appendix i - winnipeg · maximum week flow in summer = adf x flow factor for season x flow factor...
TRANSCRIPT
APPENDIX I
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
Table of Contents
Table A1 - Peak Factors Used In Preparation Of Synthetic Database .........................................1
Table A2 - Hourly Factors Used In Preparation Of Synthetic Database ......................................2
Table A3 - Selected Wastewater Characteristics Used In Biowin Modeling. ................................3
Table A4 - Selected Parameters Of Autotrophic Biomass. ...........................................................3
Table A5 - Selected Parameters Of Heterotrophic Biomass.........................................................3
Table A6 - Selected Fermentate Characteristics. .........................................................................3
Table A7 - Selected Parameters Of Fermentate Used In Modeling..............................................4
Table A8 - Reported Vfa Generation In Side-Stream Prefermenters............................................5
Table A9 - Calculations Of Required Area Of Secondary Clarifiers For All Options. ....................7
Figure A1 - Biowin Input For Option B – Bnr/Mj No Side Treatment.............................................8
Figure A2 - Biowin Input For Option C – Bnr/Mj With Side Treatment. .........................................9
Figure A3 - Biowin Input For Option D - Hpo/Bnr/Mj With Side Treatment. ................................10
Figure A4 - Biowin Input For Option I - Bnr/Mj And Hpo As Side Treatment. .............................11
Figure A5 - Synthetic Flow Distribution In Design Year 2031 – Spring Season..........................12
Figure A6 - Simulated Cod Load In Design Year 2031 – Spring Season. ..................................13
Figure A7 - Simulated Cod Concentrations In Design Year 2031 – Spring Season. ..................14
Figure A8 - Simulated Tss Load In Design Year 2031 – Spring Season. ...................................15
Figure A9 - Simulated Tss Concentrations In Design Year 2031 – Spring Season. ...................16
Figure A10 - Simulated Tkn Load In Design Year 2031 – Spring Season..................................17
Figure A11 - Simulated Tkn Concentrations In Design Year 2031 – Spring Season..................18
Figure A12 - Simulated Tp Load In Design Year 2031 – Spring Season...................................19
Figure A13 - Simulated Tp Concentrations In Design Year 2031 – Spring Season. ..................20
Figure A14 - Flow Vs Temperature In Spring 2031 – Used In Dynamic Simulation. ..................21
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc i
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
Figure A15 - Primary Clarifier Solids Overflow Rate And Hydraulic Residence Time And Daily Averages For Both Parameters (All Options).......................................................................22
Figure A16 - Option B – Dynamic Modeling Results...................................................................23
Figure A17 - Option C – Dynamic Modeling Results. .................................................................24
Figure A18 - Option D – Dynamic Modeling Results. .................................................................25
Figure A19 - Option I – Dynamic Modeling Results. ...................................................................26
Figure A20 - Option B – Secondary Clarifier Solids Loading Rate And Surface Overflow Rate During Spring 2031. .............................................................................................................27
Figure A21 - Option C – Secondary Clarifier Solids Loading Rate And Surface Overflow Rate During Spring 2031. .............................................................................................................28
Figure A22 - Option D – Secondary Clarifier Solids Loading Rate And Surface Overflow Rate During Spring 2031. .............................................................................................................29
Figure A23 - Option I – Secondary Clarifier (Bnr Plant Only) Solids Loading Rate And Surface Overflow Rate During Spring 2031. .....................................................................................30
Figure A24 - Option I – Secondary Clarifier (Hpo Plant Only) Solids Loading Rate And Surface Overflow Rate During Spring 2031. .....................................................................................31
Figure A25 - Simulated Flows In Design Year 2031 – Whole Year. ...........................................32
Figure A26 - Simulated Tss Loads In Design Year 2031 – Whole Year. ...................................33
Figure A27 - Simulated Cod Load In Design Year 2031 – Whole Year. ....................................34
Figure A28 - Simulated Tkn Load In Design Year 2031 – Whole Year.......................................35
Figure A29 - Simulated Tp Load In Design Year 2031 – Whole Year. .......................................36
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc ii
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
Table A1 - Peak Factors used in Preparation of Synthetic Database
Flow factors Season Month Week Day Peak value
Winter 1.00 1.02 1.06 1.07 1.16 Spring 1.30 1.25 1.29 1.57 3.27
Summer 1.30 1.48 1.35 1.69 4.39 Fall 1.15 1.17 1.13 1.27 1.93
Load factors - BOD Season Month Week Day Peak value
Winter 1.00 1.35 1.25 1.34 2.26 Spring 1.25 1.56 1.24 1.13 2.74
Summer 1.12 1.40 1.68 1.18 3.10 Fall 1.06 1.35 1.12 1.03 1.66
Load factors - TSS Season Month Week Day Peak value
Winter 1.00 1.66 1.22 1.37 2.78 Spring 1.47 1.68 1.27 1.16 3.63
Summer 1.36 1.55 1.52 1.48 4.70 Fall 1.06 1.62 1.17 1.08 2.19
Load factors - TKN Season Month Week Day Peak value
Winter 1.00 1.17 1.16 1.07 1.45 Spring 1.02 1.26 1.16 1.08 1.61
Summer 0.92 1.20 1.16 1.13 1.43 Fall 0.97 1.18 1.04 1.01 1.20
Load factors - TP Season Month Week Day Peak value
Winter 1.00 1.20 1.16 1.13 1.57 Spring 1.07 1.36 1.21 1.10 1.94
Summer 0.88 1.27 1.20 1.12 1.51 Fall 1.00 1.27 1.22 1.07 1.66
Example of calculation:
Maximum week flow in summer = ADF x Flow factor for season x flow factor for month x flow factor for week = 68.4 x 1.30 x 1.48 x 1.35 = 177.6 MLD
TSS load in maximum day in spring = ADF TSS load x Flow factor for season x flow factor for month x flow factor for week x flow factor for day = 17901.3 x 1.47 x 1.68 x 1.27 x 1.16 = 65128.8 kg/d
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 1
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
Table A2 - Hourly Factors used in Preparation of Synthetic Database
Time Hourly Peak factors* hr Flow COD TSS TKN TP 0 1.06 1.089 1.018 0.927 0.942 1 0.99 0.911 0.844 0.848 0.864 2 0.90 0.732 0.671 0.768 0.787 3 0.72 0.647 0.606 0.721 0.715 4 0.63 0.563 0.541 0.673 0.644 5 0.58 0.478 0.476 0.626 0.572 6 0.53 0.521 0.511 0.749 0.665 7 0.53 0.564 0.546 0.872 0.757 8 0.67 0.607 0.581 0.995 0.850 9 0.79 0.706 0.688 1.096 0.938
10 0.96 0.804 0.796 1.198 1.027 11 1.17 0.903 0.903 1.299 1.115 12 1.32 0.934 0.944 1.244 1.130 13 1.24 0.966 0.985 1.188 1.145 14 1.25 0.997 1.026 1.133 1.160 15 1.21 1.146 1.163 1.112 1.170 16 1.16 1.296 1.300 1.092 1.180 17 1.15 1.445 1.437 1.071 1.190 18 1.14 1.473 1.480 1.092 1.194 19 1.18 1.500 1.524 1.114 1.198 20 1.19 1.528 1.567 1.135 1.202 21 1.22 1.441 1.442 1.092 1.141 22 1.22 1.355 1.316 1.050 1.080 23 1.17 1.268 1.191 1.007 1.019
* - Flow factors - based on SEWPCC instantaneous flow historical data;
COD, TSS, TKN, TP factors based on diurnal study performed by Stantec in April 06 (values in bold from 3-hour composite
samples, values not in bold estimated Example of calculation:
Maximum week flow in summer at 3 pm = ADF x Flow factor for season x flow factor for month x flow factor for week x hourly flow factor = 68.4 x 1.30 x 1.48 x 1.35 x 1.21 = 214.9 MLD
TSS load in maximum day in spring at 8 am = ADF TSS load x Flow factor for season x flow factor for month x flow factor for week x flow factor for day x hourly flow factor = 17901.3 x 1.47 x 1.68 x 1.27 x 1.16 x 0.581 = 37839.8 kg/d
Note: Maximum day in spring and summer has peak hour factor of 1.6
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 2
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
Table A3 - Selected Wastewater Characteristics used in BioWin Modeling.
Table A4 - Selected Parameters of Autotrophic Biomass.
Table A6 - Selected Fermentate Characteristics.
Parameter Default Value0.2 0.8
Fac - Acetate [gCOD/g of readily biodegradable COD] 0.15 0.5Fxsp - Non-colloidal slowly biodegradable [gCOD/g of slowly degradable COD] 0.75 0.75Fus - Unbiodegradable soluble [gCOD/g of total COD] 0.05 0.05Fup - Unbiodegradable particulate [gCOD/g of tota OD] 0.13 0.13Fna - Ammonia [gNH3-N/gTKN] 0.66 0.66Fnox - Particulate organic nitrogen [gN/g Organic N] 0.5 0.5Fnus - Soluble unbiodegradable TKN [gN/gTKN] 0 0FupN - N:COD ratio for unbiodegradable part. COD N/gCOD] 0.035 0.035Fpo4 - Phosphate [gPO4-P/gTP] 0.5 0.5FupP - P:COD ratio for influent unbiodegradable part. COD [gP/gCOD] 0.011 0.011
Name Default ValueFbs - Readily biodegradable (including Acetate) [gCOD/g of total COD] 0.2 0.18Fac - Acetate [gCOD/g of readily biodegradable COD] 0.15 0.27Fxsp - Non-colloidal slowly biodegradable [gCOD/g of slowly degradable COD] 0.75 0.75Fus - Unbiodegradable soluble [gCOD/g of total COD] 0.05 0.08Fup - Unbiodegradable particulate [gCOD/g of total COD] 0.13 0.18Fna - Ammonia [gNH3-N/gTKN] 0.66 0.60Fnox - Particulate organic nitrogen [gN/g Organic N] 0.5 0.64Fnus - Soluble unbiodegradable TKN [gN/gTKN] 0 0.00FupN - N:COD ratio for unbiodegradable part. COD [gN/gCOD] 0.035 0.09Fpo4 - Phosphate [gPO4-P/gTP] 0.5 0.63FupP - P:COD ratio for influent unbiodegradable part. COD [gP/gCOD] 0.011 0.01FZbh - Non-poly-P heterotrophs [gCOD/g of total COD] 1.00E-04 1.00E-04FZbm - Anoxic methanol utilizers [gCOD/g of total COD] 1.00E-04 1.00E-04FZba - Autotrophs [gCOD/g of total COD] 1.00E-04 1.00E-04FZbp - PAOs [gCOD/g of total COD] 1.00E-04 1.00E-04FZbpa - Propionic acetogens [gCOD/g of total COD] 1.00E-04 1.00E-04FZbam - Acetoclastic methanogens [gCOD/g of total COD] 1.00E-04 1.00E-04FZbhm - H2-utilizing methanogens [gCOD/g of total COD] 1.00E-04 1.00E-04
NameMax. spec. growth rate d -1 0.9 0.9 1.072Aerobic decay rate d -1 0.17 0.17 1.029Anoxic/anaerobic decay rate d -1 0.08 0.08 1.029
Unit Default Value Arrhenius
Table A5 - Selected Parameters of Heterotrophic Biomass.
Nam niuse Unit Default Value Arrhe
Max. spec. growth rate d -1 3.2 3.2 1.029Aerobic decay d -1 0.62 0.62 1.029Anoxic/anaerobic decay d -1 0.3 0.3 1.029
dable (including Acetate) [gCOD/g of total COD]Fbs - Readily biodegra
l C
[g
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 3
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
Table A7 - Selected Parameters of Fermentate used in Modeling.
Name ValueFlow, m3/d 906Total COD mg/L 4647Total Kjeldahl Nitrogen mgN/L 80Total P mgP/L 18Nitrate N mgN/L 0pH 7.3Alkalinity mmol/L 6Inorganic S.S. mgTSS/L 60Calcium mg/L 160Magnesium mg/L 25Dissolved oxygen mg/L 0
Detailed calculations of fermentate in design year 2031:
Assumptions: average flow - 90.4 MLD
Average TSS concentration – 292 mg/L Average TSS load = 90 MLD x 388 mg/L = 26397 kg/d TSS load removed in primary clarifiers @70% removal (1995-2005 data showed 76% removal on average) = 0.7 x 26397 = 18478 kg/d Assuming 2% TS in sludge, primary sludge flow = 18478/ (1000 x 1.02 x 0.02) = 906 m3/d VSS/TSS ratio (2006 plant data suggest 0.815) = 0.80 VSS amount removed in primary clarifiers = 0.75 x 18478 kg/d = 14782 kg/d The reported range of VFA production in side-stream prefermenters is presented in Table A8.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 4
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
Table A8 - Reported VFA Generation in Side-Stream Prefermenters
Range, unit Reference 0.066 – 0.15 VFA-COD/g solids as COD Barnard, J., Shaw, A. et al. 2005 0.10 – 0.20 g VFA/g VSS applied Tchobanoglous, G., Burton, F. et al. 2003 15 – 70 mg VFA/L hour Rössle, W.H. and Pretorius, W.A. 2001
Calculated values of VFA generation: Method 1 According to recent study presented by (Wentzel, M.C., Ekama, G.A. et al. 2006) COD/VSS ratio for primary sludge varies between 1.58 to 1.93. It is assumed for the purpose of this report that 1 g VSS is equivalent to 1.75 g COD. VFA = 14782 kg VSS/d * 1.75 x 0.10 g VFA-COD/g VSS = 2587 kg VFA-COD/d Data compiled and presented by (Rössle, W.H. and Pretorius, W.A. 2001) summarized typical composition of VFA from prefermenters. According to that study on average 1.28 g VFA-COD was equivalent to 1 g VFA. Therefore: VFA = 2587 kg VFA-COD/d / 1.28 g VFA-COD/g VFA = 2021 kg VFA/d Method 2 VFA = 14782 kg VSS/d x 0.15 kg VFA/kg VSS = 2217 kg VFA/d Method 3 The rate of VFA generation is useful for determining the required tank volume. The most important parameter that determines tank volume is HRT. Reported range of HRT for side-stream prefermenters was in the range of 6 to 42 hours, with average between 15 to 18 hours (Rössle, W.H. and Pretorius, W.A. 2001). For the purpose of this report it is assumed that the average HRT of prefermentation process is 18 hours. VFA = 906 m3/d x 50 g/ m3 hour x 18 hours = 815 kg VFA/d Value of VFA calculated by method 3 differs significantly from values obtained through previous calculations. From operational perspective, it would be possible to increase VFA by extending the retention time in the fermenter. Also, it was reported that fermenter underflow contained approximately 1000 mg/L VFA as COD, and increased flow above desludging pipe allowed to elutriate desired VFA (Lindeke, D. and Barnard, J. 2005). Because of that, it was possible to increase VFA generation rate fourfold (from 50 mg/L to 200 mg/L VFA) in fermenter overflow. On the other hand, temperature was found to have a strong impact on the rate of VFA production. Drop in temperature from 20oC to 10oC was found to decrease the rate of VFA generation by approximately 50% (Barnard, J., Shaw, A. et al. 2005). Calculations by method 3 also reveal that proper design of the retention time in the fermenter will be of utmost importance for the successful operation of BNR plant in the cold climate of Winnipeg, MB.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 5
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
Estimated amount of VFA for the purpose of modeling was the average value from three calculation methods used, that is 1684 kg VFA/d. Additionally, it was assumed the biodegradable fraction of fermenter supernatant is composed in 80% from readily biodegradable fraction of COD, out of which 50% is VFA see Table A6. That calculates to 4210 kg of COD/day in the fermenter supernatant or 4647 mg COD/L.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 6
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
Table A9 - Calculations of Required Area of Secondary Clarifiers for all Options.
Design flow MLD 111 Max flow MLD 166.5Average SOR m 3 /m 2 d 24 Max SOR m 3 /m 2 d 50Area m2 8094 Area m2 5828Recycle rate 1.75 Recycle rate 1.75Average SLR kg/m 2 hr 6 Max SLR kg/m 2 hr 9Assumed MLSS mg/L 4500 Assumed MLSS mg/L 4500Area m2 6070 Area m2 6070Design flow MLD 111 Max flow MLD 124.5Average SOR m 3 /m 2 d 24 Max SOR m 3 /m 2 d 50Area m2 8094 Area m2 4358Recycle rate 1.75 Recycle rate 1.75Average SLR kg/m 2 hr 6 Max SLR kg/m 2 hr 9Assumed MLSS mg/L 4500 Assumed MLSS mg/L 4500Area m2 6070 Area m2 4539Design flow MLD 111 Max flow MLD 124.5Average SOR m 3 /m 2 d 24 Max SOR m 3 /m 2 d 50Area m2 8094 Area m2 4358Recycle rate 1.75 Recycle rate 1.75Average SLR kg/m 2 hr 6 Max SLR kg/m 2 hr 9Assumed MLSS mg/L 4500 Assumed MLSS mg/L 4500Area m2 6070 Area m2 4539Desing flow MLD 86.7 Max flow MLD 103.5Average SOR m 3 /m 2 d 24 Max SOR m 3 /m 2 d 50Area m2 3613 Area m2 2070Recycle rate 1.75 Recycle rate 1.75Average SLR kg/m 2 hr 6 Max SLR kg/m 2 hr 9Assumed MLSS mg/L 4500 Assumed MLSS mg/L 4500Area m2 4741 Area m2 3773
Design flow MLD 24.3 Max flow MLD 80Average SOR m 3 /m 2 d 24 Max SOR m 3 /m 2 d 50Area m2 1013 Area m2 1600Recycle rate 1.75 Recycle rate 1.75Average SLR kg/m 2 hr 6 Max SLR kg/m 2 hr 9Assumed MLSS mg/L 4500 Assumed MLSS mg/L 4500Area m2 1329 Area m2 2917
Option B
Option I BNR
Option I HPO
Option C
Option D
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 7
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
Raw Sludge
Pre-Anoxic Anaerobic Anoxic Aerobic BNR Effluent
WAS splitter
WAS
Secondary Clarifier
Fermenter input
Bypass Effluent
Plant Efflu
Bypass at 166.5 MLD
Existing Primary Clarifier
Additional primary clarifiers
Primary Sludge#1
Primary Sludge #2
Figure A1 - BioWin Input for Option B – BNR/MJ No Side Treatment.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 8
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
Raw Influent Pre-Anoxic Anaerobic Anoxic Aerobic BNR Effluent
WAS splitter
WAS
Secondary Clarifier
Fermenter input
Plant Efflu
Existing clarifiers
New CEPT clarifiers
Primary Sludge
Primary sludge #2Alum addition
Bypass effluent
Bypass at 124.5 MLD
Figure A2 - BioWin Input for Option C – BNR/MJ with Side Treatment.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 9
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
Figure A3 - BioWin Input for Option D - HPO/BNR/MJ with Side Treatment.
Raw Influent BNR Effluen
Primary Sludge
HPO
WAS Splitter
Existing primary clarifier
New CEPT clarifiers
Alum addition CEPT sludge
Bypass at 124.5 MLD
Bypass efflu
Pre-Anoxic Anaerobic HPO vented
Plant Efflue
BNR sludge
Fermenter input
Anoxic Secondary clarifier
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 10
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
Raw Influent Pre-Anoxic Anaerobic Anoxic Aerobic BNR Effluent
WAS splitter
WAS
Secondary Clarifier
Fermenter input
Existing HPO system Existing HPO clarifier HPO Effluent
Plant Efflu
HPO RAS splitter
HPO sludge
Bypass at 80 MLD
ByPass
Alum addition
Existing primary clarifier
Ideal primary settling tank64
HPO MIN Flow 15 MLD Bypass at 103.5 MLD
Primary sludge #1
Primary sludge #2
Figure A4 - BioWin Input for Option I - BNR/MJ and HPO as Side Treatment.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 11
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
0
50
100
150
200
250
300
350
400
3/1 3/8 3/15 3/22 3/29 4/5 4/12 4/19 4/26 5/3 5/10 5/17 5/24 5/31
Date, day/month/year 2031
Flow
, MLD
Figure A5 - Synthetic Flow Distribution in Design year 2031 – Spring Season.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 12
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
0
20000
40000
60000
80000
100000
120000
140000
1-Mar 8-Mar 15-Mar 22-Mar 29-Mar 5-Apr 12-A
pr 19-Apr 26-Apr 3-May 10-May 17-May 24-May 31-May
Date, day/month/year 2031
CO
D lo
ad, k
g/da
y
Figure A6 - Simulated COD Load in Design Year 2031 – Spring Season.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 13
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
0.00
100.00
200.00
300.00
400.00
500.00
600.00
700.00
800.00
1-Mar 8-Mar 15-Mar 22-Mar 29-Mar 5-Apr 12-Apr 19-Apr 26-Apr 3-May 10-May 17-May 24-May 31-May
Date, day/month/year 2031
CO
D c
once
ntra
tion,
mg/
L
Figure A7 - Simulated COD Concentrations in Design Year 2031 – Spring Season.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 14
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
0
20000
40000
60000
80000
100000
120000
1-Mar 8-Mar 15-Mar 22-Mar 29-Mar 5-Apr 12-Apr 19-Apr 26-Apr 3-May 10-May 17-May 24-May 31-May
Date, day/month/year 2031
TSS
load
, kg/
day
Figure A8 - Simulated TSS Load in Design Year 2031 – Spring Season.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 15
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
0.00
100.00
200.00
300.00
400.00
500.00
600.00
1-Mar 8-Mar 15-Mar 22-Mar 29-Mar 5-Apr 12-Apr 19-Apr 26-Apr 3-May 10-May 17-May 24-May 31-May
Date, day/month/year 2031
TSS
conc
entr
atio
n, m
g/L
Figure A9 - Simulated TSS Concentrations in Design Year 2031 – Spring Season.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 16
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
0
1000
2000
3000
4000
5000
6000
7000
8000
1-Mar 8-Mar 15-Mar 22-Mar 29-Mar 5-Apr 12-Apr 19-Apr 26-Apr 3-May 10-May 17-May 24-May 31-May
Date, day/month/year 2031
TKN
load
, kg/
day
Figure A10 - Simulated TKN Load in Design Year 2031 – Spring Season.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 17
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
1-Mar 8-Mar 15-Mar 22-Mar 29-Mar 5-Apr 12-Apr 19-Apr 26-Apr 3-May 10-May 17-May 24-May 31-May
Date, day/month/year 2031
TKN
con
cent
ratio
n, m
g/L
Figure A11 - Simulated TKN Concentrations in Design Year 2031 – Spring Season.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 18
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
0
200
400
600
800
1000
1200
1400
1-Mar 8-Mar 15-Mar 22-Mar 29-Mar 5-Apr 12-Apr 19-Apr 26-Apr 3-May 10-May 17-May 24-May 31-May
Date, day/month/year 2031
TP
load
, kg/
day
Figure A12 - Simulated TP Load in Design Year 2031 – Spring Season.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 19
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
0.00
2.00
4.00
6.00
8.00
10.00
12.00
1-Mar 8-Mar 15-Mar 22-Mar 29-Mar 5-Apr 12-Apr 19-Apr 26-Apr 3-May 10-May 17-May 24-May 31-May
Date, day/month/year 2031
TP c
once
ntra
tion,
mg/
L
Figure A13 - Simulated TP Concentrations in Design Year 2031 – Spring Season.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 20
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
0
50
100
150
200
250
300
350
400
22-F
eb
1-M
ar
8-M
ar
15-M
ar
22-M
ar
29-M
ar
5-A
pr
12-A
pr
19-A
pr
26-A
pr
3-M
ay
10-M
ay
17-M
ay
24-M
ay
31-M
ay
7-Ju
n
Date, day/month/year 2031
Flow
, MLD
-1
1
3
5
7
9
11
13
15
Tem
pera
ture
, Cel
sius
Flow
Temperature
Daily average flow
Figure A14 - Flow VS Temperature in Spring 2031 – used in Dynamic Simulation.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 21
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
BioWin Chart
Existing Primary Clarifier Hydraulic residence time Existing Primary Clarifier Surface overflow rateHRT - daily average SOR - daily average
DATE5/24/20315/17/20315/10/20315/3/20314/26/20314/19/20314/12/20314/5/20313/29/20313/22/20313/15/20313/8/20313/1/2031
SOR
(m3/
m2
d) a
nd H
RT
(h)
75
70
65
60
55
50
45
40
35
30
25
20
15
10
5
0
Figure A15 - Primary Clarifier Solids Overflow Rate and Hydraulic Residence Time and Daily Averages for Both Parameters (all
options).
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 22
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
BioWin Chart
Plant Effluent Total suspended solids Plant Effluent Total PPlant Effluent Total Carbonaceous BOD Plant Effluent Total N
DATE5/24/20315/17/20315/10/20315/3/20314/26/20314/19/20314/12/20314/5/20313/29/20313/22/20313/15/20313/8/20313/1/2031
CO
NC
(mg/
L)
28
26
24
22
20
18
16
14
12
10
8
6
4
2
Figure A16 - Option B – Dynamic Modeling Results.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 23
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
BioWin Chart
Plant Effluent Total suspended solids Plant Effluent Total PPlant Effluent Total Carbonaceous BOD Plant Effluent Total N
DATE5/24/20315/17/20315/10/20315/3/20314/26/20314/19/20314/12/20314/5/20313/29/20313/22/20313/15/20313/8/20313/1/2031
CO
NC
(mg/
L)
75
70
65
60
55
50
45
40
35
30
25
20
15
10
5
0
Figure A17 - Option C – Dynamic Modeling Results.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 24
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
BioWin Chart
Plant Effluent Total P Plant Effluent Total Carbonaceous BODPlant Effluent Total suspended solids Plant Effluent Total N
DATE5/31/20315/24/20315/17/20315/10/20315/3/20314/26/20314/19/20314/12/20314/5/20313/29/20313/22/20313/15/20313/8/20313/1/2031
CO
NC
(mg/
L)
75
70
65
60
55
50
45
40
35
30
25
20
15
10
5
Figure A18 - Option D – Dynamic Modeling Results.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 25
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
BioWin Chart
Plant Effluent Total suspended solids Plant Effluent Total PPlant Effluent Total Carbonaceous BOD Plant Effluent Total N
DATE5/24/20315/17/20315/10/20315/3/20314/26/20314/19/20314/12/20314/5/20313/29/20313/22/20313/15/20313/8/20313/1/2031
CO
NC
(mg/
L)
55
50
45
40
35
30
25
20
15
10
5
0
Figure A19 - Option I – Dynamic Modeling Results.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 26
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
BioWin Chart
Secondary Clarifier Solids loading rate Secondary Clarifier Surface overflow rate
DATE5/24/20315/17/20315/10/20315/3/20314/26/20314/19/20314/12/20314/5/20313/29/20313/22/20313/15/20313/8/20313/1/2031
SLR
(kg/
m2
d) a
nd S
OR
(m3/
m2
d)
170
160
150
140
130
120
110
100
90
80
70
60
50
40
30
20
10
0
Figure A20 - Option B – Secondary Clarifier Solids Loading Rate and Surface Overflow Rate During Spring 2031.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 27
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
BioWin Chart
Secondary Clarifier Solids loading rate Secondary Clarifier Surface overflow rate
DATE5/24/20315/17/20315/10/20315/3/20314/26/20314/19/20314/12/20314/5/20313/29/20313/22/20313/15/20313/8/20313/1/2031
SLR
(kg/
m2
d) a
nd S
OR
(m3/
m2
d)
150
140
130
120
110
100
90
80
70
60
50
40
30
20
10
0
Figure A21 - Option C – Secondary Clarifier Solids Loading Rate and Surface Overflow Rate During Spring 2031.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 28
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
BioWin Chart
0102030405060708090
100110120130140150160170180
03/01/31 03/08/31 03/15/31 03/22/31 03/29/31 04/05/31 04/12/31 04/19/31 04/26/31 05/03/31 05/10/31 05/17/31 05/24/31
DATE
SLR
(kg/
m2
d) a
nd S
OR
(m3/
m2
d)
Secondary clarifier Solids loading rate Secondary clarifier overflow rate
Figure A22 - Option D – Secondary Clarifier Solids Loading Rate and Surface Overflow Rate During Spring 2031.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 29
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
BioWin Chart
Secondary Clarifier Solids loading rate Secondary Clarifier Surface overflow rate
DATE5/24/20315/17/20315/10/20315/3/20314/26/20314/19/20314/12/20314/5/20313/29/20313/22/20313/15/20313/8/20313/1/2031
SLR
(kg/
m2
d) a
nd S
OR
(m3/
m2
d)
140
130
120
110
100
90
80
70
60
50
40
30
20
10
0
Figure A23 - Option I – Secondary Clarifier (BNR plant only) Solids Loading Rate and Surface Overflow Rate During Spring 2031.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 30
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
BioWin Chart
Existing HPO clarifier Solids loading rate Existing HPO clarifier Surface overflow rate
DATE5/24/20315/17/20315/10/20315/3/20314/26/20314/19/20314/12/20314/5/20313/29/20313/22/20313/15/20313/8/20313/1/2031
SLR
(kg/
m2
d) a
nd S
OR
(m3/
m2
d)
160
150
140
130
120
110
100
90
80
70
60
50
40
30
20
10
0
Figure A24 - Option I – Secondary Clarifier (HPO plant only) Solids Loading Rate and Surface Overflow Rate During Spring 2031.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 31
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
0
50
100
150
200
250
300
350
400
450
500
12/1
12/15
12/29 1/1
2
1/26 2/9 2/23 3/9 3/23 4/6 4/20 5/4 5/18 6/1 6/15
6/29
7/13
7/27
8/10
8/24 9/7 9/21
10/5
10/19 11
/211
/1611
/30
Date, day/month/year 2031
Flow
, MLD
Figure A25 - Simulated Flows in Design Year 2031 – Whole Year.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 32
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
0
20000
40000
60000
80000
100000
120000
140000
1-Dec
15-Dec
29-Dec
12-Jan
26-Jan
9-Feb
23-Feb
9-Mar
23-Mar
6-Apr
20-Apr
4-May
18-May
1-Jun
15-Jun
29-Jun
13-Jul
27-Jul
10-Aug
24-Aug
7-Sep
21-Sep
5-Oct
19-Oct
2-Nov
16-Nov
30-Nov
Date, day/month/year 2031
TSS
load
, kg/
day
Figure A26 - Simulated TSS Loads in Design Year 2031 – Whole Year.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 33
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
0
20000
40000
60000
80000
100000
120000
140000
160000
1-Dec
15-Dec
29-Dec
12-Jan
26-Jan
9-Feb
23-Feb
9-Mar
23-Mar
6-Apr
20-Apr
4-May
18-May
1-Jun
15-Jun
29-Jun
13-Jul
27-Jul
10-Aug
24-Aug
7-Sep
21-Sep
5-Oct
19-Oct
2-Nov
16-Nov
30-Nov
Date, day/month/year 2031
CO
D lo
ad, k
g/da
y
Figure A27 - Simulated COD Load in Design Year 2031 – Whole Year.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 34
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
0
1000
2000
3000
4000
5000
6000
7000
8000
1-Dec
15-Dec
29-Dec
12-Jan
26-Jan
9-Feb
23-Feb
9-Mar
23-Mar
6-Apr
20-Apr
4-May
18-May
1-Jun
15-Jun
29-Jun
13-Jul
27-Jul
10-Aug
24-Aug
7-Sep
21-Sep
5-Oct
19-Oct
2-Nov
16-Nov
30-Nov
Date, day/month/year 2031
TKN
load
, kg/
day
Figure A28 - Simulated TKN Load in Design Year 2031 – Whole Year.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 35
SEWPCC UPGRADING/EXPANSION PRELIMINARY DESIGN REPORT APPENDIX I
0
200
400
600
800
1000
1200
1400
1-Dec
15-Dec
29-Dec
12-Jan
26-Jan
9-Feb
23-Feb
9-Mar
23-Mar
6-Apr
20-Apr
4-May
18-May
1-Jun
15-Jun
29-Jun
13-Jul
27-Jul
10-Aug
24-Aug
7-Sep
21-Sep
5-Oct
19-Oct
2-Nov
16-Nov
30-Nov
Date, day/month/year 2031
TP lo
ad, k
g/da
y
Figure A29 - Simulated TP Load in Design Year 2031 – Whole Year.
klb u:\111208939\3913_report\3913_1_draft\preliminary design reports\appendices\appendix_i\figures and tables.doc 36