annual report2- 2012 -...
TRANSCRIPT
Your Benson Business Improvement District works to improve the vitality of downtown Benson by providing enhanced services, advocacy, collaboration and marketing.
Initiatives Completed in 2012
Cleaning and Maintenance -Litter and trash are removed from public spaces. -Snow is removed in a timely manner and sidewalks and alleys are unobstructed. Lighting and Security -Public safety is improved with emergency phones. -Criminal behavior is discouraged with additional lighting and signage. Promotion -A sense of place is developed with introduction of historical signage, holiday lighting, and banners. -Way finding is improved by placing informational and directional signage. -Benson is promoted as a destination by support of Benson events. Landscaping -The property within the BID is beautified with sustainable plantings, tree trimming, and weeding and mowing. Parking -The Benson Merchant’s Parking lot is improved with striping, removal of litter and trash and placement of signage.
2012 Budget
EXPENSE ITEM PROGRAM
$3,065.50 Restriping/Cleaning parking lot Maintenance
$2,641.27 Snow removal Maintenance
$5,304.68 New light fixtures on Maple Street via annual payment to city Lighting
$200.00 Additional Alley lighting Lighting
$5,451.12 Emergency phones Security
$2,500.00 125th Anniversary Celebration Sponsorship Promotion
$675.00 Business Watch Signs Promotion
$2,329.04 Banner brackets for new light fixtures Promotion
$6,211.74 Holiday lighting Promotion $1,120.00 Historic street signs Promotion
$3,514.15 Landscaping - Parking lot Landscaping $2,500.00 Landscaping - Maple Street Landscaping
$7,537.50 Administration Management $43,050.00 Total Revenue $43,050.00 Total Expenses
-$0- Remaining Revenue
$1,712.50 Weekly cleaning in downtown Separate Parking Fund
Benson Business Improvement District 2013 Initiatives and Budget
$45,202.50
Cleaning and Maintenance $8,000.00 -Litter and trash removed from public spaces -Snow plowed in a timely manner; sidewalks and alleys are unobstructed -Cigarette ash cans placed on Maple Street
Lighting and Security $10,304.68 -Emergency phones cell service. -Additional holiday lighting. -Annualized payment for replacement of street lights
Promotion $8,000.00 -Additional directional, informational, and promotional signage and banners placed. -Flagpole and monument added to new East entryway to downtown Benson.
Landscaping $4,000.00 -New East entryway to downtown Benson landscaped. -Tree wells planted and maintained.
Parking $2,897.82 + revenues from parking leases -Benson Merchant’s Parking lot maintained. -Additional parking options developed.
Management $12,000.00 -Administrative costs
Benson Business Improvement District PO Box 4672 Omaha, NE 68104