analysis of pvsyst loss diagram
TRANSCRIPT
Generation Assessment and Loss Justification
The generation was estimated considering 315Wp modules of a reputed make and 1MW solar inverter of a reputed make as initial design inputs for conducting the simulations. The project uses a seasonal tilt system for with 7.5m pitch. The DC to AC overloading that has been decided as a design parameter is 25%.
The typical loss breakdown is as shown below with relevant justifications
Table 1: Justification of PVSyst Losses
S.No. Parameter Measure Justification
1. PV Syst Version 6.41 Latest version of PVSyst simulation tool has been used
2. Tilt Angle/Tracking Angle 5 o and 30 o For seasonal tilt, the aforementioned tilt angles
for summer and winter have been assumed.
3. Pitch(m) 7.5
Considering the overloading of 25%, and
corresponding land usage and generation optimization, the pitch values given here came
out to be optimal
4. Shading
-0.2% (5 o)
Near shading is caused by inter row distance and due to tall objects like control rooms and
lightening arrestors. For shading from tall objects, sufficient spaces are left by conducting a
shadow estimation study so as to keep the PV array shadow free during generation hours. The
near shading loss due to inter row spacing is
however determined by PVSyst as per the design pitch considered. In the case of seasonal
tilt, the shading losses are low for summer tilt and is higher for winter tilt. However, the
average shading loss will fall somewhere in between the two values.
-3.7% (30 o)
5. Incidence Angle Modifier
-2.2% (5 o) IAM loss accounts for losses in radiation
penetrating the front glass of the PV modules due to angles of incidence other than
perpendicular. The loss figures is a module dependent parameter and is calculated by the
PVSyst as per the module chosen.
-3.3% (30 o)
6. Soiling Loss -1.5%
This is the loss due to dust and bird droppings
on the PV modules depending on the environmental conditions, rainfall frequency
and on the plant’s O&M module cleaning strategy.
To assure the maintenance of soiling losses below 1.5%, a novel soiling estimation setup will
be setup at plant during O&M consisting of two
PV strings. One of the PV strings will be cleaned on a daily basis, while the other one will not be
cleaned. Once, the difference between performance of the two strings will start
touching 1.25%, a module cleaning cycle of the entire plant will be initiated, thus ensuring
soiling loss in line with the design assumption.
7. Module Temperature Loss -9.5% (Seasonal)
The characteristics of a PV module are
determined at standard temperature conditions of 25˚C. Considering the temperature coefficient
of the 315Wp modules selected, the module performance decreases by -0.40% for every oC
rise in cell temperature.
Module temperature loss is computed by the PVSyst by considering the temperature profile
of the location as per the meteo database. Since, the site is located in Rajasthan, a desert region
with high temperatures, and the high temperature losses calculated are representative
of the high temperature profile.
8. Module Quality Loss +0.4%
PV modules generally deviate from the
manufacturer’s technical specifications. The 315W modules considered here are supplied
with a positive Power tolerance of 0 to 3%. The
developer has thus considered a quality gain of 0.4%, although on a conservative side so as to
account for other contingencies in generation estimation.
9.
First Year Module
Degradation (under Light Induced Degradation(LID))
-1.5%
The performance of PV modules degrades over
the time. The degradation is most significant
during few hours of first exposure of PV modules to light. This phenomenon is known as
Light Induced Degradation (LID). Factors affecting the degree of degradation include the
quality of materials used in manufacture, the manufacturing process and the quality of
assembly and packaging of cells into the
modules. The first year degradation considering LID and
annual degradation is guaranteed to be less than 2.5% in the datasheet. However, as per the
general industry experience, the first year degradation for Tier-1 modules has typically
been observed between 0.8% to 1.5%. Hence, the
first year module performance degradation has been considered as 1.5% here.
10. Module Array Mismatch Loss
-0.8%
Mismatch losses represent the mismatch in
current/voltage of modules in a string due to statistical variations. Typically, the mismatch
losses are considered as 1%. However, the loss
can be reduced by sorting the modules as per current before factory dispatch. The modules
supplied at site with a 3-bin current sorting will effectively reduce the mismatch losses. Hence,
we have considered the module mismatch losses as 0.8%.
11. DC Ohmic Wiring Loss -1.5% (STC)
Electrical resistance in the wires between the power available at the modules and at the
terminals of the array gives rise to ohmic losses (I²R).
For well-designed plants, DC cabling losses at STC vary from 1.2% to 1.5% at STC. We have
considered 1.5% as the DC Ohmic losses at STC.
The losses are at full load, and the PVsyst computed the overall losses considering the
solar plant operates at partial loads most of the times. The final loss then computed by PVSyst
corresponding to 1.5% loss at STC considering the partial load profile of plant is 1.1%
12. Inverter Loss during
Operation (Efficiency) -1.7%
Inverters convert power from DC into AC at a certain efficiency. This results in a loss of power
during conversion from AC to DC. The efficiency curves are inverter dependent. In our
case, the inverters considered are 1000kW of a
reputed make. The efficiency loss has been calculated by the PVSyst as per the
manufacturer provided efficiency curves of the inverter and stands at around 1.7%.
13. Auxiliary Losses -0.6%
Various components of plants like inverters,
PLC, module cleaning system, plant lighting, security systems etc and amenities like Air
conditioning, plumbing and others consume electricity for their operation. This is known as
auxiliary loss. The auxiliary losses vary from 0.5% to 1% depending upon the size, design and
structure of the plant. Typically, small plants
require a higher percentage of auxiliary consumption than bigger plants on relative
terms. Various measures such as night disconnect, self-powered trackers, LED lighting,
have been considered in the design for reducing auxiliary consumption. The auxiliary losses
have thus been reasonably considered at 0.6%
with sufficient margin.
14. AC Ohmic Losses -0.5% (Full Load)
This includes ohmic losses in the cable from
inverter leading to the substation, and depends
on the sizing of cables during the design. During the design of the plants, the AC cable sizing has
been done in such a way that the losses do not exceed 0.5% in the AC side. Full load AC ohmic
losses of 0.5% have been considered, corresponding to which PVsyst computes the
overall losses considering the solar plant operates at partial loads most of the times. The
final loss then computed by PVSyst
corresponding to 0.5% loss at STC considering the partial load profile of plant is 0.3%.
15. System Unavailability -0.5%
Downtime depends on the diagnostic response
time and stock of spare equipment. Further, loss
in generation due to unavailability of plant and grid are also accounted for in downtime losses.
Typically, the unavailability is higher for smaller plants, as compared to larger plants due to
relative impact of failure of a single component on the entire plant availability. The O&M
scheme thought out also considers stocking of
inverter transformer, breaker, inverter IGBT stacks, and modules, cables of all sizes,
consumables and on site deployment of service persons of critical components like
transformers, inverters on site along with regular manufacturer training of O&M
personnel. Large solar plants in solar parks are
now connected at 132kV to the grid which is ultimately connected at 400kV to green corridor
grid network, which will be extremely stable with very less downtime. Considering the
above, the system unavailability has been considered as 0.5%
16. External Transformer Loss -1.6%
Large losses may rise in the transformer but are
generally less than 1% for each transformation level. Given the fact that the plant will be
evacuating at 132kV, two levels of losses have been considered; 1.0% for the intermediate
transformation at 33/11kV, and 0.6% (following
the GTP of the transformer to be used on-site) for the second level of transformation at 132kV
in line with standard design practices.