GUIDELINES AND APPLICATION FORMFOR
ESTABLISHMENT OF NEW DIPLOMA LEVELINSTITUTIONS
FORTHE ACADEMIC YEAR 2009 2010
Directorate of Technical Education
and Industrial Training,(T. E. Wing) Punjab
Plot No. 1, Sector 36-A,Chandigarh.
Web site: www.dtepunjab.gov.in
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
2/58
SUMMARYPlease fill in the details
Proposal for Establishment of New Institution in the year 2000-2010
Programme applied for (please tick):
NDIP NDIPH NDIPPH NDIPC
Name and Address of the Applicant Name & Address of the ProposedInstitution
File No(to be filled by DTE)
Date of Registration of Society:
Land Specificationsi) Category MegaCity State Capital Dist. Head Quarters
Municipal Corporation limits Rural areas Hilly areas Others
ii) Land area in Acres..
iii) Registered Sale deed Registered Gift deed Govt. leaseiv) Date of Registration.v) Mortgaged with Bank Yes / Novi)Other institution in the same land area / premises (please tick)
Engg Pharmacy HMCT Arts & CraftsLand Use Certificate Issued by ...on date . for .
purpose.
Building Plan in the name ofproposed Institution prepared byArchitect and approved by theCompetent Authority
Issued by on date
Whether the construction of theBuilding is complete as perapproved Building Plan for theproposed institution
YES NO
* if no - Stage of construction _________________________________
Funds Position Number Amount Name of Bank
FDRs
SavingBank A/cand
CurrentA/c
Whether applied for establishment of any otherinstitution simultaneously for theyear 2008-2009.
YES NO
Name of the courses.
Note: Diploma level courses in Engineering (NDIP), Architecture Assistantship (NDIPA), HotelManagement & Catering Technology (NDIPH), Pharmacy (NDIPPH), Applied Arts and Crafts (NDIPC).
2
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
3/58
APPLICATION FOR THE ESTABLISHMENT OF A NEW TECHNICAL INSTITUTION
1. Name and address (with Pin Code) of the Applicant Society / Trust / Government / University
Name :________________________________________________________________
Address :________________________________________________________________
_________________________________________________________________
____________________________Pin Code:_____________________________
STD Code:__________________ Fax No. :_____________________________
Phone No.:________________________________________________________
E-mail :________________________________________________________
2. (i) Programmes Applied for (Please Tick only ONE Class)
NDIP NDIPPH
NDIPCNDIPH
Note: Diploma level courses in Engineering (NDIP), Architecture Assistantship(NDIPA), Hotel Management & Catering Technology (NDIPH), Pharmacy (NDIPPH),Applied Arts and Crafts (NDIPC).
(ii) Has the Society / Trust applied for more than one Programme.
YES NO
If yes, please indicate other Programmes
PROGRAMME NDIP NDIPH NDIPPH NDIPC
3 Details of the Applicant Society / Trust.
i) Society Trust
ii) Registration Number :__________________________________
iii) Date of Registration :__________________________________
iv) Place of Registration :__________________________________
v) Registered under which Act (please tick)(Trust Act / Society Act) :__________________________________
Please attach copy of Registration of Society / Trust along with details of constitution, memorandum ofassociation of the Society / Trust as Annexure - I)
3
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
4/58
4. Name and address of the proposed institution at the Permanent Site(State clearly whether the proposed site falls within Corporation limits of Mega Cities / StateCapital / Others)
Name of the ProposedInstitution
Address of the Proposed Permanent Site with PINCode & Nearest City
Classification of the proposedPermanent Site
Mega City
State Capital
Others
State PIN Code
Fax No. STD No.
Phone No.
E-mail:
Nearest City:
5. Type of Technical Institution [Government (Central / State / aided) / University / Private etc.]proposed to be started.
Central Govt. State Govt. Govt. Aided
Deemed University University Department Self Financing
6. LAND
i) Location (Strike out whichever is not applicable)[Mega Cities / State Capital / Dist. Head Quarters / Municipal Corporation limits / Rural areas/Hilly areas]* Mega Cities: Delhi, Kolkata, Mumbai, Chennai
(Attach copy of letter from Competent Authority for classification of land, if claimed to be within
the limits of Mega city / Municipal Corporation or State Capital as Annexure - II)
ii) Land Area[Please note that lease land is not acceptable except in case of government lease as perregulations]
Whether owned by the applicant Society / Trust
YES NO
If yes, thenArea /
(Attach Copy of land documents as Annexure - III)
Note: In case the land measurements are in units other than Acres / Hectares / Sq.mts., aconversion certificate from the Competent Authority may be provided.
iii) Whether the land is registered through a Sale Deed / Gift Deed / Leased by Governmentin the name of the Applicant Society / Trust / Proposed Institution. (Please tick)
YES NOIf yes, then
Registration Number :__________________________________
Date of Registration :__________________________________
Place of Registration :__________________________________
4
Acres Hectares
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
5/58
iv) If the land is on lease from Government bodies then please mention the purpose forwhich it was leased and period of lease (lease granted for a minimum period of 30 years is onlyacceptable).
Whether the full payment for the land leased by Govt. has been made and whether the lease hasbeen registered (Yes / No) ._____________
Date of possession of land _______________
(Please attach a copy of possession certificate)._____________________________________________________________________________
(Land, if leased from private bodies / persons are not acceptable.)
Any loans / mortgage raised against the titles of the land. Yes No
Whether the land has been exclusively earmarked for Yes Nothe Proposed Institution by any resolution.(Attach copy of resolution of Trust / Society / Applicant as Annexure -IV)
If land is agricultural, then whether the conversion certificate from Yes No
the Local Government / Competent Authorities has been submitted.
(Attach copy of land use certificate stating that the land can be use for educationalpurposes as Annexure V)
viii) Details of other institutions (if any) being run in the same premises.
Name & Disciplineof the Institution
Whether approved by AICTE,if yes,
Land areain acres
Sy.No. /Khasra No.
Year of IstApproval
Year of LastApproval
Total
7. Building (for exclusive use of the Proposed institution at the Permanent Site)
i) Whether building plan is approved by the Competent Authority. Yes No
If yes, then give name of authority with date of approval ____________________________
(Attach copy of approved building plan and resolution of Applicant earmarking buildingfor the proposed programme as Annexure VI)
ii) Whether the approved Building Plan is in the name of the proposed Institution. Yes No
iii) Whether Master plan duly approved by the Competent Authority for the entire institutionalcomplex with the details of the plinth area including area of laboratories, class rooms,drawing halls, workshops, library, administrative block, hostel, etc. along with the phase wiseplan for construction with details of financial estimate and sources of funds has beensubmitted. (Please tick)
Yes No
iv) Whether the approved Building Plan has survey Nos' / identification of land on it.
Yes No
v) Please state if part of building of an existing institutional complex is proposed
5
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
6/58
to be used for establishment of the new InstitutionYes No
If yes, give details regarding the other institution(s) in the same premises and status of AICTEapproval as per table given below:
Programmes and Name of theother Institution
Required Built-upArea as per AICTEnorms
Built-upAreaAvailable
AdditionalBuilt-up Areafor the
proposedprogramme
Whether verticalseparationbetween
proposed &existing Institutionis available
vi) Details of availability of Built up space at Permanent Site for this proposal as per the approvedbuilding plan [in sqm]
Sl.No.
Particulars of Built-up Space atproposed permanent site.
RCC Building(in Sqm)
ACC Shed (inSqm)
Exclusive for proposed newCourses /institution. (inSqm)
Shared withexisting courses /institution. (in Sqm)
1. Total Instructional Area
2. Total Administrative Area
3. Total Workshop and Lab Area
Total Area (in Sqm)
(Attach copy of External and Internal Photographs of the building, if any, duly attested with seal bythe applicant on the backside with date as Annexure - VII)
vii) Whether Construction has been carried out as per approved Building Plan. Yes No
8. Availability of Funds in the name of Applicant Society / Trust:
Availability of Funds in the name of Applicant Society / Trust.[Please note that Bank Guarantees against mortgage of land, building and assurance are not acceptable]
i) Fixed Deposits (FDRs / other deposits in the name of the Applicant Trust / Society)[Other than the Endowment Fund created with Joint Name of DTE & Trust / Society / RPGF
deposited with DTE for other approved institution (if any)]
[Attach Photostat copy of FD Receipt Front & Back Side]Funds Name of Bank FD No. Amount (Rs. In lakhs)
FD Receipts
Other Depositsincluding Current &Saving A/c
[Attach Xerox copies of latest Bank Statement of Account maintained by the applicant asAnnxure-VIII]
ii) Whether the Accounts of the Applicant Society / Trust are audited.
[Attach Photostat copy of last three years] Yes No
iii) Whether income-tax return are filed. Yes No
6
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
7/58
[Attach Xerox copies of last income-tax return filed of the applicant as Annexure- IX]
9. Course(s) proposed to be conducted from the academic Year 2009-2010.
Courses Duration of Course
Entry level Qualification Diploma/Post diploma
ProposedAnnualIntakeCapacity
10 i) Whether the applicant had applied in the year 2008-09 for the establishment of any other or the sametechnical institution to DTE/ All India Council for Technical Education. Yes No
ii) If yes, when and why the proposal was rejected? Please give details.
The coursesapplied for
Status of Letter ofIntent issued[YES / NO]
Status of Letter of Approval issued[YES / NO]
Reasons for Rejection
11. Name and Address of the Affiliating Board: ____________________________________________
____________________________________________
____________________________________________
DECLARATION
I / We, on behalf of ___________________________________________ hereby undertake to comply with theNorms and Standards and Regulations of AICTE. I / We do undertake to furnish the documents as may bestipulated in the letter of intent if issued in favour of our Society / Trust/ Applicant, within the stipulated period,failing which, my / our proposal shall be liable to be rejected by the Council. I / We agree to fulfill all the conditionsas may be stipulated by AICTE from time to time.
I/We hereby confirm that all the information furnished in the application is true to the best of my / our knowledgeand belief and if any information is found to be false, my / our proposal may be rejected.
(Authorized Signatory of the Applicant*)
Place: Name :____________________________
Date: Designation :_______________________( Seal )
Note: Canvassing in any form will cause the rejection / non-consideration of application.
7
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
8/58
CHECK - LIST OF ENCLOSURES
Annexure Contents Checklist
I Copy of registration of Society / Trust a long with details of constitution,memorandum of association of the Society / Trust.
II Copy of the letter from Competent Authority as designated by concerned StateGovernment for classification of land, with respect to its location i.e. Mega city
/ State Capital / Dist. Head Quarters / Municipal Corporation limits /Rural areas/ Hilly areas.
III Copy of registered land documents in the name of the Trust / Society / other Applicants.
IV Copy of resolution of Society / Trust / Applicant earmarking land for theproposed institution.
V Copy of land use certificate from Competent Authority as designated by theconcerned State Government / UT.
VI Copy of building plan prepared by an Architect and approved from theCompetent Authority as designated by the concerned State Government / UTand Copy of resolution of Society / Trust / Applicant earmarking building forthe proposed institution
VII Copy of external and internal Photographs of the Building, if any duly attestedby Authorized Representative of the proposed Institution, with date.
VIII Details of latest fund position of Applicant (Society / Trust) for the proposalalong with photocopies of FDRs, latest Bank Statement of Account maintainedby it.
IX Copy of last income-tax return filed by the applicant.
X Detailed Project Report
XI Copy of khasra plan to show that the land is contiguous.
XII Copy of Resolution of Society/ Trust/ Applicant earmarking building for theproposed institution
XIII Evaluation certificate of the Building for the proposed institution
(Signature of Authorized Representative of theProposed Institution with Name and Designation)
NOTE: For any other clarification / details, kindly refer to Approval Process 2009-10 hosted on
the DTE website (www.dtepunjab.gov.in).
8
http://www.aicte.ernet.in/http://www.aicte.ernet.in/ -
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
9/58
Acknowledgment
Date :__________
From :
Director, Technical Education& Industrial Training, Punjab,(T.E. Wing), Plot No.-1, Sector 36-A,Chandigarh.
To ,
The Secretary / Registrar / Director / Principal (To be filled by the applicant)
__________________________________
__________________________________
__________________________________
Sir,
This is to acknowledge receipt of your application for establishment of new technical institutions for
academic year 2009 - 2010.
PROGRAMME NDIP NDIPH NDIPPH NDIPC
(To be ticked by the applicant)
YourDTE file no is____________________________________________(to be filled by DTE).
Kindly quote your File No in all your future correspondence with DTE&IT, Punjab.
Yours faithfully
(Additional Director)
9
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
10/58
DETAILED PROJECT REPORT (DPR) FOR ESTABLISHMENT OF
NEW INSTITUTION
C O N T E N T S
CHAPTER I: PREAMBLE(This Chapter is expected to cover the genesis of the proposal with respect to the background ofthe technical education and industry scenario of the State where the proposed institution is beinglocated and the credentials of the Consultants, if any, engaged by the promoters for preparationof the DPR)
1.1 Introduction
1.2 Background of the Consultants
1.3 Technical Education & Industry Scenario
CHAPTER II: THE PROMOTING BODY(This Chapter is expected to cover the status of the Promoting Body, its legal standing withrespect to registration formalities, nature of the Body viz. Charitable Trust, Family Trust, Co-operative Society, Public Society etc., its activities since its inception with specific emphasis onits Social, Charitable, Educational activities along with a list of major activities undertaken todate, its mission and vision)
2.1 Introduction to its Genesis including its Registration Status
2.2 Details of its Promoters including their Background
2.3 Activities of the Promoting Body including a listing of major educational
promotion activities undertaken by it in the past
2.4 Mission of the Promoting Body
2.5 Vision of the Promoting Body
CHAPTER III: OBJECTIVES AND SCOPE OF THE PROPOSED INSTITUTION(This Chapter is expected to cover the goal of the proposed Institution, Scope and Justification ofits establishment in the light of the prevailing technical education and industry scenario in theState, Availability of students for admission, particularly the number of students passing thequalifying examination viz.+2 Science in First Class and the number of seats already available in
the particular course (Dip. Engg./ Dip. Pharm / Dip. HMCT / Dip. C etc.) in the State, and thegenesis of the proposal with respect to the technical manpower requirement of the State, ifavailable)
3.1 Objectives of the Institution
3.2 General and Technical Education Scenario of the State:
3.2.1 Status at Entry Level
3.2.2 Status of Technical Level manpower
3.3 Industrial Scenario of the State
3.4 Scope of the College vis--vis the Industrial Scenario and Educational
Facilities already available in the State.
10
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
11/58
CHAPTER IV: ACADEMIC PROGRAMMES(This Chapter is expected to cover the basic Academic Philosophy of the Institution and to list theidentified Programmes, targets, and various facilities)
4.1 Basic Academic Philosophy of the Institution
4.2 Types of Programmes
4.3 Identified Programmes4.4 Phase-wise Introduction of Programmes & Intake
4.5 Target Date for Start of Academic Programmes
4.6 Central Computing facility
4.7 Central library
4.8 Central Workshop
4.9 Central Instrumentation Facility
4.10 Affiliating Body
4.11 Scholarships
CHAPTER V: SALIENT FEATURES OF ACADEMIC DIVISIONS(This Chapter is expected to give phase-wise details of the Academic Programmes / Divisionsthat the Proposed Institution desires to setup in consonance with its Academic Philosophyincluding the Objectives, Areas of Focus, Detailed Analysis of Requirements of Faculty, BuildingSpace, Equipment, etc. for each Academic Division)
5.1 Classification of Academic Divisions i.e. Departments, Centres, Schools,
Central Academic Facilities.
5.2 Details of each Academic Department / Centre, like:
Academic Objectives
Areas of Focus
Academic Programme
Faculty Requirement & Phase-wise Recruitment
Requirement of Laboratories, Space and Equipment (cost)
5.2.6 Requirement of other Space like Class Rooms, Faculty
Rooms, Departmental Office
CHAPTER VI: QUALITY AND HUMAN RESOURCE DEVELOPMENT(This Chapter is expected to cover the Human Resource Developmental aspects of the proposedinstitution including the Policies of the Management to promote excellence among Faculty &Staff, Strategies to attract and retain bright faculty and methodologies towards qualitymanagement and fostering of academic excellence)
6.1 Academic Values
6.2 Recruitment, Strategies for Attracting and Retention of Faculty Personnel
for Excellence, Promotional Avenues, Career Ladder
6.3 Policies for Teaching and Non-teaching Staff Development
11
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
12/58
6.4 Permanent and Contract Services for Teaching, Non-teaching and other
support Personnel
6.5 Total Quality Management
6.6 Overall Teaching and Non-teaching Staff Requirements
CHAPTER VII: LINKAGES IN TECHNICAL EDUCATION(This Chapter is expected to elaborate the external linkages envisaged along with the strategies
for promotion of R&D, Partnership with Industry, etc. for the wholesome growth of students aswell as for contribution of the Institutions to Society at large)
7.1 Introduction
7.2 Linkages with Industry
7.3 Linkages with the Community
7.4 Linkages with other Technical Institutions in the region
7.5 Linkages with institutions of excellence such as the IITs and IISc.,
Bangalore
7.6 Linkages Abroad
7.7 Linkages with R&D Laboratories
CHAPTER VIII: GOVERNANCE AND ACADEMIC & ADMINISTRATIVE MANAGEMENT(This Chapter is expected to cover the basic Philosophy of Governance and AdministrativeManagement including the structure of its Board of Governors (BOG), the organizational chart foroperational management along with responsibilities vested at various levels of Administrativehierarchy. It is expected that a well thought out method of Institutional Governance andAdministration will be the key to its growth and success)
8.1 Philosophy of Governance
8.2 Board of Governors
8.3 Organizational Structure & Chart for day-to-day Operations &
Management
8.4 Role and Responsibilities of Key Senior Positions
8.5 Methods / Style of Administration / Management
CHAPTER IX: CONCEPTUAL MASTER PLAN FOR MAIN CAMPUS DEVELOPMENT(This Chapter is expected to cover the details of the Master Plan for Campus Development
starting from the selection of site to the proposed land use pattern and the Phase-wiseconstruction of various facilities / utilities to the level of landscaping. Institutional aspects ofdevelopment is expected to be taken up in consonance with the Master plan keeping in viewvarious aspects of convenience, safety and utility of the facilities)
9.1 The Site
9.2 Proposed Land Use Pattern
9.3 Design Concept
9.4 Buildings and Facilities in the Campus
9.5 External Services
9.6 Construction Systems and Materials
9.7 Landscape Proposal
12
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
13/58
CHAPTER X: REQUIREMENT OF STAFF, SPACE & EQUIPMENT AND THEIR COST(This Chapter is expected to make a consolidated estimate of Phase-wise requirements of thestaff, building, equipment and their cost, along with strategies for the mobilization of fundsrequired)
10.1 Introduction
10.2 Faculty Requirements
10.3 Non-teaching Staff Requirements
10.4 Building Requirements: Area and Costs
10.5 Estimated Cost of Equipment
10.6 Phase-wise Financial Requirements
10.7 Strategies for Financial Mobilization
CHAPTER XI: ACTION PLAN FOR IMPLEMENTATION(This Chapter is expected to cover the Activity Chart from the conceptual stage to finalimplementation, indicating a time-activity Chart for various activities, its constraints and
implementation Strategy including financial out lay.)
11.1 Activity Chart
11.2 Constraints
11.3 Financial Outlay
11.4 Strategy for Implementation
CHAPTER XII: EXECUTIVE SUMMARY OF THE DETAILED PROJECT REPORT(This Chapter is expected to present a Summary of the DPR as per the following format for readyreference)
12.1 Details about the Promoting Body
12.2 Details about the Proposed Institution
12.3 Development Plan for the Proposed Institution
13
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
14/58
12. EXECUTIVE SUMMARY OF THE DETAILED PROJECT REPORT (DPR)
DETAILS ABOUT THE PROMOTING BODY
i) Name and Address of the Promoting Body:(Government / University / Trust / Society)
ii) Date of Registration / Establishment of the Promoting Body:
iii) Nature of the Promoting Body:
iv) Activities of the Promoting Body since inception:(With special emphasis on Academic, Social & Industrial Activities and details on other
institutions run by the Promoting Body)
v) Constitution of the Promoting Body:(Give details indicating the names)
Sl.No.
Name AcademicQualification
Nature ofAssociationwith thePromotingBody
Experience in Academic Institutions (inYears)
OverallExperience(in Years)Technical Non
TechnicalPromotional Management Organisational
vi) Vision of the Promoting Body (in 50 words)
vii) Mission of the Promoting Body (in 100 words)
Religious Charitable Family Others
14
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
15/58
12.2. DETAILS ABOUT THE PROPOSED INSTITUTION
i) Category of Institution: Diploma in Engg & Tech. / Pharmacy /(Please strike out whichever is HMCT / Applied Arts &Crafts.not applicable)
ii) Name of the Proposed Institution
iii) Address of the proposed Institution
iv) Nearest City / Town / Airport / Railway station(Enclose map indicating access to the institution from the nearest airport / railway station)
v) Type of the institution
(in case of aided, mention the percentage of aid from the Government)
vi) Name of the affiliating Board.
vii) Justification for starting the proposed institution
(a) Details of the total sanctioned intake in the subject areas in the State in which the ProposedInstitution is to be located and number ofvacant seats during the last 3 years.
(b) Justification for starting the proposed institution in view of (a) above
(minimum 100 words)
15
Govt. Univ. Govt.Aided PrivatePVT.
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
16/58
12.3 DEVELOPMENT PLAN FOR THE PROPOSED INSTITUTION FOR NEXT 10 YEARS,PROJECT COST & SCHEDULE
i) Preliminary And Pre Operative Expenses(Including land cost, land development, approach road, electricity and water connections, fencing etc.)
ii) Projections for next 10 years
Give a bar chart indicating mobilization of funds for the proposed project at the time of establishment & fornext 10 years at intervals of five years.
Give a bar chart indicating the recruitment of faculty (separately for Lecturer, Senior Lecturer & HOD) for theproposed project at the time of establishment & for next 10 years at intervals of five years.
Give a bar chart indicating creation of built up area (separately for Instructional, Administrative andAmenities) for the proposed project at the time of establishment & for next 10 years at intervals of five years.
a) Give a bar chart indicating investment on equipment and machinery for the proposed projectat the time of establishment & for next 10 years at intervals of five years.
iii). Total Project cost (at the time of establishment and next five years)
Year
Courses /IntakeProposed
(I)
Built up area / Investmentto be made(Sqmt / Rs.)(II)
Investment onFurniture &Accessories (Rs.InLakhs)(III)
Investment onEquipment /Machinery(Rs. In Lakhs)(IV)
Projectedexpenditure onSalary of Staffper annum(Rs. In Lakhs)(V)
Investment onLibrary(Rs. In Lakhs)(VI)
TotalProjectCost (Ito VI)andPreoperativeExp.)(Rs. inLakhs)
Instructional Area
Admn.Area
Amenities
Dip intake ClassRoom
Lab/W/S
Labs
W/S
Comp.Centre
Teaching
Non-teaching
TextBook
Ref.Books
Journals
iv) DETAILS FOR MOBILIZATION / SOURCE OF FUNDS (CAPITAL & RECURRING)(At the time of establishment and next five years) (Rs. in Lacs)
Year FromApplicant
Donations Grants fromGovt.
Fees Loan Others
v) RECRUITMENT OF FACULTY
16
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
17/58
(At the time of establishment and next five years)
Year Recruitment Total
HOD Senior Lecturer Lecturer
vi) RECRUITMENT OF NON-TEACHING STAFF(At the time of establishment and next five years)
Year Recruitment Total
Technical Administrative
vii) PROPOSED STRUCTURE OF GOVERNING BODY
Sl.No.
Trust / SocietyRepresentative
Academic Background IndustryRep.
Others
Technical Non Technical
viii) INDUSTRY LINKAGES(at the time of establishment, and next five years)
DECLARATION
I / We, on behalf of ____________________________________________________________hereby confirm that this Detailed Project Report has been prepared for its proposed TechnicalInstitution under the name and style of ________________________________________________.
It is hereby confirmed that all the information furnished above is true to the best of my / our knowledgeand belief and if any information is found to be false, the proposal may be rejected.
(Authorized Signatory of the Applicant)
Place: Name :____________________________
Date: Designation :_______________________
( Seal )
17
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
18/58
APPROVAL PROCESS FOR ESTABLISHMENT OFNEW DIPLOMA LEVEL INSTITUTIONS OFFERINGTECHNICAL PROGRAMMES IN PUNJAB FOR THE
ACADAMIC YEAR(2009-2010)
18
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
19/58
APPROVAL PROCESS FOR ESTABLISHMENT OF NEW DIPLOMA LEVEL INSTITUTIONSOFFERING TECHNICAL PROGRAMMES IN PUNJAB AS PER CALENDER FOR THE
ACADAMIC YEAR(2009-2010)
(Diploma level courses in Engineering & Technology/Pharmacy/Hotel Management & Catering
Technology/Applied Arts & Crafts)
1.1 Requirement of Grant of Approval
No new technical institution of Government, Government Aided or Private (self
financing) institution shall be started and no new courses or programs in
Technical Education shall be introduced and no increase/variation of intake shall
be effected without obtaining prior approval of the Council.
1.2 The Application Form can be submitted by
Registered Societies and Trusts/ Self financing Private Institution.
Central/State Government Institutions/ Govt. Aided Institutions.
Application/Proposal should be submitted by:
1.2.1 The Chairman or Secretary of Society/Trust
1.2.2 The Director of Technical Education/other Officer designated
by the Government in case of Government/Government
Aided institution1.2.3 The Registrar in case of University/Deemed University
1.3 SUBMISSION OF APPLICATION
Applications duly filled in along with requisite processing Fee may be submitted any time
of the year to the Director Technical Education of the concerned State Govt./UT in
original and a copy sent to the Concerned Regional Office of AICTE
19
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
20/58
CHECK LIST TO BE FOLLOWED AT THE TIME OF SUBMISSION OFAPPLICATION
Copy of Registration of Society/Trust along with details of constitution,
memorandum of association of the Society/Trust.
Copy of letter from Competent Authority as designated by the concerned State
Government for classification of land, with respect to its location i.e. Metropolitan City/State
Capital /Others.
Copy of registered land documents in the name of applicant Trust/ Society.
Copy of building plan prepared by an Architect and approved by the Competent Authority
as designated by concerned State Govt./UT.
Copy of resolution of the Society/Trust /Applicant earmarking land for the proposed
institution(s)
Copy of land use certificate from Competent Authority as designated by concerned
State Govt./UT
Details of latest fund position along with photocopy of FDR's, SB A/c, Current A/c etc.
available with the applicant for this proposal
Detailed Project Report (DPR).
The applicants fulfilling the following conditions are eligible to apply:
If the applicant is a Society/Trust, it should have been registered under the Societies
Registration Act, The Trusts Act or any similar Act.
The application shall be considered only within the overall ceiling fixed by the
Council subject to compliance of all the requirements as per Norms of AICTE.
The land should have been registered in the name of the applicant society/trust on
or before the date of submission as per the requirements (given below) and free
from any encumbrances. The proposed institution shall only operate from this
registered land.
20
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
21/58
Class of New InstitutionsRequirement of land (in acres)
Metro / State Capital Others
Engineering & Technology (Diploma) 2.5 5.0
Pharmacy (Diploma) 1.25 2.0
Hotel Management & Catering Technology (Diploma) 1.5 2.5
Applied Arts & Crafts (Diploma) 1.0 2.0
The Application Form can be downloaded from the DTE website:
www.dtepunjab.gov.in. However, a DD for Rs. 5000/- drawn on a nationalized bank in favour
of The Director, Technical Education and Industrial Training, Punjab, Plot No.-1, Sector
36-A' payable at Chandigarh, must be enclosed with the application form failing which the
application shall not be considered.
1.3 The stages involved in the processing of applications are describedbelow:
1.3.1 Submission of applicationThe approval process for establishment of new institutions shall be open ended,
allowing any eligible applicant to submit proposals in original and its soft copy in
M.S Word in a C.D to the Directorate of Technical Education & Industrial
Training (T.E. Wing), Punjab, Plot No.-1, Sector 36-A, Chandigarh with a copy to
the Regional Office, AICTE, NWRC, Sector 42-B, Chandigarh any time round the
year. Such proposals for the establishment of a new institutions received by the
DTE shall remain valid for three years. Submission of copy of application to the
Regional Office, AICTE, NWRC, 1310, Sector 42-B, Chandigarh is mandatory,
falling which the application is liable to be rejected.
The application can be submitted any time round the year. However the
applications complete in all respects received upto 24 th October, 2008 shall be
considered for the academic year 2009-10. Application received after 24th
October, 2008 shall be considered for the next academic year (i.e 2010-2011).
Application received shall be remain valid for 3 years from the date of
submission.
Note: The proposal together with its attachments must be bound and numbered. It
must have a content page with reference to each section of the proposal.
An applicant for new institution shall be required to submit a Detailed Project
Report (DPR) as per the prescribed format along with application. The DPR should spell out,
among other things, the following:
- Background of Trust/Society with reference to its experience in promoting,managing and operating educational institutions; its legal standing with respect
21
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
22/58
to its registration; details of its promoters including their background; its activitiesin the social, charitable and educational spheres since its inception; its missionand vision.
- Vision regarding the proposed institution with a time perspective of the first 10years of its operation.
- Development plan for the proposed institution spelling out its growth plan overthe first 10-year period after its establishment in terms of the phasing of
academic programmes, increase in student intake and the time schedule for thestage-wise development of the academic infrastructure and other supportfacilities, including student amenities, such as hostel for students, sports andrecreational facilities, and recruitment of faculty.
- Resource projections and its utilization schedule.
- Sources of financing of capital and operating expenditure, besides fundsgenerated through student fees.
- Policy with regards to faculty recruitment, retention and development.
- Structure of academic and administrative governance.
- Architectural master plan indicating the land use pattern for the proposedinstitution.
The DPR shall form the basis for evaluation of the proposal and shall serve as
the blue print for proper development of the proposed institution.
1.3.2 Verification of Documents
The proposals complete in all respects shall be posted in DTE website toacknowledge the receipt and shall be evaluated at DTE.
The proposals received shall be scrutinized by Scrutiny Committee comprising
experts, including R.O of AICTE as members and Director, Technical Education
or his nominee as convenor constituted by the Principal Secretary, Technical
Education.
The applicant are required to present all the original documents mentioned
below along with photocopies in one lot for verification to the Director, TechnicalEducation & Industrial Training, (T.E. Wing), Punjab, Plot No. 1, Sector 36-A,
Chandigarh.
Registration document of the Trust/Society indicating members of Society/Trust andits objective.
Land document (s) in original showing ownership in the name of Trust/Society in theform of Registered Sale Deed/Irrevocable Gift Deed (Registered)/IrrevocableGovernment Lease (for a minimum of 30 years) by the concerned authority ofGovernment. In case, the land documents are in vernacular language, Notarized
English translation of the document needs to be produced.
22
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
23/58
Land Use Certificate/Land Conversion Certificate allowing the land to be used foreducational purpose, from the Competent Authority along with Topo-sketch/Village Map indicating land Survey Nos and a copy of City road mapshowing location of the proposed site of the Institution.
Site Plan, Building Plan in the name of proposed institution prepared by a registeredArchitect and duly approved by the Competent Plan Sanctioning Authority of theState administration. Proof of completion of building structure up to lintel level for
the required area on permanent site as per approved Engineering &Architectural Building Plan in the form of Color photographs giving External andInternal views.
Proof of adequate working capital (Funds), in the form of either Fixed Deposits inthe Bank of latest Bank Statement of Account maintained by theSociety/Trust/Applicant.
Justification and viability of the project as enunciated in the DPR.
Khasra plan (master plan) to show that the land is contiguous.
The deficiencies if any shall be communicated by the Director Technical Education underintimation to the Regional Office of the AICTE to the applicant institution within 15 daysfrom the date of receipt of the Application.
1.3.3 Issue of Letter of Intent
The recommendations of the Scrutiny Committee will be considered by the State Level
Committee whose constitutions is given below:
Secretary of Higher Education/Technical Education ofthe Concerned State/ UT/ or his nominee not below
the level of Professor/ Director/VC of a University.
Chairman
Regional Officer of AICTE/or a AICTE representativenot below the rank of Deputy Director/ Reader orequivalent.
Member
Two (2) Subject Experts to be nominated by the StateGovt./ UT Administration from the within the State oroutside the State/ UT.
Members
Director of Technical Education/ State Board of
Technical Education of the Concerned State/ UT.
Member Secretary
Based on the recommendations of the State Level Committee, the Regional
Officer of AICTE shall issue a Letter of Intent (LOI) to the applicant Trust/
Society. The Letter of Intent shall be valid for a maximum period of three years
during which the institution shall complete all requirements as per the norms and
standards and conditions as decided by the council from time to time.
In cases where Letter of Intentis denied for non-fulfillment of norms & standardsand conditions as may be stipulated by the Council, shall be informed along with
grounds of denial. The applicant may submit compliance report alongwith
23
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
24/58
documentary evidence to substantiate the claims to be considered for
reconsideration by the State Level Committee.
1.3.3 Issue of Letter of Approval.
The applicant Society/Trust to whom a Letter of Intent issued would be required
to comply with the following requirements and submit the documents to the DTEoffice.
A non-refundable processing fee of Rs. 25,000/- drawn in favour of The Director,Technical Education & Industrial Training (T.E.Wing), Punjab, Plot No 1,Sector 36-A, Chandigarh payable at Chandigarh (Government Institutions areexempted from payment of processing fee).
A joint Fixed Deposit of Rs. 15 lakhs (for self-financing institutions only) on anyNationalised Bank for a period of 8 years created in the joint names of thePresident/ Chairman of the applicant Society/ Trust and the Director, TechnicalEducation & Industrial Training, Punjab.
The original Joint Fixed Deposit Receipt shall be kept under the custody of the proposed
institution. A copy of the Joint Fixed Deposit Receipt shall be submitted to the Director
Technical Education of the concerned State Govt./UT along with an affidavit on non
judicial stamp paper of prescribed value stating that the Joint Fixed Deposit shall not be
encashed or modified without prior consent of AICTE and DTE. the Director Technical
Education of the concerned State Govt./UT shall instruct the concerned Bank not to
allow any encashment/modification of fixed deposit and grant of loan against the FDR
without prior consent of AICTE and the Director Technical Education of the concerned
State Govt./UT. The Applicant Society/Trust/ Institution may be permitted to encash the
Joint Fixed Deposit on expiry of the term of the Fixed Deposit. However, the term of the
fixed deposit could be extended for a further period as may be decided on case to case
basis and/or forfeited incase of any violation of norms, conditions, and requirements
and/or non-performance by the institution and/or complaints against the institution.
The processing fee and the Joint FDR amount for Minority institutions may be reduced
by 20%.
1.3.4 Expert Committee Visit.
(a) As and when the applicant is ready for an inspection for verification of its
preparedness for establishment of the proposed institution, it shall make an
application indicating compliance of the conditions stipulated at para 1.3.3 above forcausing an inspection.
24
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
25/58
(b) A visit of Expert Committee will be arranged by Director Technical Education of the
concerned State Govt./UT for verification of the facilities created for establishment of the
proposed Institution.
(c) The Expert Visiting Committee shall comprise of the following members:
Three Expert members not below the level of AssociateProfessor/Reader
Regional Office of the AICTE or a AICTE representative not below therank of Reader or equivalent.
Director Technical Education of the Concerned State Govt./UT or hisnominee not below the rank of JT/Dy. Director level as Convener.
(d) The Expert visiting Committee shall examine the preparedness of the institution to
impart quality education as per the norms & standards and conditions prescribed by theCouncil from time to time.
1.3.5 CONSIDERATION AND ISSUANCE OF LETTER OF APPROVAL/REJECTION:
1. The Report of the Expert Committee shall be placed before the State Level
Committee for consideration.
2. Based on the recommendations of the State level Committee the Regional Officer
of AICTE shall issue letter of approval.
3. The Letter of Approval shall be valid for a maximum period of 2 years. It shall be
the responsibility of the Applicant institutions to obtain necessary
permission/affiliation for admission of students from the concerned Admission
Authority/State Govt./UT/Board during the validity of the period of approval.
Incase the institution fails to start the approved programmes during the validity
period of approval, the applicant institution make a fresh application for
consideration of letter of intent.
In respect of cases, for which approval is denied for non-fulfillment of norms &
standards and conditions as may be stipulated by the Council, grounds of denial shall
be communicated to the concerned Applicant/Society/Trust/Institution.
25
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
26/58
The applicant is required to make available following documents to the Director,
Technical Education & Industrial Training (T.E. Wing), Punjab, Chandigarh before conduct of
Expert Committee visit:
A copy of the application submitted to DTE
The Letter of Intent, in original
A copy of DPR
Society/Trust Registration documents indicating members of the Society/Trustand its Objectives.
Minutes of the Meeting of Society/Trust, pertaining to proposed institution andallocation of land/building/funds etc.
Original Land Documents.
Village Map/Location Map/Index Map/Topo Graphic Sketch/City Road Map.
Land Use Certificate/Land Conversion Certificate, allowing the land to be usedfor educational purpose.
Original approved Building Plan.
Copy of the syllabus of concerned affiliating Board.
Details of built up structure available exclusively for the proposed institute at thepermanent site.
Proof of sanction of required electrical load.
List of equipment required as per syllabus and equipment available.
Stock Register of Equipment.
Accession Register for Library Books.
Copy of Invoice/Cash Memo for equipments and Library Books.
Cash Book of the Society/Trust.
Copy of the advertisement for recruitment of faculty
Composition of Selection Committee
Minutes of Selection Committee for Faculty.
Architectural Drawing of building construction duly prepared by an Architect andapproved by the concerned statutory authority.
Master Plan of the Campus for the entire land indicating land-use, circulation,landscaping, infrastructure etc.
Floor Plans, Sections and Elevations of all existing Academic building includingArea detail
Letter of appointment/offer Letter issued to faculty.
26
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
27/58
List of faculty appointed/identified with qualification and experience.
Joining report/consent of faculty members.
Detailed Bio-data of Principal/Director.
Joining report of the Principal/Director.
Acquaintance Register
Fund position/Original FDR and Bank Certificate/Statement.
Phase-wise Plan of construction.
Cash Flow statement for the next two years for the proposed institution showingprojected expenses and sources of fund, as indicted in DPR.
Audited statement of accounts of the Society/Trust for last three years.
Photographs (color) of the building attested by the Chairman/Secretary of theSociety
Video CD (Compatible with Windows Media Player) indicating the completephysical infrastructure/facilities and highlighting following:
- Front side of the entire building.
- Back side of the entire building
- Internal portion of at least one classroom
- Internal portion of computer room along with computers
- Internal portion of one laboratory
- Internal portion of principals room
- Internal portion of library
- Internal portion of faculty room.
The institution shall arrange for Videography of the visit conducted by the Expert
Committee.
The Expert Committee will verify the availability of infrastructure and other
facilities and submit its report alongwith the relevant documents to DTE. The ExpertCommittee while examining the infrastructure/ facilities will verify as to whether the
development is in consonance with the proposal in the DPR. The State Level Committee will
further consider the Expert Committee Report.
1.3.6 APPEAL FOR RECONSIDERATION OF THE PROPOSAL
27
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
28/58
In case approval for establishment of new institution is not granted, the applicant can make
an appeal with documentary evidence to substantiate the claims made and the appeal
shall be heard by the following Committee:
The Chairman of the AICTE Regional Committee as Chairman
Two members not below the rank of Professor to be nominated by theChairman AICTE ----------------------------------------------members
Director of Technical Education of the State Govt./UT- member Regional Office of AICTE -------------convener
Based on the Recommendations of the Appellate Committee Letter of Approval/Rejection shall
be issued by the Regional Officer of AICTE on behalf of the Council.
Incase the proposal is rejected based on the recommendations of the Appellate Committee, the
Applicant Society/Trust shall make a fresh proposal.
28
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
29/58
4. NOMENCLATURE OF COURSES
A ENGINEERING AND TECHNOLOGY COURSES (NDIP)
1. Civil Engineering2. Electrical Engineering3. Mechanical Engineering4. Mechanical (RAC)5. Production & Industrial Engineering6. Electronics and Communication Engineering7. Mechanical Engineering (Tool & Die)8. Computer Engineering9. Commercial Arts10 Garment Technology11. Textile Technology12. Electronics and Tele-Communication Engineering13. Textile Processing14. Knitting Technology15. Chemical Engineering
16. Instrumentation and Control17. Electronics (Micro- Processor)18. Plastic Technology19. Textile Design20. Medical Lab. Technology21. Leather Technology22. Library and Information Science23. Garment Manufacturing Technology24. Leather Technology (Footwear)25. Information Technology26. Fashion Design
27. Modern Office Practice28. Architectural Assistantship29. Interior Design and Decoration30. Post Diploma Course in Auto-Mobile Engineering31. Post Diploma Course in Computer Application32. Post Diploma in CAD/CAM.
B. PHARMACY (NDIPPH)
C. HOTEL MANAGEMENT AND CATERING TECHNOLOGY (NDIPH)
D. APPLIED ARTS AND CRAFTS (NDIPC)
Applied & Fine Arts
29
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
30/58
4. (A) DURATION AND ENTRY LEVEL QUALIFICATIONS OF THE PROGRAMMESPOLYTECHNIC LEVEL DIPLOMA PROGRAMMES
Sr.No.
Type of the Programme Entry Level Duration(Years-Full Time)
1. Diploma in Engg. & Tech. 10+ 3
2. Diploma in Architectural Assistantship 10+ 3
3. Post Diploma in Engg. & Tech. Diploma in Engg.Tech.
1.5
4. Advanced Diploma in Engg. & Tech. Diploma in Engg.Tech.
2
5. Diploma in Pharmacy 10+2 in Science 2
6. Diploma in Hotel Management &Catering Technology
10+2 3
7. Diploma in Applied Arts & Crafts 10 3
30
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
31/58
5. POLICY DECISIONS OF THE COUNCIL WITH REGARD TO APPROVAL PROCESS
5.1 Period of Approval
For new technical institutions, the period of approval should be initially for one
year and subsequent extension of AICTE approval will not exceed more than 5
years at a time. The permanent approval to any technical institution or
course/programme in Technical Institution my be accorded through the process
of Recognition as per provision of Section 10 (u) of the Act.
5.2 Institution(s) which started without the Approval of AICTE
Any Technical Institution, which has already started, and wishes to submit an
application/proposal, will be considered as new Technical Institution requiring the
same procedure for submission and processing of application/proposal. If AICTE
decides to issue Letter of Approval for such institution, after processing the
proposal as per laid down procedure, its legal date of starting will be from the date
of issue of the Letter of Approval and the students admitted, if any, before
receiving approval from AICTE, will have to be readmitted as per laid down
procedure for admission from the beginning of first year after AICTE approval.
Students, who are admitted prior to AICTE approval, will not have any right for re-
admission and will have to fulfill all the requirements for admission.
5.3 Location of an Institution
Location/Station of an Institution shall be as per permanent land document
submitted along with the proposal and the same cannot be changed without prior
approval of AICTE.
Change of location/ Station may be permitted after getting "No Objection Certificate"
(NOC) from the State Govt. and Affiliating Body, by the Competent Authority in
AICTE as per laid down procedure subject to the condition that norequest/representation/application for change of site will be considered after
submission of application/proposal for establishment of a new Technical Institution till
the completion of at least two years after a new institution is started with the approval
of AICTE.
5.4 Rationalised Nomenclature of Courses.
Rationalized nomenclature of courses shall be as decided by the Competent
Authority in AICTE from time to time based on recommendations of the
concerned Board of Studies of AICTE.
31
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
32/58
5.5 Name of Institutions
The use of word Indian and/or National and/or All India and/or All India
Council and/or Commission in any part of the name of a Technical Institution
and/or any name whose abbreviated form leads to IIM/ IIT/ IISC/
HIT/AICTE/UGC shall not be permitted. Any Institution which is already
functioning with the names using the above words shall submit its application for
approval of revised norms by AICTE, failing which AICTE may withdraw its
approval.
The above restrictions will not be applicable for those institutions which are
established with the name approved by the Govt. of India.
Name of the Technical Institution for which approval is accorded by AICTE
shall not be changed without the approval of AICTE. AICTE may permit the
change of name as per laid down procedure.
5.6 Change of name of Society
Name of the Society/Trust, Memorandum of Association and rules are not
allowed to be changed without prior approval of AICTE.
5.7 Institutions Functioning on Temporary Location/Site
All Technical Institutions which are functioning in temporary location/site will
have to either shift to its approved permanent site with proper building(s) and
other facilities as per requirement, or be closed down from the academic year
2008-2009 and the students admitted to such institutions may be shifted to other
approved Technical Institutions in consultation with concerned State Govt./UT
Administration and Affiliating Body.
5.8 Creation of Facilities after the Visit of Expert Committee
Creation of facilities/removal of deficiencies/compliance with conditions/ fulfillment of
requirement by any Technical Institutions after the date of visit of an Expert
Committee and/or, after a date specified by AICTE, may be communicated to the
DTE office time to time.
5.9 Effective Date for approval
The Act has no provision for retrospective Approval. All approval for establishment of
new Institutions/introduction of new courses or programmes in Technical
Education/variation in Intake capacity and Recognition shall be with prospectiveeffect.
32
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
33/58
5.10 Conduct of Courses other than those approved by AICTE in TechnicalInstitution(s)
AICTE approves the Technical Institutions/Courses on the basis of Norms & Standards
specified for these courses. Since these Norms & Standards specify the
minimum requirement for establishment of technical institution to run specified
courses, any course other than those specifically approved by AICTE cannot be
run in the same premises sharing the same facilities.
5.11 Compliance Report
Any compliance report submitted by a Technical Institution indicating creation of
facilities/removal of deficiencies/conditions/fulfillment of requirement by a
specified date may be verified by AICTE. The manner in which such Compliance
reports are submitted and the method of verification shall be decided by the
AICTE.
5.12 Status of Courses not mentioned in Approval Letter
If any institution submits application to conduct several courses and AICTE decides,
after processing the application as per laid down procedure to accord approval
for some specified courses (s) with specified intake capacity for each course
which is/are less than the number of courses proposed and/or less than the
intake proposed for each course, the course and/or the proposed intake for
which approval is not accorded, will automatically stand rejected, whether a
separate Rejection Letter is issued or not.
5.13 Approval received by an Institution after the last date of Admission
Technical Institution which received Letter of Approval/Letter indicating introduction
of Additional Course(s)/Letter indicating variation in intake etc., after the
State/National Level Central Counseling for admission is over for the concerned
State/Union Territory or State/National Level admission process is completed,
such letters will be valid for admission only for the subsequent year.
Year Engg. & Tech. Courses
Maximum Annual Intake for the Institution Maximum Number of courses
First Year 300 5
(*) Further increase can be considered after accreditation of the some or all programmes
in an institution.
33
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
34/58
5.14 Excess Admission
Excess admission shall not be allowed under any circumstances. In case any excess
admission is reported to the Council, appropriate penal action will be initiated
against the institution.
5.15 Penalty Clause
Those institutes who have not submitted compliance report by 31 December 2009 (for
the grant of extension of approval for the academic year 2009-2010) after
addressing the duly pointed out deficiencies in their respective institutes shall
have to pay a penalty of Rs 10,000/- (Rupees ten thousand only) for submitting
the compliance report after the indicated cut-off date.
5.16 Number of Maximum permissible Courses and Annual Intake
Number of course (s) and/or variation in annual intake may be considered with
maximum limit given below, subject to compliance of all the Norms & Standards
of AICTE, by the Applicant:
Year Engg. & Tech. Phar. HMCT Applied Arts& Crafts
Intake Course Intake Intake Intake
First year 300 5 60 60 60
5.17 Policy regarding Barrier Free Environment for Physically Disabled PersonsIn pursuance of the decision taken by the EC in its 46th meeting held on 03/09/2003
the Council vide circular F.No. 38-07/legal/2003 dated 29/09/2003 has issued a
policy regarding barrier free environment for physically disabled persons.
5.18 Tax Deduction at Source (TDS) Certificate
The Council vide circular F. UG/Regional/2002-03/01 dated 22/10/2003 informed all
technical institutions to implement AICTE pay scales to all faculty members. In
this regard all technical institutions must forward a copy of TDS certificate in
respect of income tax deducted from the salary of faculties to the Council).
34
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
35/58
6. AICTE NORMS FOR ESTABLISHMENT OF NEW TECHNICAL INSTITUTIONS
(Diploma level courses in Engineering & Technology/Pharmacy/ Hotel Management &Catering Technology/Applied Arts & Crafts)
6.1 Intake and Number of Courses.Diploma Level Technical Institution may be started with 5 courses with an intake
of 300. The class size should be 60 in each discipline. Intake could be increased subject to
providing additional infrastructure, faculty and other facilities as per the AICTE norms and
accreditation of progrmmes. Maximum permissible annual intake for the institution and
maximum number of courses are as given below, to start with for the first year:
Engineering & Technology Pharmacy HMCT Applied Arts & Crafts
Intake Courses Intake Intake Intake
300 5 60 60 60
The size of class shall be 60 for each course.
In order to put the available resources to optimum use, diploma level institutionsmay start courses in the relevant clusters/ groups such as:
a. Mechanical Engineering Group.b. Information Technology and Electronics Communication Engineering Group.c. Electrical Engineering Group.d. Civil Engineering and Architecture Group.e. Hotel Management, Food Technology and Travel and Tourism Group.f. Applied Arts and Crafts Group.g. Pharmacy, Bio-Medical and Lab Technologies Group.
6.2 Land Requirements for Establishment of New Technical Institutions.
Table 1: Land Requirements for Establishment of New Technical Institutions, acre#
Sr.No.
Category MegaCities*
Metro cities includingState Capitals
Others
1 Engineering/Technology 1.5* 2.5 5.0
2 Applied Arts & Crafts 0.70 1.0 2.0
3 Pharmacy 0.75 1.25 2.0
4 Hotel Management &Catering Tech.
1.0 1.5 2.5
* Mega Cities: Delhi, Kolkatta, Chennai and Mumbai# Area inclusive of Hostel facility.In hilly areas, including Northeastern states, the land can be at the most inthree adjacent pieces.
35
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
36/58
6.3 Built-up Area Requirements
As per revised norms the instructional area is to be provided @ 5 sq.mt. per studentirrespective of the location of the institute. In addition to this the circulation area, theadministrative area or any other area is required to be 4 to 5 sq. mt. therefore, the totalarea required is 10 sq. mt. per student irrespective of the programme/ course as perrevised norms of AICTE.
6.3.1 Administrative Area
Table 3: Area of Administrative offices, sq. meter
Particular Engg. &Tech.
Pharmacy/HMCT/ App.Arts & Crafts
Principals office 30 20
Strong Room 20 20
Conference room 100 25
Reception Office 25 25
Main office 300 50
Administrative office 20 20
Maintenance & Estate office 40 40
Total 535 200
6.3.2 Instructional Area
Table 4: Instructional Area Requirements, Sq. m.
Inst.. Category Engg. &
Tech.
Pharmacy HMCT Appl Arts &
CraftsClassrooms, No. 3 1 1 1
Tutorial rooms, No 2 1 1 1
Drawing Halls, Area, Sq. m. 175 na na 200*
Computer Centre, area, Sq. m. 150 150 150 150
Library, area, Sq. m. 400 100 100 100
Workshop andLabs
No. See Table 5 4 2 2
Area ofEach, Sq.m
--- 75 250 66
Area of Each Classroom = 66 Sq. m.; Area of Each Tutorial Room = 36 Sq. m.na-not applicable, * Studio.
36
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
37/58
6.3.3 Workshop and Lab Area for Engineering & Technology
Table 5: Workshop and Lab Area
SN Laboratory Carpet Area, Sq. m.
1. Physics 200
2. Chemistry 175
3. Mechanics and Kinematics 100
4. Materials Testing Strength of Material 200
5. *Electrical ScienceElectronicsElect. Engg.
200
6. WORKSHOP 900
TOTAL 1675
* When these streams are operative then applicable
6.4 Experiments:The experimental setups should be arranged as per the requirements of the affiliating
Boards curriculum, and not more than four students to work in an experiment.
6.5 Requirement of Computers/Software
Table 6: Requirement of Computers/Software
SN
Particulars Requirements
All diploma Programmes
1. No. of Computerterminals
Terminal-Student Ratio = 1:4
2. Hardware
specification
P4 or equivalent Processor, or thin clients supported
by a powerful server4. Relevant
LicensedSoftware
At least two system software packages and fourApplication Software Packages
5. Peripherals Printer: Computer Terminal ratio = 1:10
- Library, Administrative Wings and Faculty members should be provided withexclusive computing facilities along with LAN and Internet over and above therequirement meant for students.
- Utilization of Open Source Software should be encouraged.
37
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
38/58
6.6 Library/Books and Journals
Sr.No.
Class of Institutions
No. of Booksfor Tech.Subjects
No. of Books forSc. &Humaniti
es
No. ofJournals
Furniture FullTimeLibrarian
Photocopier
No. ofTitles
No. ofVolumes
(Volumes) (No) (No)
1. Engg & Tech 150 per course
500 percourse
500 3 per course
Sufficientfor Books& Seatingcapacityfor 25%of Intake
1 1
2. Pharmacy 100 300 - 3 -do- 1 1
3. Hotel Mgt. &catering Tech.
50 500 - 3 -do- 1 1
4. Applied Arts &Crafts
--- 300 - 3 -do- 1 1
For details consult norms, standards and guidelines of All India Council for TechnicalEducation, New Delhi and curricula of Punjab State Board of Technical Education.
6.7 FACULTY
S.No Class of Institutions Principal No. ofHOD No. of Sr.Lecturer No. of Lecturer Total No. of TechnicalSupporting Staff
Appointed
Identified
Identified Identified Appointed+
Identified
Appointed +Identified
1. Engg &Tech
1 1 2 8 12 1 Lab Asstt. for each Lab. + 2Maintenance Stafffor the Inst.
2. Pharmacy 1 - 1 2 4 1 Lab Asstt. for each Lab. + 1
Maintenance Stafffor the Inst.
3. Hotel Mgt.& cateringTech.
1 - 1 2 4 -do-
4. Applied Arts& Crafts
1 - 1 2 4 -do-
Teacher student ratio: Diploma level institutions should be providedfaculty in the teacher student ratio of 1:20. The faculty should be appointed withapproved designations, i.e. Heads of Departments, Senior Lecturers and Lectures.
Ratio between Senior Lecturer and Lecturer should be 1:3.
38
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
39/58
6.8 Funds
a) Rs. 50 Lakhs (excluding land and buildings)
b) Joint Fixed Deposit Rs. 15 Lakhs
Note: All other facilities shall be provided as per the requirement of curriculum of theconcerned State Board of Technical Education/ Affiliating Body.
6.9 Other Essential Requirements
Table 9: Essential Requirements
SN Description Engineering &Technology
Pharmacy HMCT Applied Arts andCrafts
1. Operationalfunds, Rs Lakhs
15 20 15 10
2. Digital Library Four Computers withMultimedia facilities, duly
networked
Two Computers with Multimediafacilities, duly networked
3. ElectricalGenerator
25 KVA 5KVA
4. Students*Canteen
100 Sq. m. 100 Sq. m.
5. Girls CommonRoom
100 Sq. m. 100 Sq. m.
Boys CommonRoom*
100 Sq. m. 100 Sq. m.
6. Scooter Parking 200 Sq. m. 100 Sq. m.
7 Medical Centre 40 Sq. m 40 Sq. m
8 Internet facilityfor students andfaculty
Band with 510 kbps,24X7, 30 nodes
Band with 510 kbps, 24X7, 15 nodes
9 Communication(language) lab
Sufficient for 30 students Sufficient for 30 students
Apart from the above, following are also essential requirements:
Barrier-Free Environment as per the PWD Act.
Safety provisions including fire and other calamities.
General Insurance to be provided for the assets against fire, burglary and othercalamities.
Group Insurance to be provided for the employees.
A Medical Room and Part Time Medical Officer should be made available.
6.10 Desirable Requirements
Insurance for students
39
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
40/58
6.11 Course Duration:For a three-year diploma-engineering programme, teaching should be divided into six
semesters, each of 15 working weeks (excluding examinations) with a totalduration of 180 working days.
MANDATORY DISCLOSURES
40
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
41/58
MANDATORY DISCLOSURES
1.1 ENGINEERING/TECHNOLOGY/PHARMACY PROGRAMMES
The following information is to be given in the Information Brochure besides being hosted on the Institution's
official Website.
"The information has been provided by the concerned institution and the onus of authenticity lies with
the institution and not on AICTE."
I. NAME OF THE INSTITUTION
Address including telephone, Fax, e-mail.
II. NAME & ADDRESS OF THE DIRECTOR
Address including telephone, Fax, e-mail.
III. NAME OF THE AFFILIATING BOARD.
IV. GOVERNANCE
Members of the Board and their brief background
Members of Academic Advisory Body
Frequency of the Board Meetings and Academic Advisory Body
Organizational chart and processes
Nature and Extent of involvement of faculty and students in academic affairs/improvements
Mechanism/Norms & Procedure for democratic/good Governance
Student Feedback on Institutional Governance/faculty performance
Grievance redressal mechanism for faculty, staff and students
V. PROGRAMMES
Name of the Programmes approved by the AICTE
Name of the Programmes accredited by the AICTE
For each Programme the following details are to be given:
Name
Number of seats
Duration
Cut off mark/rank for admission during the last three years
Fee
Placement Facilities
Campus placement in last three years with minimum salary, maximum salary and average salary
Name and duration of programme(s) having affiliation/collaboration with Foreign Board(s)/Institution(s)
and being run in the same Campus along with status of their AICTE approval. If there is foreign
collaboration, give the following details:
Details of the Foreign Institution/Board:
Name of the Board /Institution
Address Website
41
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
42/58
Is the Institution/University Accredited in its Home Country
Ranking of the Institution/Board in the Home Country
Whether the diploma offered is equivalent to an Indian Diploma? If yes, the name of the agency which
has approved equivalence. If no, implications for students in terms of pursuit of higher studies in India and abroad
and job both within and outside the country. Nature of Collaboration
Conditions of Collaboration
Complete details of payment a student has to make to get the full benefit of collaboration.
For each Collaborative/affiliated Programme give the following:
Programme Focus
Number of seats
Admission Procedure
Fee Placement Facility
Placement Records for last three years with minimum salary, maximum salary and average salary
Whether the Collaborative Programme is approved by AICTE? If not whether the Domestic/Foreign
Institution has applied to AICTE for approval as required under notification no. 37-3/Legal/2005 dated 16th May,
2005
VI. FACULTY
Branch wise list faculty members:
Permanent Faculty
Visiting Faculty
Adjunct Faculty
Guest Faculty
Permanent Faculty: Student Ratio
Number of faculty employed and left during the last three years
42
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
43/58
VII. PROFILE OF DIRECTOR/PRINCIPAL WITH QUALIFICATIONS, TOTAL EXPERIENCE, AGE AND
DURATION OF EMPLOYMENT AT THE INSTITUTE CONCERNED.
For each Faculty give a page covering
1. Name
2. Date of Birth
3. Educational Qualification
4. Work Experience
Teaching
Research
Industry
Others
5. Area of Specializations
6. Subjects teaching at diploma Level
Post diploma Level
7. Research guidanceNo. of papers published in
Masters's - National Journals
Ph.D. - International Journals
- Conferences
8. Projects Carried out
9. Patents
10. Technology Transfer
11. Research Publications
12. No. of Books published with details
VIII. FEE
Details of fee, as approved by State fee Committee, for the Institution.
Time schedule for payment of fee for the entire programme.
No. of Fee waivers granted with amount and name of students.
Number of scholarship offered by the institute, duration and amount
Criteria for fee waivers/scholarship.
Estimated cost of Boarding and Lodging in Hostels.
IX. ADMISSION
Number of seats sanctioned with the year of approval.
Number of students admitted under various categories each year in the last three years.
Number of applications received during last two years for admission under Management Quota and
number admitted.
X. ADMISSION PROCEDURE
Mention the admission test being followed, name and address of the Test Agency and its URL
(website).
Number of seats allotted to different Test Qualified candidates separately [JET (State conducted
test/Board tests)/Association conducted test]
Calendar for admission against management/vacant seats:
43
Photograph
Signature
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
44/58
Last date for request for applications.
Last date for submission of application.
Dates for announcing final results.
Release of admission list (main list and waiting list should be announced on the same day)
Date for acceptance by the candidate (time given should in no case be less than 15 days)
Last date for closing of admission.
Starting of the Academic session.
The waiting list should be activated only on the expiry of date of main list.
The policy of refund of the fee, in case of withdrawal, should be clearly notified.
XI. CRITERIA AND WEIGHTAGES FOR ADMISSION
Describe each criteria with its respective weightages i.e. Admission Test, marks in
qualifying examination etc.
Mention the minimum level of acceptance, if any.
Mention the cut-off levels of percentage & percentile scores of the candidates in the
admission test for the last three years.
Display marks scored in Test etc. and in aggregate for all candidates who were admitted.
Item No I - XI must be given in information brochure and must be hosted as fixed content in the
website of the Institution.
The Website must be dynamically updated with regard to XII-XV.
XII. APPLICATION FORM
Downloadable application form, with online submission possibilities.
XIII. LIST OF APPLICANTS
List of candidates whose applications have been received along with percentile/percentage score for
each of the qualifying examination in separate categories for open seats. List of candidates who have
applied along with percentage and percentile score for Management quota seats.
XIV. RESULTS OF ADMISSION UNDER MANAGEMENT SEATS/VACANT SEATS
Composition of selection team for admission under Management Quota with the brief profiles of members
(This information be made available in the public domain after the admission process is over)
Score of the individual candidates admitted arranged in order of merit.
List of candidates who have been offered admission.
Waiting list of the candidates in order of merit to be operative from the last date of joining of the first list
candidates.
List of the candidates who joined within the date, vacancy position in each category before operation of
waiting list.
XV. INFORMATION ON INFRASTRUCTURE AND OTHER RESOURCES AVAILABLE
LIBRARY:
Number of Library books/Titles/Journals available (programme-wise)
List of online National/International Journals subscribed.
E-Library facilities
LABORATORY:
For each Laboratory
44
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
45/58
List of Major Equipment/Facilities
List of Experimental Setup
COMPUTING FACILITIES:
Number and Configuration of Systems
Total number of systems connected by LAN
Total number of systems connected to WAN
Internet bandwidth
Major software packages available
Special purpose facilities available
WORKSHOP:
List of facilities available.
Games and Sports Facilities
Extra Curriculum Activities
Soft Skill Development Facilities
Number of Classrooms and size of each
Number of Tutorial rooms and size of each
Number of laboratories and size of each
Number of drawing halls and size of each
Number of Computer Centres with capacity of each
Central Examination Facility, Number of rooms and capacity of each.
Teaching Learning process
Curricula and syllabi for each of the programmes as approved by the University.
Academic Calendar of the Board
Academic Time Table
Teaching Load of each Faculty
Internal Continuous Evaluation System and place
Students' assessment of Faculty, System in place.
For each Post Diploma programme give the following:
i. Title of the programme
ii. Curricula and Syllabi
iii. Faculty ProfileSI Name DESIGNATION B. Subject Teaching
1.
2.
3.
Brief profile of each faculty.
Laboratory facilities exclusive to the PD programme
Special Purpose
Software, all design tools in case
Academic Calendar and frame work
45
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
46/58
Research focus
List of typical research projects.
Industry Linkage
Publications (if any) out of research in last three years out of masters projects
Placement status
Admission procedure
Fee Structure
Hostel Facilities
Contact address of co-ordinator of the PD programme
Name :
Address :
Telephone :
E-mail :
NOTE: Suppression and/or misrepresentation of information would attract appropriate penal action.
46
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
47/58
1.2 APPLIED ARTS AND CRAFTS PROGRAMMES
The following information is to be given in the Information Brochure besides being hosted on the Institution's
official Website.
"The information has been provided by the concerned institution and the onus of authenticity lies with
the institution and not on AICTE."
I. NAME OF THE INSTITUTION
Address including telephone, Fax, e-mail.
II. NAME & ADDRESS OF THE DIRECTOR
Address including telephone, Fax, e-mail.
III. NAME OF THE AFFILIATING UNIVERSITY
IV. GOVERNANCE
Members of the Board and their brief background
Members of Academic Advisory Body
Frequency of the Board Meetings and Academic Advisory Body
Organizational chart and processes
Nature and Extent of involvement of faculty and students in academic affairs/improvements
Mechanism/Norms & Procedure for democratic/good Governance
Student Feedback on Institutional Governance/faculty performance
Grievance redressal mechanism for faculty, staff and students
V. PROGRAMMES
Name of the Programmes approved by the AICTE
Name of the Programmes accredited by the AICTE
For each Programme the following details are to be given:
Name
Number of seats
Duration
Cut off mark/rank for admission during the last three years
Fee
Placement Facilities
Campus placement in last three years with minimum salary, maximum salary and average salary
Name and duration of programme(s) having affiliation/collaboration with Foreign
University(s)/Institution(s) and being run in the same Campus along with status of their AICTE approval.
If there is foreign collaboration, give the following details:
47
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
48/58
Details of the Foreign Institution/University:
Name of the University/Institution
Address
Website
Is the Institution/University Accredited in its Home Country
Ranking of the Institution/University in the Home Country
Whether the degree offered is equivalent to an Indian Degree? If yes, the name of the agency
which has approved equivalence. If no, implications for students in terms of pursuit of higher studies in
India and abroad and job both within and outside the country.
Nature of Collaboration
Conditions of Collaboration
Complete details of payment a student has to make to get the full benefit of collaboration.
For each Collaborative/affiliated Programme give the following:
Programme Focus
Number of seats
Admission Procedure
Fee
Placement Facility
Placement Records for last three years with minimum salary, maximum salary and average salary
Whether the Collaborative Programme is approved by AICTE? If not whether the Domestic/Foreign
Institution has applied to AICTE for approval as required under notification no. 37-3/Legal/2005 dated 16th May,
2005
VI. FACULTY
Branch wise list faculty members:
Permanent Faculty
Visiting Faculty
Adjunct Faculty
Guest Faculty
Permanent Faculty: Student Ratio
Number of faculty employed and left during the last three years
48
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
49/58
VII.PROFILE OF DIRECTOR/PRINCIPAL WITH QUALIFICATIONS, TOTAL EXPERIENCE, AGE AND
DURATION OF EMPLOYMENT AT THE INSTITUTE CONCERNED
For each Faculty give a page covering
1. Name
2. Date of Birth
3. Educational Qualification
4. Work Experience
Teaching
Research
Industry
Others
5. Area of Specializations
6. Subjects teaching at Diploma Level
Diploma Level
7. Research guidance
No. of papers published inMasters's - National Journals
Ph.D. - International Journals
- Conferences
8. Projects Carried out
9. Patents
10. Technology Transfer
11. Research Publications
12. No. of Books published with details
VIII. FEE
Details of fee, as approved by State fee Committee, for the Institution.
Time schedule for payment of fee for the entire programme.
No. of Fee waivers granted with amount and name of students.
Number of scholarship offered by the institute, duration and amount
Criteria for fee waivers/scholarship.
Estimated cost of Boarding and Lodging in Hostels.
IX. ADMISSION
Number of seats sanctioned with the year of approval.
Number of students admitted under various categories each year in the last three years.
Number of applications received during last two years for admission under Management Quota and
number admitted.
49
Photograph
Signature
-
8/14/2019 Application for Establishment of New Technical Institutions for the Year 2009-10
50/58
X. ADMISSION PROCEDURE
Mention the admission test being followed, name and address of the Test Agency and its URL (website).
Number of seats allotted to different Test Qualified candidates separately [JET (State conducted
test/Board tests)/Association conducted test]
Calendar for admission against management/vacant seats:
Last date for request for applications.
Last date for submission of application. Dates for announcing final results.
Release of admission list (main list and waiting list should be announced on the same day)
Date for acceptance by the candidate (time given should in no case be less than 15 days)
Last date for closing of admission.
Starting of the Academic session.
The waiting list should be activated only on the expiry of date of main list.
The policy of refund of the fee, in case of withdrawal, should be clearly notified.
XI. CRITERIA AND WEIGHTAGES FOR ADMISSION Describe each criteria with its respective weightages i.e. Admission Test, marks in qualifying examination
etc.
Mention the minimum level of acceptance, if any.