an intelligent restoration system for a self-healing smart ......university of central florida 10...
TRANSCRIPT
An Intelligent Restoration
System for a Self-healing
Smart Grid
Dr. Wei Sun, Assistant Professor
ECE Department, University of Central Florida
SmartGridComm 2015
Nov. 2, Miami, FL
University of Central Florida2
Could a smart grid have prevented
the Super Bowl blackout?
University of Central Florida3
Motivation: cascading failures,
blackouts, nature disasters
Efficient
Recovery
University of Central Florida4
Self-healing and Resilience
Fault
Identification
Protection
Decisions
Event
Identification
Potential Failure
Identification
Vulnerability
Assessment
Post-Restoration
Status Evaluation
Power System
Restoration Strategies
Remote and
Field Control
University of Central Florida5
Power System Restoration
PreparationSystem
Restoration
Load
Restoration
• Determine system status
• Restart generators
• Network preparation
• Energize transmission
paths
• Restore sufficient load
• Resynchronize islands
• Minimize unserved load
• Schedule load pickup
University of Central Florida6
Restoration Decision Support Tool
University of Central Florida7
On-line Decision Support Tool
for Power System Restoration
University of Central Florida8
System Restoration Procedure
University of Central Florida9
• Blackstart generators hydro or combustion turbine units
• Non-blackstart generators steam turbine units
Optimal Start-up Sequence
of all generators
Generation Capability Optimization
istarttistart ictpt T
maxiP
(MW)igenP
tmaxiistart ictp
ri
Pt T
R T
Generation Capability Curve
0
Gen. Characteristics:
Maximum generator MW output
Generator ramping rate
Cranking time to ramp up and parallel
with system
Critical maximum/minimum time interval
Specified system restoration period
University of Central Florida10
Generator Start-Up Sequencing
Mathematically, it is a nonlinear combinatorial optimization problem.
Developed Mixed Integer Linear Programming (MILP)-based strategies
Max Overall System Generation Capability
subject to
Critical Minimum & Maximum Time Intervals
Start-Up Power Requirements
Discrete Optimization:
• Integer variables of generator starting time
• Binary variables of generator commitment
• Continuous variables of generation level
W. Sun, C. C. Liu, and L. Zhang, “Optimal Generator Start-up Strategy for Bulk Power System
Restoration,” IEEE Transactions on Power Systems, vol. 26, no. 3, pp. 1357-1366, August 2011.
University of Central Florida11
Transmission Path Search
Find optimal transmission path to:
• Crank non-blackstart generating units
• Build transmission network
Motivation:
Max Total Generation Output
subject to
Transmission Line Thermal Limit Constraint
Logic Constraints of Bus/Line Energization
There are Generic Restoration Actions (GRAs) that exist in
diverse restoration strategies.
W. Sun, and C. C. Liu, “Optimal transmission path search in power system restoration,” Bulk Power System
Dynamics and Control - IX Optimization, Security and Control of the Emerging Power Grid, 2013 IREP
Symposium, Aug. 2013.
University of Central Florida12
Time to Take Restoration Actions
Time to Complete Each GRA
GRA Time (min)
GRA1: start_black_start_unit TGRA1=15
GRA2: find_path TGRA2=N/A
GRA3: energize_line TGRA3=5
GRA4: pick_up_load TGRA4=10
GRA5: synchronize TGRA5=20
GRA6: connect_tie_line TGRA6=25
GRA7: crank_unit TGRA7=15
GRA8: energize_bus TGRA8=5
• Blackstart Unit Module
• Non-blackstart Unit
Module
• Bus/Line Module
• Load Module
Reference: J. S. Wu, C. C. Liu, K. L. Liou, and R. F. Chu, “A Petri Net algorithm for
scheduling of generic restoration actions,” Power Systems, IEEE Transactions on., vol. 12,
no. 1, pp. 69-76, February 1997.
University of Central Florida13
MILP Optimization Modules
Overall System Generation Capability
. . Critical Time Intervals Constraint
MW Start-up Requirement Constraint
Generator Capability Function Constraints
Generato
Max
s t
r Start-up Power Function Constraints
Decision Variables Constraints
Transmission Path Search Logic Constraints
Transmission Line Thermal Limits Constraints
Restoration Action Time Constraints
Modules Connection Constraints
I
II
III
IV
University of Central Florida14
Case Studies
AEP System
With 24 seconds of computational time, find the optimal starting
sequence of total 21 NBS and 16 BS generating units
Lewis Creek
Frontier
• Entergy System
– June 15, 2005 Western Region
disturbance.
– Two 260 MW units tripped off line,
and Western Region separated
from rest of system.
– There was blackstart power from
outside to start 1 generator.
University of Central Florida15
Case Studies
PECO System
Based on PECO-Energy system data, and assume a complete
shutdown
New-England system topology
G10 was BSU and G1 – G9 were NBSUs
Step-by-step restoration actions
University of Central Florida16
Case Studies
Time
(hr)Action Target
Time
(hr)Action Target
t=0:15 Energize Bus 30 t=0:50 Energize Bus 20,22,23,32,33,38
t=0:20 Energize Bus 2Branch 19-20,21-22,24-23,10-
32,19-33,29-38
Branch 30-2 Crank G8,G1
t=0:25 Energize Bus 25,1,3 t=0:55 Energize Bus 34,35,36
Branch 2-25,2-1,2-3 Branch 20-34,22-35,23-36
t=0:30 Energize Bus 37,39,26,4,18 Crank G9
EnergizeBranch 25-37,1-39,25-26,3-
4,3-18t=1:00 Crank G2,G3,G5,G6,G7
Connect G10 t=1:10 Crank G4
t=0:35 Energize Bus 27,5,14,17 t=1:25 Connect G1,G8
Branch 26-27,4-5,4-14,18-17 t=1:30 Connect G9
t=0:40 Energize Bus 6,13,16 t=1:35 Connect G2,G3,G5,G6,G7
Branch 5-6,14-13,17-16 t=1:45 Energize Bus 9,8,7,11,15,12
t=0:45 Energize Bus 10,19,21,24,28,29,31Branch 39-9,5-8,6-7,6-11,14-15,13-
12,22-23
Branch13-10,16-19,16-
21,16-24,26-28,26-29,6-31
t=1:45 Connect G4
t=1:50 EnergizeBranch 29-28,10-11,17-27,16-15,9-
8,8-7,11-12
University of Central Florida17
Optimal Blackstart Capability
Tool for System Restoration
Planning
University of Central Florida18
Blackstart Resources
• NERC Standard EOP-005-2 “System Restoration from
Blackstart Resources”
• Define “Blackstart Resource” as “a generating unit(s) … to be
started without support from the system or … to remain
energized without connection to the remainder of the System,
with the ability to energize a bus….”
• ISO-New England is changing its system restoration
strategy from “Bottom-Up” to “Top-Down”
• Add large frame combustion turbine units (150+ MW range)
located on or near the 345 kV transmission system to establish
a high-voltage transmission backbone
University of Central Florida19
Blackstart Capability Assessment
Installing
Additional
Black Start
Generators
7-Task-Updated
Restoration Plan
Criteria of
Restoration Time
and System Gen.
Capability
Optimal
Installation
Strategy
Restoration Tools
Transmission Path
Generator Start-up
Sequence
Load Pick-up
Optimal Power Flow
•Task 1: Update generator start-up sequence
•Task 2: Update cranking path
•Task 3: Update critical load pick-up sequence
•Task 4: Update transmission path
•Task 5: Update dispatchable load pick-up
sequence
•Task 6: Update islands resynchronization
•Task 7: Update load pick-up sequence
University of Central Florida20
Optimization Modules
Overall System Generation Capability
. . Total Restoration Time
. .
Max
s t Min
s t Critical Time Intervals Constraint
MW Start−up Requirement Constraint
Generator Capability Function Constraints
Generator Start−up Power Function Constraints
Decision Variables Constraints
Transmission Path Search Logic Constraints
Transmission Line Thermal Limits Constraints
GRAs Time Constraints
Modules Connection Constraints
Total
Restoration
Time &
System
Generation
Capability
W. Sun, C. C. Liu, and S. Liu, “Black Start Capability Assessment in Power
System Restoration,” Proc. IEEE PES General Meeting, 2011.
University of Central Florida21
Case Study
A total blackout is hypothesized for one zone in NE ISO system
There are 13 generators, 139 buses and 172 branches
The generation system can be restored in 260 minutes, and the
system generation capability is 4630 MWh
21
University of Central Florida22
Power System Restoration
using Smart Grid Technologies
University of Central Florida23
Renewable Sources Integration
U.S. Department of Energy’s goal: 20% wind by
2030.
Traditional restoration excludes renewable
sources:
Cannot be dispatched like conventional generators
Large scale wind farm penetration challenges:
BSU or NBSU ?
Uncertainty and variability
Load pickup and dynamic reserve
23
University of Central Florida24
Motivation and Challenges
Lack of knowledge in handling the variability and uncertainty
of wind ( due to inaccurate forecasting tools).
As the penetration level of wind power increases, it is critical
to coordinate wind generators with conventional generation
units (ramping events,…)
Need to consider extra dynamic reserve of conventional
generator or utilizing storages (pumped-hydro, …).
Decrease the total inertia of power system which can
threaten the stability of system ( wind turbine type 3 and 4).
University of Central Florida25
Harnessing Renewables in
Restoration
Cases Wind ProfileRestoration Time
(pu)
Wind Power
Spillage (MWh)
1 No wind 36 N/A2 Low wind 36 62.983 High wind 34 308.79
4Constant Wind
Power29 559.04
0 5 10 15 20 25 30 350
0.5
1
1.5
2
2.5
3
3.5
4
4.5
5
Restoration Time (p.u.)
Po
wer
(p.u
.)
Wind forecasting value
Deterministic solution
Stochastic solution
• A two-stage stochastic MILP-based wind harnessing
strategy to handle wind variability and uncertainty
• Test in IEEE 39-bus system with one 540 MW wind farm
• Wind can contribute in restoration, but with large wind
power spillage
University of Central Florida26
Optimal Distribution System
Restoration using PHEVs PHEVs can accelerate the load pickup by compensating the
imbalance between available generation and distribution
system load
A bottom-up restoration strategy to use PHEVs for reliable
load pickup and faster restoration process
Transmission
Restoration
Obj.: Max Generation Capability
Tasks:
• Gen. Startup Sequence
• Trans. Line Energization
Sequence
Distribution
Restoration
Obj.: Max Served Energy
Tasks:
• Load Pickup Sequence
• PHEVs Charging/Discharging
Sequence
Gen.
Capability
Curve
Load Pickup
Curve
N. Kadel, W. Sun, and Q. Zhou, "On Battery Storage System for Load
Pickup in Power System Restoration," Proc. IEEE PES General Meeting,
2014.
University of Central Florida27
Optimal Distribution System
Restoration using PHEVs Test in a 100-feeder system with PHEV penetration of 0.02%, 0.2%, 2%
0 2 4 6 8 10 12 14 16 18 200
50
100
150
200
250
300
350
Restoration Time (p.u.)
Re
sto
red
Lo
ad
(M
W)
Scenario 1 - No PHEV
Scenario 2 - 217 PHEVs
Scenario 3 - 2173 PHEVs
Scenario 4 - 21730 PHEVs
0 2 4 6 8 10 12 14 16 18 200.2
0.3
0.4
0.5
0.6
0.7
0.8
Restoration Time (pu)
Sta
te o
f C
ha
rge
(%
)
Scenario 2 - 217 PHEVs
Scenario 3 - 2173 PHEVs
Scenario 4 - 21730 PHEVs
0 2 4 6 8 10 12 14 16 18 20 220
0.5
1
1.5
2
2.5
3
3.5
Restoration Time (p.u.)
Dif
fere
nc
e b
etw
ee
n G
en
era
tio
n a
nd
Lo
ad
(M
W)
2 4 6 8 10 12 14 16 18 200
100
200
300
400
500
600
Restoration Time (p.u.)
Re
sto
red
Lo
ad
(M
W)
Scenario 4 - W/O Tran. & Distr. Coordination
Scenario 4 - W/ Tran. & Distr. Coordination
University of Central Florida28
PMU-based Protection and
Restoration Use PMU data to enhance situational awareness in power
system restoration
Multi-area parallel restoration
Communication-assisted adaptive protection
W. Sun, et al., “Design and implementation of IEC 61850 in communication-
assisted protection strategy,” Proc. IEEE PES T&D, 2014.
MILP optimization
Generator start up
Line Eenrgization
Load Pick up
Parallel Restoration
Multi-area Restoration
Strategy
Area 3 Area 4
Generator start up
Line Eenrgization
Load Pick up
Area 1 Area 2
….
MILP optimization
University of Central Florida29
References
Project funded by NSF
• ECCS-EPCN #1552073, “Collaborative Research: An Intelligent
Restoration System for a Self-healing Smart Grid (IRS-SG)”
• Further Information
• A. Golshani, W. Sun, and Q. Zhou, “Coordination of Wind and Pumped-
Storage Hydro Units in Power System Restoration,” IEEE Transactions on
Sustainable Energy, in revision.
• W. Sun, C. C. Liu, and L. Zhang, “Optimal Generator Start-up Strategy for
Bulk Power System Restoration,” IEEE Transactions on Power Systems,
vol. 26, no. 3, pp. 1357-1366, August 2011.
• N. Kadel, W. Sun, and Q. Zhou, "On Battery Storage System for Load
Pickup in Power System Restoration," Proc. IEEE Power & Energy
Society General Meeting, 2014, National Harbor, MD, 27-31 July 2014.
29