an introduction to coating concrete floors
TRANSCRIPT
-
8/8/2019 An Introduction to Coating Concrete Floors
1/4
Copyright 2001, Technology Publishing Company
ingredients in concrete for floors are aggregate, Portland ce-
ment, and water. The concrete hardens by hydration. (The
Portland cement reacts with water.) The hydration of the
Portland cement glues the aggregate particles together to
form the slab. More water than is needed for the hydration
reaction is used in the mixture for pouring and workabili-
ty of the wet concrete. Expansion joints, construction
joints, and control joints are placed in the floor.
The wet concrete is consolidated with vibrators placed
into the mixture while it is wet to eliminate air voids. The
surface is then finished by floating the concrete. This con-
sists of working the surface with large, flat tools such as
wood boards or steel trowels to smooth out the surface so
that none of the large aggregate particles are sticking out of
the concrete. The top 36 mm ( in.) ends up being a ce-
ment mortar layer. A smoother, harder surface
can be obtained with a steel trowel finish.
The concrete is then cured for a pre-de-
termined time or until it reaches the design
strength requirements. It is very important
that water be kept in the concrete during
these early stages because it is needed to re-
act with the Portland cement to form the
binder. Various methods are used to prevent
the loss of moisture from the concrete. The
most common methods are applying con-
crete curing compounds to the surface to
slow evaporation, and keeping the concrete
moist with ponded water.
The concrete must be dried after the ini-
tial curing is complete. The chemical reac-
tions that occur in the curing process can
take years to complete, but most specifica-tions for concrete made with Portland ce-
ment have 28-day strength requirements.
The amount of water added to the concrete is far in excess
of what is needed for the hydration reactions. Some water
will also remain within the pore structure of the dried con-
crete. The excess water must be allowed to escape before
any polymer flooring or coating system can be applied.
Concrete cannot be coated or topped with an impervi-
ous material such as coatings, linings, tiles, epoxy terraz-
zo, carpeting, etc., until there is no movement of water in
he most common substrate forindustrial floors is concrete made
of Portland cement. Concrete floors are
coated for many reasons. Some of the
factors include aesthetics, visibility
(i.e., light reflection), ease of cleaning
and decontamination, and protection from aggressive
chemicals. Other factors are resistance to impact, abrasion,
and erosion. Coatings for floors come in two types, rein-
forced and non-reinforced. This months Applicator Train-
ing Bulletin will
examine concrete floors from a coatings perspective,
discuss the special requirements for concrete floor coat-
ings, and
present general information on preparing and installing
floor coating systems.
Concrete Floors
Concrete floors are constructed by pouring and finishing
concrete on a prepared base. Various factors must be con-
sidered in designing concrete floors. Con-
structing the floor starts with a foundation
or soil support system. Depending on local
conditions, either the soil is compacted or a
mixture of fine and coarse aggregates is
placed on top of the local soil and compact-
ed. The end result is an even surface de-
signed to support the intended weight. The
walls and roof are then constructed so the
ground underneath the roof can dry. A
vapour barrier system is installed over the
portion of the prepared ground where the
slab will be poured. The vapour barrier sys-
tem is an impervious material such as 250-
micron (10-mil) polyethylene sheeting that
is overlapped and sealed. The purpose of the
vapour barrier is to prevent the concrete
from curling up at its edges during curingand drying. The barrier provides a more uni-
form release of the excess water. It also pre-
vents water from entering the slab from beneath, which
can cause osmotic blistering in the flooring material when
it is installed on top of the concrete. A sand layer is then
put on top of the vapour barrier. Be aware, however, that
some designers are of the opinion that the sand layer
should be placed below the vapour barrier in some or all
situations.
The next step is pouring the concrete. The three main
JPCL December 2001 PCE40
ApplicatorTrainingBulletin
An Introduction to
Coating Concrete Floors
This months installment of the Applicator TrainingBulletin was written by Lloyd Smith, Ph.D., Corrosion
Control Consultants and Labs, Herndon, Virginia, USA.T
Industrial plant floors are coated for
many reasons, including visibility and
protection from chemicals.
(Photos courtesy of Stonhard,
part of the StonCor Group)
-
8/8/2019 An Introduction to Coating Concrete Floors
2/4
Copyright 2001, Technology Publishing Company JPCL December 2001 PCE 41
the slab. This movement is commonly referred to as the
moisture vapour transmission rate. The actual amount of
water that remains in a concrete slab is of no importance.
What is important is if the water is moving into, and out
of, the surface. Think of moisture vapour transmission as
evaporation. Take a plate, wash it, and leave it by the side
of the sink. The plate will be dry with time, depending on
the temperature and relative humidity. The water did not
boil away; it evaporated. This is the same thing that hap-
pens with concrete. The water in the pore structure of the
concrete rises to the surface and evaporates until an equi-
librium condition is established.
A possible consequence of applying an impervious film
to concrete if water is moving into the concrete is osmotic
blistering. The osmotic pressure that develops can be
tremendous. The author has witnessed 0.3-metre (1-foot)
blisters in a 9.5-millimetre- (38-inch-) thick epoxy terraz-
zo floor that was the result of osmotic pressure. Water shot
up like a fountain when a hole was drilled through the ter-
razzo.
A common myth in the painting industry is that con-
crete can be painted 28 days after it has been poured. This
certainly is not true for floors. The amount of time it takes
for the water to evaporate from the slab depends on
many variables such as thickness of the slab, water-to-ce-
ment ratio of the concrete, air temperature, concrete tem-
perature, relative humidity, and wind speed. It may take 60
days or more before the floor is ready to be coated.
Detecting Moisture Movement
The various methods for detecting moisture movement inconcrete are described in ASTM E1907, Determining Mois-
ture-Related Acceptability of Concrete Floors to Receive
Moisture-Sensitive Finishes. The most commonly used
methods when applying a floor topping to concrete pre-
sented in this standard are the plastic sheet test, anhydrous
calcium chloride test, and hygrometer (relative humidity)
test. The plastic sheet method consists of taking a 460 x
460 mm (18 x 18 in.) piece of transparent polyethylene
sheeting that is at least 0.1 mm (4 mils) thick and tightly
attaching it to the floor with duct tape on all edges (ASTM
D4263, Standard Test Method for Indicating Moisture in
Concrete by the Plastic Sheet Method). The sheeting iskept in place for at least 16 hours. It is then removed, and
both the underside of the sheet and the floor surface are
examined. Any signs of moisture on the underside of the
sheet or on the floor (as evidenced by a darker grey colour)
mean that moisture is moving through the concrete, so it
would not be ready for coating.
The quantitative anhydrous calcium chloride test con-
sists of placing a cup with a known, weighed amount of
anhydrous calcium chloride on the floor, covering it with a
plastic canopy, and sealing the canopy to the floor with a
moisture-tight sealant (gun-grade) or sealant tape. The unit
is left on the floor for 60 to 72 hours. The sealed container
with the calcium chloride is then weighed after the test. The
weight gain in relation to the time of the test and the sur-
face area covered give the moisture emission rate. The max-
imum moisture emission rate most commonly required by
manufacturers of floor toppings is 15 g/m2 per 24 hours (3
lb/1,000 ft2 per 24 hours). The anhydrous calcium chloride
test is more popular in the United States than in Europe.
The quantitative method most widely used in Europe is
the hygrometer test. This method consists of measuring the
relative humidity of a pocket of air underneath a canopy
sealed to the concrete surface. The canopy acts as a vapour
barrier. Suitable materials are sheet metal, glass, or 2-mm
(0.080-in.) acrylic or polyvinyl chloride sheet. Insulation is
also needed to isolate the pocket of air from the surround-
ing environment. The hygrometer can be either a dial type
or a probe type. The canopy is sealed to the floor with a
gun-grade sealant or tape-type sealant in such a mannerthat allows relative humidity readings to be taken without
breaking the seal. Measurements are made for a sufficient
length of time for the entrapped air to reach moisture equi-
librium with the floor. Experimental evidence has shown
that when the moisture has evaporated from the coarse
pores of the concrete, the relative humidity falls to 80 per-
cent. It is reasonable, therefore, to require a relative hu-
midity of 75 percent or lower before the floor can be con-
sidered acceptable for installation of the flooring system.
The most detailed information on this test can be found in
British Standards Institute BS 5325:1983 British Standard
Code of Practice for Installation of Textile Floor Coveringsand BS 8203:1987 British Standard Code of Practice for In-
stallation of Sheet and Tile Flooring.
It is important to point out that any test on moisture
movement is only indicative of what is occurring at the time
of measurement. If the moisture vapour barrier was not in-
stalled properly or was ripped when pouring the slab, and
the test was performed in dry weather (i.e., the ground was
not saturated), then the tests may show that there is no
moisture movement. Similarly, a water pipe rupturing be-
Continued
For successful floor
coatings work, cont-
aminants must be
removed.
-
8/8/2019 An Introduction to Coating Concrete Floors
3/4
JPCL December 2001 PCE42 Copyright 2001, Technology Publishing Company
low the slab at a later date can cause water to enter the con-
crete, resulting in the formation of osmotic blisters at coat-
ed areas. Another common cause of moisture moving
through concrete is a change in ambient conditions. For ex-
ample, performing the moisture test when the slab is ex-
posed to the outside atmosphere, then heating or air condi-
tioning the room to a relative humidity lower than when the
flooring system was installed can cause water to accumu-
late beneath the coating, resulting in osmotic blistering.
Surface Preparation
All contaminants must be removed before applying a coat-
ing or lining to concrete floors. Common contaminants to
be aware of are concrete curing compounds, laitance, efflo-
rescence, and chemical contaminants.
The possible presence of concrete curing compounds is
mainly related to new construction. The use of concrete
curing compounds should be avoided when a coating or lin-
ing will be applied. Information should be obtained fromthe concrete subcontractor on whether or not a curing com-
pound was used.
Laitance is a thin, weak, brittle layer of cement and ag-
gregate fines on the surface of the concrete. Technically, lai-
tance is not a contaminant because it is a natural product
of cement hydration. But it is a weak layer that does not
support flooring systems or coatings. Laitance arises from
concrete finishing operations that cause weakly adherent
fines and cement paste to float to the concrete surface.
Efflorescence is a white crystalline or powdery deposit
on the surface consisting of lime or calcium hydroxide that
has leached out of the concrete and has carbonated (react-ed with carbon dioxide in the air). It is a loose material, so
it does not make a good base for coating.
Chemical contaminants are mainly associated with old
floors. Contaminants can include chemicals that have at-
tacked the concrete. Oils, grease, or other organic materials
are of concern especially in machine shops, food processing
facilities, and manufacturing facilities. Visually examine the
concrete for integrity. Tapping it with a hammer or picking
at it with a knife will reveal weak areas that may have un-
dergone chemical attack. Also look for dark stains, espe-
cially around equipment where lubricants or other materi-
als may have spilled. If oil or grease contamination is
found, its depth of penetration must be determined. This
may include the need to take core samples. Surface oil and
grease can be removed by scrubbing the surface with a
strong, low-foaming detergent and then thoroughly clean-
ing it with water.
Organic contaminants such as non-visible oil, grease,
concrete curing compounds, or other materials can be iden-
tified with a water bead test. For this test, a drop of water
is placed on the surface. If it beads, an organic contaminant
is present. Be aware that if the floor is coated, this test will
also be positive. It may be possible to remove oils and
grease by scrubbing the surface with commercial de-
greasers or floor strippers. If not, it will be necessary to
physically remove the contaminated concrete layer. Con-
crete is alkaline, so surface pH measurements could be in-
formative for other types of contaminants such as those
formed from acid attack.SSPC-SP 13/NACE No. 6, Surface Preparation of Concrete,
presents various methods for decontaminating and cleaning
concrete prior to coating. The most common method used
for floors is abrasive blasting. The intent of abrasive blasting
is to remove any loose surface materials and roughen the
concrete surface. The standard recommends a surface profile
appearance of fine (150 grit) sandpaper for light service
where there is minimal foot traffic, chemicals, or changes in
temperature. An appearance of coarse (60 grit) sandpaper is
recommended for severe service.
Dry or wet abrasive blasting can be performed. Cen-
trifugal blasting, discussed in the July 2001 ApplicatorTraining Bulletin, is also appropriate for floors.
Another surface preparation method is acid etching.
This procedure involves applying an acid on the floor, al-
lowing it to react, then neutralising the acid by rinsing with
plenty of water. The floor must then be allowed to dry. A
normal acid etching solution is a mixture of one part of 20
Be hydrochloric acid (muriatic acid) diluted with one part
of water. Fizzing will occur, indicating the acid is reacting
with the cement. If fizzing does not occur, this indicates the
presence of a curing compound or other organic material
such as grease or an existing coating on the concrete. This
contamination would have to be removed by solvent clean-ing or physical methods (i.e., power tool cleaning), and the
area would need to be re-etched. The acid is then left on
the concrete until a roughened surface is achieved (as indi-
cated when the tops of the pea gravel are exposed). Hy-
drochloric acid is a dangerous material requiring skin, eye,
and respiratory protection. The spent solution must be dis-
posed in accordance with local regulations. This has limit-
ed the use of acid etching in the United States. Acid etch-
ing is not used in Europe, although a non-toxic acid, citric
acid, is an alternative to muriatic.
ApplicatorTrainingBulletin
Rolling sealer onto a broadcast flooring system
-
8/8/2019 An Introduction to Coating Concrete Floors
4/4
Copyright 2001, Technology Publishing Company
quence and must be thoroughly mixed to wet out all the ag-
gregate particles. Some flooring materials are self-levelling
while others may require finishing, including techniques
such as trowel application or board-finishing like concrete.
Some products may need to be back-rolled to smooth the
surface or rolled with a spiked roller to remove air bubbles.
Always read the manufacturers application instructions
and talk to the manufacturer to determine the proper tools
and methods to use for a specific product.
Another variation of floor system application is to place
sand or another abrasive into the coating to reduce the pos-
sibility of slipping by increasing friction. This is referred toas a broadcast system. In this case, the aggregate is thrown
over the floor while the coating is still wet so the aggregate
(sand or abrasive) particles stick out of the coating or form
a rough surface. This is different than the flooring systems
previously discussed where the aggregate is mixed into the
coating and forms a smooth surface. A thin layer of topcoat
or sealer may need to be applied.
Conclusion
Floor coatings applied to concrete present unique situations
compared to other coating applications. Floors must be
tested for moisture movement before applying the floorcoating system. Old concrete must be examined for conta-
minants, especially in shop or plant environments or where
chemical contaminants are present. Floor coating systems
come in two main types, thin-film and thick-film. Thin-film
systems are applied by techniques commonly used for coat-
ings application. Thick-film systems may require special
application techniques, especially squeegee and trowel ap-
plication.
JPCL December 2001 PCE
Floor Coating Systems
The most common coating materials for industrial con-
crete floors are epoxies, vinyl esters, and polyesters. There
are many variations; the selection is based upon the expo-
sure environment, especially for chemical exposure. Floor
coatings can be thin-film or thick-film systems. An exam-
ple of a thin-film system is an epoxy at 250375 microns
(1015 mils) that is applied in two coats. Thick-film sys-
tems include aggregate-filled systems and reinforced sys-
tems such as those described in the November 2001 Ap-
plicator Training Bulletin. These systems normally are
applied at 1.6 to 6.5 mm (116 in. to 14 in.) thickness.
Application
The procedures described here are generalisations. Always
consult the manufacturer for specific directions.
The first step is determining what must be done to the
concrete surface after the surface preparation has been
completed. The floor may contain holes or irregularitiesthat have to be filled. The manufacturer will provide in-
formation on how deep an irregularity must be if it is to be
filled and the product to use. The next step is addressing
cracks, including stress cracks and joints. They may or
may not have to be treated, depending on the flooring sys-
tem used and the exposure environment. What is impor-
tant is how much movement will take place and not the
actual width of the crack. For example, a floor in a climate-
controlled area would not undergo thermal expansion and
contraction compared to an outside floor, so for the inside
system, joints and cracks may not have to be addressed.
The most common way to address cracks and joints ifthey must be treated is with the use of joint sealants or
bond breakers. Joint sealants are elastomeric materials
that can move if expansion or contraction occurs. Bond
breakers are materials such as vinyl tape or polyethylene
sheeting that are placed over the crack or joint. These ma-
terials will allow movement of the concrete underneath the
coating. Large joints may require a more detailed treat-
ment consisting of saw-cutting a groove, inserting a piece
of material called a backer rod into the groove, and filling
in the remainder of the groove with the manufacturers re-
quired material.
The flooring system may need a primer coat. Primersare thin-film systems (usually