annex 2 eacp overview of preliminary feasibility study

Upload: lkosgey

Post on 29-May-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/8/2019 Annex 2 EACP Overview of Preliminary Feasibility Study

    1/20

    2004-01-31

    East AfricanCarrier Project

    Preliminary

    Feasibility Study

    EAST AFRICAN COMMUNITYSECRETARIAT

    Elias BahandaAnders Engvall

    Annex 2

  • 8/8/2019 Annex 2 EACP Overview of Preliminary Feasibility Study

    2/20

    2

    Present State of Telecom-

    munications in EAC CountriesEAC commissioned a communications strategystudy for Lake Victoria Basin, which identifiedthat the SERI OUS I SSUEof inadequate capacityand inefficient operation* of the regionaltelecommunications network, is resulting in

    Bottlenecks and constraints for regional economic development

    Reduced interest in regional investments due to inadequatetelecommunications services

    * E.g. some transmission equipment of the incumbent operators has longpassed its economic life time, congestion is high and speech quality poor

  • 8/8/2019 Annex 2 EACP Overview of Preliminary Feasibility Study

    3/20

    3

    Privatisation and Liberalisation? Have successfully contributed to the spectacular

    growth of the sector with large investments, but

    ? Have had a detrimental effect on regional co-

    operation and cross-border transmission projects, dueto:

    ? Entrance of new operators in the Partner States

    ? Focus on domestic priorities

    ? Monopoly Licensing restricts freedom of action for new

    power centres? Present situation poses a t hreat t o the economic

    and social co-operat ion in the Lake Victoria Basin

  • 8/8/2019 Annex 2 EACP Overview of Preliminary Feasibility Study

    4/20

    4

    Side-effects of Competition? Has created an atmosphere of distrust in the

    telecommunications sector

    ?

    Has reduced the frequency of activities forregional co-operation programmes in thesector

    ? Specifically, the liberalization has resulted inEAC inter-regional traffic being routed viasatellite even in cases where transmissioncapacity is available across borders

  • 8/8/2019 Annex 2 EACP Overview of Preliminary Feasibility Study

    5/20

    5

    Identified #1 Priority of

    the EAC Strategy Study

    Solve the regional traffic restrictions by

    establishing a regional backbone network (the

    Carrier Project) by? Involving all stakeholders including the new mobile

    operators and regulators

    ? Focusing upon small projects with immediate benefitsto the stakeholders, like direct interconnection

    between mobile operators including cross-borderinterconnections for regional traffic

  • 8/8/2019 Annex 2 EACP Overview of Preliminary Feasibility Study

    6/20

    6

    Recent EAC Actions? The key recommendations of the Strategy

    Study were agreed upon and adopted by theEAC Secretariat for implementation

    ?A pre-feasibility study was embarked upon todefine the investment needs and establish thefinancial viability of the Carrier Project

    ? The Communications Commissions of eachEAC country is jointly studying the legalimplications of the recommendations

  • 8/8/2019 Annex 2 EACP Overview of Preliminary Feasibility Study

    7/20

    7

    Methodology for

    Pre-feasibility StudyThe Regional Operators and all threeCommunications Commissions were visited to:

    ?

    Explain the objectives of - and to explore eachoperators interest in participating in - the proposedCarrier Project

    ? Find out the lay-out and capacity of existing andplanned transmission networks and demand forregional circuits

    ? Discuss the legal implications of the proposed CarrierProject

  • 8/8/2019 Annex 2 EACP Overview of Preliminary Feasibility Study

    8/20

    8

    Operator and Regulator

    Interest

    XDi rTA NZantel

    TA N

    TA N

    TA N

    TA N

    TA N

    KEN

    KEN

    KEN

    KEN

    UGA

    UGA

    UGA

    UGA

    Country

    XActing CEOTCRA

    XCEOTTCL

    XCEOMobitel

    X*CEOCeltel (MSI)

    XDi rVodacom

    XCEOCCK

    XCEOTK L

    XDi rKencell

    X*Di rSafaricom

    XCEOUCC

    XDi rUTL (Telcel)

    XDi rCeltel (MSI)

    XDi rM TN

    ScepticalPassive SupportActive SupportLevel MetOrganization

    * Subject to no objection by their shareholders

  • 8/8/2019 Annex 2 EACP Overview of Preliminary Feasibility Study

    9/20

    9

    Operators Views? One fixed line monopoly holder was reserved

    towards the proposed Carrier Company

    (infringement on the monopoly)

    ? All mobile operators were strongly supportive tothe idea, but:

    ? They were questioning the likelihood of the threeCommunications Commissions being able to agree on ajoint licensing for all three countries

    ? Safaricom and Celtel (Tz Ltd.) felt constrained in activelysupporting the idea due to being owned by KTL andTTCL respectively

  • 8/8/2019 Annex 2 EACP Overview of Preliminary Feasibility Study

    10/20

    10

    Regulators Views? All three Communications Commissions were very

    positive towards the proposal of a Regional CarrierCompany and did not see any legal obstacles

    ? Since fixed line monopolies are expiring in June2004 for Kenya and February 2005 for Tanzania,they felt that the proposal of the Carrier Companywas very timely

    ? A joint licensing mechanism for the three EACcountries would need to be established since there

    is no EAC licensing authority? Licensing policy would need to be agreed

    (e.g. auction or beauty contest)

  • 8/8/2019 Annex 2 EACP Overview of Preliminary Feasibility Study

    11/20

    11

    Availability of Transmission

    Capacity? The Mission got confirmation that some mobile operators

    have spare capacity (even if not fully equipped with radio)on individually owned transmission links, but not legallyavailable due to present licensing conditions

    ? Mobile operators in Kenya and Tanzania have been allowedby the regulators to build their own transmission links in lieuof provision by the fixed line monopoly carriers

    ? Uganda has two combined fixed mobile operators, both ofwhich have their own backbone network

    ? The Mission identified three microwave links, which could be

    built to establish a high-capacity regional transport networkand be ready in a short time span and at modest costs

  • 8/8/2019 Annex 2 EACP Overview of Preliminary Feasibility Study

    12/20

    12

    Project ProposalSince Kenya-Uganda links are becoming

    available, the following three microwave linkswere identified for establishing a regionalbackbone network:

    ? Mombasa Tanga (five sites, four hops)

    ? Arusha Nairobi (six sites, five hops)

    ? Masaka Bukoba (minimum three sites, but to

    Mwanza maximum 12 sites, 11 hops)

  • 8/8/2019 Annex 2 EACP Overview of Preliminary Feasibility Study

    13/20

    13

    Estimated Project Costs

    Low-cost Alternative

    ? 1.8 million*

    ? Making maximum use of existinginfrastructure

    High-cost Alternative

    ?

    5.2 million*

    * Includes 10% contingency

  • 8/8/2019 Annex 2 EACP Overview of Preliminary Feasibility Study

    14/20

    14

    Deployment of Capacity(at full utilization in 2009)

    36 E1 Circuits*Masaka - Bukoba Mwanza

    10 E1 Circuits Arusha Nairobi

    56 E1 Circuits*Mombasa Tanga

    * Includes 16 E1 for one34 Mb/s TV channel

  • 8/8/2019 Annex 2 EACP Overview of Preliminary Feasibility Study

    15/20

    15

    Key Assumptions for

    Viability Calculations? Traffic estimates have been made prorate in

    relation to present number of subscribers (June2003)

    ?

    Base traffic have been available from a few EACoperators only, but have been deemedrepresentative and used in the extrapolations

    ? Annual growth rates were estimated at 10%annually for voice and 10% - 50 % for data (froma very low initial level)

    ? Conservative revenue stream used at only sixyears (alternative fiber replacements will becomeavailable)

  • 8/8/2019 Annex 2 EACP Overview of Preliminary Feasibility Study

    16/20

    16

    Financial Viability(expressed as Internal Financial Rate of Return)

    Low-cost Alternative

    ? Kenya Tanzania Links 41 % IRR

    ? Tanzania Uganda Link 96 % IRR

    ? Total P roject 53 % IRR

    High-cost Alternative

    ? Kenya Tanzania Links 25 % IRR

    ? Tanzania Uganda Link 18 % IRR

    ? Total P roject 23 % IRR

  • 8/8/2019 Annex 2 EACP Overview of Preliminary Feasibility Study

    17/20

    17

    Sensitivity Analysis

    17%45%OPEX increased by 50%

    4%27%CAPEX increased by 50%

    6%20%Rentals reduced by 50% butRevenue Stream 10 years

    -8%9%Leased line rental reduced by

    50%

    High-CostIRR

    Low-CostIRR

    Parameter Change

  • 8/8/2019 Annex 2 EACP Overview of Preliminary Feasibility Study

    18/20

    18

    Non-financial Benefits? Will improve the spirit of EAC regional co-

    operation since the venture would be owned andoperated by the regional stakeholders

    ? Will remove bottlenecks, stimulate regional trafficand drive tariffs down

    ? Will enable the establishment of a regional datanetwork, reducing the dependence on expensivesatellite links

    ?

    Will provide the back-haul network that isessential for the East African Submarine Cableproject to materialize

  • 8/8/2019 Annex 2 EACP Overview of Preliminary Feasibility Study

    19/20

    19

    Implementation Issues? A full feasibility study should be carried out and

    include:? A detailed lay-out of a Regional Transmission Backbone

    Network? Study of the switching issues including switching

    interconnect points between operators

    ? A consortium of the regional operators needs to beformed to commit to and bring the Carrier Projectforward

    ? The licensing process needs to be monitored forrapid progress

  • 8/8/2019 Annex 2 EACP Overview of Preliminary Feasibility Study

    20/20

    20

    Conclusion of the Pre-feasibility

    Study for the Carrier Company

    The shown strong viability of the CarrierCompany gives the EAC the opportunity

    of rapidly improving regional telecom-munications services, greatly benefitingthe economies of the Partner States inaddition to getting a much better

    utilization of existing infrastructure