Andy Dobson

Manager of Facilities

Staff Recruitment & Retention

Dept. not fully staffed since April 2012

50% of schools without sub-caretakers

Aging workforce (loss of man hours & many eligible to retire)

Ministry Funding Levels

Aging infrastructure & operating systems

-Weyburn Transportation Shop

-Teacherages

-ECS HVAC

Replacement Cost escalation

-Roofing projects are minimized – 20% increase annually

Contractor costs

-Electrical & Plumbing

-Capital Projects – APES Portable

Department’s Budgetary Focus – HVAC & Roofs Heating & ventilation upgrades

Roof upgrades to sections protecting critical assets

CADD Drawings – Integrated Space Inventory Systems Update School floor plans

Ministry CADD standards

Building asset management

Assiniboia Park Elementary School – Portable Classroom Versatile Concepts – 24’x40’ Portable

Pattison MGM Architects – tender link addition

Playground Safety Audits Inventory & condition of playground structures

Assessment of risk & liability

Preventative Maintenance Program Comprehensive quarterly assessments

Asset Planner reminders

Management field reports supported with photographs

PMR Funding 3 Year Plan

(Note: aligns with Ministry's fiscal year Apr- Mar) Submission

(Feb 2014)

2014-15 PMR PROJECT PLAN - April 1, 2014 - March 31, 2015

Radville High School boiler replacement 500,000.00$

ECS roof replacement (section 13 & 17 original - revised to section 2, 3 &11) 565,000.00

Div. Office HVAC - establish reserve fund 300,000.00

2014-15 TOTAL 1,365,000.00$

2015-16 PMR PROJECT PLAN - April 1, 2015 - March 31, 2016

Maryfield roof replacement (section 2, 3 & 4) 627,000.00$

ECS roof replacement (section 5 original - revised to section 17 gym) 654,500.00

Div. Office HVAC - establish reserve fund 300,000.00

2015-16 TOTAL 1,581,500.00$

2016-17 PMR PROJECT PLAN - April 1, 2016 - March 31, 2017

Midale roof replacement (section 2 & 4) 533,500.00$

Radville roof replacement (section 6 & 7) 240,000.00

Pleasantdale roof replacement (section 3, 8 & 9) 300,000.00

Div. Office HVAC - balance for completion 500,000.00

2016-17 TOTAL 1,573,500.00$

SECPSD - PMR 3 YEAR PLANto be sumitted to the Ministry of Education

WCS Construction Schedule – as of January 9, 2015

CONTRACT #1 – (awarded June 30, 2011)…………August 2013……(Substantially Complete – July 8, 2014)

April 3/11 Phase 1 – Renovation of Resource Rm, Server Rm. & Computer Lab…..………March 2012 Aug. 30/12 Phase 2a – G Block; Science Labs………………………………………………………………..August 2012 Mar. 11/14 Phase 2b – G Block; Commercial Kitchen…………………………………………………….February 2014 Feb. 5/13 Phase 3a – NEW Addition; Admin Office & Arts………………..…………………………January 2013 May 7/14 Phase 3b – NEW Addition; North Entrance & Commons Area …………………….February 2014 May 7/14 Phase 3c – NEW Addition; Auditorium…………………………………………………………April 2014 Dec. 10/13 Phase 3d – NEW Addition; Band & Choral……………………………………………………December 2013 Oct. 8/13 Phase 4a – B Block; Classroom renovations.………………………………………….…….June 2013 Dec. 13/13 Phase 4b – B Block; FIP Room………………………………………………………………………December 2013 Dec. 2/13 Phase 5 – A Block; renovations for Daycare………………………………………….……..December 2013 July 31/14 Phase 6 – Parking Lot…………………………………………………………………………………..July 2014

//////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////

CONTRACT #2 – (awarded June 9, 2013).…………December 2015 (Projected Completion)

Sept. 11/14 Phase 1 – Renovation C Block; Computer Lab, Green rm. & Sound rm………..June 2014 May 9/14 Phase 2a – Demolition 1913, 1947 & 1961 sections…………………………………….March 2014 July 15/14 Phase 2b – NEW Block H (Middle Years) & J (SERC) Foundation…………………..June 2014

Phase 2c – NEW Block H (Middle Yrs. Classroom & Courtyard)…………………….May 2015 Phase 2d – NEW Block J (Southeast Regional College)………………………………….December 2015 Phase 3 – Gymnasium & change room renovations…………………………….……….March 2015 Phase 4 – Reno D Classrooms (west side)…………………………………………………….March 2015

Oct. 28/14 Phase 4 – Reno PAA Cosmo, Home Ec. & Washrooms……………..………………….October 2014 Phase 5 - Reno West Vestibule, Football Storage & Janitorial……………………..February 2015 Phase 6 – Landscaping, Parking Lots…………………………………………………………….October 2015 (40% complete) Phase 7 – Reno PAA Electrical Lab, Mechanical & Welding…………………………..September 2015 Phase 8 – Reno Block C & D; Classroom (east side corridor).………………………..October 2015 Phase 9 – Reno Corridors………..…………………………………….……………………………..December 2015

WCS Construction Schedule

WEST AREA

Total Titles 83 Sold 41 Not Sold 42

SOUTH AREA

Total Titles 58 Sold 41 Not Sold 17

EAST AREA

Total Titles 45 Sold 29 Not Sold 16

Initial letter was sent to all adjacent land owners. Then a follow up letter was sent about 6 – 9 months later to the land owners who did not respond to the first letter.

Office: 848-4779

[email protected]

Questions