analysis and design of fast charging system with flywheel …
TRANSCRIPT
1
Abstract— In this study is aiming at the design and analysis of a
fast-charging system (FCS) to decrease charging time and reduce
the high demand effect on the power grid using Flywheel and
with/without battery energy storage structure. In addition, the
electric bus charging and battery sizing analysis to better charging
system design. The flywheel energy storage has advantages to fast-
charging applications. Besides, the target fast-charging system will
support transportation electrification infrastructures, reduced
operational costs, and CO2 emissions. The analysis of the FCS
system will provide resilient features to ensure minimum
operation interruptions. The design of the system can use flywheel
technology to reduce the adverse effects of the high demand in the
power grid. Also, the fast charging system can affect the EV
battery size, especially the public bus. Thus, the relation between
the Electric bus battery and the charging process has been
analyzed. The design of the fast charging system aims to optimize
power-flow and minimize the sizing and protect battery life on
both (the vehicles and the storage) sides. The fast charging system
with flywheel energy storage has been analyzed with two different
perspectives. The proposed FCS has high power charging
technology with energy storage platforms and infrastructures.
Index Terms— Electric vehicles, Energy Storage, Fast charging systems,
Flywheel, Battery sizing
I. INTRODUCTION
ITH the impact of globalization, humanity has become
more conscious and people became more prone to
environment friendly energy sources instead of fossil fuels. In
addition, for transportation need which is indispensable for
people, the electrical vehicles provide an eco-friendlier option
rather than fossil fuel vehicles. When these advantages are
considered, the electrical vehicles (EV) are expected to spread
more in the near future.
The prevalence of the electrical vehicles increased the
importance of the studies made in this field. Especially, for a
more efficient and long drive performance of EV’s, the
innovations in the inverter/converter and battery technologies
boosted [1], [2]. Besides, significant studies are performed on
the EV’s charging technologies. Those studies show that, the
fast charging stations designed for EV’s, causes an over load
demand on the grid which’s effects should be reduced. Also,
there are some other studies are made on the interaction
between the EV’s and the grid in which the EV’s are not only
the load but also a source for the grid as a power supplier [3][7].
In one of these studies, the charging of the EV’s in different
power levels are examined depending on the transportation
time, distance and parking period [3]. Also, an optimum power
flow scenario developed on the basis of a MILP substructure
and a micro grid structure that EV supplies building/grid loads
[6]. The EV charging topology is divided three levels. These are
classified as level 1, level 2 and level 3. The level 3 charging
mode includes direct current (DC) which provides fast charging
by using high power. That is the reason of the effects of DC fast
charging to the grid. There are some different suggestions to
solve this situation. In one of them, a hybrid charge station
structure supplied by photovoltaic (PV) solar panels is proposed
for DC fast charging [8].
The charging stations designed to charge the electrical
vehicles are classified under different standards. These
standards are set by the international institutions like
International Electro-technical Commission (IEC), Society of
Automotive Engineers (SAE) and CHAdeMO [19] depending
on the defined technical data and qualifications. The
interconnection of the electrical vehicles with the grid is also
defined under the given standards. Especially the level 1 and
level 2 type of charging stations, which use AC and have lower
power values, are preferred for houses. In addition, charging
time of the electrical vehicles in these stations can last longer
(approximately 6-8 hours). That is the reason of the tries for
increasing the number of the DC fast charging stations which
can rise to higher power values. Decreasing the charging
duration is very important for the electrical vehicles to become
widespread. Because long charging durations affect the driving
comfort of the vehicles very much and perceived as negative
for the end users. As a solution for this situation, by using DC,
the EV’s batteries can be charged in a short time with high
current values. Today Tesla, the electrical vehicle producer that
set the fast charging stations and spreading them rapidly, fast
charging stations can raise 120kW charging power and can
fulfill the battery of a 90-kWh vehicle 50% in 20 minutes and
80% in 40 minutes [9]. Also, in some other charging station
examples, the charging power values can raise 350kW power
values instantaneously. These new generation charging stations
are named ultra-fast charging stations. The DC fast charging
station is named also extreme fast charging [10]. The type of
fast charging needs high power. So, some of the application is
used the Medium voltage level grid connection [10]. Also,
ultra-fast charging stations have some adverse effects on the
grid. Thus, these charging stations need the local power supply
like energy storage to reduce power demand from the grid. The
flywheel has developed rapidly as an alternative energy storage
unit. Flywheel stores the energy in the form of the kinetic
energy of a spinning mass. Conversion from the kinetic to
electric energy is accomplished by electromechanical systems
Hossam A. Gabbar1,2*, Onur Elma1, Md Ibrahim Adham1 1Faculty of Energy Systems and Nuclear Science, Ontario Tech University, Oshawa, ON, Canada
2Faculty of Engineering and Applied Science, Ontario Tech University, Oshawa, ON, Canada *Corresponding Author: Hossam A.Gabbar, Email: [email protected]
ANALYSIS AND DESIGN of FAST CHARGING SYSTEM
with FLYWHEEL ENERGY STORAGE PLATFORM
W
2
[11-12]. In the flywheel storage system, system control is the
most important part to operating states. One of the control
topologies is magnetic integration technique [12]. DC-DC
converter is a critical part of the fast charging system which has
also flywheel and/or battery storage system. There is different
type of DC-DC converter topologies are used for the fast
charging applications [13].
Also, the fast charging systems need high power density.
Thus, some of the hybrid resources and/or energy storage
system are integrated with FCS to reduce high demand on the
grid [14-16]. Multi-flywheel system is used to study the effect
of the hysteresis control on the FCS dynamics stability [15]. In
another study, an advanced computational intelligence
technique based on an enhanced artificial immune system
(EAIS) is used to improve the performance of the FFCS to
support transportation electrification [17]. The wireless
charging another popular charging method. Flywheel based
wireless charging system has been proposed and analyzed [18].
Thus the flywheel has a good potential to use in charging
system especially for stability, storage and reducing charging
time.
The Figure 1 is given in the proposed hybrid fast charging
configuration. The proposed system uses the battery and
flywheel to reduce effects of the peak demand on the grid side.
Fig. 1. Proposed hybrid fast charging configuration
II. FAST CHARGING STANDARDS
The charging time is one of the most important disadvantages
for electric vehicles. However, advances in the field of power
electronics and battery packaging and management have
enabled to be shortened of the charging time. The fast chargers
which have high power rates has been developed. These off-
board high power chargers are called ultra-fast chargers. New
standards are needed for equipment that can provide this
charging power. For this purpose, CHAdeMO which is the one
of the fast charger standard associations have developed a next-
gen ultra-high power charging standard [19]. Another charge
connection standard developed for e-buses is OppCHARGE
and it is becoming more widespread in Europe [20]. In addition,
Society of Automotive Engineers (SAE) has been working on
ultra- fast charging standard which will be up to 1-1.2 MW [21].
The charging standards which are related to Electric bus (EB)
are given in Table 1 [19]–[21].
TABLE I CHARGING STANDARD RELATED ELECTRIC BUSES
Levels Maximum
power rating
(kW)
Maximum
current rating
(A)
Maximum
voltage
rating (V)
SAE STANDARD
AC Charging 133 160 480
DC Charging
Level 1
Level 2
350
1200
600
1200
500
1000
CHADEMO
DC Charging
Level 1
Level 2
62.5
400
125
400
500
1000
OPPCHARGE (IEC) STANDARD
DC Charging
Level 1
Level 2
150
300 & 450
200
600
450-750
The electric vehicles need an energy to charge their batteries.
This process is called charging and the all charging components
and equipment are manufactured depend on national and
international standards. These standards cover the different type
of layers of the charging process. The standards can be divided
4 layers which are connector, communication, safety, charging
topology as given Figure 2.
Fig. 2. The divided standards of EV-charging
The fast charging systems need these standards to spread.
The big vehicles like bus, truck need more energy in order to
fulfill their missions. Thus, the charging time is a critical
challenge for that type of vehicles. The fast charging system can
be reduced charging time depend on power rate and charging
structure. Especially the buses for using public transportation.
Their operation times are long and the charging times are
limited. Therefore, there are two option to get operational
energy. First is a huge battery size which is expensive and have
some limitation to mount to the bus. The second, the ultra-fast
charging systems which have high power rate to charge the
battery very limited time. When the charging time is limited,
the connection should be very quick. So, the overhead charging
connectors are suitable for these types of charging.
III. FAST CHARGING FOR E-BUS
E-buses needs high power density for enough driving range.
3
The charging power range is really high. So, they need a special
charging equipment and systems. Pantograph, a kind of
connector, is used to reach higher powers especially in charging
systems for public transportation.
These connector connections are designed in three different
types under overhead chargers which are downward
pantograph, upward pantograph and side insertion. There are
different options for charging electric buses used in public
transportation. These options are given in Figure 3.
Fig. 3. Charging options for E-buses
A. On-route Charging
The electric bus is driven underneath the charging station,
which consists of a bipolar catenary. The bus driver starts the
charging procedure by raising the pantograph to the catenary,
and stops it by lowering the pantograph again.
Overhead charging (500-600 kW)
o Terminal charging (5-30 mins) (may categorize
under off-route charging)
o Flash charging (20 secs-1 min)
Wireless charging (limited charging power)
Mobile charging (-)
Battery changing (no charging limit)
B. Depot Charging
Plug-in charging (50-150 kW)
Overhead charging (300 kW)
The charging options for Electric buses affect from public
transportation strategy, routes, locations, grid connection and
etc. Thus, these affects should be analyzed with case studies.
Grid connection is a critical part of the fast charging structure
for electric buses.
IV. ANALYSIS OF THE ULTRA-FAST CHARGING TOPOLOGIES
High required charging rates lead to high power demands,
which may not be supported by the grid. Especially for
commercial vehicles the power limits are higher than personal
vehicles. The parking area can be converted to a hybrid fast
charging station or there will be mobile charging units. The fast
charging systems need DC charging to charge the battery with
high power limits. The dc/dc converter in between the energy
storage system and the rectifier is used primarily to control the
charging and discharging rates of the battery storage. It can be
also used to reduce or eliminate the grid harmonics, resulting in
a higher power factor for a more efficient charging
configuration. The DC/DC converter has to be bidirectional,
enabling the battery storage charging from the grid and
discharging through the EVs. The single- and dual stage
DC/DC converter topologies are analyzed to be used in an EV
charging station infrastructure. The different converter options
considered for the comparison can be classified into two main
categories which are given in Figure 4.
Fig. 4 The classified bidirectional converters
The UFC systems need DC charging to charge the battery with
high power limits. The dc/dc converter in between the energy
storage system and the rectifier is used primarily to control the
charging and discharging rates of the flywheel. It can be also
used to reduce or eliminate the grid harmonics, losses and other
adverse effects. The DC/DC converter has to be bidirectional,
enabling the flywheel energy storage charging from the grid and
discharging through the EVs. In the flywheel based ultra-fast
charging design, dual stage Cascaded Buck Boost (CBB)
topology can be chosen. The CCB type bidirectional converter
is shown in Figure 5. This topology has more benefits about
efficiency and suitable for the EV applications [27].
Fig. 5 The CCB type bidirectional converter
The proposed ultra-fast charging system has some of
substructure and power devices. The schematic of the proposed
system is given in the Figure 6.
4
Fig. 6 Proposed schematic for ultra-fast charging design
The proposed schematic has been used to designing steps of the
proposed system. The sub-structure in the system can be
analyzed.
A. Fast Charging Technologies with Wireless
Wireless charging can be enabled by the inductive charging
method which has already existed but still not standardized in
the industry yet. This method is facilitated by transferring the
energy from the power supply underneath the EV to the EV
battery through the magnetic induction capability based on the
principle of electromagnetic induction at high frequency. The
main components of inductive charging are two coils; the
primary coil, which is placed on the road interface (charging
pad) in the building construction linked to the wall socket
(power network), and the secondary coil which is placed on the
EV battery pack plate.
Currently, conductive charging is considered the most
common charging technique which is categories into two types
namely; AC and DC changings. This conductive method
provides much more flexibility to the user of choosing where to
charge whether at home, workplace or at a public charging
station [28].
AC conductive charging, also known as Level-1 or Level-2,
can be implemented almost anywhere provided that a standard
electrical outlet with AC power is available. A Battery
Management System (BMS) is usually used to facilitate
communication as provided by the internal wiring network.
This provides high performance and low-cost advantages as
BMS is suitable for Plug-in Hybrid Vehicle (PHV) application
in which the specific energy is lower. However, this conductive
charging has two disadvantages namely; power output
limitation due to the size and weight restriction on the on-board
charger, as well as relatively long charging time. Additionally,
the AC power of the utility grid outlet has to be converted to
DC power using an on-board inverter coupled with a DC-DC
converter in order to charge the EV battery via its DC positive
and negative terminals [11-12].
DC charging solution, also known as Level-3; on the other
hand, is suitable for high power charging applications. The
power output of the DC chargers is limited only by the ability
of the EV battery to accept the charge. Rapid charging is
enabled utilizing a DC fast charger which usually takes less
than 1 hour for a single charge. The biggest advantages of such
DC charger is that it can be designed with either high or low
charging rates and it is not limited to its weight and size. DC
charging solutions use off-board chargers which are located
outside the EV and this setup provides flexibility in terms of
power that can be delivered. The higher the power of the DC
charger, the faster the charging gets. Nevertheless, DC charging
requires high investment for installation compared to AC
charging, and could be availably accessed at public charging
stations only. In order to ensure safe and reliable DC charging
services, there are some challenges that needs to be overcome.
First is the adverse impact on the electricity grid including
harmonic contamination and high current demand
superimposing on peak hours. Second is the availability of this
method which is restricted due to the limitations of the electrical
supply network. Finally, since the off-board charger and BMS
are physically separated, complex communication network is
required to ensure correct charging conditions depending on the
battery type, voltage, temperature, and state of charge supplied
by BMS, and their off-board charger should adapt a proper
charging method [28].
EV battery chargers can be classified into on-board and off-
board with either unidirectional or bi-directional power flow
capabilities. Unlike on-board chargers that are widely installed
in many places, off-board chargers are less constrained by size
and weight. However, the charging time and battery life are
closely linked to the characteristics of the off-board charger
used. Different schemes and topologies have been proposed for
offboard chargers [29].
DC fast charger typically operates at Level-3 charging powers
and is designed to charge EVs quickly within an electric output
ranging between 50 kW and 450 kW. With higher power
operation, the AC/DC converter, the DC/DC converter and the
power control circuits become larger and more expensive. This
is why DC fast charger is implemented as off-board chargers
rather than on-board chargers so that it does not take up space
within the vehicle and also the fast charger can be shared by
many users.
To analyze the power flow for DC charging from the DC
charger to the EV battery, in the first step the alternating current
or AC power provided by the AC grid is converted into direct
current or DC power using a rectifier inside the DC charging
station. Then, the power control unit appropriately adjusts the
voltage and current of the DC converter to control the variable
DC power delivered to charge the EV battery. There are safety
interlocks and protection circuits used to de-energies the EV
connector and to stop the charging process whenever there is a
5
fault condition or any improper connection between the EV and
the off-board charger. The battery management system (BMS)
of the EV battery plays a key role of communicating between
the charging station and EV to control the voltage and current
delivered to the EV battery and to operate the protection circuits
in case of any unsafe situation. For instance, control area
network shortly referred to as CAN or power line
communication referred to as PLC are used for communication
between the EV and the charger [30].
The Combined Charging System (CCS) called the combo one
connector which is mainly used in the USA. The second is the
CCS combo-2 connector which is mainly used in Europe. The
third is the CHAdeMo connector used globally by cars built by
Japanese car manufacturers predominantly. Fourth is Tesla DC
charging connectors which are used for AC charging as well for
Tesla vehicles. Finally is the Chinese DC connector based on
China's GB/T standards.
Although DC fast charging is quite attractive as it delivers
high power going all the way up to 400kW to the EV battery
which results in very short recharging times, DC charging has
a number of limitations as the power cannot be increased
infinitely. This is due to three technical limitations of fast
charging. First, the high current charging leads to high overall
losses in charger and battery (I2R). Suppose the internal
resistance of the EV battery is R, and the power losses in the
battery can be expressed simply by using I2R, where I is the
charging current, then the losses would increase by a factor of
4 times whenever the current is doubled.
The second limitation of DC fast charging is coming from the
EV battery. When fast charging the EV battery, the State-of-
Charge SOC of the battery can only go up to 70-80% SOC. This
is because fast charging creates a lag between the voltage and
SOC and this phenomenon increases as the battery is being
charged faster. Hence, fast charging is typically done in the
constant current (CC) region of the battery charging. And after
that, the charging power is reduced gradually in the constant
voltage (CV) region of the battery charging. Moreover, the
battery charging rate (C-rate) increases with fast charging and
this then leads to reduction in the battery lifetime. The third
limitation is coming from the charging cable.
For any EV charger, it is important that the cable is flexible
lightweight so that user can carry the cable and connect to the
car. With higher charging powers, thicker and thicker cables are
needed to allow more charging current. Else, it will heat up due
to the losses. DC fast charging systems today can already
transmit charging currents up to 250A without cooling.
However, in the future with currents above 250A, the charging
cables would become too heavy and less flexible for usage. This
applies to CHAdeMO 3.0 that is 350-400kW charging enabled
up to 600A and 1.5 kV [31]. The solution would then be to use
thinner cables for the given current with cooling systems built-
in and thermal management to ensure that the cable do not heat
up which is more complex and costly to implement compared
to using a cable without cooling.
Canada is home to four manufacturers of electric vehicles,
especially battery electric buses namely; Green Power Motor
Company [32], The Lion Electric Company [33], New Flyer
Industries [34] and Nova Bus [35]. Nova Bus battery has
powerful modular options capable of storing up to 594 kWh of
on-board energy.
For such public transit buses, there are some world-leading
electrification technology developers including BTC Power
[38], BAE Systems [39], Proterra [40], SIEMENS [41] and
ABB [42].
The most popular of this charge system is Versi Charge Ultra
50/175 developed by Siemens-USA, rated at 50 and 175kW,
taking only half hour to fully charge the bus battery.
Siemens Si-charge is currently being developed for overhead
and depot chargers rated at 50-600kW, with flexible dispenser
configurations and semi-parallel charging [37].
The charging station main power source can be either a high-
voltage or a low voltage supply, depending on if the connection
point is 10 kV or 400 V, respectively. In a high voltage
connection, a 10/0.4 kV substation and a connecting 10 kV-
cable is usually installed in addition to a 400 V service.
In order to decrease the power demand from the buses on the
utility grid especially at peak loads, an energy storage system
as a buffer can be connected to the charging station. Charging
the energy storage system when no bus is at the station is
usually implemented in practice, and later, when a bus arrives
for charging, it helps provide adequate charging power. This
method, the energy out take from the power grid is spread out
over a longer time, which decreases the required power. The
storage can be optimally sized to provide the full power demand
or only a portion. It can be designed to recharge fully in between
each bus or make it so large that it does not have to recharge
fully during the busiest hours.
The flow of power from the power grid and the energy storage
system and the electric vehicle battery can be managed via a
DC bus and two power converters as shown in Figure 32 below:
Using flywheel as the energy storage system as a buffer, the
charging topology with the power electronic converter is quite
complex due to the control scheme required in order to regulate
the dynamics of the flywheel. Flywheel-based fast charging
system structure including system level control structure is
shown in Figure 7 below.
Fig. 7 Flywheel-based fast charging system structure
A hysteresis control strategy employs a droop-based DBS
control method to avoid digital communication between the
grid and flywheel energy storage system converters. The
proposed algorithm provides a good response to system-level
signals while not interrupting the predefined charging profiles
of the electric vehicle battery.
Using a super capacitor energy storage system in the charging
system can be implemented with the flywheel energy system as
proposed by G. Joos and M. de Freige [36].
Today’s EVs mostly utilize electrochemical storage devices
to store energy and power its powertrain. These devices must
fulfill certain requirements, so that the EV can perform in an
6
efficient and satisfactory manner. The key requirements are as
follows:
1 High specific energy to ensure a satisfactory range.
2 High specific power to meet acceleration expectations.
3 Maintenance free and long lifetimes.
4 Safe operation under a wide range of conditions including
cold and hot weathers.
5 End of life disposal has minimum environmental impact.
6 High efficiency in charge and discharge cycles.
Batteries that can only discharge once are called primary cells,
for example AAA Alkaline batteries. Batteries that can be
recharged are called secondary batteries. Examples of which are
lead-acid, nickel metal hydride and lithium ion batteries.
Batteries consist of a positive and a negative pole or electrode.
In a charged battery, energy is stored in a chemical form in the
electrodes which is released as electrical energy when
discharged. Vice versa, secondary batteries can be charged
using electricity which is when electrical energy is converted to
chemical energy, stored in the battery.
V. ANALYSIS OF THE ADVANTAGES OF THE FUFC
In this section, the flywheel-based energy storage application
for fast charging has been analyzed. Flywheels store energy as
kinetic energy, which works by accelerating a rotating mass to
high speed and using the momentum to generate electricity
when needed. Flywheels have higher efficiency and have a
higher life cycle than batteries with little decrease in efficiency
[22]. The total charge/discharge of the flywheel is better than
the battery. In addition, flywheels operate in ambient
temperature and with tremendously less cooling system
requirements. Thus, they have less footprint and generate less
heat than batteries [23]. On the other hand, batteries may be
broken via undetectable internal failures, even with regular
maintenance. Thus, flywheel energy storage system has some
advantages for ultra-fast charging applications.
A. Proposed Flywheel Based Ultra-Fast Charger
It can slow charge from the grid, reducing demand, and then
deliver high bursts of power for short durations. The main aim
of fast charging with FESS is the peak demand control and
reduce effects of the peak demand on the grid. In addition, the
get cost benefits for fast charger owners. The scenario of flash
charging with flywheel is given Figure 8.
Fig. 8. Proposed flash charging with Flywheel
B. Flywheel Energy Storage (FES)
Flywheels store energy as kinetic energy, which work by
accelerating a rotating mass to high speed and using the
momentum to generate electricity when the energy needed.
Flywheels have higher efficiency and have a higher life cycle
with little decrease in efficiency. The total charge/discharge of
the flywheel is better than the battery. In addition, flywheels
operate in ambient temperature and in tremendous less cooling
system requirements. Thus, they have fewer footprints and
generates less heat than batteries [23]. On the other hand,
batteries may be broken into undetectable internal failures, even
with regular maintenance. The efficiency of flywheel which
takes into account the required energy in order to keep the
flywheel spinning, and/or standby loss of the flywheel. The
flywheel standby loss is between 0.2% to 2% according to
manufacturers [24]. The structure of the FES is given in Figure
9.
Fig. 9. The structure of the flywheel
C. Case Study: Performance Analysis of FESS for on-route
charging
The on-route ultra-fast chargers are one of the charge
solutions for public transportation. The proposed ultra-fast
charger has FES, bidirectional DC-DC converter, rectifier and
contactors. The both charge and discharge process of the FES
are done via DC-DC converter. Thus, system not needs another
inverter to connect to the grid that helps to reduce the system
capital and maintenance costs. The flywheel is used as an
energy storage in the proposed system. Because of advantages
of high-power density, charge/discharge cycles and fast
response time. The system performance is analyzed via bus stop
in the one of the busiest bus routes in the Toronto, Canada.
Toronto is a biggest city in the Canada and one of the crowded
cities in the North America. The route 32 is the busiest bus route
under the Toronto Transit Commission (TTC) [25]. The one of
the bus stops is chosen which is in the Eglinton Avenue and
Dynevor road. This bus stop is located the nearest the one of the
busiest intersections between Eglinton Avenue and Dufferin
Street.
The buses stop on this stop every 4-5 minutes in the rush
hours. The each pick up/ drop off might be around 1-1.5 minute.
7
When the bus come to the bus stop the charger pantograph is
down and connect to the bus and the charging process starts.
The connection and disconnection times may take 20 seconds.
So the charging time is around 1 minute. The charger power
rate is 600 kW that power rate is already used in some of on-
route charger [26].
When the charging to the e-bus, the switch 1 is active and the
flywheel supply to the e-buses. After the e-bus charging, there
is a 3 minutes time to charge flywheel from the grid. The switch
1 is inactive and Switch 2 is active and the flywheel is charging
from the grid. The process of the charging/discharging are
given in Table 1.
TABLE II. The charging periods of the system
From FES to E-bus From Grid to FES
S1 S2 S1 S2
Power
rate
Charging
time
Energy Power
rate
Charging
time
Energy
600 kW 1 minute 10 kWh 200 kW 3 minute 10 kWh
As seen in Table II, the proposed FES system can reduce 66%
peak demand on the Grid side. The fast response of the flywheel
and advance control of the charge/discharge process can enable
this to be feasible. The charged energy is 10 kWh which can
contribute 6-8 km range to the E-bus. The total route distance
is 15 km, so the on-route charge can give the around 50% of
energy to complete the route.
VI. ANALYSIS OF PUBLIC BUS BATTERY SIZE DEPEND ON
ROUTES AND OTHER PARAMETERS
The mostly fast chargers have 50-150 kW power rates in the
market. These power rates may give a suitable charging time
for personal EVs but not for commercial electric vehicles. Thus,
the DC fast charger should be improved to charge bigger battery
capacities in acceptable charging times. Especially, the regular
DC fast chargers cannot give acceptable charging time for the
buses and/or heavy trucks. The new battery and power
electronic technology make possible to use much more power
rate for fast charging. These high-power rate chargers are called
ultra-fast charging and extremely fast charging. The proposed
analysis, the ultra-fast charging system has been modeled to
reduce the charging time of public buses. The updated charger
standards have been taken into consideration such as
CHAdeMO and SAE. Accordingly, the 450 kW ultra-fast
charging system is analyzed. In addition, the public bus routes
have been used to optimize bus battery capacity according to
the bus schedule, stop time and the flash charging power limit.
The optimum battery size is calculated for the E-buses.
Size of EB battery has been evaluated based on number trip,
waiting time, power rating of the charging station, route length,
peak period operation, off-peak period operation and number of
terminal charging station. 30% margin has been added while
calculating the final battery size considering that the bus battery
will charge & discharge between 20% to 90% of SOC. The
required battery size of EB has been calculated for scenario 1
and scenario 2 and compare them with no terminal charging
station scenario. To make the study versatile, instead of using a
specific route length, 100 different route lengths within specific
boundary have been considered with Monte Carlo method for
both scenarios.
The amount of energy that will be supplied from the Fast
Charging Station (FCS) to EB while waiting in the terminal
during peak period operation is,
EP=EP1=EP2 = (2÷60) ×450 = 15 kWh.
Here, EP is the amount of energy from FCS during peak
period operation (kWh), EP1 is the amount of energy from FCS
at terminal 1 during peak period operation (kWh), EP2 is the
amount of energy from FCS at terminal 2 during peak period
operation (kWh)
The amount of energy that will be supplied from FCS to EB
while waiting in the terminal during off-peak period operation
is, EOP = EOP1 = EOP2 = (6÷60) ×450 = 45 kWh.
Here, EOP is the amount of energy from FSC during off-peak
period operation (kWh), EOP1 is the amount of energy from FCS
at terminal 1 during off-peak period operation (kWh), EOP2 is
the amount of energy from FCS at terminal 2 during off-peak
period operation (kWh)
Considering both peak period and off-peak period
operation, the battery size of EB for scenario 1 can be calculated
by as follows:
BSP = [[{(RL×2×M) – EP}×NTP]+EP]×1.3 (1)
BSOP = [[{(RL×2×M) – EOP} ×NTOP] +EOP] ×1.3 (2)
Here, BSP is the battery size of EB for peak period
operation (kWh), BSOP is the battery size of EB for off-peak
period operation (kWh), RL is the route length/distance
between terminals (km), M is the energy consumption rate of
EB per km (kWh/km), NTP is the number of trips during peak
period, NTOP number of trips during the off-peak period.
Similarly, the battery size of EB can be calculated for both
peak period and off-peak period operation for scenario 2 is as
follows: BSP = [[{(RL×2×M) -EP1-EP2} ×NTP] +EP1+EP2]×1.3
(3) BSOP = [[{(RL×2×M) – EOP1- EOP2} ×NTOP] +EOP1
+EOP2] ×1.3 (4) Size of EB battery if there is no charging station in the
terminal can be obtained by the below equation: FBSWCS = RL×2×M×1.3 (5)
The final battery size of EB considering both peak period and
off-peak period operation for scenario 1 can be calculated as
follows: 𝐹𝐵𝑆 =
{ BS𝑝, RE1 ≤ EOP
[(BSP ÷ 1.3) + {(RE1 − EOP) × NTop}] × 1.3, RE1 > EOP
(6)
here, RE1 is the amount of energy required by EB for the 1st
trip for scenario 1 (kWh).
Final battery size for scenario 2 considering both peak period
and off-peak period operation can be found as follows:
8
𝐹𝐵𝑆 =
{
BS𝑝, RE1−2 ≤ Eop1
[(BSp ÷ 1.3) + {(RE1−2 − Eop1) × NTop}] × 1.3, RE1−2 > Eop1
(7)
Here, RE1-2 is the amount of energy required by EB for the 1st
trip for scenario 2 (kWh).
The algorithm for calculating the EB battery size is has been
shown in Figure 10.
Fig. 10 The flowchart of the batter size calculation
Two scenarios have been considered in this study to find out
the size of EB battery. In the first scenario, single terminal with
a charging station of 450 kW has been considered. 100 different
routes have been taken which length are between 10 km to 20
km. Mileage or energy consumption rate is one of the deciding
factors for the battery size of EB. Mileage or energy
consumption rate is the amount of energy needed by a EB to
travel one km and expressed as kWh/km. The real public bus
route data is used for both scenarios which is given in TABLE II.
TABLE III . PUBLIC BUS ROUTE DATA
Bus route
number
Route
distance
Bus time-
schedule
Bus energy
needs each route
401 24 km 10-12 mins 28.8 kWh
417 6.5 km 30 mins 7.8 kWh
915 21 km 30 mins 25.2 kWh
910 18 km 30 mins 21.6 kWh
950 40 km 30 mins 48 kWh
304 22 km 30 mins 26.4 kWh
A. Case Study I
In this case, single terminal with a charging station of 450 kW
has been considered. 100 different routes have been taken
which length are between 10 km to 20 km. As single terminal
has been considered so the length of each trip will be between
20 (10*2) km to 40 (20*2) km. Since bus will get charge from
terminal charging station, waiting time in the terminal is very
important & this waiting time depends on which part of the day
has been considered. Waiting time will be less if there is a rush
of commuters as the EB needs to commute high number of
passenger & will be high if there is less commuter rush. Both
scenarios have been considered & divided into rush period/peak
period operation & off-peak period operation. In general, the
first peak period starts in the morning from 6am & continues
till around 10am & the second rush period is from 4 pm to 8
pm. During peak period, EB waiting time will be minimum &
in this case it has been considered as 2 min & during off-peak
period the waiting time is 6 min. For connecting &
disconnecting the charger with EB, there will be required some
extra time & this will not be more than 30 sec. Waiting time has
been considered excluding this preparation time. Mileage or
energy consumption rate is one of the deciding factors for the
battery size of EB. Mileage or energy consumption rate is the
amount of energy needed by an EB to travel one km and
expressed as kWh/km. In this case a 12-meter bus with energy
consumption rate of 1.2 kWh/km has been considered. Also,
while calculating the final size of the battery, 30% margin has
been added considering that the bus battery will charge &
discharge between 20% to 90% of SOC. Parameters that have
been considered has been summarized in the Table IV. TABLE IV. Parameters of Case-1 and Case-2
Parameters Value
Case 1 Case 2
Number of Terminal/s 1 2
Route Distance/ Distance between Terminals 10 to 20
km
10 to 20
km
Number of Charging Station 1 2
Power Rating of the Charging Station 450 kW 450 kW
E-Bus waiting time during peak hour
operation in terminal 2 min 2 min
E-Bus waiting time during off-peak hour
operation in terminal 6 min 6 min
Number of trips during peak period
operation 5 5
Number of trips during off-peak period
operation 5 5
Energy Efficiency of EB 1.2
kWh/km
1.2
kWh/km
B. Case Study II
In case study 2, two terminals have been considered & each
terminal has one 450 kW charging station. Distance between
the two terminals is 10 km to 20 km. Parameters of case 2 have
been given in Table IV. Flowchart of calculating the bus battery
size has been shown in Figure 11 and 12, respectively.
Fig. 11 Analysis of battery size of bus with single terminal
9
Fig. 12 Analysis of bus battery size of bus with two terminals
VII. RESULTS AND DISCUSSION
The first analysis for flywheel-based fast charger unit is built
in the bus stop which can be possible to flash charging without
any over demand on the grid side. Also, the proposed system
can reduce the charging demand around 66%. This show that
the flywheel can help to control high demand caused by ultra-
fast chargers.
In addition, another analysis for the fast-charging and the EV
bus battery sizing has been done. That can show the relation
between route, battery size and charging system structure.
As seen in Figure 11 shows the battery size for peak period
operation, off-peak period operation, and total battery size
considering both peak & off-peak period operation for case 1.
If the EB gets more energy compared to the required energy for
a specific route length while waiting in the terminal, total
battery size does not depend on number of trips for that certain
route. For case 1, if the route length is less than 18.75 km,
battery size will not depend on the number of trips during off-
peak period. To clarify more, for route length 17.22 km the total
bus battery is 190.632 kWh. Now if 10 trips during off-peak
period is considered instead of 5 trips then the total bus battery
size will be same as 190.632 kWh. In this paper peak period
operation has been considered firstly then off-peak period has
been considered. EB battery size will be increased to a large
extend if there is no on route ultra-fast charging station in the
terminal. Also, for route length 17.22 km bus battery size will
be 413.28 kWh if there is no on route ultra-fast charging station
in the terminal but if a 450 kW ultra-fast charging station is
considered in the terminal & EB is operated maintaining the
waiting time in peak and off-peak period operation then the bus
battery will be 190.632 kWh. So, for this case EB battery size
can be reduced by 222.648 kWh by putting an ultra-fast
charging station in a terminal. As bus battery comprises around
30% to 40% of total cost, so the cost EB can be reduced to a
great extent by using this on route ultra-fast charging station.
As seen in Figure 12, if there are two terminals, then the
battery size can be reduced further. In case -1 when the route
length is 15.31 km the final battery size is 160.836 kWh for 10
trips (5 trips during peak period & 5 trips during off-peak
period) but in case-2 for the same route length and for the same
number trips the battery size is 82.836 kWh which is almost half
compared to case-1. Also, it can be noted that if the distance
between the two terminals is less than 11.10 km the battery size
does not depend on the number of trips which means if the
number of trips is increased during both peak period & off-peak
period, the battery size will not increase. EB battery size is
noticeably high if there is no charging station in the two
terminals compared to 450 kW charging station in each
terminal. For example, when the distance between 2 terminals
is 15.31 km, the bus battery size is 82.836 kWh if there is
charging station at each terminal but if there is no charging
station, the battery size is more than four times higher which is
367.44 kWh. So, just putting 2 charging stations, battery size
can be reduced greatly & hence the total cost of the EB fleet can
be reduced to a large extent.
VIII. CONCLUSION
The ultra-fast charger is a critical key factor for transportation
electrification. Public transportation has a huge potential to
reduce carbon emissions. The transition to electric buses has
some challenges. One of them is the effects of fast charging on
the grid side. The proposed flywheel-based ultra-fast charging
system gives a solution to reduce peak demand on the grid side.
The system can reduce peak demand by 66% based on the case
study.
In addition, another analysis has been done which is about
fleet charging and electric bus battery size. The benefit of
having an ultra-fast charging station in terminals on EB battery
has been evaluated and quantified. Also, a comparison has been
made between having a single charging station in one terminal
and having two charging stations in two terminals. It has been
found that the EB battery will be 4 times higher if there is no
charging station in terminals compared to two charging stations
in two terminals and the EB battery will be around 2 times
higher if there is a single charging station compared to two
charging stations in two terminals. This study also showed the
optimized route length for the single terminal charging station
and two charging stations in two terminals. This will help the
EB fleet operator to determine the optimized route length for
their operation which will increase their revenue. Also, the EB
battery is directly proportional to the number of trips.
The ultra-fast charger needs to be improved and this is really
important to increase EVs on the road.
ACKNOWLEDGMENT
The study is supported by CUTRIC and Mitacs -IT15756.
Thanks to Faisal Mumtaz from Smart Energy Systems Lab at
Ontario Tech University for his support to this work.
REFERENCES
1. M. Ibrahim, S. Jemei, G. Wimmer, and D. Hissel, “Nonlinear
autoregressive neural network in an energy management strategy for
battery/ultra-capacitor hybrid electrical vehicles,” Electr. Power Syst.
Res., vol. 136, pp. 262–269, 2016.
2. S. Ozdemir, O. Elma, F. Acar, and U. S. Selamogullari, “Analyzing the
capacity utilization rate of traction motor drives in electric vehicles with
real world driving cycles,” in 2014 IEEE Vehicle Power and Propulsion
Conference, VPPC 2014, 2014.
3. M. R. Mozafar, M. H. Amini, and M. H. Moradi, “Innovative
appraisement of smart grid operation considering large-scale integration
of electric vehicles enabling V2G and G2V systems,” Electr. Power Syst.
Res., vol. 154, pp. 245–256, 2018.
10
4. B. Aluisio, A. Conserva, M. Dicorato, G. Forte, and M. Trovato,
“Optimal operation planning of V2G-equipped Microgrid in the presence
of EV aggregator,” Electr. Power Syst. Res., vol. 152, pp. 295–305,
2017.
5. C. Peng, J. Zou, L. Lian, and L. Li, “An optimal dispatching strategy for
V2G aggregator participating in supplementary frequency regulation
considering EV driving demand and aggregator’s benefits,” Appl.
Energy, vol. 190, pp. 591–599, 2017.
6. D. Thomas, O. Deblecker, and C. S. Ioakimidis, “Optimal operation of
an energy management system for a grid-connected smart building
considering photovoltaics’ uncertainty and stochastic electric vehicles’
driving schedule,” Appl. Energy, vol. 210, pp. 1188–1206, 2018.
7. O. Elma and U. S. Selamogullari, “Investigation of cost reduction in
residential electricity bill using electric vehicle at peak times,” in Lecture
Notes in Electrical Engineering, 2013, vol. 239 LNEE, pp. 123–133.
8. M. O. Badawy and Y. Sozer, “Power Flow Management of a Grid Tied
PV-Battery System for Electric Vehicles Charging,” in IEEE
Transactions on Industry Applications, 2017, vol. 53, no. 2, pp. 1347–
1357
9. “Tesla fast charging station.” [Online]. Available:
https://www.tesla.com/supercharger. [Accessed: 09-Mar-2019].
10. V. M. Iyer, S. Gulur, G. Gohil and S. Bhattacharya, "Extreme fast
charging station architecture for electric vehicles with partial power
processing," 2018 IEEE Applied Power Electronics Conference and
Exposition (APEC), San Antonio, TX, 2018, pp. 659-665. doi:
10.1109/APEC.2018.8341082.
11. A. Elserougi, A. M. Massoud and S. Ahmed, "Flywheel Energy Storage
System based on boost DC-AC converter," IET Conference on
Renewable Power Generation (RPG 2011), Edinburgh, 2011, pp. 1-7.
doi: 10.1049/cp.2011.0194.
12. X. Wang, D. Li, X. Mai and X. Li, "Flywheel energy storage system
based on DC/DC converter with integrated magnetic structure," 2015 5th
International Conference on Electric Utility Deregulation and
Restructuring and Power Technologies (DRPT), Changsha, 2015, pp.
2179-2184.
doi: 10.1109/DRPT.2015.7432600.
13. N. Trivedi, N. S. Gujar, S. Sarkar and S. P. S. Pundir, "Different fast
charging methods and topologies for EV charging," 2018 IEEMA
Engineer Infinite Conference (eTechNxT), New Delhi, 2018, pp. 1-5.
doi: 10.1109/ETECHNXT.2018.8385313.
14. B. Sun, T. Dragicevic, J. C. Vasquez and J. M. Guerrero, "Distributed
cooperative control of multi flywheel energy storage system for
electrical vehicle fast charging stations," 2015 17th European
Conference on Power Electronics and Applications (EPE'15 ECCE-
Europe), Geneva, 2015, pp. 1-8.
doi: 10.1109/EPE.2015.7311762.
15. Bo Sun, T. Dragicevic, F. Andrade, J. C. Vasquez and J. M. Guerrero,
"Provision of flexible load control by multi-flywheel-energy-storage
system in electrical vehicle charging stations," 2015 IEEE Power &
Energy Society General Meeting, Denver, CO, 2015, pp. 1-5. doi:
10.1109/PESGM.2015.7286184.
16. O. Elma and H. A. Gabbar, "Sizing Analysis of Hybrid DC Fast
Charging System for Electric Vehicles," 2018 International Conference
on Smart Energy Systems and Technologies (SEST), Sevilla, 2018, pp.
1-5.
doi: 10.1109/SEST.2018.8495688.
17. H. A. Gabbar, A. M. Othman, F. Pino and M. Repetto, "Improved
Performance of Flywheel Fast Charging System (FFCS) Using Enhanced
Artificial Immune System (EAIS)," in IEEE Systems Journal.
doi: 10.1109/JSYST.2019.2892002.
18. A. H. Fahad and H. A. Gabbar, "Wireless Flywheel-Based Fast Charging
Station (WFFCS)," 2018 International Conference on Renewable
Energy and Power Engineering (REPE), Toronto, ON, Canada, 2018,
pp. 1-6. doi: 10.1109/REPE.2018.8657482.
19. “CHAdeMO Standard,” 2020. [Online]. Available:
https://www.chademo.com/tag/next-generation-ultra-high-power/.
[Accessed: 28-Jan-2020].
20. “OppCharge.” [Online]. Available: https://www.oppcharge.org/.
[Accessed: 15-Feb-2020].
21. SAE, “J3105, J3015,” 2020. [Online]. Available:
https://www.sae.org/standards/. [Accessed: 10-Feb-2020].
22. R. T. Doucette and M. D. McCulloch, “A comparison of high-speed
flywheels, batteries, and ultracapacitors on the bases of cost and fuel
economy as the energy storage system in a fuel cell based hybrid electric
vehicle,” J. Power Sources, 2011.
23. R. Arghandeh, M. Pipattanasomporn, and S. Rahman, “Flywheel energy
storage systems for ride-through applications in a facility microgrid,”
IEEE Trans. Smart Grid, 2012.
24. R. S. Weissbach, G. G. Karady, and R. G. Farmer, “A combined
uninterruptible power supply and dynamic voltage compensator using a
flywheel energy storage system,” IEEE Trans. Power Deliv., 2001.
25. TTC, “32 Eglinton West bus route,” 2020. [Online]. Available:
http://www.ttc.ca/Routes/32/Eastbound.jsp. [Accessed: 20-Feb-2020].
26. ABB, “Pantograph down for electric buses.” [Online]. Available:
https://new.abb.com/ev-charging/products/pantograph-down.
27. M. O. Badawy et al., “Design and implementation of a 75-kW mobile
charging system for electric vehicles,” IEEE Trans. Ind. Appl., 2016.
28. Pop, V., Bergveld, H.J., Danilov, D., Regtien, P.P.L., Notten, P.H.L.
Battery Management Systems. Philips Research Book Series, vol 9.
Springer, Dordrecht.
29. Kesler, Metin ; Kisacikoglu, Mithat C ; Tolbert, Leon M, Vehicle-to-
Grid Reactive Power Operation Using Plug-In Electric Vehicle
Bidirectional Offboard Charger, IEEE transactions on industrial
electronics (1982), 2014-12, Vol.61 (12), p.6778-6784.
30. Khan, Saad ; Mehmood, Khawaja ; Haider, Zunaib ; Bukhari, Syed ; Lee,
Soon-Jeong ; Rafique, Muhammad ; Kim, Chul-Hwan, Energy
Management Scheme for an EV Smart Charger V2G/G2V Application
with an EV Power Allocation Technique and Voltage Regulation,
Applied sciences, 2018-04-21, Vol.8 (4), p.648.
31. Chandra Mouli, Gautham Ram ; Schijffelen, Jos ; van den Heuvel, Mike
; Kardolus, Menno ; Bauer, Pavol, A 10 kW Solar-Powered Bidirectional
EV Charger Compatible With Chademo and COMBO, IEEE
transactions on power electronics, 2019-02, Vol.34 (2), p.1082-1098.
32. Green Power Motor Company, www.greenpowerbus.com.
33. The Lion Electric Company, www.thelionelectric.com.
34. New Flyer Industries, www.newflyer.com.
35. Nova Bus, www.novabus.com.
36. Joos, G ; de Freige, M ; Dubois, M, Design and simulation of a fast
charging station for PHEV/EV batteries, 2010 IEEE Electrical Power &
Energy Conference, 2010-08, p.1-5.
37. Siemens SICHARGE,
https://new.siemens.com/global/en/products/energy/medium-
voltage/solutions/emobility/sicharge-uc.html.
38. BTC Power, www.btcpower.com.
39. BAE Systems, https://www.baesystems.com.
40. Proterra, www.proterra.com.
41. SIEMENS, www.siemens.com.
42. ABB, https://global.abb/group.