application form for epa works approval€¦ · proposal 2.1 project description ... while waiting...
TRANSCRIPT
Application form for EPA works approval
1. APPLICANT
1.1 Company details
Company name ACN
Auslak Timber Treatment P/L 159 894 443
Registered address
24 Vesper Drive, Narre Warren, Victoria, 3805
1.2 Contact details
Name Position
Ian Clarke (TimTech Chemicals)
Sales & Services Manager
Phone Email
0417 749 481
1.3 Premises details
Premises address Municipality
24 Vesper Drive, Narre Warren, Victoria, 3805 City of Casey
2. PROPOSAL
2.1 Project description
Provide a simple, one-line explanation of the project. Attach a site and location plan.
The proposal is for the installation of a waterborne timber preservation plant.
2.2 Cost of works and application fee
Cost of works Application fee
$381,523.30 $5,420.50
2.3 Proposed dates
Start construction: Month, Year Start operation: Month, Year
November 2012 It will take 5 months to build and ship the plant from Europe once a purchase order is placed. Work on the concrete bund will be completed while waiting for shipment of the plant. The installation and commissioning of the plant once it arrives from Europe will be 3 to 5 days. Purchase order for the plant is subject to getting EPA Works Approval.
March 2013
Application form for EPA works approval
3. APPROVALS
3.1 Need for works approval
Schedule type Act section that applies
F01 Timber Preservation
List any exemptions that apply: section of the Regulations
3.2 Planning and other approvals
Planning Zone Type of approval required
Industrial 3 Zone N/A
Approving authority Approval received or pending
N/A N/A
3.3 Existing EPA approvals (if any)
List any EPA documents held
N/A
4. ENVIRONMENT AND COMMUNITY
4.1 Track record
Summarise the company’s recent environmental performance
N/A See preamble in SBMP for the industry experience of Auslak’s managing director.
Report any relevant offences; e.g. indictable and summary offences
N/A
List any enforcement actions related to this site
N/A
4.2 Key environmental considerations
List the main environmental aspects of your proposal
The timber preservation plant will be of zero discharge configuration. The plant will be designed and built to AS 2843 Part 1-Plant Design and Part 2-Plant Operation. The plant will use the latest technology in relation to processes and will therefore minimize the amount of water used during operation. It is also planned to farm rain water from the roof of the shed housing the plant to use during operation and therefore reduce the volume of mains water required.
4.3 Community engagement
Summarise any public consultation that has been undertaken or planned
N/A
Indicate any issues that have been raised
N/A
Application form for EPA works approval
5. PROCESS AND BEST PRACTICE
5.1 Process and technology
Key process steps Key inputs Key outputs Key Controls
The plant will use variations of the Vacuum Pressure Impregnation (VPI) process to provide the best outcome for the type and species of wood to be treated. This process is described in more detail in the attached SBMP.
The plant plans to use both TimTech C Oxide (Copper Chrome Arsenate) and TimTech Q (Alkaline Copper Quaternary). These will be supplied in concentrate form to site in 1,000 litre Intermediate Bulk Containers (IBC’s). Both preservatives will be diluted with water on site. Further description on the preservatives is supplied in the MSDS’ in appendix 1 of the SBMP and also the Emergency Spills Procedure which is appendix 5 of the SBMP.
Treatment of timber greatly enhances it’s durability and the applications for use. It can take non-durable plantation grown timber and turn it into a durable value added product. Waste generation and minimisation is discussed in section 4 of the attached SBMP.
Records are kept of each charge (individual process) that goes through the the timber preservation plant. These records include the process used, volume treated, level of treatment (retention of preservative), volume of preservative used etc.
5.2 Environmental best practice
Indicate steps taken to determine industry best practice
The plant will be sourced from a European based company, IWT Moldrup. They are recognised as industry leaders in the design and supply of timber preservation plants and use the latest control technologies available.
Explain why waste generation and resource use cannot be avoided or minimised
Please refer to section 4 of the attached SBMP which discusses waste generation and minimisation.
Explain options considered and why this process is considered best practice
Application form for EPA works approval
5.3 Integrated environmental assessment
Indicate any areas where there are competing environmental demands
N/A
Indicate how you will determine net environmental benefit in these areas
N/A
5.4 Choice of process and technology
Process or technology Advantages Disadvantages
The plant will be sourced from IWT Moldrup in Europe.
They are widely recognised as industry leaders and use industry best practice in both the design and manufacture of their plants.
5.5 Choice of location and layout
Location or layout Advantages Disadvantages
24 Vesper Drive, Narre Warren Victoria. See site map attached in SBMP.
Initially Auslak looked at a new site in Thomas Murrell Drive, Dandenong for the plant however initial discussions with Local Council indicated that we would have trouble gaining approvals as this land was designated for Industry that required a significant buffer. This area is one of only three in the state and therefore used to encourage industries requiring significant buffer zones. The use of the Vesper Drive location meets the required 100 metre buffer zone to sentitive areas. Currently the site is used for a timber wholesale and retail operation.
6. RESOURCES
6.1 Carbon
Type of energy use or greenhouse gas emission Amount in GJ/yr or tCO2e
Please refer to section 1.4 (Operational Issues) of the SBMP for a detailed explanation of power consumption.
Application form for EPA works approval
It is estimated the plant will use 941kW of power per month.
6.2 Water use
The water usage: ML per year
1.75 ML per year
6.3 Solid waste
Type of solid waste Amount t/yr Destination
Very little solid waste will be produced. The only solid will be from the occasional strap or glut that maybe dislodged from a pack during handling on site.
6.4 Prescribed industrial waste
Type of prescribed waste Amount t/yr Destination
Treatment plants generate waste from two areas.
1. Chemical sludge which can be minimized by process selection etc.
2. Contaminated sawdust and soil that is carried in on packs of timber. This can be minimized through good house keeping.
See section 4 of the SBMP for further information on waste management.
1.2-1.5 tonnes (800-1,000 litres) Will be disposed of via recognised waste disposal company ie Virotec.
7. EMISSIONS
7.1 Air emissions
Type of air emissions Rate or scale of emissions List any class 3 indicators
Refer to SBMP for details of vacuum pump configuration.
N/A N/A
7.2 Discharge to surface water
Provide reasons for any discharge to water (rather than to sewer or to land)
N/A
Application form for EPA works approval
Rate of discharge to water; litres per day Indicate water quality or treatment level
N/A
7.3 Discharge to land
Rate of discharge or deposit to land, Types of waste and level of treatment litres/or tonnes per day e.g. secondary or tertiary
N/A
For reuse, demonstrate that the proposal will meet EPA guidelines
N/A
Provide the reasons for any discharge to groundwater and indicate segment
N/A
7.4 Noise emissions
Hours of operation Noise sources Are they audible at nearby residences?
7.00am to 5.00pm Pumps - including vacuum, pressure and transfer pumps. These pumps do not run simultaneously and are used at different stages of the treatment process. The SBMP details noise generated from the vacuum pump which will generate the most noise.
The nearest residence is 205 metres to the South-East of the proposed site and therefore will not be impacted by the project.
8. ENVIRONMENTAL MANAGEMENT
8.1 Non-routine operations
List process upsets that could impact on the environment
The only chances of an environmental risk could come from an equipment failure or leak. Both of these are discussed in more detail in the SBMP. But essentially the plant will be housed inside a bund and therefore will be able to contain any spills from plant failure or leak.
8.2 Separation distances
Proposed buffer distances, in metres Recommended buffer distance, in metres
205 metres from nearest senititive receptors 100 metres
8.3 Management system
Explain the system that will be used to manage environmental risk
The plant will be housed inside a bund that has 120% capacity of the entire contents possible to be stored on site. In the highly unlikely event (never happened before) of both work tanks failing the entire contents of the plant will contained and not present an environmental risk.
Application form for EPA works approval
8.4 Construction
Identify any environmental risks that will need to be managed during installation
N/A
Identify any existing site contamination issues
N/A
Explain how construction will be managed to prevent environmental impacts
The plant will be housed inside an existing shed and therefore require no earthworks. The plant bund/drip pad will require 280 m2 (18 x 15.6 metres) of concrete to be poured over the existing concrete floor. The plant will be fabricated and tested prior to shipment from Europe. On site all that is required for the plant installation is for it to be bolted together. This will prevent any environmental impacts during construction.
Application Form for EPA Works Approval
A. CARBON
A1. Energy use and greenhouse gas emissions
Note any existing energy use and greenhouse gas emissions
Type of energy use or Amount (TJ/year) or Process step greenhouse gas tCO2e/year
Basis for numbers
A2. Best practice carbon management
Outline the steps taken to identify best practice carbon management
Summarise the options considered to avoid or minimise carbon emissions
Explain why the chosen option is best practice
B. WATER
B1. Water use
Note any existing water use
Process step Type of water use Amount (ML/year)
Application Form for EPA Works Approval
Basis for numbers
B2. Best practice water management
Outline the steps taken to identify best practice for saving water
Summarise the options considered to avoid or minimise water usage
Explain why the chosen option is best practice
C. SOLID WASTE
C1. Solid waste generation
Note any existing solid waste generation
Process step Type of waste generated Amount (t/year)
Basis for numbers
C2. Best practice solid waste management
Outline the steps taken to identify best practice for solid waste management
Summarise the options considered to avoid or minimise solid waste
Explain why the chosen option is best practice
Application Form for EPA Works Approval
Indicate where these wastes will go
D. PRESCRIBED INDUSTRIAL WASTE
D1. Prescribed industrial waste generation
Note any existing prescribed industrial waste generation
Process Type of waste Waste category Amount (t/year)
Basis for numbers
D2. Best practice prescribed waste management
Outline the steps taken to identify best practice for prescribed waste
Summarise the options considered to avoid or minimise prescribed waste
Explain why the chosen option is best practice
Indicate where these wastes will go
E. AIR
E1. Air emissions
Note any existing air emissions
Application Form for EPA Works Approval
Process step Type of air emission* Amount (g/min)
*Identify any class 3 indicator emissions
Basis for numbers
E2. Best practice air emissions management
Outline the steps taken to identify best practice# for air emissions
Summarise the options considered to avoid or minimise air emissions
Explain why the chosen option is best practice#
#For class 3 indicator emissions assess against maximum extent achievable
E3. Impact on air quality
Predicted maximum
concentration (project) Background concentration
Predicted maximum
concentration (total)^
^Where any predicted concentrations are above the design criteria, provide a risk assessment. Assess any emissions that could impact on regional air quality.
Application Form for EPA Works Approval
F. WATER
F1. Water discharges
Note any existing water discharges
Process step Type of water discharge Flowrate (L/day)
Basis for numbers
F2. Best practice water management
Outline the steps taken to identify best practice for discharge to water
Summarise the options considered to avoid or minimise water discharges
Explain why the chosen option is best practice
F3. Impact on waterway
Indicator Maximum concentration Median concentration (mg/L)
Water quality objective^
^Where any predicted concentrations are above the objectives, provide a mixing zone assessment
Application Form for EPA Works Approval
G. LAND AND GROUNDWATER
G1. Discharge or deposit to land
Note any existing discharge or deposit to land
Process step Type of discharge Flow rate (L/day)
Or Type of waste Amount (t/year)
Basis for numbers
G2. Best practice land and groundwater management
Outline the steps taken to identify best practice in discharge or deposit to land
Summarise the options considered to avoid or minimise discharge to land
For landfills, demonstrate best practice siting and design
Explain why the chosen option is best practice
G3. Impact on land and groundwater
Provide a land capability assessment
Groundwater Indicator Predicted Concentration Water quality objective^
Application Form for EPA Works Approval
^Where any predicted concentrations are above the objectives, provide an attenuation zone assessment
Assess any impacts on the level of the water table
H. NOISE EMISSIONS
H1. Noise emissions
Process step Source/type of emission Sound power level (dBA)
Basis for numbers
H2. Best practice noise management
Outline the steps taken to identify best practice for noise emissions
Summarise the options considered to avoid or minimise noise emissions
Explain why the chosen option is best practice
H3. Noise impact
Location of Noise levels Existing noise Background receptor(s) from project^ levels (site)^ noise level^
Total noise level^ Noise limit^
^dBA for each of day, evening and night where relevant. Where existing site noise is above the limit, provide a noise reduction plan.
Application Form for EPA Works Approval
I. ENVIRONMENTAL MANAGEMENT
I1. Non routine operations
Outline the steps taken to identify potential process upsets or failures
Outline approach to identifying best practice in managing these environmental risks
Type of process upset Potential environmental Measures to reduce
impact likelihood and impact
Explain why the buffer distance to residents is acceptable
I2. Monitoring
Indicator Monitoring Monitoring Use of Process Measured type frequency monitoring
APPLICANT STATEMENT
I declare that to the best of my knowledge the information in this application is true and correct, that I have made all the necessary enquiries and that no matters of significance have been withheld from EPA. Signed CEO or delegate