appendix e public hearing information
TRANSCRIPT
Appendix E
Public Hearing Information
1
STATE OF MICHIGAN 1
2
In the Matter of: 3
Clinton-Oakland Sewage Disposal System 4
State Revolving Fund Project Plan 5
Oakland County Water Resources Commissioner
6
/
7
PUBLIC HEARING 8
9
1 Public Works Drive, Waterford, Michigan
Wednesday, June 20, 2012, 7:00 p.m. 10
11
APPEARANCES: GREGORY P. KACVINSKY, PE 12
Orchard, Hiltz & McCliment
13
PHIL SANZICA, PE
Water Resource Commission 14
TIM PRINCE, PE 15
Water Resource Commission
16
17
RECORDED BY: Rachel Sunde, CER 6538
Certified Electronic Recorder 18
Network Reporting Corporation
Firm Registration Number 8151 19
1-800-632-2720
20
21
22
23
24
25
2
TABLE OF CONTENTS 1
PAGE 2
3
Opening statement by Mr. Sanzica . . . . . . . . . . . . . 3
Presentation by Mr. Kacvinsky. . . . . . . . . . . . . . . 3 4
Closing statement by Mr. Sanzica . . . . . . . . . . . . .11
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
3
Waterford, Michigan 1
Wednesday, June 20, 2012 - 7:02 p.m. 2
MR. SANZICA: Good evening. My name is Philip 3
Sanzica, I'm a chief engineer with the Oakland County Water 4
Resources Commissioner's Office. Tonight is the hearing for 5
the Clinton-Oakland Sewage Disposal System SRF Project plan. 6
It was published in the Oakland Press on May 20th, 2012. 7
And this is the time and place listed, 7:00 p.m. on June 8
20th, 2012 at the Water Resources Commissioner's Office 9
Public Works Drive, Building 95 West, Waterford, Michigan. 10
Tonight Orchard, Hiltz, & McCliment will be presenting the 11
project plan. Greg Kacvinsky of OHM, project manager, will 12
be presenting the project plan. Also in attendance is Tim 13
Prince who is also a chief engineer with the Water Resources 14
Commissioner's Office. And for the record, there is no 15
public here at the meeting. So we will be proposing -- we 16
will be dictating the presentation as Greg states it. So 17
therefore why don't we hand it over to Greg and we'll 18
continue on. 19
MR. KACVINSKY: Thank you, Phil. My name is Greg 20
Kacvinsky, I'm with OHM. We're the consulting engineer who 21
prepared the SRF project plan. And I'll be presenting 22
tonight as required by the Michigan Department of 23
Environmental Quality a public hearing and the presentation 24
of the proposes projects for the Clinton-Oakland Sewage 25
4
Disposal System. This meeting was public noticed more than 1
30 days ago as required by the MDEQ. And this meeting is a 2
required component of the SRF application process. All 3
comments received in writing or by the public at the public 4
hearing will be addressed either at this meeting or within 5
the project plan document. 6
At this meeting we'll cover the regulatory history 7
that led to this project plan, discuss the project plan 8
summary, and how the costs for the recommended projects will 9
be apportioned to the users in Clinton-Oakland Sewage 10
Disposal system. The benefits of the projects, and the 11
proposed schedule for design and construction of the 12
recommended projects. This project or this project plan 13
came about through correspondence between the WRC and the 14
MDEQ starting in 2006 as a result of a sanitary sewer 15
overflow in 2004. Between 2006 and 2009 the WRC and the 16
MDEQ discussed the need for a district compliance agreement 17
to address hydraulic insufficiency in the interceptor. In 18
2009 the WRC signed a district compliance agreement with the 19
MDEQ. And that district compliance agreement set into 20
motion several projects, several tasks that led to this 21
project plan. 22
It started with the master plan in 2010 that was 23
completed in January 2010 for the Clinton-Oakland system. 24
That master plan identified several hydraulic upgrades to 25
5
the system that would help increase hydraulic capacities and 1
decrease potential for sanitary sewer overflows. There were 2
two bottlenecks identified in the system and the projects 3
we're going to discuss tonight will directly address those 4
bottlenecks. 5
The proposed action plan that was developed by 6
MDEQ and the WRC was agreed upon in 2010. Several of those 7
tasks have been completed. The tasks that remain to be 8
completed are developing this SRF project plan, which is 9
what's being covered tonight. And then design and 10
implementation of the projects to address the 11
Clinton-Oakland system. The master plan in 2010 for the 12
Clinton-Oakland system identified several bottlenecks along 13
the main interceptor line. One main upstream bottleneck and 14
one downstream bottleneck within the service area. 15
A hydraulic analysis completed as part of that 16
master plan confirmed that several reaches of the 17
Clinton-Oakland interceptor sewer did not have sufficient 18
hydraulic capacity to handle wet weather floss. And so this 19
is a profile, the hydraulic profile of a portion of the 20
system that was identified as having a bottleneck where 21
there is potential for an SSO. The following slides 22
summarize the 2012 SRF project plan that was prepared in 23
draft form and discussed tonight. 24
There are two recommended projects, one is on the 25
6
upstream side of the system, the upstream of the system. 1
Which would take flows pumped from the Elizabeth Lake pump 2
station into a 5.5 million gallon storage retention tank 3
near the or at the Road Commission of Oakland County 4
facility. The other proposed project, the downstream end of 5
the system or towards the downstream end of the system, is a 6
diversion to the Pontiac Wastewater Treatment Plant at Perry 7
Street in the City of Pontiac. 8
In evaluating upstream projects, we looked at 9
several alternatives to -- several different locations for 10
storage facility. And including diverting, instead of 11
storing the wastewater in a tank, diverting a portion of the 12
flow to the Pontiac wastewater treatment plant from 13
Elizabeth Lake Pump Station. The most cost efficient 14
project was identified as a 5.5 million gallon storage tank 15
at the Road Commission of Oakland County property. The 16
reason that project was less expensive than the others is 17
there wasn't the larger land acquisition costs associated 18
with purchase of private property. Putting the tank on 19
public property is more cost efficient. And because it's 20
going on a site that does not require multi use, the tank 21
can be above ground, we can reduce the construction cost of 22
the tank by putting it above and ground instead of below 23
ground. 24
This figure illustrates the proposed forced main 25
7
extension from Elizabeth Lake Pump Station to the proposed 1
Road Commission of Oakland County site where the 5.5 million 2
gallon tank would be located. Figure two shows the location 3
of the tank. A 250 foot diameter above ground tank. Water 4
would be pumped in, the wastewater that is, would be pumped 5
in. And the tank would discharge after the storm when the 6
interceptor -- the flows in the interceptor were low enough 7
to accept flows. To summarize the upstream project, the 5.5 8
million gallon tank will accept up to 13 cfs flow, wet 9
weather flow diverted from Elizabeth Lake Pump Station. 10
Would require 6,700 feet of force main extension from the 11
existing force main to the proposed site, proposed storage 12
tank site. And as I mentioned before, use of public 13
property reduces land acquisition costs. And the above 14
ground tank will reduce excavation and structural costs. 15
We also evaluated the downstream projects to 16
address the downstream hydraulic bottlenecks. Of all the 17
projects that we evaluated, the Perry Street diversion 18
project was the least expensive. We also evaluated storage 19
options and gravity flow options from Perry Street to the 20
Pontiac Wastewater Treatment Plant. This figure illustrates 21
the location and configuration of the diversion from Perry 22
Street to the Pontiac Wastewater Treatment Plant. Consists 23
of approximately two miles of a 36 inch gravity sewer at the 24
upstream end of pump station that diverts water from the 25
8
interceptor. And that sanitary sewer would flow to the 1
Pontiac Wastewater Treatment Plant. 30 percent of the total 2
Clinton-Oakland service area flows would be diverted to the 3
wastewater treatment plant, which is the contractual maximum 4
diversion from DWSD system. And the flow rates would range 5
from 14 cfs during dry weather to up to 47 cfs for future 6
wet weather flows. 7
The following two figures illustrate the proposed 8
pump station location and sanitary sewer. Starting at 9
Galloway Lake Park in the City of Pontiac adjacent to the 10
Clinton-Oakland interceptor. The proposed sanitary sewer 11
would flow south through a railroad right-of-way along the 12
west side of the Silverdome to the existing Auburn plant 13
City of Pontiac Wastewater Treatment. The details on the 14
downstream project, dry weather flow will be approximately 15
14 cfs. The flow rate during wet weather that will be 16
diverted will be up to 47 cfs. And the pump station would 17
be designed to handle that range of flow rates. The 18
diversion will reduce the flows in the interceptor thereby 19
solving the hydraulic bottleneck at that location. 20
In addition to the upstream and downstream 21
projects, we also evaluated a single project that would 22
address the upstream and downstream hydraulic bottlenecks 23
together. And that is a diversion from the Elizabeth Lake 24
Pump Station to the City of Pontiac Wastewater Treatment 25
9
plant diverting all flows that reach Elizabeth Lake Pump 1
Station. Doing so would alleviate the hydraulic pressures 2
downstream and solve the hydraulic issues identified in the 3
2010 master plan. 4
The main concerns with that is that it would 5
require five miles of force main. It would also require 6
significant upgrades and capital improvements to the 7
Elizabeth Lake Pump Station. And also removing all flows 8
from the system at that point would mean that we'd have a 9
significant length of the interceptor that would have little 10
to no flow that would cause maintenance problems and odor 11
problems. And when we evaluated the cost for this single 12
project alternative it was not cost effective. Comparing 13
the cost of the single project alternative to the sum of the 14
two recommended projects, the total cost was slightly higher 15
for the single project alternative. Therefore we came to 16
the conclusion that the combination of the upstream storage 17
and downstream diversion would be more cost effective and 18
are recommended. 19
The key project schedule started with the draft of 20
the SRF Project Plan that was submitted for public review 21
approximately one month ago. We have a public hearing as 22
required you the MDEQ tonight. We will take any comments 23
received and submit the final project plan including a 24
transcript of tonight's meeting to the MDEQ before the end 25
10
of June 2012. The Perry Street diversion, the downstream 1
project will be designed starting this fall. And 2
anticipated construction start date in fall of 2013. The 3
upstream proposed project, the SRT, storage retention tank, 4
at the Road Commission for Oakland County site would likely 5
not be designed and constructed until the 2014-1016 range. 6
And that is because there are some continued improvements 7
going on in the communities upstream of that tank that need 8
to be evaluated before the tank can be sized, we can 9
finalize the size for that tank. 10
The combination of the two proposed projects will 11
require an increase in user fees. Because these two 12
projects benefit all communities tributary to the 13
Clinton-Oakland interceptor, we are considering these 14
projects to be common to all in that all communities benefit 15
from reducing the hydraulic restriction on the interceptor. 16
The cost of the two recommended projects together will raise 17
the average annual residential user fee by approximately 18
$38.97 a year. And that's based on a 3-person household. 19
And that is based on jut the capital improvement cost to 20
construct those two improvements. And operations and 21
maintenance costs of those facilities as well. 22
The key benefits of these projects is that it does 23
address the hydraulic bottlenecks identified in the 2010 24
master plan. And helps reduce the frequency of SSO's. It 25
11
results in compliance with the MDEQ's and WRC's district 1
compliance agreement. And allows the WRC to maintain the 2
schedule on that district compliance agreement. It improves 3
overall system reliability. And there's also a side benefit 4
of reduced -- potential for reduced overall costs because 5
flows are being diverted to the City of Pontiac Wastewater 6
Treatment Plant treating the wastewater closer to home and 7
thereby having an overall economic benefit to the community 8
and all of the users within the Clinton-Oakland system. 9
We are ahead of schedule on developing an SRF 10
project plan, one year ahead of schedule. That's primarily 11
because the WRC was able to work with the City of Pontiac to 12
finalize an agreement to divert wastewater to the City of 13
Pontiac Wastewater Treatment Plant. So these efforts have 14
begun a little bit ahead of schedule. However, it is 15
anticipated that the upstream project, the 5.5 million 16
gallon SRT would be designed and constructed on schedule. 17
Are there any questions or comments? 18
MR. SANZICA: This is Philip Sanzica again, from 19
the Water Resources Commissioner's Office. This concludes 20
our public hearing. We will be submitting the project plan 21
to the State MDEQ before the July 1st deadline. So I'd like 22
to thank Greg for his fine job and we'll conclude the 23
hearing at this time. Thank you. 24
25
12
(Meeting concluded at 7:18 p.m.) 1
2
-0-0-0- 3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25