii C17 C12LET C5OC11/C16L}LOT C50 C17 C12

227

Page 259: An evaluation of production output for in situ concrete work

B.1.9 GEEAL W0R

RETE 'data'PRINT C1-C17CON STCORE C9 C13 C16 Cl?RXR C9 2 ci6 Cl?RFR C9 1 C16PLOT C9 C13PLOT cg C16PLOT C9 C17LET C2OC9/C13OMIT '*' C20 C2, C80 C62ONEWAy-c80 C62OMIT '*' C9 C2, C69 C62ON EWAY-c69 C62LPLOTCgO9OC13O 1 O , C2RETR 'data'CON STREDO '*' C3 0 C3REDO '*1 Ck 0 C1RECO '* C5 0 C5RECO '*' C6 0 C6RECO '*' C? 0 C7RECO '*' C8 0 C8RECO 0 dO 0 dOREDO '*' Cli 0 CiiLET C2O=C+C5+C6+C7+C8LET C21=C3+C1O+C11LET C12=C2O+C2l3JBS 525 10 C1i29JBS 605 21 Ci2CORE C9 C20 C21 C12PLOT C9 C20PLOT C9 C21PLOT C9 CZL2RFR C9 2 C20 C21LET C30=C9/Ck2OMIT 1*t C30 C2, C90 C62ONEWAY- C90 C62LELOT C9 C$2 C2LPLOT C9 0 80 C12 0 500 , C2RR C9 1 C12CORR C9 Ck2RR C9 1 C1t2CORR Cg CZI2LET C20=C9/C13OMIT '*' C20 C2 , d80 C62ONEWAYC8O C62CHOOSE 1 C2 C9 Ck2, C21 C22 C23RER C22 1 C23CORE C22 C23PLOT C22 C23CHOOSE 2 C2 C9 Ck2, C21 C22 C23REX3R C22 1 C23CORE C22 C23PLOT C22 C23CHOOSE 3 C2 C9 C112, C21 C22 C23RE3R C22 1 C23CORE C22 C23PLOT C22 C23

228

Page 260: An evaluation of production output for in situ concrete work

CHOOSE i C2 C9 Ck2, C21 C22 C23RBR C22 1 C23CORR C22 C23PLOT C22 C23RECO 3 C2 1 C2RECO 1( C2 2 C2OMIT '*' C30 C2 C90 C62ONi Ay c9O C62CHOOSE 1 C2 C9 C12 , C31 C32 C33PLOT C32 C33REX3R C32 1 C33NOCORER C32 1 C33CONSCORR C32 C33CHOOSE 2 C2 C9 C1t2 , C31 C32 C33PLOT C32 C33REX3R C32 1 C33NOCOREY3R C32 I C33CORR C32 C33END

B. 2 PROGRAM 'TESTI .MINEXEC'RETR 'data'NAME Cl 'TEST'NAME C2 'METHOD'NAME C3 'PRTOOLS'NAME C1 'POUR'NAME C5 'VIBRATE'NAME C6 'SHOVL'NAME C7 'TAMP'NAME C8 'TRL'NAME C9 'GENERAL'NAME dO 'CLTOOLS'NAME Cli 'COVER'NAME C12 'TYPE'NAME C13 'VOLUME'NAME Clk 'WIDTH'NAME C15 'LENGTH'NAME C16 'AREA'NAME C17 'DEPTH'NAME C19 '.3JB-TOTAL'LET C20= C1+C5+C6+C7+C8LET C21C3+ClO+Ci1LET C22=C20+C21+C9LET C19=C20+C21LET Ck3:l1 .7+O.501*C13LET Ck=5.I5+1 .67'C13LET CZ53.1I6*C13

LET C'16=8.07+O .737'C16LET Ck7lO.7+l .12'C16LET Ck8=27 .6+2.79'C16LET C50=6 .83+0 .310'C13LET C51:8 .62+0.86 1'C13+O .202'C16LET K5l.13OOLET K6=1 .0775LET C52=16.1O+1 .18'C13LET C53 .7 9+9 .6 5'C 13LET CS 1I5 .6 9'C 13LET C55=22.8'C 13

229

Page 261: An evaluation of production output for in situ concrete work

LET C56=9.37+O.5119*c13LET C571.51'C16LET C58=5.00LET C59=13.2+O.8118'C13LET C6O5.k3+4.O2'C13REO 1 2 C2 0 C36RECO 3 C36 I C36REDO 4 C36 0 C36RECO 3 C2 1 C37RECO 2 4 C37 0 C37LET C38C37-1RECO -1 C38 1 C38RECO 1 C12 0 C32RECO 2 C12 0 C33RECO 3 C12 0 C34RECO 4 C12 0 C35S1N C32 C32SIGN C33 C33SIGN C34 C311SIGN C35 C35LET C32=C32-1LET C33=C33-1LET C34=C34-1LET C35=C35-1RECO -1 C32 1 C32RECO -1 C33 I C33RECO -1 C34 1 C34RECO -1 C35 I C35LET C1L 11= C44*C32+C52* (C 33+C34) +C53*C35LET Ck5C1I5*C32+C54* (C33+C34)+C55*C35LET C48=C48*C18+C57*C68LET C50=(C50+C56'C36)LET C49=K5'C37+K6'C38LET C7O=(Ck3+C44+Ck5+C16+Ck7+C48+C5O+C51)'Ck9LET C71=C70/C49PLOT C3 C43RR C3 I C43CORR C3 C43PLOTC4C1I4E)3R C4 1 C44CORE CI C44PLOT C5 C45EB3R C5 1 C45CORR C5 C45PLOT c6 CI6REX3RC6 1C46CORE c6 C46PLOT C? C$7

RE3R c't I C47CORE ? C47

PLOT cB C48RER c8 1 C48CORE c8 C48PLOT do C50REX3R dO 1 C50CORE dO C50PLOT Cli C51REZR Cli 1 C51CORE Cli C51SAVE 'temp'END

230

Page 262: An evaluation of production output for in situ concrete work

B. 3 £KfX1RAM 'TEST2 MINEIE C'

RETR 'temP'RECO 'it C3 0 C3RECO '*' C4 0 CJREcO 'it C5 0 C5RECO 'it c6 0 C6RECO 'i' C? 0 C?RECO 'it C8 0 C8RECO ii' dO 0 dORECO '*' Cli 0 CliLET C2O=C+C5+C6+C7+c8LET C21=C3+C1O+C11LET C22=C20+C21+C9

LET C19=C20+C21JB3 525 10 C19JBS 605 21 C19

LET Ck9=C19'(C49-1)PLOT C9 Ck9REGRC91CJt9CORR C9 dugPRINT C9 C19 C37 C38LET Cu9=( 1.152*C19_8 . 63)*C37+( 1.068'C19+1t.O0)C38

LET Cz19:Ck9_C19PLOT C9 Cu9RER C9 1 CZ9CORE C9 C149SAVE 'general'

END

B. I IROG RAM 'TEST . MINEXE C'

RETE 'temp'NAME C19 'JB'NAME C22 'TOTAL'SIGN C3 C23SIGN CII C21SIGN C5 C25SIGN C6 c26SIGN C7 C27SIGN C8 C28SIGN C9 C29SIGN ClO C30SIGN Cli C31RECO 0 C23 1 C23RECO 0 C2k 1 C2IIRECO 0 C25 1 C25RECO 0 C26 I C26RECO 0 C2? 1 C27RECO 0 C28 1 C28RECO 0 C29 1 C29RECO 0 C30 1 C30RECO 0 C31 1 C31RECO '*' C23 0 C23RECO a' C2 11 0 C2kREdO 'a' C25 0 C25RECO 'a' C26 0 c26RECO 'a' C27 0 C27RECO C28 0 C28

231

Page 263: An evaluation of production output for in situ concrete work

RECO '*' C29 0 C29RECO "' C30 0 C30RECO '*' C31 0 C31LET 3_lI3*C23

LET ciCIlll*C2kLET 5...5*C25LET C1i6Cii6'C26

LET Ck7C117'C21LET C118=Cii8'C28LET 9il9*C29

LET C50=C50'C30LET CiC51'C31LET lC1I3+C^C1t5+C1l6+C1I7+Ck8+C5O+C51LET C7o( 1.152'C71-8.63)'C37+( 1.068*C71+1I.0O)*C38LET Ci9CT0-C71BECO 'at C3 0 C3RECO 'a' C11 0 C!RECO 'a' C5 0 C5RECO 'a C6 0 C6REDO 'a' C? 0 C7RECO 'a' C8 0 C8RECO *, dO 0 ClORECO 'a' Cli 0 CliLET C20C2I+C5+C6+C7+C8LET C21=C3+C1O+C11LET C22 C20+C2 1 +C9

JBS 'a' 10 C22JBS 'a' 21 C22

LET C19=C20+C21PLOT C22 C70CORE C22 C70PLOT C22 0 600 C70 0 600LPLOT C22 0 600 C70 0 600 C2LPLOT C22 0 600 C70 0 600 C12RBR C22 1 C70NOCORER C22 1 C70PLOT C19 C7iCORE C19 C71PLOT C190600 C71 0600LPLOT C19 0 600 C71 0 600 C2LPLOT C19 0 600 C71 0 600 C12RFJJR C19 1 C71CONSRR C19 1 C71PRINT C19 C71 C22 C70 C37 C38

232

Page 264: An evaluation of production output for in situ concrete work

B5 IROGRAM 'TESTILMINEXEC'

RETR 'temp'NAME C19 'JB'NAME C22 'TOTAL'SIGN C3 C23SIGN C1 C2kSIGN C5 C25SIGN C6 C26SIGN CT C21SIGN C8 C28SIGN C9 C29SIGN do C30SIGN Cli C31REDO 0 C23 1 C23REdO 0 C2$ 1 C21tRECO 0 C25 1 C25RECO 0 C26 1 C26RECO 0 C27 1 C2tRECO 0 C28 1 C28RECO 0 C29 1 C29RECO 0 C30 1 C30RECO 0 C31 1 C31REDO '*' C23 0 C23RECO i C211 0 C214RECO ti ' C25 0 C25RECO 'i' C26 0 C26RECO ' i ' C2T 0 C21RECO vi' C28 0 C28REdO 'iv C29 0 C29RECO 'i' C30 0 C30RECO vi' C31 0 C31LET c13-C$3'C23LET C1C114*C2JLET Ci5C1t5'C25LET CZ6=C16'C26LET Ci7C7C27LET C8CJ48'C28LET 9C9'C29LET coc5O'C3OLET ClC51'C31LET c'l iC3+C +C45+CI6+Ck7+C8+C50+C5 1LET C70=1 .130*C71*C37+1 .0775'C71'C38

LET Ck9C7O-C71RECO 'it C3 0 C3RECO vi' C1t 0 CIRECO v i' C5 0 C5RECO vi' C6 0 C6REDO ' i ' C? 0 C7REdO 'iv C8 0 C8RECO 'iv dO 0 dOREdO vi' Cli 0 CliLET C2O=C+C5+C6+C?+C8LET C21=C3+C10+C11LET C22=C20+C21+C9

JBS vi' 10 C22JBS i' 21 C22

LET C19=C20+C21PLOT C22 C70CORR C22 C70PLOT C22 0 600 C70 0 600

233

Page 265: An evaluation of production output for in situ concrete work

LPLOT C22 0 600 C70 0 600 C2L?LOT C22 0 600 C70 0 600 C12EEGR C22 1 C70NOCORR C22 1 C70PLOT C19 C71CORR C19 C71PLOT C19 0 600 C71 0 600LPLOTCI9O600CIIO600C2LPLOT C19 0 600 C71 0 600 C12RR C19 1 C71CON SREZR C19 1 C71PRINT C19 C71 C22 C70 C37 C38FRD

23 4

Page 266: An evaluation of production output for in situ concrete work

APPENDIX C

BASIC OPERATION TIMES FOR CONCRETE GANGS

235

Page 267: An evaluation of production output for in situ concrete work

APPENDIX C

BASIC OPERATION TIMES FOR CONCRETE GANGS

C.1 INTROTh3CTION

In this appendix, basic operation times are presented for theconcrete operatives. The data for slabs, beams, walls and columnsare presented separately, taking into account the method ofplacement.

The-relevant equations, f or example those relating to slabs, areselected from the generalized concrete model and presented under thefollowing headings:

(a) Fixed Activities;

(b) Variable Activities;

(c) Method Related Activities.

These equations are used to determine basic times for mostconcreting operations. In order to simplify the equations, certainaspects relating to the variable activities were assimied, forexample, all pours were taken to be covered. The times required toclean the shutters prior to concrete placement are also included.

The basic operation times, based on the simplified equations,and a description of each operation are presented under the followingheadings:

(a) Operational Statement;

(b) Method Statement;

(a) Method Description;

Cd) Materials and Tools Required;

Ce) Basic Operation Times (Tables);

(f) Operational Information (Diagrams).

236

Page 268: An evaluation of production output for in situ concrete work

C.2 BASIC OPERATION TIMES FOR CONCRETE ABS

The following equations, obtained frcn the generalized concrete

model presented in Table 5.1$, can be used to calculate the basic

operation times for concreting slabs.

( j) Fixed Activities

CLEAN = 0.00 + 1.000 x APRTOOLS = 11.70 + 0.501 x VPOUR = 51$5 + 1.670 x VSHOVEL = 8.01 + 0.737 x ATAMP = 10.70+ 1.l2OxACLEAR = 6.83 + 0.310 x V

TOTAL = 112.75 + 2.1181 x V + 2.857 x A

(ii) Variable Activities

VIBRATE = 3.116 x VTROVIEL 27.6 + 2.790 x A DOUBLE TRMELTRMEL = 1.510 x A SINGLE TRMLCOVER =8.62+O.861xV+0.2O2xA

(iii) Method Related Activities

CLEAR 9.37 + 0.5119 x V RJMPGERAL = 0.1300 x C1$2 SKIPGENERAL = 0.0175 x C112 DIRECT OR PUMP

When V = VCLUMEA AREA

C112 = JM OF OTHER ACTIVITIES

If a concrete slab requires vibrating, trowelling once and

covering, the basic operation time can be obtained by applying one of

the following equations.

BASIC TINE = (51. 11 + 6.81V + 11.57A) x 1.0175

DIRECT

BASIC TINE (51.11 + 6.81V + 11.57A) x 1.130

SKIP

BASIC TIME (60.7 + 7.36V + 1l.57A) x 1.0175

EU MP

237

Page 269: An evaluation of production output for in situ concrete work

C.2.1 Concrete Slabs Poured Usirg a Crane and Ski D

(i) Ooeration

Pour concrete into a slab using a crane and skip.

(ii) Method

The two main items of work within this operation are thetransportation of concrete by the crane and subsequent placement bythe concrete gang.

(iii) Method Description: Concrete Gang

One man cleans the shutters before the rest of the gang arrives.The tools and work area are prepared before the crane begins totransport the concrete. The concrete is trowelled as workprogresses, but it Is not covered until all the other activities havebeen completed.

(iv) Materials and Tools Required

(a) Shovel(b) Vibrator (+1 on standby)(c) Trowel(d) Tamp(e) Rake(f) Knee Pads(g) Covers(h) CompressorCi) CraneCi) Skip

(v) sic Operation Times

The basic operation times, presented in Table Cl, are forconcrete slabs which require vibrating, trowelling once and covering.

Table Cl Basic Operation Times(mins.)

Vol. Depth (mm)

Cum. 100 150 200 250 300 350 1400 500 750 1000

2.5 205 165 1140 130 120 115 110 105 95 90

5.0 355 269 225 200 180 170 160 150 130 120

10.0 651 1480 395 3110 305 280 265 2140 205 185

15.0 9118 690 560 1185 1130 395 365 330 275 250

20.0 12115 900 730 625 555 505 1170 1170 350 315

25.0 15110 1110 895 765 680 620 575 510 1120 380

30.0 18140 1320 1065 910 805 730 675 600 1495 11145

35.0 2135 1530 123 0 1050 930 8145 780 690 570 510

110.0 21430 17115 11100 1190 105 11 955 882 780 6111 570

238

Page 270: An evaluation of production output for in situ concrete work

0

•_

'1/

Vibrate concrete.

Shovel concrete.

--

Figure Cl:OPERATIONAL INFORM&TION.

Method Statemen.tkThe placement of concreteinto a slab using a craneand skip for sitetransportation.

Fetch and prepare tools.

Clean shutters withairline,

Soak deck with water.

Pour concrete into skip.

Pour concrete into slab.

,_> .-'

Tamp concrete.On wide pours internaltamp supports have to be -, -rnoved. -- -Trowel finish slab. - -This is sometimes omitted - -or done tw ice. ______ -

Cover and protect slabfrom wthør. -

Clean and remove tools. • V

I.'

Page 271: An evaluation of production output for in situ concrete work

C.2.2 Concrete Slabs Poured Using Mobile or Static PLImDS

Ci) Operation

This operation involves pouring concrete slabs using either amobile or static pump.

(ii) Method

The two main items of work within this operation are the pumpingand subsequent placement by the concrete gang.

(iii) Method Description: Concrete Gang

One man cleans the shutters before the rest of the gang arrives.The tools and work area are prepared before starting to pump theconcrete. The concrete is trowelled as work progresses, but is notcovered until all the other activities have been completed.

(iv) Materials and Tools Required

(a) Shovel(b) Vibrator (+1 on standby)(c) TrowelCd) TampCe) Rake(f) Knee Pads(g) Covers(h) Compressor(1) Concrete Pump

Cv) Basic Oneration Times

The basic times presented in Table C2 are for concrete slabswhich require vibrating, trowelling once and covering.

Table C2 Basic Operation Times (mins.)

Vol. Depth (nun)

Cu.m. 100 150 200 250 300 350 1100 500 750 1000

2.5 210 165 1115 135 125 120 115 110 100 100

5.0 351 270 230 2OI 185 175 165 155 1 110 130

10.0 637 1473 390 3110 310 285 270 2115 210 195

15.0 923 677 5514 1180 113 0395 370 330 280 260

20.0 1210 880 715 620 550 505 1170 1120 355 320

25.0 1 1195 108 11 1880 755 675 615 570 510 1130 385

30.0 1780 1290 1O10 895 795 725 670 600 500 1150

35.0 2065 11190 1205 1030 915 835 775 690 570 515

40.0 2350 1695 1365 1170 10110 9115 875 775 6115 580

2110

Page 272: An evaluation of production output for in situ concrete work

Vibrate concrete.

Shovel concrete.

Figure (:OPERATIONAL INFORX&TION.

Method StatementThe placement of concreteinto a slab by eitherstatic or mobile pumps.

Fetch and prepare tools.

Clean shutters withairline.

Soak deck with water.

Pour concrete into pump.

)CD

Pour concrete into slab.

Tamp concrete.On wide pours interrltamp supports have to berenov ed.

Trowel finish slab.This is sometimes omittedor done twice.

Cover and protect slabfrom weather.

Clean and remove tools.

Page 273: An evaluation of production output for in situ concrete work

C.2.3 Concrete Slabs Poured Directly fron a Lorry

(i) Operation

Concrete is poured directly into a slab from ready-mix lorry.

(ii) Method

The two main items of work within this operation are the directpouring of concrete and subsequent placement by the concrete gang.

(iii) Method DescriDtion: Concrete Gang

One man cleans the shutters before the rest of the gang arrives.The tools and work area are prepared before starting to pump theconcrete. The concrete is trowelled as work progresses, but is notcovered until all the other activities have been completed.

(iv) Materials and Tools Required

(a) Shovel(b) Vibrator (+1 on standby)(a) Trowel(d) Tamp(e) Rake(f) Knee Pads(g) Covers(h) Compressor

BasieODeration Times

The basic times presented in Table C3 are I or concrete slabswhich require vibrating, trowelling once and covering.

Table C Basic Ooeration Times (mins.

Vol. Depth (nim)

Cu.m. 100 150 200 250 300 350 1100 500 750 1000--

2.5 195 155 135 120 115 110 105 100 90 85

5.0 338 256 215 190 175 165 155 1110 125 115

10.0 621 p157. 325 290 2T0 250 230 195 180

15.0 9011 660 535 1160 1110 375 350 315 265 2110

20.0 1187 860 695 595 530 1185 1150 1100 335 300

25.0 11170 1060 855 730 650 590 5115 1185 1105 360

30.0 1755 1260 1015 865 770 695 6115 570 1170 1125

35.0 2035 11160 1174 1000 885 805 7110 655 5110 1185

110.0 2320 1660 1335 1135 1005 910 8110 7110 610 51j5

2112

Page 274: An evaluation of production output for in situ concrete work

Figure C:OPERATIONAk INFORX&TIOL

Nethod Statement:The direct placement ofconcrete into a slab froma ready-mix lorry.

Fetch and prepare tools.

Clean shutters withairline.

Soak deck with water.

Pour concrete into slab.

Vibrate concrete.

Shovel concrete.

Tamp concrete.On wide pours internal ______ ________tamp supports have to bernove d.

Trowel finish beam.This is sometimes omitted ___________or done twice. __________

Cover and protect slabfrom weather.

Clean and remove tools.

Page 275: An evaluation of production output for in situ concrete work

C.3 BASIC OPERATION TIMES FOR CONCRETE BEAKS

The following equations, derived from the generalized concrete

model presented in Table 5.11, can be used to calculate the basic

operation times for concreting beams.

(i) Fixed Activities

CLEAN 5.00 + 1.500 xVPETOOLS 11.70 + 0.501 x VPOUR = 16.10+ 1.180 xVSHOVEL = 8.01 + 0.737 x ATAMP 10.70 + 1.120 x ACLEAR = 6.83 + 0.310 x V

TOTAL = 58.1(0 + 3.1191 x V + 1.857 x A

(ii) Variable Activities

V]BRATE = 5.69 x VTRO,IEL = 27.6 + 2.790 x A DOUBLE TRO,4ELTRO.1EL 1.510 x A SINGLE TROIELCOVER = 8.62 + 0.861 x V + 0.202 x A

(iii) Method Related Activities

CLEAR = 9.37 + 0.5119 x V PUMPGENERAL 0.1300 x C112 SKIPGENERAL = 0.0175 x C112 DIRECT OR PUMP

When V = VOLUMEA=AREA

0(2 = JM OF OTHER ACTIVITIES

If a concrete beam requires vibrating, trowelling once and

covering, the operation basic time can be obtained by applying one of

the following equations.

BASIC TIME = (67.0 + 10.0kV + 3.57A) x 1.0175

DIRECT

BASIC TIME = (67.0 + 10.0kV + 3.57A) x 1.130

SKIP

BASIC TIME (76.11 + 1O.59V + 3.57A) x 1.0175

PUMP

21111

Page 276: An evaluation of production output for in situ concrete work

C. 3.1 Concrete Beams Poured Using a Crane and SkiD

(i) perat1on

This operation involves pouring concrete into beams, using acrane and skip.

(ii) Method

The two main Items of work within this operation are thetransportation of concrete by the crane and subsequent placement bythe concrete gang.

(iii) Method DescriDtion! Concrete Gang

One man cleans the shutters before the rest of the gang arrives.The tools and work area are prepared before the crane begins totransport the concrete. The concrete is trowelled as work progressesbut is not covered until all the other activities have been completed.

(iv) Materials and Tools Reouired

(a) Shovel(b) Vibrator (+1 on standby)Ce) TrowelCd) TampCe) Rake(f) Knee Pads(g) Covers(b) Compressor(i) CraneCi) Skip

(v) Basic Oneration. Times

The basic operation times, presented in Table dl, are f' orconcrete beams which ruire vibrating, trowelling once and covering.

Table C Basic ODeratIonTimes (mins.)

Vol. Area (Sq. in.)

Cu.m 2 i 6 8 10 15 20 25 30

2 106 115 125 130 1110 160 180 200 220

11 130 135 145 155 160 180 200 220 2110

6 150 160 170 175 185 205 225 2115 265

8 175 185 190 200 205 225 2115 210 285

10 195 205 215 220 230 250 210 290 310

12 220 230 235 2115 250 215 290 315 335

111 2115 250 260 265 275 295 315 335 355

16 265 275 280 290 300 320 3110 360 380

18 290 295 305 310 320 3110 360 380 1100

20 310 320 325 335 3115 365 385 1105 1125

2l5

Page 277: An evaluation of production output for in situ concrete work

Figure C:

OPERATIONAL INFORMATION -.

Method Statement:The placement of concreteinto a beam using a craneand skip for sitetransportation.

Soak beam with water.

::: ::::::: :::: ::______________________

Tamp concrete.

Trowel finish beam. //W //" 4///AV ?"This Is sometimes omitted

Cover and protect beamfrom weather.

Cl ean and rem ave tool s.

( -L/ /

Page 278: An evaluation of production output for in situ concrete work

C.32 ConereteBeams Poured Using Mobile or Static Pumns -

(i) ODeration

This operation involves pouring concrete beams, using either amobile or static pump.

(ii) Method

The two main items of work within this operation are the pumpingof concrete and subsequent placement by the concrete gang.

(iii) Method T)escrlDtion: Concrete Gang

One man cleans the shutters before the rest of the gang arrives.The tools and work area are prepared before starting to pump theconcrete. The concrete is trowelled as work progresses, but is notcovered until all the other activities have been completed.

(iv) Materials and Tools Required

(a) Shovel(b) Vibrator (+1 on standby)(C) Trowel(d) Tamp(e) Rake(f) Knee Pads(g) Covers(h) Compressor(1) Concrete Pump

(v) Basic ODeration Times

The basic operation times, presented in Table C5, are forconcrete beams which require vibrating, trowelling once and covering.

Table C5 Basic Operation Times (sins.)

Vol. Area (Sq. m.)

Cu.m 2 14 6 8 10 15 20 25 30

2 110 120 130 135 1i5 165 180 200 220

II 135 1115 150 160 165 185 205 225 21156 160 165 175 180 190 210 230 2115 265

8 180 190 195 205 210 230 250 270 29010 205 210 220 230 235 255 275 295 310

12 225 235 2110 250 260 275 295 315 335

114 250 260 265 275 280 300 320 3110 36016 275 280 290 295 305 325 3110 360 380

18 295 305 310 320 325 3115 365 385 1105

20 320 325 335 3110 350 370 385 1405 1125

2117

Page 279: An evaluation of production output for in situ concrete work

Figure Oi:OPERATIONAL INFORMATION.

Method Statement:The placement of' concreteinto a beam by eitherstatic or mobile pumps.

Fetch and prepare tools.

t

h1c r. _____________

Pour' concrete into pump.

Pour concrete 1. nto beam.

Vibrate concrete.

Shovel concrete.i/

/

Tamp concrete.On wide pours internaltamp supports have to be

/

omitted __/

Cover and protect beam r .from weather.

C]. ean and remove tool s.

Page 280: An evaluation of production output for in situ concrete work

C.3.3 porete Beams Poured Direetly from a Lorry

(i) ODeration

Concrete is poured directly into a beam from ready-mix lorry.

(ii) Method

The two main items of work within this operation are the directpouring of concrete and subsequent placement by the concrete gang.

(iii) Method Description: Concrete Gang

One man cleans the shutters before the rest of the gang arrives.The tools and work area are prepared before starting to pump theconcrete. The concrete is trowelled as work progresses, but is notcovered until all the other activities have been completed.

(iv) Materials and Tools Req uire

(a) Shovel(b) Vibrator (+1 on standby)(c) Trowel(d) TampCe) Rake(f) Knee Pads(g) Covers(h) Compressor

(v) Basic Oneration Times

The basic operation times, presented in Table C6, are f orconcrete beams which require vibrating, trowelling once and covering.

Table C6 Basic Operation !imes (mins.)

Vol. Area (Sq. m.)

Cu.m 2 11 6 8 10 15 20 25 30

2 100 110 115 125 130 150 170 190 2101$ 123 130 1IO 15 155 175 190 210 2306 1t5 15O 160 170 175 195 215 235 2558 165 175 180 9O 195 215 235 255 27510 190 195 205 210 220 2W 255 275 29512 210 220 225 230 21O 260 280 300 31511 230 210 245 255 260 280 300 320 31016 250 260 270 275 285 305 320 310 36018 215 280 290 300 305 325 315 365 38020 295 305 310 320 325 3115 365 385 1105

219

Page 281: An evaluation of production output for in situ concrete work

IHFOEMATIOL

Method Statement:The di.rect placement of C 91concrete into: beam from -

1 5'1j • '•ISoak beam with water.

C'Pour concrete into beam.

eNTamp concrete.On wide pours internal

have to1.

Trowel finish beam. -Thisissonietimesomitted .

/

Cover and protect beam

tools.

Page 282: An evaluation of production output for in situ concrete work

C 11 BASIC OPERATION TIMES FOR CONCRETE WALLS

The following equations, obtained from the generalized concrete

model presented in Table 5 .k, can be used to calculate the basic

operation times for concreting walls.

(1) Fixed Activities

CLEAN = 5.00+ 1.500xVPRTOOLS 11.70 + 0.501 x VPJR = 16.10+ 1.l8OxV&IOVEL = 8.01 + 0.737 x ATAMP = 10.70 + 1.120 x ACLEAR = 6.83 + 0.310 x V

TOTAL = 58. 1 O + 3 .k91 x V + 1 .857 x A

(ii) Variable Activities -

VIBRATE = 5.69 x VTRCI,IEL = 27.6 + 2.790 x A DOUBLE TRCMELTRiEL = 1.510 x A SINGLE TRYV1ELCOVER = 8.62+O.861xV+0.202xA

(iii) Method Related Activities

CLEAR = 9.37 + O.519 x V

RJ MPGENERAL = 0.1300 x C1t2

SKIPGENERAL = O.Clj75 x C'2

DIRECT OR HJMP

When V = VOLUMEA: AREA

Ck2 = JM OF OTHER ACTIVITIES

If a concrete wall requires vibrating, trowelling once and

covering, the basic operation times can be obtained by applying one

of the following equations.

BASIC TIME = (67.0 + 10.04V + 3.57k) x 1.0175

DIRECT

BASIC TIME = (67.0 + 1O.04V + 3.57k) x 1.130

SKIP

BASIC TIME = (76.k + 1O.59V + 3.57k) x 1.0175

EU MP

251

Page 283: An evaluation of production output for in situ concrete work

C.1$.1 Concrete Walls Poured Usin a Crane and SkiD

(1) Operation

This operation involves pouring concrete into walls, using acrane and skip.

(ii) Method

The two main items of work within this operation are thetransportation of concrete by the crane and subsequent placement bythe concrete gang.

(iii) Method Description: Concrete Gang

One man cleans the shutters before the rest of the men arrive.The tools and work area are prepared before the crane begins totransport the concrete. The concrete is trowelled as workprogresses, but is not covered until all the other activities havebeen completed.

(iv) Materials and Tools Required

(a) Shovel(b) Vibrator (+1 on standby)(c) TrowelCd) Tamp(e) • Rake(f) Knee Pads(g) Covers(h) Compressor(1) Crane(j) Skip

(v) Basic peration Times

The basic operation times, presented in Table C7, are forconcrete walls which require vibrating, trowelling once and covering.

Table C7 Basic Operation Times (mine.)

Volume. Area (Sq. in.)

Cu.m. 0.5 1.0 2.0 3.0 14.0

20 100 100 105 110 1152.5 105 110 110 115 120

3.0 110 115 120 120 125125 125 130 135 135

5.0 1314 135 1140 1145 150

7.5 160 165 170 170 175

10.0 190 195 197 200 20515.0 2145 250 255 260 260

20.0 305 305 310 315 320

25.0 360 365 365 370 375

252

Page 284: An evaluation of production output for in situ concrete work

Figjire CT:OPEE&TIONM.. INFORMATION.

Method StatementThe placement of concreteinto a wall using a craneand skip for sitetransportation.

Fetch and prepare tools.

Clean shutters withai. ri I ne.

Soak wall with water.

Pour concrete into skip.

Pour concrete into wall.

Vibrate concrete.

Shovel concrete.

Tamp concrete.On wide pours internaltamp supports have to bereinov ed.

Trowel finish wall.This is sometimes omittedor done twice.

Cover and protect wallfrom weather.

Clean and remove tools.

• •••

Hf -

vLrV(Lv-llv2"----

-••.

ILfrELE

\\ Ifsly'

Page 285: An evaluation of production output for in situ concrete work

C. l .2 Concrete Walls Poured Us1n Mobile or Static Pumps

Ci) oeration

This operation involves pouring concrete walls using either amobile or static pump.

(ii) Method

The two main items of work within this operation are the pumpingof concrete and subsequent placement by the concrete gang.

(iii) Method Descriotion: Concrete Gang

One man cleans the shutters before the rest of the gang arrives.The tools and work area are prepared before starting to pump theconcrete. The concrete is trowelled as work progresses, but is notcovered until all the other activities have been completed.

(iv) Materials and Tools Required

(a) Shovel(b) Vibrator (+1 on standby)(a) Trowel(d) TampCe) RakeCt) Knee Pads(g) Covers(h) Compressor(1) Concrete Pump

Cv) Basic Operation Times

The basic operation times, presented in Table C8, are forconcrete walls which require vibrating, trowelling once andcovering.

Table C8 Basic Operation Times (mins.)

Volume Area (Sq. m.)

Cu.m. 0.5 1.0 2.0 3.0

2.0 105 110 110 115 120

2.5 110 115 120 122 125

3.0 120 120 125 130 130130 130 135 1O 1k5

5.0 11O 1l5 15 150 155

7.5 170 170 175 180 180

10.0 200 200 205 208 210

15.0 255 255 260 265 270

20.0 310 315 320 320 325

25.0 370 370 375 380 385

25

Page 286: An evaluation of production output for in situ concrete work

1Iii/Y1=iki /

Figure C8:OPERATIONAL INFORMATION.

}jethod StatementThe p1 aceni ent of coerteinto a wall by eitherstatic or mobile pumps.

Fetch and prepare tools.

Clean shutters withairli ne.

Soak wall with water.

Pour concrete into pump.

Pour concrete into wall.I

Vibrate concrete.

Shovel concrete.

Tamp concrete.On wide pours interrltamp supports have to bereinov ed.

Trowel finish wall.This is sometimes omittedor done twice.

Cover and protect wallfrom weather.

Clean and remove tools.

iii'=fl;T! /

Page 287: An evaluation of production output for in situ concrete work

C.5 BASIC OPERATION TIMES FOR CONCRETE COLUMNS

The following equations, obtained from the generalized concrete

niodel presented in Table 5.1, can be used to calculate the basic

operation times for concreting colns.

(i) Fixed Activities

CLEAN = 5.00 + 1 .500 x VPRTOOLS = 11.70 + 0.501 x VPOUR = '1.79 + 9.650 x VSHOVEL = 8.07 + 0.737 x ATAMP = 10.70 + 1.120 x ACLEAR = 6.83 + 0.310 x V

TOTAL = 17.09 + 11.96 x V + 1.857 x A

(ii) Variable Activities

VIBRATE = 22.80 x VTROWEL = 27.60 + 2.790 x A DOUBLE TROWELTROWEL = 1.510 x A SINGLE TROWELCOVER = 8.62 + 0.861 x V + 0.202 x A

(iii) Method Related Activities

CLEAR 9.37 + 0.5119 x V FUMPGENERAL = 0.1300 x C112 SKIPGENERAL 0.0775 x C'12 DIRECT OR PUMP

When V VOLUMEA = AREA

C112 JM OF OTHER ACTIVITIES

For concrete columns which require vibrating, trowelling once

and covering, the basic operation times can be obtained by applying

one of the following equations.

BASIC TIME = (55.7 + 35.62V + 3.57A) x 1.0775

DIRECT

BASIC TIME = (55.7 + 35.62V + 3.57A) x 1.130

SKIP

BASIC TIME = (65.1 + 36.17V + 3.57A) x 1.0775

PUMP

256

Page 288: An evaluation of production output for in situ concrete work

C.5.1 Conoret& Coltna Poured Using a. Crane and Skip

(i) operation

This operation involves pouring concrete into columns, using acrane and skip.

(ii) Method

The two main items of work within this operation are thetransportation of concrete by the crane and subsequent placement bythe concrete gang.

(iii) Method Description! Concrete Gang

One man cleans the shutters before the rest of the gang arrives.The tools and work area are prepared before the crane begins totransport the concrete. The concrete is trowelled as workprogresses, but is not covered until all the other activities havebeen completed.

(iv) Materials and Tools Required

(a) Shovel(b) Vibrator (+1 on standby)(c) TrowelCd) Tamp(e) Rake(f) Knee Pads(g) Coy er S(h) Compressor(i) Crane(j) Skip

Cv) Basic. Operation Tines

The basic operation times, presented in Table C9, are forconcrete columns which require vibrating, trowelling once andcovering.

Table cq Basic Oneration Times (mins.)

Volume First SubsequentCu. m. Pour Pours

0.50 85 70

0.75 95 80

1.00 105 90

1.50 125 110

2.00 15 130

2.50 165 150

3.00 185 170

3.50 205 190

iI.00 225 210

.5O 25 230

257

Page 289: An evaluation of production output for in situ concrete work

Pour concrete into skip.

iI

Pour concrete intocol mn.

Vibrate concrete.

Shovel concrete.

Tamp concrete.

Trowel finish column.This is sometimes omittedor done twice.

'2'

Figure C9:OPERATIONAL INFORI1ATIOL

Method StaterrLexitThe placement of concreteinto a column using acrane and skip for sitetransportation.

Fetch and prepare tools.

Clean shutters withairline.

Soak column with water.

Cover and protect columnfrom weather.

Clean and remove tools.

Page 290: An evaluation of production output for in situ concrete work

C.5.2 Concrete Columns Poured Using Mobile or Static Pumos

(i) Ooeration

This operation involves pouring concrete columns, using either amobile or static pump.

(ii) Method

The two main items of work within this operation are the pumpingof concrete and subsequent placement by the concrete gang.

(iii) Method Deseriotion: Concrete Gang

One man cleans the shutters before the rest of the gang arrives.The tools and work area are prepared before starting to pump theconcrete. The concrete is trowelled as work progresses, but is notcovered until all the other activities have been completed.

(iv) Materials ai Tools Required

(a) Shovel(b) Vibrator (+1 on standby)(c) Trowel(d) Tamp(e) Rake(f) Knee Pads(g) Covers(h) Compressor(1) Concrete Pump

(v) Basic Operation Times

The basic operation times, presented in Table ClO, are forconcrete columns which require vibrating, trowelling once andcovering.

Table ClO Basic Operation Times (sins.)

Volume First SubsequentCu. m. Pour Pours

0.50 90 70

0.75 100 80

1.00 110 90

1.50 130 120

2.00 150 1302.50 170 150

3.00 185 1653.50 205 185

225 205

2115 225

259

Page 291: An evaluation of production output for in situ concrete work

Figure Cl 0: 1 _-4FTOPERATIONAL INFORMATION.

Method StatementThe placement of concreteinto a column by eithersta tic or mobil e pum ps. - :.

Fetch and prepare tools. "

Clean shutters withairline.

Soak column with water.

Pour concrete into pump.

Pourco ncr ete into

Vibrate concrete.

Shovel concrete.

Tamp concrete.

Trowel finish col urn rThis is sometimes omitted ___ =or done twice.

Cover and protect. columnfrom weather.

Clean and remove tool

Page 292: An evaluation of production output for in situ concrete work

APPENDIX D

OMFUTER PRINT-cUTS

26 1

Page 293: An evaluation of production output for in situ concrete work

APPENDIX_D

COMPUTER PRINT-CUTS

D. 1 SELECTED PRINT-CUTS IRON ANALYSIS PROGRAMS

This appendix contains a selection of computer print-outs

obtained during the analysis which is presented in Chapter Five. The

first two selected print-outs were obtained during the analyses of

the times taken to prepare tools and tamp the concrete. In the

analysis, the results extrapolated from these two print-outs were

combined with the results from six other programs and used to

construct the generalized model. Once this model was constructed

four more programs were used to test the predicted durations with the

measured durations. The print-outs from three of these four programs

('TESTl.MINEXEC', 'TEST2.MINEXEC' and 'TEST3.MINEXEC') are also

included in this appendix.

262

Page 294: An evaluation of production output for in situ concrete work

NE THODPR TOOL SPOURVIBRATESHOV ELTAMPTRCMELGENERALCL TOOL SCCV ERTYPEVOLUMEWIDTHLENGTHAREADEPTH

TYPE VOLUME WIDTH LENGTH AREA

-0.363-0.623-O .3112-0.5270.796

0.6514

0.570 0.157

0.831 0.888 0.1171-0.116 -0.521 -0.307 -0.1450

MS= SS/DF

F-RATIO

11127. 5.791923.

D. 1.1 Print-Out from Analysis of Preparing Tools

MINITAB RELEASE 81.1 " COPYRIGHT - PENN STATE UNIV. 1981APRfl 2k, 1986 '* Loughborough Uriiversity,of Techno1orSTORACE AVAILABLE 150000

-- RETR 'data'

-- CONST

-- CORR C1-C17

TEST METHOD PETOOLS POUR VIBRATE0.1169

-0.161 0.203

0.175 0.189 0.300

0.072 0.292 0.5110 0.787

0.060 0.11k 0.262 0.630 0.60k

0.1511 0.135 0.233 O.7 J16 0.585

0.186 0.0 141 0.05k 0.532 0.11811

0.031 0.129 0.2111 0.80k 0.639

0.2 111 0.068 -0.028 0.781 0.633

0.11116 0.503 0.1183 0.619 0.627

0.200 0.08? -0.172 -0.160 -0.099

0.12k 0.179 0.503 0.795 0.8111-0.002 -0.019 0.200 0.517 0.372

0.015 o.Okk 0.577 0.1103 0.1173

0.158 0.123 0.368 0.661 0.591

-0.010 0.1117 0.081 -0.0113 0.192

SHOV EL

0.8200.7590.61180.6090.7 511

-0.5570.7860.7 91O.k 9110.889

-0.1186

TAMP TROvIEL

0.86 0

0.806 0.582

0.778 0.0914

0.655 0.6380.51lk -0.399

0.807 0.572

0.838 0.530

0.1120 0.1155

0.928 0.831-0.11111 -0.356

CL TOOL SCCV ERTYPEVOL UNEWIDTHLENGTHAREADEPTH

GENERAL CLTOOLS COVER0.8111

0.693 0.O146-0.397 -0.266 -0.329

0.695 0.731 0.716

0.662 . 0.6112 0.317

0.271 0.2118 0.535

0.693 0.660 0.669-0.2116 -0.208 -0.225

-_ ONEWAY C16 C2

ANALYSIS OF VARIANCE

LJEW DF SSFACTOR 3 33381.ERROR 66 126916.TOTAL 69 160297.

263

Page 295: An evaluation of production output for in situ concrete work

LEWL N MEAN ST. DEV.1 12 24.8 19.12 14 11.9 15.53 15 75.2 66.2LI 29 31.3 115.7

POOLED ST. DEV. = 43.9

INDIVIDUAL 95 PERCENT C. I. FOR LEVEL MEANS(BASED ON POOLED STANDARD DEVIATION)

4-.--------4---------4 --------4 --------4 --------4 --------+12 -3

+---------4---------4------------------1---------4--------- +-20. 0. 20. 110. 60. 80. 100.

-- ONEWAY C17 C2

ANALYSIS OF VARIANCE

JXJETO DF SSFACTOR 3 38.07ERROR 66 212.40TOTAL 69 250.47

)=SS/DF F-RATIO12.69 3.94

3.22

LEVEL N MEAN ST. DEV.1 12 0.61 0.592 14 2.37 1.973 15 0.59 0.96

29 1.94 2.28

POOLED ST. DEV. 1.79

INDIVIDUAL 95 PERCENT C. I. FOR LEVEL MEANS(BASED ON POOLED STANDARD DEVIATION)

I---------4---------4 --------4---------4---------4---------+1 I**********I***********1I2 - - I***********I***********I3

+---------4---------4---------_4-.--------4---------4--------- +-0.80 0.00 0.80 1.60 2.40 3.20 4.00

-- ONEWAY C13 C2

ANALYSIS OF VARIANCE

L*JETO DF SSFACTOR 3 1957.ERROR 66 11704.TOTAL 69 13661.

45= S/DF

F-RATIO

652. 3.68177.

264

Page 296: An evaluation of production output for in situ concrete work

LEVEL N MEAN ST. DEV.1 12 10.9 6.32 14 5.0 5.43 15 21.0 17.34 29 14.2 15.5

POOLED ST. DEV. = 13.3

INDIVI]XJ.AL 95 PERCENT C. I. FOR LEVEL MEANS(BASED ON POOLED STANDARD DEVIATION)

---4---------4---------4---------4 --------4---------+1 I**a*******I**ft*******I231!

+---------4---------+---------4---------4---------4--------- +

-7.0 0.0 7.0 9.0 21.0 28.0 35.0

-- ONEWAY C16 C12

ANALYSIS OF VARIANCE

D(JETO DF

SS

MS=SS/DF F-RATIO

FACTOR 3

48779. 16260. 9.62ERROR 66

111518. 1690.TOTAL 69

160297.

LEVEL N MEAN ST. DEV.

1 41 57.7 52.62 6 14.4 11.03 9 2.84 14 0.5 O.k

POOLED ST. DEV. = 41.1

INDIVIL1JAL 95 PERCENT C. I. FOR LEVEL MEANS

(BASED ON POOLED STANDARD DEVIATION)+---------4---------4---------4---------4---------4---------+

1 I******I*****I23ii

+---------4--------4---------4---------4---------4--------- +-40. -20. 0. 20. 110. 60. 80.

-- ONEWAY C17 C12

ANALYSIS OF VARIANCE

L(JETO DF SS

FACTOR 3 187.984ERROR 66 62.485TOTAL 69 250.469

45= SS/DF

F-RATIO

6 2.66 1

66.190.947

265

Page 297: An evaluation of production output for in situ concrete work

LEVEL N MEAN ST. DEV.I 141 0.335 0.3112 6 0.633 0.141493 9 14.306 2.13614 114 3.518 1.2714

POOLED ST. DEV. = 0.973

INDIVJ:t*JAL 95 PERCENT C. I. FOR LEVEL MEANS(BASED ON POOLED STANDARD DEVIATION)

4. --------I---------4.---------+----------+---------4 --------+1 I'II2 I*ft*I*I

3I****I****I

+---------4---------4--------4---------4-.--------4---------+-1.0 0.0 1.0 2.0 3.0 14.0 5.0

-- ONEdAY C13 C12

ANALYSIS OF VARIANCE

WETO DF SSFACTOR 3 27214.ERROR 66 10937.TOTAL 69 13661.

tS= SS/DF

F-RATIO908. 5.148

166.

LEVEL N

MEAN

ST. DEN.1 141

16.9

15.72 6

9.2

7.63 9

17.7

9.814 lIt

1 .6

1.1

POOLED ST. DEV. = 12.9

INDIVIWAL 95 PERCENT C. I. FOR LEVEL MEANS(BASED ON POOLED STANDARD DEVIATION)

•1---------4.---------4.---------4---------4.---------4. --------+1 - I***'*I*'***I2 I" * * * * * *** ** * ft ]** * ** ft ft *******

3 - i*i''*i14

--------4---------4---------4---------4---------+-7.0 0.0 7.0 14.0 21.0 28.0 35.0

-- OMIT '' C3 C2 , C63 C62

-- ONEAY C63 C62

ANALYSIS OF VARIANCE

DUETO DF SSFACTOR 3 661.ERROR 149 8352.TOTAL 52 9013.

MSSS/DF F-RATIO

220. 1.29170.

266

Page 298: An evaluation of production output for in situ concrete work

LEVEL N

MEAN ST. DEV.1 6

9.3 6.112 12

16.5 9.23 12

21.6 10.611 23

19.1 16.5

POOLED ST. DEV. = 13.1

INDIVIDUAL 95 PERCENT C. I. FOR LEVEL MEANS(BASED ON POOLED STANDARD DEVIATION)

4---------4---------4---------4---------4---------4---------+1 I***ftftftft*ft*****I*ftftftaftftftft**ftftft*I2 -

311

+---------4---------9 --------4------------------4-------- +-7.0 0.0 7.0 111.0 21.0 28.0 35.0

-- PLOT C3 C13PR TOOL S60.+ *

- * ft*

- * ** *- ft- ft

20.+ • 2 2 2 ft

-11- ft ft- 2 2- ft

- 2 * ft

0.+ 22-4----------4----------I---------4--------- -i-VOLUME

0. 15. 30. 115. 60. 75.

17 MISSING CESERVATIONS

267

Page 299: An evaluation of production output for in situ concrete work

-- PLOT C3 C16PR TOOL S60.+ *

_* *ft *

3-a-a

20.+ 2' ft 3*1 *- lj• * ** *_42** 2 '-ft- 22

0.+ 32+---------+AREA

0. 80. 160. 240. 320. 400.

17 MISSING CESERVATIONS

-- LPLOT C3 C13 C2PR TOOL S60.+ D

- D CBDD D

- D CC C-B- B

20.+ D2C 2D 2 C-4DB C D- 4DAB 2 A 2-c- 2 A A

0.+ 22D+---------+ --------+ --------+---------+---------+V0LU}0. 15. 30. 45. 60. 75.

17 MISSING CSERVATIONS

268

Page 300: An evaluation of production output for in situ concrete work

A

-9----------4---------+VOLUME115. 60. 75.

-- LFLOT C3 Ci6 C12PR TOOL S60.+ A

-c AA A

-D 3-c-D

20.^ 2A A 3AA A- AAA A-42AA 2 AA-D- 22

0.+ 32.1------------------4---------4--------- +AREA

0. 80. 160. 240. 320. 1100.

17 MISSING CESERVATIONS

-- LFLOT C3 C13 C12PR TOOL S60.+ A

- C ACCA

- D AA A-c- D

20.+ A2A 2A 2 A-4AA A A- JIAAA 2 A 2-D- 2 B B

0.+ 22A+---------4---------4-------0. 15. 30.

17 MISSING CSERVATIONS

-- OMIT '' C3 C2 , C63 C62

-- ONEWAY c63 C62

ANALYSIS OF VARIANCE

DUE TO DF SS MS=SS/DF F-RATIOFACTOR 3 661. 220. 1.29ERROR 49 8352. 170.TOTAL 52 9013.

269

Page 301: An evaluation of production output for in situ concrete work

LEVEL N

MEAN ST. DEV.1 6

9.3 6.112 12

16.5 9.23 12

21.6 10.611 23

19.1 16.5

POOLED ST. DEV. 13.1

INDIVIDUAL 95 PERCENT C. I. FOR LEVEL MEANS(BASED ON POOLED STANDARD DEVIATION)

•1- --------4.---------4---------1---------4----------I.---------+

1 Ia*************I*a**a*•******ft*I2 I***u***a*I****a**a*I

311

+---------4---------+---------4'.--------4.'.--------+-..-------+

-7.0 0.0 7.0 1l.0 21.0 28.0 35.0

-- CORR C3 C13CORRELATION OF PRTOOLS AND VOLUME = 0.503

-- RE)3R C3 1 C1353 CASES USED17 CASES CONTAINED MISSING VALUES

THE REX)RESSION FUATION ISY = 11.7 + 0.501 Xl

COLU) COEFFICIENT-- 11.712

Xl VOLUME 0.5005

ST. DEV. T-RATIO =

OF COEF. COEF/S.D.

2.182 5.37

0.1203 4.16

THE ST. DEV. OF Y ABCUT RE13RESSION LINE ISS = 11.119WITH C 53- 2) = 51 DEGREES OF FREEDOM

R-3UARED = 25.3 PERCENTR-UARED = 23.9 PERCENT, ADJUSTED FOR D.F.

ANALYSIS OF VARIANCE

DUETO DF

SS MS=SS/DFREGRESSION 1

2282.6 2282.6RESIDUAL 51

6730.4 132.0TOTAL 52

9013.0

Xl Y PRED. Y ST.DEV.

RCM VOLUME PRTOOLS VALUE PRED. Y RESIDUAL

25 66.0 * 114.75 6.63 *

42 34.0 60.00 28.73 3.03 31.27

115 65.0 40.00 44.24 6.51 11.24

63 37.0 45.00 30.23 3.311 111.77

67 41.0 15.00 32.23 3.77 -17.23

R DENOTES AN (ES. WITH A LARGE ST. RES.X DENOTES AN (ES. WHOSE X VALUE GIVES IT LARGE INFLUEJCE.DURBIN-WATS STATISTIC 1.48

ST. RES.ax

2.82R0.115 X1.311 X

-1.59 X

270

Page 302: An evaluation of production output for in situ concrete work

-- MEAN C3AVERAGE = 17 .981

-- L0T C3 C16 C2PR TOOL S60.+ D

-D CJi0.+DB D D

-D 3-B-B

20.+2DA 3CD C..lj DBC D-II2AB 2 CC-C- 22

O.+ 32-4----------1---------4---------4-------- ..^AREA

0. 80. 160. 210. 320. kO•

17 MISSING SERVATIONS

-- RFJ3R C3 2 C13 C1653 CASES USED17 CASES CONTAINED MISSING VALUES

THE RRE.SSION UATION ISY 11.8 + 0.5811 Xl -0.03115 X2

ST. DEV.COLUMN COEFFICIENT OF COEF.-- 11.792 2.2011

Xl VOLUME 0.58115 0.20111X2 AREA -O.O3451 0.067118

THE ST. DEV. OF Y ABQJT R&3R&SSION LINE ISS 11.57WITH ( 53- 3) 50 DEGREES OF FREEDOM

R-UARED = 25.7 PERCENTR-UARED = 22.7 PERCENT, ADJUSTED FOR D.F.

ANALYSIS OF VARIANCE

T-RATXO =COEF/S. D.

5.352.86

-0.51

DUE TO DF SS MS=SS/DFREGRESSION 2 2317.6 1158.8RESIDUAL 50 6695.11 133.9TOTAL 52 9013.0FURTHER ANALYSIS OF VARIANCESS EXPLAINED BY EACH VARIABLE WHEN ENTERED IN THE ORDER GIVEN

DUETO DF SS

R&RESSION 2 2317.6VOLUME 1 2282.6AREA 1 35.0

211

Page 303: An evaluation of production output for in situ concrete work

Xl Y PRED. Y ST.DEV.R VOLUME PRTOOLS VALUE PIlED. I RESILUAL

16 23.2 45.00 25.25 4.30 19.7520 23.2 110.00 25.25 4.30 14.7522 23.2 20.00 25.25 4.30 -5.2525 66.0 * 40.53 10.60 *26 23.2 20.00 25.25 4.30 -5.2529 28.5 * 28.11 4.87 a

42 34.0 60.00 28.32 3.15 31.68115 65.0 40.00 43.78 6.62 -3.7867 41.0 15.00 31.06 4.1111 -16.06

R DENOTES AN OHS. WITH A LARGE ST. RES.X DENOTES AN OHS. WHOSE X VALUE GIVES IT LARGE INFLUEJCE.

rAJIN-WATsON STATISTIC: 1.47

ST. RES.1.8 11 X1.37 X

-0.49 Xax

-0.49 Xax

2.85R-0.40 X-1.50 X

-- CORR C3 C13 C16

PRTOOLS VOLUMEVOLUME 0.503AREA 0.368 0.831

-- LET C30=C3/C13-_ OMIT 'a' C30 C2 , C90 C62-- ONEWAYC9O C62

ANALYSIS OF VARIANCE

IXJETO DF SSFACTOR 3 208.9ERROR 119 898.1TOTAL 52 1107.0

MS=SS/DF F-RATIO

69.6 3.8018.3

LEVEL N MEAN ST. DEV.1 6 1.17 1.2112 12 7.19 5.713 12 2.84 2.63

23 2.87 4.55

POOLED ST. DEV. = 11.28

INDIVILUAL 95 PERCENT C. I. FOR LEVEL MEANS(BASED ON POOLED STANDARD DEVIATION)

4---------+---------•1• -------- .1 --------4 --------.4-.--------+

12 -

311 - -

+---------4 -----...4---------4---------4---------.4-.--------+

-2.5 0.0 2.5 5.0 7.5 10.0 12.5

272

Page 304: An evaluation of production output for in situ concrete work

-- TABLE C2 C12;-- DATA C3;-- MEANS C3.

RCMS: METhOD COLUMNS: TYPE

1 2 3 Il ALL

21 .000 5.000 -- -- --

11.000 5.000 -- --

11.000 -- --

10.000 -- --

11.500 5.000 -- -- 9.333

2 15.000 -- 29.000 16.000 --

5.000 -- 38.000 12.000

11.000 -- 10.000

-- 10.000

-- 15.000

-- 15.000

-- 22.000

10.333 -- 33.500 111.286 16.500

3 30.000 -- -- 9.000 --

30 . 000 -- --

30 . 000 -- --

20.000 -- --

20.000 -- --

20.000 -- --

10.000 -- --

10.000 -- --

15.000 -- --

20.000 -- --

115.000 -- --

22.727 -- -- 9.000 21 .583

14 10.000 -- 115.000 30.000 --

15.000 -- 110.000 10.000

0.000 -- 20.000 0.000

20.000 -- 20.000 0.000

60.000 -- 0.000 15.000

110.000 -- 0.000

110.000 --

20.000 --

10.000 --

10.000 --

20.000 --

15.000 --

21.667 -- 25.000 9.167 19.130ALL ---- -- -- --

19.567 5.000 27.1129 11.71 11 17.981

CELL CONTENTS --PRTOOLS:DATA

MEAN

273

Page 305: An evaluation of production output for in situ concrete work

-- CHOOSE I C12 C3 C13 , C21 C22 C23

-- PLOT C22 C23C 2260.+

- a,,

20.+ *2 2

- a-, -a- *** 2

*

aa

*

**

' 2

- 2*

----+---------+---------+---------+- -------- +C230. 15. 30. l5. 60. 75.

11 MISSING (ESERVATIONS

--RB3RC221C2330 CASES USED11 CASES CONTAINED MISSING VALUES

THE RE3RESSION UATION ISY = 12.6 + 0.1122 Xl

ST. DEV. T-RATIO

COLUMN COEFFICIENT OF COEF. COEF/S.D.-- 12.605 3.312 3.81

Xl C23 0.11223 0.1516 2.79

THE ST. DEV. OF Y ABQJT REX]RESSION LINE IS S = 11.90WITH ( 30- 2) = 28 DEGREES OF FREEDOM

R-UARED = 21 .7 PERCENTR-UARED 18.9 PERCENT, ADJUSTED FOR D.F.

ANALYSIS OF VARIANCE

EVE TO DF SB MS=SS/DFREtIRESSION 1 1098.7 1098.7RESIIJJAL 28 3964.7 llsl.6

TOTAL 29 5063.11

Xl Y PEED. Y ST.DEV.RM C23 C22 VALUE PEED. Y RFSILUAL

16 66.0 * 110.118 7.81 *

27 311.0 60.00 26.96 3.1(3 33.0k29 65.0 110.00 110.05 7.67 -0.05

R DENOTES AN (ES. WITH A LARGE ST. R&S.X DENOTES AN (ES. WHOSE X VALUE GIVES IT LARGE INFLUENCE.DURBIN-WATSON STATISTIC 1.66

ST. RES.ax

2.90R-0.01 X

271$

Page 306: An evaluation of production output for in situ concrete work

CHOOSE 3 C12 C3 C13 , C21 C22 C23

FLOT C22 C23C 2260.+

*

110.4. * *

- *

20.+ 2

o.+-+ --------+ -------- .i --------+ --------+C23

0.0 7.0 111.0 21.0 28.0 35.0

2 MISSING (ESERVATIONS

-- RFJ3R C22 1 C237 CASES USED2 CASES CONTAINED MISSING VALUES

THE RF3RESSION EQUATION ISI = 13.2 + 0.8 118 Xl

ST. DEV. T-RATIO =

COLUMN COEFFICIENT OF COEF. COEF/S. D.

-- 13.20 10.83 1.22Xl C23 0.81181 0.5625 1.51

THE ST. DEV. OF Y ABaJT RFRESSION LINE ISS 111.09WITH ( 7- 2) = 5 DEGREES OF FREEDOM

R-SUARED 31.3 PERCENTR-UARED = 17.5 PERCENT, ADJUSTED FOR D.F.

ANALYSIS OF VARIANCE

DUE TO DF SS MS:SS/DFRE)ThESSION 1 1151.3 1151.3RE.SIrUAL 5 992.1$ 198.5TOTAL 6 111113.7

DURBIN-WATSON STATISTIC 0.51

-- CHOOSE it C12 C3 C13 , C21 C22 C23

275

Page 307: An evaluation of production output for in situ concrete work

-- R.OT C22 C23

C22

30.+ *

*20.+

- '2

*10.+ **

a * *--.1.---------- +-.---------1---------+-.------- ^C23

0.0 1.0 2.0 3.0 11.0 5.0

-- RFXJR C22 1 C23

ThE RE3RESSION EQUATION ISy = 5.113 + 11.02 Xi

ST. DEV. T-RATIO

COLUMN COEFFICIENT OF COEF. COEF/S.D.-- 5.1127 3.6112 1.119

Xl C23 11.015 1.9111 2.07

THE ST. DEV. OF Y ABUT REX3RESSION LINE ISS 7.513WITH C i1l 2) = 12 DEGREES OF FREEDOM

R-UARED 26.3 PERCENTR-UARED 20.1 PERCENT, ADJUSTED FOR D.F.

ANALYSIS OF VARIANCE

EVE TO DF SS MS=SS/DFREXRESSION 1 2111.58 2111.58RESIDUAL 12 677.27 56.1111TOTAL 13 918.86

Xl Y PRED. Y ST.DEV.EM C23 C22 VALUE PRED. Y RESIDUAL ST. RES.

3 2.00 30.00 13.116 2.18 16.511 2.30R8 11.70 22.00 211.30 6.111 -2.30 -0.59 X

R DENOTES AN CBS. WITH A LARGE ST. RES.X DENOTES AN CBS. WHOSE X VALUE GIVES IT LARGE INFLUENCE.

E1JRBIN-WATSON STATISTIC 1.80

276

Page 308: An evaluation of production output for in situ concrete work

D.1.2 Print-0it from Analysis of Taoin Conoret

.-RETR 'data'-- CONST-- CORR C7 C13 C16 C17

TAMP VOLUME AREAVOLUME 0.807AREA 0.928

0.831

DEPTH -0.1l4 -0.116 -0.450

-_ RR Cl 2 C16 Cl?THE RBRESSION EQUATION ISY = 10.4 + 1.12 Xl + 0.139 X2

ST. DEV. T-RATIO =COLUMN COEFFICIENT OF COEF. COEF/S.D.-- 10.369 11.654 2.23

Xl AREA 1.11821 0.06120 18.27X2 DEPTH 0.139 1.5118 0.09

THE ST. DEV. OF Y ABJT RRESSION LINE IS S 21.88WITH C 70- 3) = 67 DEGREES OF FREEDOMR-UARED = 86.2 PERCENTR-&UARED = 85.7 PERCENT, ADJUSTED FOR D.F.

ANALYSIS OF VARIANCE

DUETO DF SSREXRESSION 2 199552.0RES]I1JAL 67 32070.2TOTAL 69 231622.2

MS=SS/DF99776.0

1178.7

FURTHER ANALYSIS OF VARIANCESS EXPLAINED BY EACH VARIABLE WHEN ENTERED IN THE ORDER GIVEN

EUETO DF SS

REGRESSION 2 199552.0AREA 1 1995118.1DEPTH 1 3.9

Xl Y PRED. Y ST.DEV.

RCM AREA TAMP VALUE PRED. Y RESIDUAL

16 3 26.00 14.38 7.211 11.62

20 3 29.00 111.38 7.211 111.62

22 3 27.00 111.38 7.24 12.62

25 285 309.00 329.09 111.71 -20.09

26 3 28.00 14.38 7.24 13.62

27 2 15.00 13.03 7.23 1.97

1(3 99 69.00 121.01 14.33 -52.01

115 1711 195.00 204.99 8.25 -9.99

51 102 175.00 124.80 11.118 50.20

52 81 155.00 101.411 3.65 53.56

53 93 180.00 114.07 11.07 65.93

55 50 130.00 66.33 3.08 63.67

56 101 180.00 123.35 4.112 56.65R DENOTES AN (ES. WITH A LARGE ST. RES.X DENOTES AN CBS. WHOSE X VALUE GIVES IT LARGE INFLUENCE.LURBIN-WATSON STATISTIC 0.91

ST. RES.0.56 X0.71 X0.61 X

-1.24 X0.66 X0.10 X

-2.43R-0.119 X

2.311R2.118R3.07 R2.94R2.61R

277

Page 309: An evaluation of production output for in situ concrete work

--ELOTC7C13TAMP

- a

280.+

- a

- '3lkO.+ * *

- a_a a- *- *5** * * ** a- -

- 532 ' 50.+2+ a *

4---------4 --------9 --------4---------4--------- +VOLUME

0. 15. 30. 15. 60. T5•

-- FLOTC7C16TAMPk20.+

*

280. +

- a

-140.+ * - *

- aa a-- * 3'52 *- 56252'

4----------4---------4---------4----------.4.--------- +AREA0. 80. 160. 240. 320. 400.

278

Page 310: An evaluation of production output for in situ concrete work

xlAREA

25

28543

99115

171151

10252

8153

9355

5056

10167

136

-- aQTc 017

TAMP

420.+

- *

280 .+

- I

140.+ 2- '2- *4- 611*' *- 36-4' * * - 5

0.+ '2 *- .35 5 * 2--+ -----------------1- --------.1--------- I-DEPTH

0.0 1.5 3.0 4.5 6.0 7.0

-- REX3R 07 1 C16

THE RFZ)RESSION BUATION ISI 10.7 + 1.12 Xl

COLUMN COEFFICIENT-- 10.667

Xl AREA 1.11573

ST. DEV. T-RATIO =

OF COEF. cOEF/S. D.

3.239 3.29

0.052124 20.57

THE ST. DEV. OF I ABJT RFflRESSION LINE ISS = 21.72WITH ( 70- 2) = 68 DEGREES OF FREEDOM

R-SUARED = 86.2 PERCENTR-SQUARED = 85.9 PERCENT, ADJUSTED FOR D.F.

ANALYSIS OF VARIANCE

WETO DF ssRFX3RESSION 1 199548.1EESIt1JAL 68 32074.0TOT/iL 69 231622.2

MS= SS/DF199548.1

471.7

ITAMP

309.0069.00

195.00175.00155.00180.00130.00180.00135.00

PRED. IVALUE

328.65121.01204.801211.81101.49114.1066.215

123.36162.41

ST. DEV.PEED. I

13.7711.307.9114.453.594.042.714.396.03

B ES 1W AL-19.65-52.01-9.8050.1953.5165.9063.5556.64

-27.41

ST. RES.-1.17 X

2.1111R-0.49 X

2.36 R2.50R3.09R2.95 B2 .66 B

-1.31 X

279

Page 311: An evaluation of production output for in situ concrete work

R DENOTES AN (ES. WITH A LARGE ST. RES.X DENOTES AN OBS. WHOSE X VALUE GIVES IT LARGE INFLUENCE.DIJRBIN-WATSON STATISTIC = 0.91

-- END

END OF EXEQJTION OF STORED INSTRUCTIONS

'** MINITAB " STATISTICS DEPT * PENN STATE UNIV. * RELEASE 81.1 aSTORAGE AVAILABLE 150000

280

Page 312: An evaluation of production output for in situ concrete work

D.2 PRINT-WT FROM TEST PRO(1RA1

281

Page 313: An evaluation of production output for in situ concrete work

D.2.1 int-Out from Progr 'TESTl.MINEXEC'

!4INITAB RELEASE 81.1 *** COPYRIGHT- PENN STATE UNIV. 1981

APR]L 21, 1986 " Loughborough University, of Techno1o'

STORAGE AVAiLABLE 150000

-- retr 'data'

-- NAME Cl 'TEST'

-- NAME C2 'METHOD'

-- NAME C3 'PRTOOLS'

-- NAME Ck 'POUR'

-- NAME C5 'VIBRATE'

-- NAME C6 'SHOVEL'

-- NAME C7 'TAMP'

-- NAME C8 'TR(qt

-- NAME C9 'GENERAL'

-- NAME ClO 'CLTOOLS'

-- NAME Cii 'COv'

-- NAME C12 'TYPE'

-- NAME C13 'VOLUME'

-- NAME C1 1 'WIDTH'

-- NAME C15 'LENGTH'

-- NAME C16 'AREA'

-- NAME C17 'DEPTH'

-- NAME C19 'JB-TOTAL'

-- LET C2O=C1+C5+C6+C7+C8

-- LET C21=C3+C10+C11

-- LET C22=C20+C21+C9

-- LET C19C2O+C21

-- LET C113=11.7+O.501'C13

-- LET C11,=5.1I5+1.67'C13

282

Page 314: An evaluation of production output for in situ concrete work

-- LET Ck53.Z6*C13

-- LET C116:8.07^O.737*C16

-- LET C171O.7+1.12*C16

-- LET C18=27.6+2.79*C16

-- LET C5o=6.83+O.310'C13

-- LET C51=8.62+O.861*C13^O.202*C16

-- LET K5=1.1300

-- LET K61.O775

-- LET C52=16.1O+1.18'C13

-- LET C531I.79+9.65*C13

-- LET C51=5.69'C13

-- LET C5522.8'C13

-- LET C569.37+O.549'C13

-- LET C57=1.51'C16

-- LET C5B5.00

-- LET C59=13.2+O.8118*C13

-- LET C60=5.k3+1I.02*C13

-- REDO 1 2 C2 0 C36

-- REDO 3 C36 1 C36

-- RECO 1 C36 0 C36

-- RE0 3 C2 1 C37

-- RE0 2 C37 0 C37

-- LET C38=C37-1

RECO -1 C38 1 C38

RECO 1 C12 0 C32

-- RECO 2 C12 0 C33

RECO 3 C12 0 C31

-- RECO k C12 0 C35

283

Page 315: An evaluation of production output for in situ concrete work

-- SIGN C32 C32

O NEGATIVE VALUES 11 ZERO VALUES 29 POSITIVE VALUES

-- SIGN C33 C33

O NATIVE VALUES 6 ZERO VALUES 61 POSITIVE VALUES

-- SIGN C31t C311

O NEGATIVE VALUES 9 ZERO VALUES 61 POSITIVE VALUES

-- SIGN C35 C35

O NEX3ATIVE VALUES 11 ZERO VALUES 56 POSITIVE VALUES

-- LET C32=C32-1-- LET C33C33-1-- LET C3:C314-1-- LET C35C35-1

--RECO-1 C321 C32-- RECO -1 C33 1 C33-- RECO -1 C3k 1 C31--REcO-1C35 1C35

-- LET C1:C1I1I*C32+C52'(C33+C31)+C53'C35

-- LET Ck5=C15*C32+C5l'(C33+C3lI)+C55*C35

-- LET CZI8C18*C18+C57'C68

-- LET C50:(C50+C56'C36)

-- LET C19=K5*C37+K6*C38

-- LET c7O=(Ck3+Ck+CJ45+C1 6+C1I7+CI4 8+C50+C51 )*C19

-- LET C71C70/C119

-- ELOTC3Ck3PR TOOL S

60.+ *

- a a

a., - a

"a,*-a

20..,. •2 2' 2 *k'' -* -5** 2 a 2a---2''

0.. 23.4. --------4 --------.4---------4---------.4-

9.0 18.0 27.0 36.0 15.O 54.0

2811

Page 316: An evaluation of production output for in situ concrete work

17 MISSING CBSERVATIONS

-- RFXR C3 1 C11353 CASES USE])17 CASES CONTAINED MISSING VALUES

THE REGRESSION EQUATION ISY = 0.0230 + 0.999 Xl

ST. DEV. T-RATIO

COLUMN COEFFICIENT OF COEF. COEF/S.D.-- 0.023 11.597 0.00

Xl C113 0.9990 0.21102 4.16

THE ST. DEV. OF Y ABCUT REGRESSION LINE IS S = 11.119WITH C 53- 2) = 51 DEGREES OF FREEDOM

R-SUARED = 25.3 PERCENTR-UARED = 23.9 PERCENT, ADJUSTED FOR D.F.

ANALYSIS OF VARIANCE

DUE TO DF SS MS=SS/DF

REGRESSION 1 2282.6 2282.6RESIDUAL 51 6730.4 132.0TOTAL 52 9013.0

Xl Y PRED. Y ST.DEV.RCM C113 PRTOOLS VALUE PRED. Y RESIDUAL25 1111.8 1111.75 6.63 ft

42 28.7 60.00 28.73 3.03 31.27115 1111.3 110.00 1111.211 6.51 -4.2463 30.2 115.00 30.23 3.34 111.7767 32.2 15.00 32.23 3.77 - -17.23

R DENOTES AN CBS. WITH A LARGE ST. RES.X DENOTES AN CBS. WHOSE X VALUE GIVES IT LARGE INFLUENCE.DURBIN-WATSON STATISTIC = 1.48

-- CORR C3 C113CORRELATION OF PRTOOLS AND C113 = 0.503

ST. RES.

2.82 R-0.115X

1.3 IIX-1 .59X

285

Page 317: An evaluation of production output for in situ concrete work

-- PLOT Ck CkkPOUR150.+

**

100.+ *

- 2

- *

- * * *

- *

50.+ ** * **

- ***

- *2* * *

- *2223**2* -

- 329k 2 **

o.+ *4---------4---------*---------+---------+Ckk

0. 30. 60. 90. 120. 150.

I MISSING (FSERVATIONS

-- RER Ck 1 C1$k

69 CASES USED1 CASES CONTAINED MISSING VALUES

THE REflRESSION UATION ISY = -0.0099 + 1.00 Xl

ST. DEV.COLUMN COEFFICIENT OF COEF.-- -0.010 3.150

Xl Cull 1.00126 0.08389

THE ST. DEV. OF Y ABOUT R3RESSION LINE ISS = 15.17WITH C 69- 2) = 67 DEGREES OF FREEDOM

R-UARED = 68.0 PERCENTR-SUARED = 67.5 PERCENT, ADJUSTED FOR D.F.

ANALYSIS OF VARIANCE

WE TO DF SS MS=SS/DFRFRESSI0N 1 3277k.5 321711.5RESItUAL 67 151115.2 230.1TOTAL 68 118189.7

T-RATIO =COEF/S. D.

-0.0011.911

286

Page 318: An evaluation of production output for in situ concrete work

xl

RM

cli1;

13

2125 116

62ii';

52

53

62

23

67

71;

YPOU R

6 5.00123 .0025.00

115.0095.0055.0055.00

PEED. YVALUE20.66

115.8161.63

11IL1353 . 1 022.7671;.00

ST. DEV.PEED. I

2.017.373.187.232.621.91;1; .07

B ES IDU ALI;l; .31;

7.19-36.63

0.87lfl .90

32.21;-19.00

ST. RES.2.95R0.5 kX

-2.k7R0.06 X2.80 R2.1l;R

-1 .30X

B DENOTES AN CUS. WITH A LARGE ST. RES.X DENOTES AN CBS. WHOSE X VALUE GiVES IT LARGE INFLUENCE.E1JRBIN-WATSON STATISTIC = 1 .96

-- CORR Cl; Ck1I

CORRELATION OF POUR AND ClIl; = 0.825

--PLOTC5Ck5VIBRATE300.+

- *

- a

200.+

- . 2

- **

- aa a

- * *

100.+ * aa a

- * * *2

- aa

- *a *a a

- 5k27***2* a

0.... 2 *a

-I----------.f---------.4---------.4---------.4--------0. 60. 120. 180. 2k0. 300.

10 MISSING (ESERVATIONS

--RE3RC51Ck5

60 CASES USED10 CASES CONTAINED MISSING VALUES

THE RE3RESSION EUATI0N ISI = - 3.80 + 1.01; Xl

COLUMN COEFFICIENT-- -3.805

Xl C1;5 1.03579

ST. DEV. T-RATIOOF COEF. COEF/S. P.

l;.8o50.06027 17.18

THE ST. DEV. OF Y ABCUT REGRESSION LINE IS S 2k.99WITH ( 60- 2) = 58 DEGREES OF FREEDOM

287

Page 319: An evaluation of production output for in situ concrete work

R-3UARED = 83 . 6 PERCENTR-UARED = 83.3 PERCENT, ADJUSTED FOR D.F.

ANALYSIS OF VARIANCE

DUE TO DF SS MS=SS/DFREGRESSION 1 18'398.O 18I398.0RESIDUAL 58 36216.0 621.ItTOTAL 59 2206111.0

Xl Y PRED. Y ST.DEV.ROW C115 VIBRATE VALUE PRED. Y RESIDUAL

13 31 101.00 28.81 3.63 72.1925 228 216.00 232.73 10.70 -16.7329 162 130.00 1611.16 7.00 -311.16115 225 285.00 229.111 10.50 55.8663 128 115.00 128.80 5.26 -83.80

R DENOTES AN (US. WITH A LARGE ST. RES.X DENOTES AN (US. WHOSE X VALUE GIVES IT LARGE INFLUENCE.

D(JRBIN-WATSON STATISTIC = 2.32

-- CORR CS C115

CORRELATION OF VIBRATE AND C115 = 0.9111

-- PLOT C6 C116SHOV EL270 • +

- a

180.+ a

- a a

g0.+ a a

- ** 2 a a

- *2 3* **

- aa2*3* a- 35*11 a a

0•+ +-*

----+ --------.i---------+---------.4.-------- .+C1l6

0. 50. 100. 150. 200. 250.

1 MISSING (ESERVATIONS

-- RB3R C6 1 C11669 CASES USED

1 CASES CONTAINED MISSING VALUES

THE RRESSION FJUATION ISY = -0.0012 + 1.00 Xl

ST. RES.2.92R

_O.7 11 X-1.112 X

2.116RX-3.113R

288

Page 320: An evaluation of production output for in situ concrete work

JXJETO DFREGRESSION 1RESIE*JAL 67TOTAL 68

xl

RYrJ C116

19

26

21

31

25

218

112

80

1j3

81115

136

63

88

67

108

ST. DEV. T-RATIO =COLUMN COEFFICIENT OF COEF. COEF/S.D.-- -0.001 3.080 -0.00

Xl C116 1.000110 0.06295 15.89

THE ST. DEV. OF Y ABCUT REGRESSION LINE IS S 18.115WITH ( 69- 2) 67 DEGREES OF FREEDOM

R-UARED 79.0 PERCENTR-UARED 78.7 PERCENT, ADJUSTED FOR D.F.

ANALYSIS OF VARIANCE

SS85986 .922807 .9

1087911.8

YSHOVEL63.0068.00192.00110.00123.00180.00115.00125.00

MS= SS/DF

85986.93110.11

PEED. Y

ST. DEV.

V AL UE

PEED. Y

26 .36

2.27

30.71

2.23

218.20

11.81

79.59

3.63

80.99

3.70

136 .36

6.82

88 .1114

11.09

108 .31k

5.18

RES IDU AL36 .61137.29

-26 .20-39.59112.01113 .614

_113 .111116.66

ST. RES2.00R2.OIIR

-1.85 X-2.19R2.32R2.55EX

-2.'IlR0.914 X

R DENOTES AN OBS. WITH A LARGE ST. RES.X DENOTES AN CBS. WHOSE X VALUE GIVES IT LARGE INFLUENCE.

DURBIN-WATSON STATISTIC = 2.01

-- CORR C6 C116CORRELATION OF SHOVEL AND C116 = 0.889

-- PLOT C7 C117TAMP1420 .+

- a

280.+

a

-11I0.+ a ft

- aa a

- aa** a

- a9352a

o.+ +6 a4---------4 --------+ --------I --------4 --------+C1170. 90. 180. 270. 360. 1150.

289

Page 321: An evaluation of production output for in situ concrete work

-- RFXR C7 1 C117

THE REI3RESSION EQUATION ISY 0.0077 + 0.996 Xl

ST. DEV.COLUt4 COEFFICIENT OF COEF.-- 0.008 3.573

Xl C117 0.99619 0.0118113

THE ST. DEV. OF Y ABJT RB3RESSION LINE ISS = 21.72WITH ( 70- 2) = 68 DEGREES OF FREEDOM

R-3UARED 86.2 PERCENTR-SUARED 85.9 PERCENT, ADJUSTED FOR D.F.

T-RATIOCOEF/S. D.

0.0020.57

ANALYSIS OF VARIANCE

DUETO DF SSRE3BESSION 1 1995118.1

RESIDUAL 68 320711.0TOTAL 69 231622.1

MS=SS/DF1995118.1

1171.7

Xl Y PRED. Y ST.DEV.

C117 TAMP VALUE PEED. ! RESIDUAL25 330 309.00 328.65 13.77 -19.65113 121 69.00 121.01 11.30 -52.01115 206 195.00 2011.80 7.911 -9.8051 125 175.00 1211.81 11.115 50.1952 102 155.00 101.119 3.59 53.5153 115 180.00 1111.10 11.011 65.9055 67 130.00 66.'15 2.71 63.5556 1211 180.00 123.36 11.39 56.61167 163 135.00 162.111 6.03 27.111

R DENOTES AN OBS. WITH A LARGE ST. R.X DENOTES AN (ES. WHOSE X VALUE GIVES IT LARGE INFLUENCE.

tURBIN-WATSc STATISTIC 0.91

-- CORR C7 C47

CORRELATION OF TAMP AND C117 = 0.928

ST. RES.-1.17X-2.114R_O.119X

2.36 R2.50R3.09R2.95R2.66R

-1 .31X

290

Page 322: An evaluation of production output for in situ concrete work

--LOTc8C48TR cw EL

300.+ *

200.+

- a

- -a

- a aa

100.+ *

- a a

- !2 aa

- 2a4-a.a5a 11

-a---+ --------.4.---------+---------+---------+C118

0. 70. 1IO. 210. 280. 350.

36 MISSING (ESERVATIONS

-- RB3R 8 1 C48

34 CASES USED36 CASES CONTAINED MISSING VALUES

THE REXRESSION EQUATION ISY = - 1.17 + 1.01 Xl

COLUMN COEFFICIENT-- -1.17k

Xl C118 1.01169

ST. DEV. T-RATIO =

OF COEF. cOEF/S. D.

5.656 -0.21

0.06702 15.10

THE ST. DEV. OF Y ABJT RB3RESSION LINE IS S = 22.33WITH ( 34- 2) 32 DEGREES OF FREEDOM

R-UABED 87.7 PERCENTR-UARED = 87.3 PERCENT, ADJUSTED FOR D.F.

ANALYSIS OF VARIANCE

]XJE TO

DF

SS MS=SS/DFREXRESSION

1

113648.7 1136118.7RESIDUAL

32

15959.1 1198.7TOTAL

33

1296 (11 .8

Xl

Y PRED. ! ST.DEV.

Ck8

TRtMPL VALUE PRED. Y RESIDUAL30

123

185.00 123.18 5.59 61.82112

1116

80.00 147.01 6.83 -67.0145

263

295.00 264.64 13.98 30.36

R DENOTES AN (ES. WITH A LARGE ST. RES.X DENOTES AN (ES. WHOSE X VALUE GIVES IT LARGE INFLUENCE.DURBIN-WATSON STATISTIC = 2.09-

ST. RES.2.86 R

-3.15R1.711X

291

Page 323: An evaluation of production output for in situ concrete work

-- CORR C8 Ck8

CORRELATION OF TRCMEL AND C18 0.936

-- PLOT ClO C50CL TOOL S90.+

- a

60- a- a **- a

30.+- * a- 2***- 2**-3* * *- 3*

+---------+---------+-.--------•1---------..-------- +C505. 20. 35. 50. 65. 80.

113 MISSING CESERVATIONS

-- RB)R ClO 1 C50

27 CASES USED113 CASES CONTAINED MISSING VALUES

THE RB3RESSION EQUATION ISy = 0.0066 + 0.999 Xl

ST. DEV. T-RATIOCOLUMN COEFFICIENT OF COEF. COEF/S.D.-- 0.007 2.390 0.00

Xl C50 0.99918 0.09065 11.02

THE ST. DEV. OF Y ABCIJT REX3RESSION LINE ISS = 7.1167WITH ( 27- 2) = 25 DEGREES OF FREEDOM

R-UARED 82.9 PERCENTR-3UARED = 82.3 PERCENT, ADJUSTED FOR D.F.

ANALYSIS OF VARIANCE

tUE TO DF SS MS=SS/DFREX3RESSION 1 67711.19 67711.19RESIDUAL 25 1393.98 55.76TOTAL 26 8168.17

292

Page 324: An evaluation of production output for in situ concrete work

Xl Y PRED. Y ST.DEV.

RCM C50 CLTOOLS VALUE PRED. Y RESILUAL

25 72.9 72.00 72.814 14.91 -0.814

29 140.7 55.00 140.65 2.29 114.35

36 26.9 9.00 26.814 1.53 -17.814

51 142.6 25.00 142.514 2.142 -17.514

55 30.14 145.00 30.36 1.67 114.614

R DENOTES AN OBS. WITH A LARGE ST. RES.X DENOTES AN CBS. WHOSE X VALUE GIVES IT LARGE INFLUENCE.

DURBIN-WATSON STATISTIC = 1.75

-- CORR dO C50

CORRELATION OF CLTOOLS AND C50 = 0.911

-- OT Cli C51COVER120

a

80.+ ' *

*

- *

- 23

- 22''

- 2

0.+ 2'--+ --------+ --------+ -----------------+C51

0. 30. 60. 90. 120. 150.

149 MISSING (SERVATI0NS

-- RE)3R Cli 1 C51

21 CASES USED49 CASES CONTAINED MISSING VALUES

THE REGRESSION EQUATION ISY = -0.00514 + 1.00 Xl

ST. DEV. T- RATIOCOLUMN COEFFICIENT OF COEF. COEF/S.D.

-0.005 6.818 -0.00Xi C51 1.0001 0.2067 14.84

THE ST. DEV. OF Y ABOUT REGRESSION LINE IS S = 18.33WITH ( 21- 2) 19 DEGREES OF FREEDOM

ST. RES.-O.15X2.02R

-2.1414 R-2.48R2.O1R

293

Page 325: An evaluation of production output for in situ concrete work

R-UARED z 55.2 PERCENTR-UARED = 52.8 PERCENT, ADJUSTED FOR D.F.

ANALYSIS OF VARIANCE

IXJETO DF SSREX3RESSION 1 7863.0RESIIUAL 19 6381.2TOTAL 20 142411.3

MS= SS/DF7863.0

335.9

Xl Y PEED. Y ST.DEV.

ROW C51 COVER VALUE PRED. Y RESItUAL

21 33 79.00 32.90 4.20 46.10

25 123 * 123.02 20.30 *

43 58 98.00 57.53 7.52 40.47

45 100 80.00 99.74 15.61 -19.74

63 62 * 62.50 8.41 *

67 71 a 71.39 10.06 *

R DENOTES AN CBS. WITH A LARGE ST. R.X DENOTES AN CBS. WHOSE X VALUE GIVES IT LARGE INFLUENCE.

DURBIN-WATSOW STATISTIC = 2.58

-- CORR Cli C51

ST. RES.2.5 8R

ax2.42B

-2. 06 RXax

CORRELATION OF COVER AND C51

= 0.743

-- SAVE V tempt

-- END

END OF EXECUTION OF STORED INSTRUCTIONS

a** MINITAB *** STATISTICS DEPT * PENN STATE UNIV. * RELEASE 81.1

STORAGE AVAILABLE 150000

2911

Page 326: An evaluation of production output for in situ concrete work

D.2.2 PrintOut frn ProRram 'TESI2.MINEXEC'

MINIT!B RELEASE 81.1 " COPYRIGHT - PENN STATE UNIV. 1981APRIL 21, 1 986 " Loughborough University, of Teehno1o'STORAGE AVA]LBLE 150000

-- RETR 'temp'

-- RECO 'a' C3 0 C3-- BECO 'a' C1 0 C4-- RECO 'a' C5 0 C5-- RECO 'a' C6 0 C6-- RECO 'a' CT 0 C7-- RECO 'a' 08 0 C8-- RECO a' dO 0 ClO-- RECO *' Cli 0 Cli

-- LET C2OC1+C5+C6+C7+C8-- LET C2iC3+C10+C11-- LET C22:C20+C21+C9

-- LET C19=C20+C21

-- &JBS 525 10 C19-- &JBS 605 21 C19

-- LET C9C19*(C19_1)

-- PLOT cg C19

GENERAL150.+

aa-

100 .+

- a aa

- a *

50.+ ** aft -- 21* *- * a a-a,- 5aa3i1 a

- 112a1122aa *

0+ '7"22 ---+---------+---------+---------+---------+0119

0. 30. 60. 90. 120. 150.

2 MISSING CSERVATIONS

295

Page 327: An evaluation of production output for in situ concrete work

-- RE)3R C9 1 C119

68 CASES USED2 CASES CONTAINED MISSING VALUES

THE RRESSION EQUATION ISY = 0.01111 + 0.999 Xl

ST. DEV.COLUMN COEFFICIENT OF COEF.-- 0.0111 2.368

Xl C49 0.99856 0.07655

THE ST. DEV. OF Y ABC*JT RFRESSION LINE ISS = 13.116WITH ( 68- 2) = 66 DEGREES OF FREEDOM

R-UARED 72.1 PERCENTR-SUARED = 71.6 PERCENT, ADJUSTED FOR D.F.

ANALYSIS OF VARIANCE

T-RATIO =COEF/S. D.

0.0113.05

*JE TO DF SS MS=SS/DFREX3RESSION 1 30846 .7 308116 .7RESIIXJAL 66 11963.6 181.3TOTAL 67 42810.3

Xl Y PRED. Y ST.DEV.RCM C49 GENERAL VALUE PRED. Y R&SIL*JAL

9 116 9.00 115.58 2.111 -36.5821 117 75.00 46.83 2.118 28.1725 119 120.00 118.110 7.511 1.60115 92 70.00 92.11 5.59 -22.1152 64 80.00 63.62 3.56 16.3853 61 105.00 60.70 3.36 44.3056 67 60.00 66.87 3.78 -6.87

R DENOTES AN CBS. WITH A LARGE ST. RES.X DENOTES AN CBS. WHOSE X VALUE GIVES IT LARGE INFLUENCE.

L*JRB IN-WATSON STATISTIC = 1 .39

-- CORE C9 C149

CORRELATION OF GENERAL AND C119 = 0.8119

ST. RES.-2.76R

2.13R0.1 11 X

-1.80 X1.26 X3.4ORX

-0.53 X

296

Page 328: An evaluation of production output for in situ concrete work

C3770

1.1.1.1.1.0.0.0.1.0.0.0.0.0.0.0.0.0.0.0.0.0.0.0.1.0.0.1.1.1.1.1.1.1.1.1.1.1.1.1.0.0.0.0.0.0.0.0.0.0.1.1.1.1.1.

C3870

0.0.0.0.0.1.1.1.0.1.1.1.1.1.1.1.1.1.1.1.1.1.1.1.0.1.1.0.0.0.0.0.0.0.0.0.0.0.0.0.1.1.1.1.1.1.1.1.1.1.0.0.0.0.0.

-- PRINT C9 C19COLUMN GENERALCOUNT 70RM

1 5.

2 5.3 9.

4 20.5 16.

6 18.

7 16.

8 3.

9 9.

10 32.

11 21.12 43.

13 5I.

14 0.

15 0.

16 26.

17 16.

18 10.

19 20.

20 35.

21 75.

22 10.

23 15.21 21.

25 120.

26 21.

27 0.

28 36.*1*1

30

31 8;

32 19.

33 18.

34 10.

35 13.

36 12.

37 0.

38 15.

39 0.

40 8.

41 0.

42 20.

43 25.

44 0.

45 70.

46 7.

47 7.

48 50.

49 40.

50 45.51 60.

52 80.53 105.54 0.55 50.

C37 C38C1970

124.00128.00143.00161.00146.00113.00130.00181.00351 .00525.00265.00212.00479.0051 .0052.00

341.00147.00120.00227 .00302.00605.00197.00102.00128.00912.002611.00174.00152.00410.00325.00185.00132.00173.00159.00151.00229.0088.0068.00

105.001011.00110.00

480.00590.0055.00

1190.0030.0040.00

360.00207.00265.001120.00490.00467.5077.00

310.00

297

Page 329: An evaluation of production output for in situ concrete work

56

60. 515.00

1. 0.

57

15. 205.00

0. 1.58

0. 75.50

0. 1.59

0. 411.00

0. 1.60

0. 45.00

0. 1.61

10. 180.00

0. 1.62

10. 130.00

0. 1.

63

25. 285 .00

1. 0.

64

10. 50.00

0. 1.65

5. 150.00

0. 1.66

5. 45.00

0.

1.67

35.

1195.00

0. 1.68

0. 15.00

0.

1.

69

0. 45.00

0. 1.70

30. 125.00

0. 1.

-- LET C119=(1.152aC19_8.63)aC37+(1.068*C19+4.00)aC38-- LET C49=Ci49-C19

-- PLOT C9 C119GENERAL150.+

- aa

100 .+

- a a*

- a a

50.+ aa aa- *2-a a

- *• * aaa- 5332 *

- 5442 * a

O.+ a34_i.-----------------+---------+---------4---------+ C119

0. 30. 60. 90. 120. 150.

2 MISSING CSERVATI0NS

-- RF3RC9 1 C11968 CASES USED

2 CASES CONTAINED MISSING VALUES

THE REflRESSION FUATION IS

Y = -0.0990 + 1.00 Xl

COLUMN COEFFICIENT-- -0.099

Xl C119 1.00368

ST. DEV. T-RATIO =OF COEF. COEF/S. D.

2.2 112 -0.0110.07201 13.911

THE ST. DEV. OF Y ABCUT REX3RESSION LINE IS S = 12.83WITH ( 68- 2) = 66 DEGREES OF FREEDOMR-UARED 711.6 PERCENTR-UARED 711.3 PERCENT, ADJUSTED FOR D.F.

298

Page 330: An evaluation of production output for in situ concrete work

ANALYSIS OF VARIANCE

IXJE TO DF SS MS=SS/DFREZRESSION 1 31953.4 31953.4RIL*JAL 66 10856.8 164.5TOTAL 67 42810.3

Xl ! PEED. Y ST.DEV.ROW C119 GENERAL VALUE FRED. Y RF.5IL*JAL

9 i5 9.00 '44.79 2.24 357921 '45 75.00 I5.21 2.26 29.7925 130 120.00 130.37 7.90 -10.37'45 85 70.00 85.13 14.76 -15.1352 66 80.00 65.99 3.49 14.0153 62 105.00 62.56 3.27 '42.4456 70 60.00 69.81- 3.74 -9.81

R DENOTES AN (ES. WITH A LARGE ST. RES.X DENOTES AN (ES. WHOSE X VALUE GIVES IT LARGE NFLUEICE.

WEBIN-WATSON STATISTIC = 1.147

- CORE C9 C149

CORRELATION OF GENERAL AND CJI9 = 0.864

ST. RFS.-2.83R2.36R

-1.03 I-1.27 X

1.1 18 I3J$2RX

-0.80 1

-- SAVE 'general'

-- END

END OF EXECUTION OF STORED INSTRUCTIONS

'I' MINITAB *U STATISTICS DEPT * PENN STATE UNIV. * RELEASE 81.1 *STORAGE AVAILABLE 150000 -

299

Page 331: An evaluation of production output for in situ concrete work

D.2.3 Print-Out frn Program 'TEST.MINEXEC'

MINITAB RELEASE 81.1 ** COPYRIGHT - PENN STATE UNIV. 1981APR]L 21, 1986 " Loughborough University,of TechnologySTORAGE AVAiLABLE 150000

-- RETR ttempt

-- NAME C19 'JB'

-- NAME C22 'TOTAL'

-- SIGN C3 C 23 -O NEZ3ATIVE VALUES 5 ZERO VALUES 18 POSITIVE VALUES

--SIGNCJ C2110 NEXATIVE VALUES 0 ZERO VALUES 69 POSITIVE VALUES

-- SIGN CS C250 NX3ATIVE VALUES 0 ZERO VALUES 60 POSITIVE VALUES

--SIGNC6C260 NECATIVE VALUES 18 ZERO VALUES 51 POSITIVE VALUES

--SIGNC7C2TO NECATIVE VALUES 7 ZERO VALUES 63 POSITIVE VALUES

-- SIGN C8 C28O NECATIVE VALUES 0 ZERO VALUES 3l POSITIVE VALUES

--SIGNC9C29O NRATIVE VALUES 13 ZERO VALUES 55 POSITIVE VALUES

-- SIGN ClO C30O NEX3ATIVE VALUES 0 ZERO VALUES 27 POSITIVE VALUES

-- SIGN Cli C310 NEX]ATIVE VALUES 0 ZERO VALUES 21 POSITIVE VALUES

-- RECOO C23 1 C23

-- RECO 0 C2k 1 C2k

-- RE000 C25 1 C25

300

Page 332: An evaluation of production output for in situ concrete work

-- RECO 0 C26 1 c26

- RECO 0 C27 1 C27

- REcO 0 C28 1 C28

- RECO 0 C29 1 C29

- RECO 0 C30 1 C30

-- RECO 0 C31 1 C31

-- RECO 'i C23 0 C23

-- RECO '*' C24 0 C2k

-- REcO '*' C25 0 C25

-- RECO '. C26 0 C26

-- RECO a C27 0 C2'T

-- RECO at C28 0 C28

-- RECO at C29 0 C29

-- RECO a' C30 0 C30

-- RECO 'a C31 0 C31

-- LET C13=C3*C23

-- LET C11ICJ41*C2k

-- LET CII5=CI5'C25

-- LET C1l6=C16*C26

-- LET Ck7C'7'C2t

-- LET Ck8=Ck8'C28

-- LET C19J49*C29

-- LET C50=C50*C30

-- LET C51=C510C31

-- LET C7 1=Ci 3^ ^CI5+C'6+Ci47+CJj 8+C50+C51

-- LET C7Q:(1.152'C71-8.63)*C37+(1.068*C71+l.00)*c38

-- LET C9:C70071

-- RECO 'I' C3 0 C3

-- RECO iat C1 0 C1

-- RECO eav C5 0 C5

301

Page 333: An evaluation of production output for in situ concrete work

RECO 'it c6 0 C6

-- RECO 'it C7 0 CT

-- RECO 'it C8 0 C8

-- RECO 'it ClO 0 dO

-- EECO 'ft•' Cli 0 Cli

LET C20=Ck+C5+C6+C7+C8

-- LET C21=C3+C10+C11

-- LET C22=C20+C21+C9

-- JBS '*' 10 C22

-- JBS '*' 21 C22

-- LET C19=C20+C21

-- PLOT C22 C70TOTAL1500

- ft

1000.+ ft

- '2

500.4 ft ' "

- ii, ft

- 3ft ft ft

- 3'5632- 2'+'3

0.+ 31

+---------.*---------+---------+---------+---------+C700. 300. 600. 900. 1200. 1500.

1 MISSING C8SERVATIONS

-- CORE C22 C70

CORRELATION OF TOTAL AND C70 = 0.962

302

Page 334: An evaluation of production output for in situ concrete work

-- PL0TC220600C700600TO TA!..600.+

* **

* *- *

1 OO.+ *** a

- aa aa a

- 2*aa-

200.+ a 3*- -*a

- *3a*2*2- a

- 2*a*aa -* aa*a -

25 *2a

-----------+ --------4 --------+---------+C70

0. 120. 2)O. 360. 180. 600.

k POINTS CUT OF BCUNDSlj MISSING (ESERVATIONS

-- LFLOT C22 0 600 C70 0 600 C2TOTAL600.+

- C CC- B D- C

D- CD A- DD C- D B- 2DBD

200.+ A 3B DD- D3DD2C2 D- 2DBAAA- D CADA- 25 B2

0.+ D+---------4---------4---------4---------+--------- +C700. 120. 2110. 360. 180. 600.

1 POINTS CUT OF BCUNDS1 MISSING CESERVATIONS

303

Page 335: An evaluation of production output for in situ concrete work

-- L1'LOT C22 0 600 C70 0 600 C12TO TAL600.+

- A AA

- A A

- A

AAC B

- AC A

- C A

- 2AAA

200.+ A 3B CAA3DC2A2 A

- 2AAABAD DADA25 D2

D+---------+---------4 --------4 --------4--------- +C700. 120. 2i0. 360. 180. 600.

11 POINTS QJT OF BCUNDS1 MISSING CESERVATIONS

-- RFR C22 1 C70

66 CASES USEDk CASES CONTAINED MISSING VALUES

THE REGRESSION FUATI0N ISY=- 10.0+ 1.02X1

ST. DEV. T-RATIO =

COLUMN COEFFICIENT OF COEF. COEF/S. D.-- -10.01 11.68 -0.86

Xl C70 1.01866 0.03610 28.22

THE ST. DEV. OF Y ABCIJT RE3RESSION LINE ISS 61.86WITH ( 66- 2) = 6 1$ DEGREES OF FREEDOM

R-SUARED = 92.6 PERCENTR-SQUARED = 92. 11 PERCENT, ADJUSTED FOR D.F.

ANALYSIS OF VARIANCE

DUE TO DF SS MS=SS/DFRFRESSION 1 30116289 30116289RESIDUAL 611 21111880 3826TOTAL 65 3291170

30J1

Page 336: An evaluation of production output for in situ concrete work

xl

Rc1

C70

13

3514

25

1103

112

614

143

6119

115

1165

51

500

52

1109

53

1179

56

11911

63

506

67

559

xl

RM

C7 0

13

3511

25

1103

112

6111

143

6 149

115

1165

52

4O 9

63

506

YTOTAL

533.00103 2. 00500.006 15.00

1260.00570.00310.00

PRED. YVALUE

350.1171113.55615.65651 .56

1177.221106.32505.38

ST. DEV.PEED. Y

8.5631.8815.31116 .115314.08

9.6312.10

R ES IDIJ AL182.53-81 .55

-115.65-36.56

82 .78163.68

-1 95.38

ST.RES.2.98R

-1 .511X

-1.93X-0.6 1X

1.6 OX2.6 8R

-3.22R

R DENOTES AN CBS. WITH A LARGE ST. RES.X DENOTES AN (ES. WHOSE X VALUE GIVES IT LARGE INFLUENCE.

LURBIN-WATSON STATISTIC = 1.914

-- NOCO

-- REOR C22 1 C70

66 CASES USED14 CASES CONTAINED MISSING VALUES

THE REORESSION EQUATION ISY + 0.995 Xl

COLUMN COEFFICIENTNO CONSTANTXl C70 0.99520

ST. DEN. T-RATIO =OF COEF. COEF/S. D.

0.023118 112.38

THE ST. DEV. OF Y ABJT REORESSION LINE ISS 61.73WITH ( 66- 1) = 65 DEGREES OF FREEDOM

ANALYSIS OF VARIANCE

DUE TO DF SS

REOBESSION 1 681111118RESIDUAL 65 2147691TOTAL 66 7091808

MS= SS/DF681111118

3811

YTO TAL

533.001032.00500.00615.00

1260.001180.00570.00572.50575.00310.00530.00

PRED. YVALUE

352. 181097.68611.256116.311

1159.881197.391106 .7111476.201191 .611503.52555.98

ST. DEN.PRED. I

8.3125.90111.14215.2527.3711.7119.60

11.21111.6011.8813.12

RES IDU AL180.82-65.68

-111.25-31 .311100.12-17.39163.2696.3083.36

-193.52-25.98

ST. RES.2.96R

-1.17 X

-1.85 I-0.52 X1.81 X

-0.29 X2.68R1.59 X1.37 X

-3 . 1 9RX0.113 I

R DENOTES AN (ES. WITH A LARGE ST. RES.X DENOTES AN (ES. WHOSE X VALUE GIVES IT LARGE INFLUENCE.DURBIN-WATSON STATISTIC = 1.91

305

Page 337: An evaluation of production output for in situ concrete work

-- PLOT C19 C71JB

1500 .+

- *

1000

- a

- a

500.+ ** 2 * *

- ** 2

- aa22.a a

- 2a32-

0.+ 35---4 --------4 --------4 --------4 ------- --+C7 1

0. 250. 500. 750. 1000. 1250.

-- CORE C19 C71

CORRELATION OF &JB AND C71 = 0.967

-- PLOT C19 0 600 C71 0 600aJB

600.^ a

- a

- a a a a a

- a

koo.+ a

- 2 a

- aaa -

- * a a a

- aa

200.+ aaaaa 2

- a a3,a a

- 32'23'

- 2aa*

- 2211 a-*

4.----------+---------+---------+--------- +C7 10. 120. 2110. 360. 1180. 600.

2 POIN clJT OF BUNDS

306

Page 338: An evaluation of production output for in situ concrete work

-- LPLOT C19 0 600 C71 0 600 C2JB

600 .+

- BC

1100

D

CC D D

CC

- 2A D

- DCA

- D D B C

- CD

200.+ BBBD 2

- 2D A3AC D

- 32D23A

- 2ADA

- 2211B20.+ D

+---------4---------4---------4---------4--------- +C710. 120. 2110. 360. 1180. 600.

2 POINTS C*JT OF BCUNDS

-- LPLOT C19 0 600 C71 0 600 C12JB

600.+

- A

- AA A

- A

1I00.+ C

A

A A

- 2B A

- CAA

- A C A A

- AA

200.+ ADBAC 2

- 2D A3AA A

- 32A23A

- 2ADA

- 2211D2

0..,. D+---------4---------4---------4---------+---------+C71

0. 120. 2110. 360. 1180. 600.

2 POINTS CUT OF BCUNDS

-- RB3R C19 1 C71

THE REGRESSION FUATION IS+ 1.01 Xl

307

Page 339: An evaluation of production output for in situ concrete work

ST. DEV. T-RATIO =

COLUMN COEFFICIENT OF COEF. COEF/S.D.NOCONSTANTXl C71 1.00860 0.02113 117.73

THE ST. DEV. OF Y ABCUT REGRESSION LINE IS S = 51.81WITH ( 70- 1) 69 DEGREES OF FREEDOM

ANALYSIS OF VARIANCE

DUE TO DF SS MS=SS/DFREGRESSION 1 6115965 6115965RESIDUAL 69 185222 268kTOTAL 70 6301186

Xl Y PEED. Y ST. DEV.RCM C71 JB VALUE PRED. Y RESIDUAL

13 328 1179.00 330.112 6.92 1118.5825 965 912.00 973.2k 20.39 -61.2k112 571 1480.00 576.26 12.07 -96.261$3 6014 590.00 609.56 12.77 -19.56115 1088 1190.00 1096.88 22.98 93.1251 14141 1120.00 11115.13 9.33 -25.1352 362 1190.00 365.38 7.65 1211.6253 1123 1167.50 1426.50 8.914 141.0056 1436 515.00 14110.08 9.22 711.92

63 11117 285.00 1450.52 9.114 -165.5267 519 1195.00 523.81 10.97 -28.81

R DENOTES AN OBS. WITH A LARGE ST. RES.X DENOTES AN OBS. WHOSE X VALUE GIVES IT LARGE INFLUENCE.

LURB IN-WATSON STATISTIC = 1 .95

-- CONS

-- REGR C19 1 C71

THE REGRESSION EQUATION IS- 9.11 + 1.03 Xl

ST. DEV. T-RATIO =COLUMN COEFFICIENT OF OEF. cOEF/S. D.-- -9.106 9.663 -0.911

Xl C71 1.032114 0.03297 31.31

THE ST. DEV. OF Y ABCUT REGRESSION LINE ISS 51.85WITH C 70- 2) = 68 DEGREES OF FREEDOM

R-9UARED 93.5 PERCENTR-UARED = 93.14 PERCENT, ADJUSTED FOR D.F.

ANALYSIS OF VARIANCE

DUE TO DF SS MS=SS/DFREGRESSION 1 26361433 26361133RESIDUAL 68 1828311 2689TOTAL 69 2819267

ST. RES.2.89R

-1.29 X-1.91 X-0.39 X

2.O1EX_o.l9 X

2. 113 R0.80 X1.117 X

-3.25RX-0.57 X

308

Page 340: An evaluation of production output for in situ concrete work

C22 C70 C37 C38

C71 TOTAL

C7 0

70 70

70C 3770

1.1.1.1.1.0.0.0.1.0.0.0.0.0.0.0.0.0.0.0.0.0.0.0.1.0.0.1.1.1.1.1.1.1.1.1.1.1.1.

C3870

0.0.0.0.0.1.1.1.0.1.1.1.1.1.1.1.1.1.1.1.1.1.1.1.0.1.1.0.0.0.0.0.0.0.0.0.0.0.0.

xl

RcM

C7 1

13

328

25

965

142

57 1

143

6014

145

1088

52

362

63

11147

YSJB

147 9.00912.001180.00590.00

1190.001490.00285.00

PEED. YVALUE

329.12987.145 80 .776114.86

1113.703614.911152.06

ST. DEV.PEED. Y

7.0625.1813.0013.9629.117.689.59

R ES IDU AL149.88-75. 111

-100.77-214.8676.30

125.09-167 .06

ST. RES.2.92R

-1.66 X-2.O1RX-0.50 X

1.78 X2.1114R

-3.28R

R DENOTES AN CBS. WITH A LARGE ST. RES.X DENOTES AN CBS. WHOSE X VALUE GIVES IT LARGE INFLUENCE.

DURBIN-WATSON STATISTIC 1 .99

-- PRINT C19COLUMNCOU NT

I231$

56789

10111213ill1516171819202122232112526272829303132333143536373839

C7 1aJB70

1214.00128.001143.00161.001146.00113.00130.00181.00351 .00

89.00265.00212.001479.0051 .0052.00

3141 .001147.00120.00227 .00302.00366.00197.00102.00128.00912.002614.001714.00152.001410.00325.00185.00132.00173.00159.00151.00229.0088.0068.00

105.00

170.87152.09172.39180.79152.09132.72112.332011.03296.36

83.514321 .60217 .29327.60119.78119.78270.19106 .37119.22213.68227 .00275.80227.00.95.6 295.62

9614.914256 .17117.21113.62379.63271.711 80.69151.75187.714162.11169.38186 .26120 • 05101 .58100.78

129.00133.001 52.00181.00162.00131.001116 .001811.00360.00

286.00255.00533.0051 .0052.00

367.00163.00130.002147.00337.00

207 00117.001149.00

1032.00285.001711.00188.00'I,,,,

193.00151.00191.00169.001611.002141.0088.0083.00

105.00

188.21166.57189.97199 .6 11

166.571145.75123.97221 .91332.78

93.22353 .88236.06353.88131.92131.92292.56117.60131.33232.212116.1411298.552116.1411106.12106.12

1102.98277.58129.18122.261128.703014.38199.52166.18207.65178.12186.50205 .911129.67108.39107.117

309

Page 341: An evaluation of production output for in situ concrete work

1.0.0.0.C.0.0.0.0.0.0.1.1.1.1.1.1.0.0.0.0.0.0.1.0.0.0.0.0.0.0.

0.1.1.1.1.1.1.1.1.1.1.0.0.0.0.0.0.1.1.1.1.1.1.0.1.1.1.1.1.1.1.

140

142

143Ill;

145

146

117148149

5051525351155565758596061626361i656667686970

--

1014.00140.00

1180.00590.0055.00

1190.0030.00140.00

360.00207.00265.001120.001490.001461.5077.00

310.00515.00205.0075.501111.00115.00

180.00130.00285.0050.00

150.00115.00

1195.0015.00115.00

125.00

159.7267.03

57 1 .3146014.36

95.501087 .53

67.0367.03

380.110190.59209.8614141.33362.27i422.8688.17

252.061136.322147 .1414105.1551 .5051 .50

2117.1414106.1111116.68

55.118233.2965.58

519 .3 14115.3767 .614

129.53

112.00140.00

500.00615.00

55.001260.00

37.00117.00

1410.002147.00310.001480.00570.00572.5077.00

360.00575.00220.0075.501411.00145.00

190.001110.00310.0060.00

155.0050.00

530.0015.00145.00

155.00

175.3775.59

614.196119.145105.99

1165.11875.5975.59

410.27207.55228.131199.791408.701478.50

92 .911281 .71

14911.02268.27116.3059.0159.01

268.27117.33505.9563.25

253.157 11.014

558.665276 .214

1142.314

END OF EXECUTION OF STORED INSTRUCTIONS

•" MINITAB *'* STATISTICS DEPT * PENN STATE UNIV. • RELEASE 81.1 'STORAGE AVAILABLE 150000

310

Page 342: An evaluation of production output for in situ concrete work

APPENDIX E

OPERATIVE NOTIVATION

311

Page 343: An evaluation of production output for in situ concrete work

mEND III

DPERATIVE MOTIVATION

E.1 INTRODUCTION

The early results of this research indicated that there was a

distinct relationship between remuneration, motivation and siteefficiency. Consequently, observations taken on later site visits

were used to quantify this relationship and determine the relevance

of the major motivation theories to the construction industry.

E.2 REVIEW OF MAJOR MOTIVATION THEORIES

The main purpose of any theory is to relate important variables

associated with a particular topic. The usefulness of any theorydepends upon its ability to account for a wide diversity of

variables, whilst combining them into a cohesive and succinct form.

The important variables influencing motivation are the individual's

characteristics, type of job, working environment and productivity.

There are five main theories on motivation; these concentrate on the

first three variables with the most important, productivity, being

sparsely investigated. The individual's motivational factors have,

therefore, been subjected to thorough examination, but the affect ofthese factors on productivity has been limitted to the subjective

assessment of the individual's desire to perform.

312

Page 344: An evaluation of production output for in situ concrete work

None of the existing motivation theories cover all situations,

and the selection of one or more to suit certain conditions is often

a matter of personal opinion. However, it is possible to select a

combination of theories suited to the narrow band of jobs associated

with construction operatives.

The early theories of' Maslow (El) McClelland (E.2) and Atkinson( E.3) are primarily models based on the individual's motivation,

although job-related and work environment variables are not entirely

ignored. The main emphasis is placed on the individual's

characteristics and the role played by personal needs in determining

work behaviour.

Herzberg's (E.) model attaches more importance to the nature ofthe task and whether a job allows for recognition, advancement andachievement, whilst earlier researchers concentrated on the

individual and working environment. Herzberg's "two-factor theory"advances the argument that Intrinsic rewards are the key to

increasing job performance and satisfaction. The interrelationshipsbetween the major variables are ignored, as in previous "need

theories", although marj are implicit in his model.

The relationships between the main variables associated

with operative motivation have been investigated in several theories.For example, Loche (E.5) focused upon the interaction between task

characteristics and personal aspiration levels; whilst Adams's (E.6)theory of inequity investigated the relationships between the

individual's attitudes towards input, outcomes and reward practices.

Lawler's expectancy-valence theory (E7) acknowledges the

variation in individuals' needs, and that people have differentbeliefs that certain actions will lead to the desired rewards. The

expectancy-valence model points out bow job related variables can

affect future expectancies and emphasizes that certain job attitudesmay serve as intrinsic rewards.

313

Page 345: An evaluation of production output for in situ concrete work

E.2.1 Maslow's HierarchY of Needs

Maslow's hierarchical model is based on the principle that an

individual's needs can be classified into five basic groups, as

summarized in Figure E.1. Also incorporated is the concept that

needs are arranged in levels of prepotency; the lower need being the

dominant motivational factor which monopolizes consciousness until it

is gratified, upon which the next need becomes active. Thus, the

satisfaction of a particular need reduces its power to motivate. At

the highest level Maslow proposed that the "satisfaction-importance"

relationship is reversed and gratification increases motivation.

SLF-ACTtJ AL IZ AT IONself fulfilment or the realization

of one's potential.

ESTEEM

personal feelings of achievnent or

self-esteem, recognition or respect

from others.

AFF]L IAT IONbelong or receive affection.

SAFETY

security, stability, absence of pain.

PH YS Ict OG ICALfood, water and air.

Figure E. I Maslow' s Hierarchvof Needs

3111

Page 346: An evaluation of production output for in situ concrete work

L2.2 Achievement Motivation. Theory

Murray's Achievement Theory (E.8) was derived from the concept

that there is a separate need for each type of human behaviour.

Murray suggests that these needs are not predetermined but part of a

learning process; for example, an individual whose needs for

achievement are aroused will attempt to become involved in areas

where he can excel. Murray posits that each need comprises of two

elements, a directional component towards which the motive is

directed, and an intensity component representing the strength of themotive.

These needs, according to Murray, can either be active or

dormant. A dormant need does not necessarily have a weak intensity

component, but the lack of opportunity has restricted its growth.

Murray's theory is similar to Maslow's because they are bothhypothetical statements based upon clinical observations, rather than

empirical, research with behaviour being determined by need orientatedgoals.

Considerable research has been carried out by MeClelland and

Atkinson, resulting in the presentation of a formal model of'

motivated behaviour, based on several principles originating from

earlier research. Atkinson's theory takes the starting point thatindividuals have the potential to exhibit a variety of behaviour

patterns. The aroused motives, and hence the behaviour generated,

depends upon the relative strength (or state of readiness) of the

individual's motives and the stimuli presented by the situation.

Atkinson's model represents the level of' motivation created by

the "need for achievement" although it extends to explain behaviourrelated to the "need f or power" and the "need I or affiliation". The

model holds that the aroused motivation is a joint multiplication

factor of: the original strength of the basic motive CM); the level

of' expectancy that the goal can reach (E); and the perceived value of

the incentive (I), as represented by the following expression.

Aroused Motivation = M x E x I

- 315

Page 347: An evaluation of production output for in situ concrete work

E.2.3 J4Qivat1oni41vgiene TheorYi

Frederick Herzberg' s motivation/hygiene theory, sometimes known

as two-factor theory, has two distinct aspects: the first being atheoretical standpoint on work behaviour; the second focuses upon the

practical aspects of job enrichment and its affect on behaviour.

Herzberg began his initia]. research on motivation in the 1 950's,

and had a tremendous impact on the experimental side of validatingtheories on motivation. The majority of previous research, for

example Maslow's need hierarchy and Murray and Atkinson's work on

achievement motivation, was based on inferences from personal insigJtand experience. Herzberg's systematical style in dealing with the

problem of' motivation involved keeping his theory simple and basing

it on empirical data. This resulted in Herzberg's work being wellreceived by managers, especially as he offered recommendations aimed

at improving motivation via job enrichment.

Herzberg's two-factor theory was based on a study of 200engineers and accountants. In this study each Individual was askedto rank events In their work w.hich led to either extreme

dissatisfaction or extreme satisfaction. The resulting conclusionswere that the job satisfaction consisted of events capable of causingsatisfaction and other events capable of causing dissatisfaction.

These events were found to belong to one of two separate scales and

not opposite ends of' the same scale. The important satisfiers were

found to be related to the nature of the work and the subsequentrewards. For example, the opportunity to fulfil the individual's

needs for self-actualization and self-realization. The main

dissatisfiers were associated with the working environment such as

comparr policy. The three main criticisms of the two-factor theory

are that:

316

Page 348: An evaluation of production output for in situ concrete work

(a) People tend to claim credit for the work they have

done when things go well, but blame the failure of

their working environment when problems occur.

(b) The experiments are a measure of peak (extreme)

feelings, which results in instantaneous eventshaving the greatest measured affect. For example,

an operative may be satisfied with his pay on a

long term basis but is not likely to exhibit

extreme feelings of' satisfaction.

(c) Murray states that a need can be dormant owing to a

lack of' possible expression, and events an

individual has no control over cannot serve as a

stimuli to his needs. For example, supervision, or

comparer policy.

E.2. 1I Equity Theories

Equity theories were developed along a similar line of thoughtby several theorists working independently, in contrast to the

earlier theories usually associated with a line of thought presented

by an individual These earlier theories focused on theidentification of the motivational factors, for example, the

characteristics of the individual or work environment. However,equity theories concentrated on the process of generating behaviour.

The concept of measuring the motivating factors' in terms of theperceived rather than actual situation was also introduced. Adams

states in his theory of inequity that:-

tInequity exists for a Person whenever he perceivesthat the ratio of his outcomes to inputs and the

ratio of Other's outcomes to Other's inputs are

unequal." (E.6)

Inputs are the contribution an individual makes towards hiswork; these may be skill, age or effort. Outcomes are the rewards an

individual receives through his endeavours, these may be pay or

status.

317

Page 349: An evaluation of production output for in situ concrete work

L2.5 Exuectancy/ Valence Theorvi

The initial observations leading to the expectancy/valence

theory originated in the 1930's when Tolinan (E.9) began to introduce

expectancies, and Lewin (E.10) presented the idea of valence (value).The main thrust of the expectancy/valence theory is the relationship

between variables affecting behaviour rather that the identification

of the variables. The development of this theory has resulted in a

number of versions, each having a slightly different emphasis. A

more detailed review of these versions is discussed by Henemen and

Schwab (E.11)• These earlier theories were mainly formulated on theprinciple that:

MOTIVATION = EXPECW1ANCY x VALENCE.

Vroom (E.12) devised a form of motivational assessment and

measurement system in his valency theory of 196k. This was thenamended by Lawler (E.8) taking into account later developments,

resulting in Lawler's comprehensive expectancy/valence theory based

on the following premises.

(a) People have preferences among the various outcomes

that are potentially available to them.

(b) People have expectancies about the likelihood thatan action (effort) on their part will lead to the

intended behaviour or performance.

(c) People have expectancies about the likelihood thatcertain outcomes will follow their behaviour.

(d) In any situation, the actions a person chooses to

take are determined by the expectancies and

preferences that person has at the time.

In Lawler's model, the motivational force is a product ofexpectancies concerning outcomes and the value (valence) assigned to

these outcomes. Vroom's assignment of values to expectancies can

range from 0 (for absolutely no belief that an outcome will follow)to +1.0 (for complete certainty that an outcome will follow). Thevalues assigned to valence can range from -1.0 (when the subject

318

Page 350: An evaluation of production output for in situ concrete work

E

LEXPECTANCY

strongly prefers not to achieve the stated outcome) to +1.0 (when the

subject has a strong preference to reaching the stated outcome). The

probability assigned to the expectancies that an outcome will follow

a particular action (E-0) is the product of these two

probabilities.

(a) The expectancy that he will accomplish his intended

performance (E—.'.P).

(b) The expectancy that reaching the Intended

performance will lead to certain outcomes (P—'-O).

The determinants of a person's E—.-P expectancies are shown in

Figure E.2. The single most important of these factors is the

Individual's perception of' a situation. Past experiences are alsoimportant as perception Is part of the overall learning process.

People with low self-esteem usually underestimate the probability of

their own success, and are therefore difficult to motivate with

rewards linked to success.

Communication

from others

Figure E.2 DeterRlnants of K—s-P ExDectancIea

319

Page 351: An evaluation of production output for in situ concrete work

The determinants of P—q..O expectancies are shown in Figure E.3.

Again, the most influential of these are the actual situation,

previous experiences in similar situations and comments made by

people about the situation. A person who thinks he can significantly

control what happens to him will have high P—' . O expectancies.

j.gure E. Determinants of P—.O Exiectanoiea

The valence of an outcome is determined by the perceived

fairness of the input - output balance. The presence of inuity, asstated by Adams, will motivate an individual to redress thesituation.

320

Page 352: An evaluation of production output for in situ concrete work

An important point in Lawler's Expectancy Motivation Model is

that. while some outcomes are sort after as a goal in themselves,

others (Outcome V5) are seen as paths leading to future outcomes

(Outcome V1), as illustrated in Figure E.k. For example, an initial

outcome may be recognition with the final goal being promotion.

The motivational strengths of individual outcomes can be

summated to obtain the overall motivational strength for a given

situation. This can be represented by the following formula, as

developed by Lawler.

Motivation Strength = [(E—.P) x

where V Valence

For example, at the start of a contract a steel fixer may rate

his probability of reaching a certain pert orinance as 0.70 and the

probability of then receiving a full bonus as 0.90. The perceived

probability of receiving a full bonus is therefore +0.63 (i.e. 0.70 x

0.90). Also, at the end of the project be may realize that the

probability of this level of performance resulted in him being out of

Work sooner is 1.0. The value assigned to receiving a full bonus

could be +1.0 and the value assigned to being out of work soonercould be -0.8. The motivational strength caused by these two factors

is therefore +O.(1, as calculated below.

Expectancy Valence = Motivational Strength

Bonus :0.7 0 x 0.90 x (+1.0) = 0.63

No work = 0.7 0 X 1.00 x (-0.80) -0.56

+0.07

321

Page 353: An evaluation of production output for in situ concrete work

["1L1<

H

r'i

>1

'H

r

H

r

r

'-I

'P.'H

H.P.'.1)

H

in4.1

C

w

WCj

4.1 .,.

'P4

J Il

H>

II H ii

I

0,

'4.4a,In0,0

0)

'-4

9.40a,a,0,U00

in'

I

Page 354: An evaluation of production output for in situ concrete work

E.2.6 Re1.aion$hiD between Motivation and Perforiance

A hypothetical relationship between performance and degree of

motivation was posited by Vroom. In which there are three main

determinants influencing job performance, namely motivation, skill,

strength and clarity of job objectives; these can be expressed as:

Performance motivation x ability x job clarity.

This relationship holds true for most situations. However, when

motivation is very high, resulting in pressure to perform, ability

may be impaired, (i.e. more haste less speed).

E.2.7 Summy or Major Motivation Theories

The five theories on motivation have been discussed in order to

show how the Expectancy/Valence theory was developed. The main

problem with this theory is that, although it is very matheniatie in

structure, all the input values are dependent on subjective

assessments and predictions. The main advantage of this system is

that motivational strengths of different goals can be quantified and

combined, this enables comparisons of different situations to be

made. The earlier models are still appropriate, and often preferred,when the motivational strength of one goal is significantly greaterthat the remainder.

Maslow' s hierarchy of needs should be divided into two separate

stages. The first stage in the hierarchy contains the basic

physiological and safety needs, which have to be satisfied before the

next stage can operate. The attainment of these first stage needs isnot sufficient on its own to create motivation, hence the second

stage in the hierarchy. The second stage needs are "Affiliation","Esteem" and "Self-Actualization" and represent the motivating goalsin the Expectancy/Valence modeL

323

Page 355: An evaluation of production output for in situ concrete work

E,3 CONSTRUCTION OPERATIVE MOTIVATION

Maslow realized that individuals wish to feel necessary in their

work, gain respect from their employer and colleagues, and to

Identify with a specific skill. However, few jobs contain all these

and Herzberg observed that management try to Increase jobsatisfaction by providing extrinsic rewards such as improved

earnings. The transient nature of the construction industry hasrestricted the use of non-materialistic motivators, although the

monotonous factory environment is often avoided. Consuently,

financial incentives are the predominant methods used to improve

operative motivation.

E.3.1 Financial Incentives

The payment of financial incentives in the construction industry

is an inherent part of wage structures and of paramount importance in

Industrial relations. The remainder of this appendix describes the

various types of incentive schemes currently operating on

construction sites, and also compares the attitudes of management and

labour towards the payment of incentives and the affect on

motivation.

E.3.2 TvDes of Incentive Schemes

Research undertaken by Mackenzie (E13) was based on a survey of

thirty contractors, and showed that a wide variety of incentiveschemes were in operation. However, many of the schemes were very

similar, the following groups being identified.

(i) Piecework Schemes

A large proportion of construction companies pay their workforcein accordance with one of the National Work Rule Agreements, asopposed to piecework Incentive schemes. However, nearly a].].contractors also employ a large element of sub-contractor labour, whogenerally work to a schedule of prices (piecework).

3 2I

Page 356: An evaluation of production output for in situ concrete work

(ii) Direct 1OO Schemes

Mackenzie found this to be the most widely used type of

incentive scheme among the contractors he visited, although several

variations were encountered. The variations in direct schemes are as

a result of the actual calculation of bonus paid, these are:

(a) 'Hours saved' (e.g. target = X hours/pipe laid)(b) 'Cash' (e.g. target = £X/pipe laid)

(c) 'Output' (e.g. target = £X/pipe laid/week)

(iii) Direct, Geared Schemes

The majority of geared direct schemes work on an hours savedbasis, with the percentage increase in performance not rewarded bythe same percentage increase in bonus payment. The extent of gearingis usually between forty and ninety per cent

(iv) Indirect Schemes

Indirect schemes are used where operatives are involved in

providing a service rather than a finished product, and the level of'

performance is difficult to determine. For example, a general

labourer may have his bonus linked to performance of the concretegang.

(v) Banded Schemes

Banded schemes are based on the same principles as the other

schemes, but there are distinct steps instead of' a linearrelationship between performance and bonus paid. This type of scheme

is not very common but is effective where the work performed iscomplex and varied.

325

Page 357: An evaluation of production output for in situ concrete work

(vi) Merit Scheies

Merit schemes are paid not as a bonus but as a reward for

experience or qualifications. The most common type being the paymentmade to a ganger above the normal rate. The payment in this type of

scheme may involve variable daywork rates, increased bonus rates or

other one-off benefits.

(vii) Policy Schees

'Very few contractors have formal policy schemes, althougi someprovisions are made for adjustments to be made for any fluctuations

in labour demand. Policy schemes introduced to attract key

individuals are difficult to remove once the demand has passed.

E. 3.3 Ranking of ODerativea' Needs

As previously discussed, an individual is not merely motivatedby the actual. rewards he receives but also by how he perceives the

benefits. The perceived ranking of operatives' needs has been

researched by Wilson (E.1k) from the operatives' point of view and by

Mackenzie (E.15) from the management point of' view. A comparison ofthe results is presented in Table E.1.

326

Page 358: An evaluation of production output for in situ concrete work

Table Li Comnarison of Incentive Rankings

Theoretical Ranking Operative Management

(After Maslow) Ranking Ranking

(A.J. Wilson) (RI. Mackenzie)

Physiological. Needs

Earnings 3 1

Short travel to and from site 7 -

Safety Needs -

Physical/Safety/Working Conditions 1 7

Welfare Conditions 2 6

Job Security 18

Belonging Needs

Friendliness of site 10

Work with people as a team 12 9

Work on a well organized site k: 2

Good relations and management 1k 3

Fringe benefIts 15 8

Need for esteea

Recognition from management/

work-mates 10 -

Working for a successful company 18 -

Working for a modern compa 15: -

Need for seif-actualisation

Challenge in the job 17 -

Job freedom 9 11

Plenty of time f or personal/

family life 6 5

Prospects for promotion 21 12

Opportunities for training 20 12

Ability to make use of, and

develop skills 8 -

32?

Page 359: An evaluation of production output for in situ concrete work

From the simplified ranking system used in both studies, and theresults presented in Table El, it would appear that management havemisinterpreted the iinportence of some of the operatives' needs. The

management survey suggests that, given the opportunity to increaseearnings through increased output, the site operative will readily

accept poor working conditions. However, the operatives' surveysuggests that the need for increased earnings is overshadowed by a

greater need f or improved safety and physical working conditions.

The second factor misinterpreted by management Is job security.

It is thought by the majority of management that this was quite a

powerful incentive, particularly towards the end of a project.However, job security was given a very low ranking by the operatives,

probably because moving at the end of a project has become an

accepted facet of construction work. The low ranking given by the

operatives to needs such as esteem and self-activation probably stemsfrom the lack of opportunity to obtain these rewards In theconstruction industry.

R.3 .4 ConstructIon Operative Performance

The motivation theories discussed in this appendix are complexand are aimed at identifying factors which affect operativemotivation, rather than measuring results in terms of productivity.

For example, Maslow, Murray and Herzberg all concentrate on theisolation of the individual's basic needs. Thus, several complex

hypotheses, relating motivational strength to the Individual's basic

needs, have developed with little or no quantative measurements made.

The complexity of existing motivation theories renders them virtually

useless in any quantative assessment of relationships between

incentives and productivity. A more simplistic approach is taken

during this research and a quantative relationship between motivation

and production is developed. Productivity is measured in terms ofsite factors and some of the variables affecting operative motivation

are isolated. For example, Figure E.5 illustrates the relationshipbetween site factors and level of remuneration. This figure has been

extracted from Chapter 9.

328

Page 360: An evaluation of production output for in situ concrete work

TOTAL SITE FACTOR AGAINST REMUNERATION

3 Legend

2.8 ........................................

2 .6 ........................................

A CONCRETE GANGS

X FORMWORK GANGS

o STEELWORK GANGS

REiNFORCEMENT GANGS

PRE-CAST CONCRETE GANGS

2.4

2.2

U2

cc)

-J

01.8

1.6

1.4

1.2

12

xA

........................I.......................................

........><.......................................................

.....................................................

xzx0

2.5 3 3.5 4 4.5REMUNERATION 5/Hr.

LFIGURE E

Page 361: An evaluation of production output for in situ concrete work

APPENDIX F

BASIC STATISTICAL ThEORI

330

Page 362: An evaluation of production output for in situ concrete work

APPENDII F

BASIC STATISTICAL THEORIES

F.1 INTRODUCTION

Chapters Five and Nine investigate the degree of relationship

between several variables, and determine how well linear or other

equations describe or explain these relationships.

To assist in these investigations a statistical package called

MINITAB is used. This appendix outlines the main theories used

throughout these stati stical i rwe stiga tions.

F. 2 MEASURES OF VARIATION

A sample can be described by the location of co-ordinates when

plotted on a graph. However, characteristics describing both the

location and the manner of dispersion provides considerably more

information about the sample than does a single measure only

describing the location of the data. Several quantities that can be

used as 'measures of dispersiod are: the 'mean absolute deviation',

the 'variance', and the 'standard deviation'.

331

Page 363: An evaluation of production output for in situ concrete work

F.2.1 Mean Abzolute Deviation

The 'mean absolute deviation' (denoted by M.LD.) Is the

numerical (i.e. positive) value of the deviation of each observation

(Xi) from the sample mean (1). The mean absolute deviation is

sometimes referred to as the 'mean deviation' or 'average deviation'

and can be expressed as:

M.A.D. = I xi

n

Where XI - X is the absolute value of (Xi - X).

The mean absolute deviation Is easy to calculate and simple to

interpret. However, this measure of dispersion does not lend Itselfto further statistical investigations as absolute values are not

suitable for mathematical analysis.

F.2.2 Variance and Standard Deviation

To accommodate measures of variation in more detailed analysis

it is important to remove arty absolute values. One solution may beto define a 'mean signed deviation' as shown below.

'Mean signed deviation' =c1(Xi__1)

Lin

However, this definition does not produce much ioformation about

the overall variation in the data, because E(XI - I) Is always zero.

To obtain the most suitable measure, non-negative values are rsquiredwhilst avoiding absolute values. This Is achieved by squaring the

individual values, the sum of which is called the 'sum of squares'.

332

Page 364: An evaluation of production output for in situ concrete work

To convert the 'sum of squares' into a measure of variation wehave to divide by the number (n) of sample observations. Theobtained value is called the 'sample mean squared deviation' and isdefined as:

= (Xi -X)2n

Usually the sum of squares is divided by n-i rather than by n,because the resulting value represents a better estimate of thestandard deviation of a population from which the sample is taken.In this research n-i is taken as the denominator and 'samplevariance' is defined as:

S2 = (Xi-X)2n-i

In order to obtain a measure of dispersion having the same unitsas the observed values, it is necessary to take the square root ofthe sample variance. The obtained value is known as the 'samplestandard deviation' (S) and is defined as follows:

S =[iXi_i)2 In-i

P.3 LINEAR-CORRELATION

If X and Y denote the two variables under consideration, ascatter diagram shows the location of points (X, I) on a rectangularco-ordinate system. If' these points are close to a straigit line, asin Figures F.i to F2, there is 'linear' correlation. If the pointslie near some curve, there is non-linear correlation, as in FigureF.3. If' the points do not lie near either, they are 'uncorrelated',as in Figure F.4. If Y increases as X increases (Figure F.1) thereis positive or direct correlation. If' y decreases as X increases(Figure F.2) there is negative or inverse correlation.

333

Page 365: An evaluation of production output for in situ concrete work

40

V)><

>-

20

Figure F.160

Positive Linear Correlation

.

A...................

4 LA

................................ .

0

2

4 6 8 10

X AXIS

Figure F.2 Negative Linear Correlation60

A

A

40 A

(I)

A><

>-

20

................................

.1

1 I I

0 2 4 6 8 10

XAXIS

Page 366: An evaluation of production output for in situ concrete work

(1

>-

50

Figure F.3 Non—Linear Correlation

too

4

o-t0

2 4 6 8 10

X AXIS

Figure F.4 Uncorrelated Results

20-

15-

(I)><<1-

>-

5-

0'0

A.F..........................................

A...........................

- ______________ _______2 4 6 8 10

X AXIS

Page 367: An evaluation of production output for in situ concrete work

Several plots are produced as part of the statistical analysis

presented in Chapter 5. These plots are used in a qualitative

manner to determine how well a given line or curve describes the

relationship between two variables. Some of the scatter diagrams are

selected and plotted in Figures 5.1 to 5.15.

F. II LEAST SQUARES REGRESSION LINES

The method of least squares is used to determine actual

relationships between variables. If there is a linear relationship

between the two variables, the 'best-fiV line can be expressed in

terms of its y-intercept (a) and its slope (b) as shown below.

Y = a+bX

The best-fit line is obtained by minimizing the sum of the

squares of the deviations of the predicted y-values from the observed

y-values. This is known as the 'method of least squares' and the

values of 'a' and 'b' can be obtained from the following uations(F.i)

a = (Efl(zX2) - (EX)(ZXY)

NZX 2 - (ZX)2

b = N2XY - (zX)(zY)

NZX2 - (ZX)2

336

Page 368: An evaluation of production output for in situ concrete work

F. 5 COEFFICIENT OF CORRELATION

The 'total variation' of Y is defined as the sum of the squares

of the deviations of' the Y values from the mean value (Y). This

total variation can be separated into 'unexplained variation' and

'explained variation', as follows.

By definition 'total variation' J (Y)2

If Ye represents the value of Y for given values of X as

estimated from the best-fit line, then:

Y-Y (Y-Ye) + (Ye-Y)

Squaring both sides and then summing produces:

= (Y-Ye) 2 +(Ye-Y) 2 + 2 z(Y-Ye)(Ye-Y)

As the last sum is zero, total variation can be expressed as:

total variation (Y-Ye) + (Ye-Y)2

The first sum in the above equation is called the 'unexplainedvariation' because the deviations Y-Ye are random and unpredictable.

The second term is called the 'explained variation' because the

deviations Ye-Y have a definite pattern.

The ratio of the explained variation to total variation is

called the coefficient of determination. If there is no explained

variation, i.e. the total variation is all unexplained, this ratio is

zero. Conversely, if there is no unexplained variation, i.e. thetotal variation is all explained, the ratio is one. This ratio isdefined as:

R2 = Z(Ye-Y)2E(Y-Y)2

337

Page 369: An evaluation of production output for in situ concrete work

The quantity R is known as the 'coefficient of' correlation' and

varies between -1 and +1. To avoid confusion between these two termsthe coefficients of determination are expressed as percentages

throughout this thesis.

The previous expression (f or R 2) is very general and can be usedfor both linear and non-linear relationships. However, if a linear

relationship is assumed, the following 'product-moment formula' canbe derived, resulting in the following expression:

R Z (X.)(Y-)

F.6 jULTSIS OF VARIANCE

Essentially, the analysis of variance is a technique which

separates the variation that is present into independent components;

these components are subsequently analysed in order to test certain

}rpotheses. In its simplest form this technique is known as the one-way analysis of variance.

The time taken to perform certain activities (eg. vibrate

concrete) often relates to the type of construction (i.e. slabs,walls, beams or columns). Consequently, it is sometimes appropriate

to seperate observations into different samples. Where this is the

case, one-way anova tests are performed to test the hypothesis that

the means of' the different samples are significantly different.

In a one-way analysis of' variance each observation is classifiedinto one sample, and the Irpothesis that: "the means of' these samples

are equal" is tested. This hypothesis is tested by calculating theratio of the "among samples mean square" to the "within samples mean

square", (MSC/MSE). The hypothesis is rejected if' this value (knownas the F statistic) exceeds the upper-point of the F-distribution

having the appropriate degrees of freedom. The level of significanceis the probability of' rejecting the hypothesis when it is, in fact,

true. This value is taken as 0.025.

338

Page 370: An evaluation of production output for in situ concrete work

MEAN

9.3

16.5

21.6

19.1

N

6

12

12

23

ST. DEV.

6.'

9.2

10.6

16.5

LEVEL

I

2

3

F.6.1 Exanple of Analvais of Variance

The following example has been extracted from Appendix D, to

illustrate how the one-way analysis of variance was used to determine

if time taken to prepare the tools was dependent upon the method used

to pour the concrete.

Table P.1 ExamDle of AnalYsia of Variance

-- ONEWAY C63 c62

ANALYSIS OF VARIANCE

DUE TO

DF

ss

MS= SS/DF

F-RATIO

FACTOR

3

661. 220. 1 .29

ERROR

Z9

8352. 170.

TOT AL

52

9013.

POED ST. DEV. =

13.1

INDIVIDUAL 95 PERCENT C. I. FOR LEVEL MEANS

(BASED ON POCLED STANDARD DEVIATION)

4---------4 --------4---------4 --------4 --------4--------+I

2

311 I******I*l*****± - -

+---------4 --------+---------4---------4 --------4--------+-7.0 0.0 7.0 111.0 21.0 28.0 35.0

339

Page 371: An evaluation of production output for in situ concrete work

Fonnulate the null and alternativelrpotheses

HO : Means are all sual.

Hi : Means are not all eival.

Form the above table F 1.29

Calculate from F-Tables F [k-i, n-k]= level of significance = 0.025

n = number of observations 53

k = number of samples - 4

F0025 [4-1, 534)

F0025 [3 49] 3.4

F<F

1.29 < 3.4

We accept Ho

This test shows that the time taken to prepare the tools is not

dependent upon the method used to pour the concrete.

340

Page 372: An evaluation of production output for in situ concrete work

REFERENcES AND B]BLIOGRAFIIT

3k1

Page 373: An evaluation of production output for in situ concrete work

REFERENCES

Reference Page

1 .1 ASHWORTH, A., The source, nature and comparison of 2

published cost information.

Building Teohnolor and Management, March 1980.

1.1 MASON, C., The limitations of estimators' data bases. 2

- M.Sa. project report, Department of Civil Engineering,

Loughborough University of Teohnolor, September 1979.

1 .2 RITTIaJDEN VOOR BOUWACTIVITEN, Volumes 1lI, 3

Boekuitgave 1977, Utigeversmaatsohappij.

C. Misset By, Doetinchen. S.O.A.B., Holland.

1.3 McKEE, K., 3

Productivity in Civil Engineering and Construction.

Civil Engineering A.S.C.E., February 1982.

2.1 BRITISH STANDARDS INSTIIUTION, Glossary of Terms used 11in work study and organization and methods (0 & M).

BS3138: 1979.

2.2 O'MALLEY, C.D. and S&JNDERS, 12Leonardo da Vinci on the Human Body.

Schumann, 1952.

2.3 LARKIN, J.k, 13Work Study - Theory and Practice.

McGraw-Hill, London, 1969, p. 2.

2.k TAYLOR, F.W.,

The Principles of Scientific Management.

Harper & Brothers, New York, 1929, p. 36.

3

Page 374: An evaluation of production output for in situ concrete work

Reference Page

2.5 TAYLOR, F.W., Scientific Management; Comprising Shop iLl

Management, Principles of Scientific Management, and

Testimorr before Special House Committee.

Harper & Brothers, New York, 1 9147.

2.6 GILBRETH, F.B., Motion Study. 16

D. Van Nostrand Co., Princeton,.N.J., 1911.

2.7 GILBRETH, FB., and GILBRETH LM., 16

Classifying the 16 Elements of Work.

Mangement and Administration, Vol. 8,

No. 2, page 151, August, 19214.

2.8 QJRRIE, R.M., Work Study. 17

PiUnan, 1963, page 7.

2.9 TIPPETT, L.H.C., 17

Statistical Methods in Textile Research.

Shirley Institute Memoirs, Vol. 26, pp. 51-55, 75,

February, 1935.

2.10 MORROW, B.A., Motion Economy and Work Measurement. 17Ronald Press, New York, 1957, 1468 pages.

2.11. MAYNARD, RB., STEGEMERTEN, G.J., and SCHWAB, J.L., 18

Methods - Time - Measurement.

McGraw-Hill Book Co., New York, 19148, 292 pages.

2.12 TEAKE, S., 19Proournent and Productivity - the scope for change.

Industrial Forum, Vol. 5, No.1-2, 19714, pp. 9-17.

2.13 GANTT, ILL, Work, Wages and Profits. 19Engineering Co., New York, 1913.

3113

Page 375: An evaluation of production output for in situ concrete work

Reference Page

2.1 11 Marshall Report, 1970. 211

Departhient of the Envirormient.

2.15 Report No. 29. 211

Prices and Incomes Board, March 1967.

2.16 CORNWALL COUNTY CGJNC]L HIG,JAYS DEPARTMENT, 211

Composite Work Values, Highways Construction and

Maintenance. August 1982.

2.16 LINCOLNSHIRE COUNTY COUNCIL, Standard Minute Values. 211

July 1978.

2.17 HIGThJAY ENGINEERING COMIUTER BRANCH, The Rate System. 2)1

Department of Transport.

2.17 B.S. PARMENTER, Estimating resources and costs f or 211

highway works - development of the Rate System.

T.R.R.L. Report 957.

2.18 NOTTINGHAMSHIRE COUNTY COUNCIL, Standard Minute Values. 211

Managnent Services, 1979.

2.19 JOINT INDUSTRY BOARD FOR ThE ELECTRICAL CONTRACTING 25

INDUSTRY, National Library of Work Study Data. 1973.

2.20 BRITISH WATERWAYS BOARD, 27

Piling and Dredging Bonus Schemes. 1982.

2.21 BUILDING SERVICES RESEARCH AND INFORMATION SERVICE, 28

Estimator' s Guide to Labour Times. BSRIS.

2.22 FORBES, W.S., 31

The Rationalisation of House Building.

B.R.E. CPII8/77.

31111

Page 376: An evaluation of production output for in situ concrete work

Ref erence Page

2.22 FORBES, W. S. and STJERNSIEDT, J. I., 31The Finchamatead Project Building.

B.R.E., CP. 13 October 1972.

2.23 TRANSPORT AND ROAD RESEARCH LABORATORY, 30

CODDLE and COSSIT work study data on road surface.

Internal Data stored on tape.

2.2k ThICKETT, H., 31

The Impact of Frank Gilbreth,

Scientific Business, August 1965, pp 199-2C6.

2.2k FORBES, W. S. and MAYER, J.F., 31.

The output of bricklayers.

Building Research Station, Current Papers, March 1968.

3.1 HARRIS, F.C. and MoCAFFER. R., 36

Modern Construction Management. Granada, 2nd Edn, 1983.

3.2 BORCHERDING, J.D., 39

Participative Decision Making in Construction.

A. S. C. E., Journal of the Construction Division, Vol. 103,

No. it, 1977, pp. 567-575.

3.3 EASTON, G.R. and WOODHEAD, R.W.. 39

A survey of motivation and productivity on Australian

construction sites. Report prepared for the Australian

Project Managers's Forum, School of Civil Engineering

University of' New South Wales, Australia, 1981.

3.lt BYGOFORBUNDET, "Method 0th Data". Standard times for

building operations used in Sweden. 1976. B.R.F Library.

5.1 RYAN, T.A., JOINER, B.L. and RYAN B.F., 68

MINITAB Referance Manual.

Pennsylvania State University, March 1981.

3 1t5

Page 377: An evaluation of production output for in situ concrete work

Reference Page

7.1 MOORES, B., Relaxation allowances. Work Study and

1211

Management Services, March 1968, pp 145-153.

7.2 HARRIS, F.C. and McCAFFER, R., 1211

Modern Construction Management.

Granada, 2nd Edn., 1983.

7.3 LAMSAC, Manual work within Local Authorities: 121

Relaxation Allowances. LAMSAC, August 1971.

7.11 ASTRAND, I., Aerobic work capacity in men and women 130

with special reference to age.

Aota physiol. scand4,, 119, supplement 169.

7.5 LEGG, S.J. and MILES, W.S., Maximum acceptable lifting 130

workloads for an 8-how' work-day using psychophysical

and subjective rating methods.

Ergonomics, 1981, Vol 211, No 12, pp 907-916.

7.5 DEIVANAYAGAM, S. and AYOUB, M.M., Prediction of

130

endurance time for alternating workload tasks.

Ergonomics, 1979, Vol 22, pp 219-290.

7.5 MURRELL, K.F.}L, 130The nature and measurement of Industrial fatigue.

Work Study and Industrial Engineering.

December 1960, pp 11211_2116.

7.5 MURREL, K.F.H., 130The relationship between work and rest pauses.

Work Study and Management Services,

June 1967, pp 303-306.

7.5 IJRRL, K.F.H., Ergonomics. 130Chapman and Hall, 1965.

3116

Page 378: An evaluation of production output for in situ concrete work

Page

130

Reference

7 .5 MULLER, EA. and FRANZ, M.,

The Physiological Basis of Rest Pauses in Heavy Work.

1952.

7 .5 LEMANN, G., Physiological measurement as a basis of

work organisation in industry.

Ergonomics, 1 958, Vol. 1, 328-31111.

7 .6 ASTRAND, L, Degree of strain during building work as

related to individual aerobic work capacity.

Ergonomics, 1967, Vol. 10, pp 293-303.

7.7 HAMLEY, E.J., The recovery allowance project.

Institute of Management Services, 1980.

7.7 HAMLEY, E.J. and MENNEER, R.H., Scientific evaluation

of cost allowances. Unpublisbed Report, 19814.

7.7 VARIOUS, Bioastronauts Data Books pp. 859-865.

7 .7 MINTER, A.L., The estimation of enerr expenditure.

Work Study and Management Services, July 1970.

7.8 ABEEG, V., ELGSTRAND, K., MAGNUS, P. and LINDHOLM, A.,

Analysis of components and prediction of enerr

expenditure in manual tasks. The International Journal

of Production Research, 1968, Vol. 6, No.3, pp 189-196.

7.8 RYAN, T.A.,

Work and effort: the psycholo of production.

Ronald, 19117.

7.9 SPITZER, H. and HETTINGER, T.,

Tafeln fur den Kalorienumsah bei keorperlicher Arbeit.

196 11, Berlin, Beuth Vertrie GmbIl.

130

130

130

130

130

130

131

131

136

3117

Page 379: An evaluation of production output for in situ concrete work

Reference Page

7.10 GIVONI, H., and GcLDMAN, RF., 137Predicting metabolic energy cost.

Journal of Applied Physiology, 1971, Vol.30, pp 429-1133.

7.11 PANDOLF, LB., GIVONI, B. and GCLDMAN, R.F., 137Predicted energy expenditure with loads while

standing or walking very slowly.

Journal of Aplied Phyhsiology, Vol. 113, pp 577-581.

7.11 PITMENTAL, N.A. and PANDOLF, LB., 137Energy expenditure while standing or walking

slowly uphill or downhill with loads.

7.12 ROHMERT, W., Determination of relaxation periods in 1115

Industrial Operations, Part L

Work Study and Management, November 19611, pp 500-505.

7.12 ROHMERT, W., Determination of relaxation periods In 1115

Industrial Operations, Part II.

Work Study and Management, December 19611, pp 550-556.

7.13 COILETT, LN., MANENICA, L, 1119

The effects and measurement of working postures.

Applied Ergonomics, March 1980,. Vol. 11, pp 7-16.

7.1 11 CORL ETT, K H., MADEL EY, a J. and MAN EN ICA, L, 152

Posture Targetting : A Technique for Recording

Working Postures.

Ergonomics, 1979, Vol. 22, pp 357-366.

7.1 11 LUNDQUIST, OWAS - A method for observing and correcting 152

working postures in agriculture and horticulture.

XXX CIOSTA - Congress and CIGR (V) Symposium, September

1982.

3118

Page 380: An evaluation of production output for in situ concrete work

Reference

Page

7.15 KAEHU, 0., KANSI, P. and KVORINKA, L, 15k

Correcting working postures in industry

A practical. method for analysis.

Applied Ergonomics, December 1977, Vol. 8, pp 199-201.

7.15 KARHU, 0. HARKONEN, R., SORVALI, P. and VEPSALAINEN, P., 15k

Observing working postures in industry. Examples

- of' OWAS application.

Applied Ergonomics, March 1981, Vol. 12, p 13-17.

7.16 SCHMIDLKE, M and MALLACH, A., 156

Erholungszuschlage vei leistungshontrollierter.

Industriearbeit REFA-Naehrichten, 1969, Vol.22, pp 77-81.

7.17 ROHMERT, W., 159

Problems in determining rest allowances, Part I.

Applied Ergonomics, August 1973, pp 9 1-95.

7.17 ROHMERT, W., . 159

Problems in determining rest allowances, Part IL

Applied Ergonomics, September 1973, pp 158-162.

10. 1 GRIFFITHS, G., 190

Griffith& building price book.

Barton, 1 980.

10.2 CHRYSTAL-SMITH, G., 190

Spenee Geddes Estimating f or Building and

Civil Engineering Works.

Newnes-Butterworths, London, 1977.

10.3 PRICE, S.G., 190

The Ccmiprehensive Building Price Book, 1983/k.

Wessex.

31j9

Page 381: An evaluation of production output for in situ concrete work

Reference Page

10. L FLEMING, M. C., Pricing in Constuction: 197

the relationship of constants to productivity.

Building Technolo' and Managnent, March 1980, pp 33-37.

11.1 DANLADI, SIC. and HORNER, R.M.W. 200

Managnent control and construction efficiency

J. Cons. Div., A. S. C. E., 1 or co1 , pp. 705-718, Dec. 1981.

11 .2 E14..EY, M. W. and F. C. HARRIS, 208

Computerised Collection of Work Study Data.

Building Technologist, Vol 11, 1981V85.

E.1 MASLOW, AJL, A Thoery of Human Motivation. 313

Psychological Review, 193, 50, Page 370-396.

E.2 McCLELAND, D.C., The achieving society. 313

Princton, N.J., Van Nostrand, 1961.

E.3 ATKINSON, J.W., An introduction to Motivation. 313

Priceton, N.J., Van Nostrand, 1961.

E. HERZ BERG, F., 313

The motivatioWIgiene concept and problems of manpower.

Personnel Administration, 1964, 27 (1), pp. 3-7.

E.5 LOaIE, D.A., 313

Goal setting a motivational technique that works

Prentice-Hall, 19811.

E.6 ADAMS, J.S., Inequity in social exchange. 313

Advances in experimental, social psychology,

pp. 276-299, Academic Press, 1965.

E.7 LAWLER, F..E., Motivation in work organizations. 313Brooks/Cole, 1973, pp.1111-147.

350

Page 382: An evaluation of production output for in situ concrete work

Reference Page

E.8 I4JRRAY, E.J., Motivation and notion, 315

Prentice-Hall, 1964.

E.g TOLMAN, E.L, Purposive behaviour in animals and men. 318

New York, Century Co., 1 932.

E. 10 LEWIN, K., A Dynamic thoery of personality. 318

New York, McGraw, 1935.

E.11 HENEMEN, }LG. and SCHWPB, D.P. 318

Perspectives on Personnel: Human Resource Management.

Irwin, 1982.

E.12 VROOM, V.11., Work and motivation, 318

New York, Wiley, 19614.

E. 13 MACKENZIE, K. I., A review of incentive schemes in 3214

building and civil engineering. MSc. Project Report,

Loughborough University of Technology.

E.14 WILSON, A.J., Need-improtant and need-satisfaction for 326

construction operatives. MSc. Project Report,

Loughborough University of Technology.

E. 15 MACKENZIE, K. I and Harris, F. C., 326

Money the only motivator?

Building Technology and Management, May 19814.

351

Page 383: An evaluation of production output for in situ concrete work

BIBLIOGRAPHY

ARTICLES AND PAPERS PUBLISHED AT LO(JGHBOROUGH

HARRIS, P.C. and PRICE, A.D.F.,

An evaluation or production output for construction labour and plant.

SERC Grant GR/B 55138, 1981_1981.

PRICE, A.D.F. and HARRIS, P.C.,

Methods and Rates for Concrete and Bituminous Road Paving Operationa

Internal report published for S.E.R.C., 1985.

PRICE, A.D.F. and HARRIS, F.C.,

Methods and Rates for Concreting Operations.

Internal report published f or S. E. R. C., 1985.

PRICE, A. D. F. and HARRIS, F. C.,

Methods and Rates for Formwork Operations.

Internal report published f or S. E. B. C., 1985.

PRICE, A.D.F. and HARRIS, F.C.,

Methods and Rates for Fixing Reinforcnent.

Internal report published f or S.E.R.C., 1985.

PRICE, A. D. F. and HARRIS, F. C.,

Methods and Rates for Drainage Operations.

Internal report published f or S. E. B. C., 1985.

352

Page 384: An evaluation of production output for in situ concrete work

EMEY, M. W. and HARRIS, F. C.,

Methods and Rates for Structural' Steel.

Internal report published for S. E. R. C., 1985.

EMSLEY, M.W. and HARRIS, F.C.,

Methods and Rates for Pre-oast Concrete.

Internal report published for S.E.R.C., 1985.

BROOMFIELD, J.R., PRICE, A.D.F. and HARRIS, F.C.,

Production analysis applied to work improvement.

Proceedings , Institution of Civil Engineers, -

Part 2, 198k, k, Sept, pp 379-386.

PRICE, A.D.F. and HARRIS, F.C.,

Methods of' measuring production times for construction work.

C.LO.B., Technical Information Service, No. 1g, 1985.

PRICE, A.D.,

Methods and Rates for Concreting Operations.

Concrete, Journal of the Concrete Society,

Aug. 1985, Vol. 19, No. 8.

BROOMFIELD, J. R., PRICE, A. D. and HARRIS, F. C.,

Production analysis applied to work improvent:

Discussion. Proceedings , Institution of Civil Engineers,

Part 2, 1985, 79, June, pp 131..133.

An evaluation of' production output f or labour and plant on

specialised construction work.

Current research sponsored by the Science and Engineering Research

Council for three years. 1985-1988.

353

Page 385: An evaluation of production output for in situ concrete work

HARRIS, F.C.,

A model for evaluating the effects of weather on construction

projects. A thesis submitted in partial fulfilment for a Doctor's

Degree of L oughbor ough University of Tech no]. ogy, Nov em ber 1 979.

SHORT, N.L,

A comparison between trench support systems and traditinal methods of

shoring. B.Sc. Project Report, Department of Civil Engineering,

Loughborough University of Technology, April 1981, and a paper

jointly with F.C. HARRIS published in Building Technology and

Management, April 1983 .-

BROOMFflLD, J.,

Construction work study in perspective M.Sc. project report,

Department of Civil Engineering, Loughborough University of

Technology, September 1983.

WPLLACE, W.A.,

Management organisation and operative performance, M.Sc.project

report, Department of Civil Engineering, Loghborough University of

Technology.

3 51j

Page 386: An evaluation of production output for in situ concrete work

WORK S1JDI

LARKIN, J.A., Work Study - Theory and Practice.

McGraw-Hill, Maidenhead.

BARNES, R.M.,

Motion and Time Study Design and . Measurement of Work.

John Wiley & Sons, New York, 1976.

VARIOUS. Introduction to Work Study.

I.L.O., Geneva, 1978

MODER, J.J.,

Activity Sampling with Application to time Standard Estimation.

The Journal of Industrial Engineering, January 1967, pp 2k-29.

NOEL-BROWN, S.J., The History of Work Study.

Work Study and Management Services, December 1969, pp 816-822.

DUDLEY, N.A., Research findings and work study practice.

Work Study and Management, September 1986, pp l56-157.

GIBSON, D., Work sampling monitors job-shop productivity.

Industrial Engineering, June 1970, pp 12-19.

DAVIDSON, 11.0., Work Sampling - Eleven Fallacies.

The Journal of Industrial Engineering,-October 1960, pp 367-371.

ROWE, D.N., A Binomial Procedure for Activity Sampling.

Work Study and Management Services, March 1973, pp 162_1611.

ESPIE, 11.3. and METCALFE, M.,

A Practical Technique of Sjuential Work Sampling.

Time and Motion Study, January 1962, pp 17-21.

STEVENS, A.J.,

Activity Sampling Studies Aided by the use of an Optical Reader.

Work Study, January 1967, pp 21-29.

355

Page 387: An evaluation of production output for in situ concrete work

WORK STUDY STATISTICS

MOSKOWITZ, A.D. and BURKACHI,

Wqrk Sampling - sample size and confidence limits.

Work Study and Management, pp 12-14.

SASTRY, £S.R.,

Control charts for work sampling studies with variable sample size.

Work Study and Management Services, April 1968, pp 221221I.

CONWAY, LW.,

Some Statistical Considerations in Work Sampling.

The Journal of Industrial Engineering, April 1957, pp 107-111.

GREGERMAN, LB.,

The productivity measurement of construction labour using work sampling.

A.S.C.E. Transactions, 1981, pp 1.81-5.

KANON, D.,

Application of Nonparametric Statistics to Industrial Engineering.

The Journal of Industrial Engineering, Volume 18, No. k, pp 272-276.

MELLOR, R.,

Multiple regression.

Work Study and Management Services, July 1910, pp 572_5711.

MINTER, A.L.,

Statistics and Work Study.

Work Study and Management:

Part 1, June 1966, pp 298-33.

Part 2, July 1966, pp 352-35k.

Part 3, August 1966, pp kOl-k04.

Part k, Septnber 196 6 , pp 161I-1466.

Part 5, 1966, pp 530-532.

356

Page 388: An evaluation of production output for in situ concrete work

FENSKE, R.W.,

Extracting more Information from a Work Sampling Study.

The Journal of Industrial Engineering, July 1967, Volume 18,

No. 7, pp 17-20.

CLAY, M.J.,

Sensitivity Analysis.

Work Study and Management Services, August 1970, pp 639-643.

JONES, N.G. and GHARE, P.M.,

Statistical Standards.

AIIE Transactions, March 1970, pp 37-5.

MOORE, J.M.,

Which Test Statistic? - A Scramble Book Approach.

The Journal of Industrial Engineering, May 1967, pp 300-305.

BENJAMIN, J.R. and CORNELL, C.A.,

Probability.

Statistics and Decisions for Civil EngIneers, pp 16O5O0.

357

Page 389: An evaluation of production output for in situ concrete work

CONSTRUCTION VORI STUD!

EVERWYN, G.,

Chart Aids Construction.

Work Study, February 1967, pp 31-32.

McDAVID, 1.3.,

The European Work Study Federation.

Work Study and Management Services, August 1970, pp 653-655.

STEVENS, A.J.,

Activity Sampling on Building Sites -

Further Experiences in the use of Optical Readers.

B.R.E. CP. 16/69.

WALLIS, H.P.,

Work Study applied to the cost of Building Research.

Work Study, March 1967, pp 3l_39.

TREDWELL, J.E.B.,

The Application of Work Study Techniques in the Construction Industry.

Work Study, January 1967, pp 9-17.

KOEHN, E.,

Work Sampling and Unit Man-hours,

Cost Engineering, Volume 25, No. 1, February 1983. pp 35-1O.

GEARY, B,

Work Study - Applied to Building.

George Godwin, Aidwych, 1965.

WILDE, E.,

The Building Industry could well employ Work Study -

and get out of the Redi

Work Study, February 1975, pp 13-25.

358

Page 390: An evaluation of production output for in situ concrete work

BURGASS, LA.,

Management Services in construction.

Management Services, February 1968, Volume 12, No. 2, pp 32-35.

BLAIN, B.C.L,

Incentive Pay Schemes in the Construction Industry.

Work Study, November 1981, pp 32-39.

SKERM, WC.,

Plumping: An analysis of the time spent on site activities. -

The Heating and Ventilating Research Association,

Laboratory Report No. 69, July 1971.

FINLAYSON, D.M.,

Productivity in railway civil engineering.

Work Study and Management Services, August 1969, pp 506-510.

FOSTER, A.G. and SMITH, E.R.,

A confirmatory case study of installation work.

The Heating and Ventilating Research Association,

Laboratory Report No. 69, April 1966.

PARFITT, R.,

The comparison of actual and expected costs in contracting.

The Heating and Venilating Research Association,

Laboratory Report No. 76.

359

Page 391: An evaluation of production output for in situ concrete work

£ONSTRUJ TION PRODUCTIVITY

ANON,

Better trained construction supers would boost productivity.

Civil Engineering/A.S.C.E., March 1983, pp 60-62.

PEUIFOY, R.L.,

Fifty years of construction cost-reducing analyses.

Proceedings of the American Society of Civil Engineers,

Vol. 101, No. CO2., June 1975, pp 299-307.

PAULSON, B.C.,

Estimation and control of construction labour costa

Proceedings of A.S.C.E., Voltme 101, No. CO3,

September 1975, pp 623-633.

BORCHERDING, J.D.,

Improving Productivity in Industrial Construction.

Proceedings A.S.CE., Volume 102, No. C04, December 1976, pp 599-613.

LOGCHER, R.D. and COLLINS, W.W.,

Management Impacts on Labour

Productivity. Proceedings A.S.C.E., Volume 104, COIl, December 1978.

WIGGLESWORTN, G. and WISDOM, D.,

Procurement Methods - their Affect on the Industrialization of Building.

Industrialization Forum, Volume 5, No. 1-2, 197Il, pp 19-21.

HOHNS, N.M.,

Productivity - an updated concept of management.

A.S.C.E. Transactions, 1979, pp 1.1-1.3.

WATSON, B.W,

The operator - the unknown factor in considering plant operating costs.

A. R. R. B. Proceedings, Volume 8, 1976, pp 16-22.

360

Page 392: An evaluation of production output for in situ concrete work

CONSTRUCTION ESTIMATING

FLEMING, M.C.,

Pricing in construction the relationship of constants to productivity.

Building and Technology Management, December 1978, pp 6-9.

HARRIS, F.C.,

Controlling costs on site.

Building Technology and Management, November 1976, pp 5-8.

NEALE, R.H.,

Estimating for f'alsework.

I.O.B. Estimating Information Services, No. 2 1 , Spring 1977.

BAKER, E.M.,

Formwork and Site Management.

I.O.B. Site Management Information Service, No. 53, November 1973.

BENTLEY, J.I.W.,

Pricing formwork.

LO.B. Estimating Information Service, No. iLl, October 197k.

361

Page 393: An evaluation of production output for in situ concrete work

CONSTRUCTION PLANNING

CARR, I.R.,

Simulation of Construction Project Duration.

A.S.C.E. Proceedings, Volume 105, No. CO2, June 1979, pp 117-127.

GATES, H. and SCARPA, A.,

Conceptual RMC/Time Synthesis.

A.S.C.E. Proceedings, Volume 102, No. c02, June 197 6 , pp 3Y1-323.

CRANDALL, K.C.,

Analysis of Schedule Simulations.

A.S.C.E. Proceedings, Volume 103, No. c03, September 1917, pp 3&T-3911.

BURGER, A.M. and HALPIN, D.W.,

Data Base Methods for Complex Project Control.

A.S.C.E. Proceedings, Volume 103, No. CO3, September 1917, ppjil53.*il3.

POPESCU, C.M.,

Update of CPM/PERT Glossary of' Terms.

LS.C.E. Proceedings, Volume 10Z, No. COl, March 1978, pp 35k1.

POPESCU, C.M.,

CPM-Interactive Training Tool.

A. S. C. E. Pro ce e di ngs, Volume 1 OIl, No. CO2, June 197 8, pp 157-166.

POPESCU, C.M. and BORCHERDING, J.D.,

Developments in CPM, PERT and Network Analysis.

LS.C.F Proceedings, Volume 101, No. CO il, December 1915, pp 769-783..

POPOESCU, CM.,

CPM - Cost Control by Computer.

A.S.C.E. Proceedings, Volume 103, No. CO il, December 1977, pp 593-609.

362

Page 394: An evaluation of production output for in situ concrete work

PANP.OIOTAKOPOULOS, D.,

Cost-Time Model for Large CPM Project Networks.

A.S.C.E. Proceedings, Volume 103, No. CO2, June 1977, pp 201-21.

CRANDALL, K.C.,

Scheduling Network Loop Detection.

A.S.C.E. Proceedings, Volume 103, No. COIl, December 1977, pp 555-565.

KAWAL, D.E.,

Information Utilization in Project Planning.

A.S.C.E. Proceedings, Volume 97, No. CC2, November 1971, pp 227-239.

O'BRIEN, J.J.,

VPM Scheduling f or High-Rise Buildings.

LS.C.F. Proceedings, Volume 101, No. COIl, December 1975, pp 895-905.

PAULSON, B.C.,

Man-computer concepts f or planning arid scheduling.

A. S.C.E. Proceedings, Volume 98, No. CO2, September 1972, pp 275-286.

363

Page 395: An evaluation of production output for in situ concrete work

CONSTRUCTION OPERATIONS

BAKER, E.M.,

An appreciation of site management problems in the production of in

situ concrete structures.

I.O.B., S.M.I.S., No. 39, July 1971.

JLLINGWORTH, J.R.,

Rei nf' orced concrete constructi on.

Building Technolor and Management, September 1982, pp 13-15.

WALKER, }LB.,

Design and economics of steel-framed multi-storey buildings.

Building Technolor and Management, September 1982, pp 17-20.

MINTER, A.L.,

The distribution of concrete.

Work Study and Management Services.

NEALE, R.H. and ROEDER, A.R.,

Factors influencing the cost of concrete.

I. 0. B. Estimating Information Service, No. 13, July 197 1.

WADDELL, JJ.,

Handling Concrete - Then and Now.

A.S.C.E. Proceedings, Volume 101, No. C01, December 1975, pp 819..87.

SHUTIEN, L. and STEWART, D.A.,

Pertinent techniques for compacting concrete.

CF. Proceedings, Volume 98, No. CO2, September 1972, pp 173_180.

36 1

Page 396: An evaluation of production output for in situ concrete work

MOTIVATION

HOOSE, R.J., and WIGDOR, L.A.,

Herzberg's dual-factor theory of' job satisfaction and motivation:

A review of the evidence and a criticism.

Personal Psychology, 1967, 20, pp 369-389.

STEERS, R.M. and PORTER, L.W.,

Motivation and Work Behaviour.

McGraw-Hill, 1975.

WESLEY-LEES, J.N.,

Motivation, expectancy theory and design of payment systems.

Loughborough University, 1976.

365

Page 397: An evaluation of production output for in situ concrete work

RELAXATION ALLCM&NCES

CHAMBERS, E.G.,

Industrial fatigue.

Work Study and Industrial Engineering, March 1962, pp 91.914.

MoDAVID, I.S.,

Rest pauses and relaxation allowances - problems of practical

application.

Work Study and Management, September 19611, pp 398-11011.

HUMBLE, L.,

Rel axation allowances.

Work Study and Management, August 1965, pp 31111-3116.

MADLEY, S.,

The development of a new technique f or the analysis of work load.

PhD Thesis, Department of Engineering Production, University of

Birmingham, 1971!.

SOULE, E.G. and GOLDMAN, R.F.,

Terrain coefficients f or energy cost prediction.

Applied PIsio1ogy, 32, pp 706-708, 1972.

TOMLINSON, R.W. and MANENICA, L,

A study of physiological and work study indices of forestry work.

Applied Ergonomics, Vol. 8, No. 3, 1977, pp 165-172.

ELVERS, D.A.,

Planning monitoring frequences f or CPM projects.

A.S.C.E. Proceedings, Voliine 97, No. CO2, Novnber 1971, pp 211-225.

366

Page 398: An evaluation of production output for in situ concrete work

RECOBDING

DAVIS, D.,

Video Tape Recording.

Work Study and Management Services, March 1970, pp 217-218.

SAKUMA, A.,

Video time study.

LE. Special Report, February 1973, pp 11-15.

PEER, S. and KENNEDY, W.B.,

Video methods analysis.

LE. Special Report, February 1973, pp 16-20.

RYDELL, R. L.,

Timelapse photography gets the data.

LE. Special Report, January 1973, pp 1012.

VITS, L.J.,

Video tape f or cost reduction.

LE. Special Report, February 1973, pp 21-23.

AN ON,

Mobile VTR Laboratory.

Building, 8 October 1971, pp 125-130.

367 -